Prior art keywords
post
support
cast strip
jacking
plane template
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201721322972.8U
Other languages
Chinese (zh)
Inventor
张自品
饶松青
钟文辉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Fujian Southern Aluminum Structure Technology Co.,Ltd.
Original Assignee
Fujian South Aluminium Mould Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Fujian South Aluminium Mould Technology Co Ltd filed Critical Fujian South Aluminium Mould Technology Co Ltd
Priority to CN201721322972.8U priority Critical patent/CN207332309U/en
Application granted granted Critical
Publication of CN207332309U publication Critical patent/CN207332309U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

A kind of support shuttering of post-cast strip, including plane template and support component, the support component includes at least two jacking and supporting rod, at least two jacking is respectively arranged on the both sides of the plane template and is detachably connected with plane template, the upper surface of the jacking is concordant with the upper surface of the plane template, and at least two supporting rods support at least two jacking respectively.The late poured band support template of the utility model includes a set of post-cast strip private use plane template and more set support components, compared to traditional wooden model, reduces template and human input, improves construction efficiency.

Description

A kind of support shuttering of post-cast strip
Technical field
Technical field of buildings is the utility model is related to, more particularly to a kind of support shuttering of post-cast strip.
Background technology
It is to prevent monolithic reinforced concrete structure since autogenous shrinkage is uneven or settles not in construction that post-cast strip, which is, Issuable harmful cracks, according to design or job specfication requirement, stay what is set to face in sole plate, wall, beam relevant position When construction joint.
If structure is temporarily divided into stem portion by post-cast strip, shunk by component inside, poured again after some time and smash this Structure, is linked to be overall area by construction joint concrete.Unit in charge of construction generally uses wooden model system or pure wooden model under the prior art Support system pours post-cast strip, in order to ensure construction quality, it is necessary to ability form removal after the completion of post empiricism is waited, Therefore need that substantial amounts of template is lost, it is of high cost, do not meet the theme of today's society low-carbon environment-friendly yet.
Utility model content
Technical problem to be solved in the utility model is:A kind of template less investment is provided, construction efficiency it is high and save into The support shuttering of this post-cast strip.
In order to solve the above-mentioned technical problem, the technical solution adopted in the utility model is:
A kind of support shuttering of post-cast strip, including plane template and support component, the support component include at least two Jacking and supporting rod, at least two jacking is respectively arranged on the both sides of the plane template and detachably connects with plane template Connect, the upper surface of the jacking is concordant with the upper surface of the plane template, and at least two supporting rods support at least respectively The jacking of two.
Further, the plane template and the material of support component are respectively aluminium alloy.
Further, the supporting rod has the hollow structure of opening for top.
Further, the jacking is made of planar support plate and mandril, one end of the mandril and the planar support plate Bottom is connected, and the other end of the mandril is arranged in the supporting rod.
Further, between at least two supporting rod be smaller than be equal to 1.3m.
The beneficial effects of the utility model are:During construction, the concrete structure beyond post-cast strip is poured first, Remove the support shuttering of other concrete structures after the completion of pouring, and can premature removal post-cast strip plane template and only retain Support component, support component continues to support the cantilevered structure of post-cast strip both sides, then post-cast strip is poured, and premature removal is put down Face die plate can be used for pouring for other job location post-cast strips.Therefore needed relative to wooden model system using more set templates and branch Support system, this programme only need a set of post-cast strip private use plane template and more set support components, reduce template and human input, improve Construction efficiency.
Brief description of the drawings
Fig. 1 is the front view of the support shuttering of the post-cast strip of the utility model embodiment.
Label declaration:
1st, plane template;2nd, support component;21st, supporting rod;22nd, jacking;221st, planar support plate;
222nd, mandril;3rd, post-cast strip;4th, concrete substrate.
Embodiment
To describe the technology contents of the utility model, the objects and the effects in detail, below in conjunction with embodiment and match somebody with somebody Attached drawing is closed to be explained.
The design of the utility model most critical is:Jacking supports the cantilevered structure of post-cast strip both sides, ensures plane template It can reduce template input with premature removal, reduce construction cost.
It refer to Fig. 1, a kind of support shuttering of post-cast strip, including plane template 1 and support component 2, the support component 2 Including at least two jacking 22 and supporting rod 21, at least two jacking 22 be respectively arranged on the both sides of the plane template 1 and It is detachably connected with plane template 1, the upper surface of the jacking 22 is concordant with the upper surface of the plane template 1, and at least two The supporting rod 21 supports at least two jacking 22 respectively.
As can be seen from the above description, the beneficial effects of the utility model are:During construction, first to the coagulation beyond post-cast strip Soil structure is poured, remove the support shuttering of other concrete structures after the completion of pouring, and can premature removal post-cast strip Plane template and only retain support component, support component continue support post-cast strip both sides cantilevered structure, then to post-cast strip carry out Pour, the plane template of premature removal can be used for pouring for other job location post-cast strips.Therefore needed relative to wooden model system More set templates and support system are used, this programme only needs a set of post-cast strip private use plane template and more set support components, reduces Template and human input, improve construction efficiency.
Further, the plane template 1 and the material of support component 2 are respectively aluminium alloy.
Seen from the above description, the stability of aluminium alloy is good, high capacity, reuses often, and average unit cost is low.
Further, the supporting rod 21 has the hollow structure of opening for top.
Seen from the above description, hollow supporting rod 21 saves raw material, lighter in weight and is easily portable.
Further, the jacking 22 is made of planar support plate 221 and mandril 222, one end of the mandril 222 with it is described The bottom of planar support plate 221 is connected, and the other end of the mandril 222 is arranged in the supporting rod 21.
Seen from the above description, mandril 222 is arranged in hollow supporting rod 21, convenient for disassembly and assembly.
Further, between at least two supporting rod 21 be smaller than be equal to 1.3m.
Seen from the above description, the less supporting rod 21 of spacing can preferably support the concrete structure of post-cast strip 3 with The cantilevered structure of 3 both sides of post-cast strip.
Fig. 1 is refer to, the embodiment one of the utility model is:
A kind of support shuttering of post-cast strip, including plane template 1 and support component 2, the plane template 1 and support component 2 material is respectively aluminium alloy.The support component 2 includes at least two jacking 22 and supporting rod 21, the supporting rod 21 There is the hollow structure of opening for top.The jacking 22 is made of planar support plate 221 and mandril 222, and the one of the mandril 222 End is connected with the bottom of the planar support plate 221, and the other end of the mandril 222 is arranged in the supporting rod 21.At least two Jacking 22 be respectively arranged on the both sides of the plane template 1 and be detachably connected with plane template 1, the planar support plate 221 Upper surface is concordant with the upper surface of the plane template 1.It is smaller than being equal between at least two supporting rod 21 1.3m。
During the utility model embodiment Specific construction, the jacking 22 is to be used to support post-cast strip both sides molding mixed Solidifying soil matrix material 4, concrete substrate 4 herein can be flooring or beam.
At practice of construction scene, the tricks of support component 2 for post-cast strip pour number of days divided by 5 (in construction general five days it is complete Into pouring for one layer of post-cast strip), and whole major project is using single upright bar support technology, the same full hall frame for comparing wooden model, more Construction efficiency can be improved.
In conclusion the utility model provides a kind of template less investment, the high and cost-effective post-cast strip of construction efficiency Support shuttering.During the support shuttering construction of the utility model, the concrete structure beyond post-cast strip is poured first, is poured Technology implementation is early torn open using aluminum alloy pattern plate early to tear open, first remove the support shuttering of other concrete structures, and can shift to an earlier date after the completion of building To remove the plane template of post-cast strip and only retain support component, support component continues to support the cantilevered structure of post-cast strip both sides, then Post-cast strip is poured, the plane template of premature removal can be used for pouring for other job location post-cast strips.Therefore it is opposite Needed in wooden model system using more set templates and support system, this programme only needs a set of post-cast strip private use plane template and more set branch Support component, reduces template and human input, improves construction efficiency.
The above description is only the embodiments of the present invention, and it does not limit the scope of the patent of the present invention, every Equivalents made based on the specification and figures of the utility model, are directly or indirectly used in relevant technology neck Domain, is equally included in the patent within the scope of the utility model.

Claims (5)

1. a kind of support shuttering of post-cast strip, including plane template and support component, it is characterised in that the support component includes At least two jacking and supporting rod, at least two jacking are respectively arranged on the both sides of the plane template and can with plane template Dismantling connection, the upper surface of the jacking is concordant with the upper surface of the plane template, and at least two supporting rods prop up respectively The jacking of support at least two.
2. the support shuttering of post-cast strip according to claim 1, it is characterised in that the plane template and support component Material is respectively aluminium alloy.
3. the support shuttering of post-cast strip according to claim 1, it is characterised in that the supporting rod has opening for top Hollow structure.
4. the support shuttering of post-cast strip according to claim 3, it is characterised in that the jacking is by planar support plate and mandril Composition, one end of the mandril are connected with the bottom of the planar support plate, and the other end of the mandril is sheathed on the supporting rod It is interior.
5. the support shuttering of post-cast strip according to claim 1, it is characterised in that between at least two supporting rod Be smaller than or equal to 1.3m.
CN201721322972.8U 2017-10-13 2017-10-13 A kind of support shuttering of post-cast strip Active CN207332309U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201721322972.8U CN207332309U (en) 2017-10-13 2017-10-13 A kind of support shuttering of post-cast strip

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201721322972.8U CN207332309U (en) 2017-10-13 2017-10-13 A kind of support shuttering of post-cast strip

Publications (1)

Publication Number Publication Date
CN207332309U true CN207332309U (en) 2018-05-08

Family

ID=62368459

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201721322972.8U Active CN207332309U (en) 2017-10-13 2017-10-13 A kind of support shuttering of post-cast strip

Country Status (1)

Country Link
CN (1) CN207332309U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108661313A (en) * 2018-08-15 2018-10-16 哈尔滨学院 A kind of cast-in-place linkage section mould plate supporting device of tool-type concrete folding plate
CN110242040A (en) * 2019-07-08 2019-09-17 中信国安建工集团有限公司 Construction method based on building post-cast strip
CN116201351A (en) * 2023-03-01 2023-06-02 中国建筑第四工程局有限公司 Assembled reinforced concrete post-pouring strip template supporting system

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108661313A (en) * 2018-08-15 2018-10-16 哈尔滨学院 A kind of cast-in-place linkage section mould plate supporting device of tool-type concrete folding plate
CN110242040A (en) * 2019-07-08 2019-09-17 中信国安建工集团有限公司 Construction method based on building post-cast strip
CN116201351A (en) * 2023-03-01 2023-06-02 中国建筑第四工程局有限公司 Assembled reinforced concrete post-pouring strip template supporting system

Similar Documents

Publication Publication Date Title
CN207332309U (en) A kind of support shuttering of post-cast strip
CN207568180U (en) Water stopping thresholds formwork ruggedized construction
CN207419520U (en) Piping lane construction template component
CN209384132U (en) Assembled box culvert template
CN106193588A (en) A kind of method pouring building post-cast strip and pour mould
CN109386050A (en) A kind of multi-layer combined type house structure
CN107419904A (en) Chute mounting structure for concrete column pouring and using method thereof
CN206233566U (en) It is a kind of early to tear method alter-pouring strips mould plate supporting construction open
CN209163440U (en) A kind of easy-to-dismount late poured band support reinforcing construction
CN210685393U (en) Eave cantilever concrete structure formwork support
CN105178593B (en) Fill the mold method and structure of wall construction post
CN209652990U (en) The antiseepage plugging structure of the hole for hoist of basement computer room
CN207686280U (en) A kind of aluminum alloy mould plate early dismantling head device that assortable full hall scaffold uses
CN206070404U (en) Oblique formwork support structure at the section haunch of box culvert top
CN109025262A (en) A kind of molding construction method of concrete flanging one-time-concreting
CN205976472U (en) Pour mould of building post -cast strip
CN109610679A (en) A kind of 3D printing wall and processing method for going along with sb. to guard him constructional column with embedded type
CN207846677U (en) The ductility connecting structure of first floor vertical member and basement roof
CN208633518U (en) Prestressed concrete laminated floor slab hangs mould pouring construction structure
CN205876346U (en) Integral template of pouring of tunnel invert and short side wall
CN106481082A (en) A kind of improvement casting method of constructional column
CN207538506U (en) The independent supporting rack of efficient construction of precast floorslab
CN2097869U (en) Outer wall insulating compound shuttering
CN202164555U (en) Bottom support of concrete box culvert template bracket post
CN207727997U (en) Concrete floor slab placement construction frame body platform structure for building construction

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20200610

Address after: 350000 Fujian Fuzhou high tech Zone Haixi science and Technology East Road universal R & D center 8 layers

Patentee after: CHINALCO NANPING ALUMINIUM (FUJIAN) ALUMINUM STRUCTURE TECHNOLOGY DEVELOPMENT Co.,Ltd.

Address before: Nanping City, Fujian province 353099 Yanping District Industrial Road No. 91

Patentee before: FUJIAN NANLYU ALUMINUM MOLD TECHNOLOGY Co.,Ltd.

CP01 Change in the name or title of a patent holder
CP01 Change in the name or title of a patent holder

Address after: 350000 8 / F, universal R & D center, science and Technology East Road, haixiyuan, high tech Zone, Fuzhou City, Fujian Province

Patentee after: Fujian Southern Aluminum Structure Technology Co.,Ltd.

Address before: 350000 8 / F, universal R & D center, science and Technology East Road, haixiyuan, high tech Zone, Fuzhou City, Fujian Province

Patentee before: CHINALCO NANPING ALUMINIUM (FUJIAN) ALUMINUM STRUCTURE TECHNOLOGY DEVELOPMENT Co.,Ltd.