CN207316236U - A kind of Novel pipe clamp combination - Google Patents
A kind of Novel pipe clamp combination Download PDFInfo
- Publication number
- CN207316236U CN207316236U CN201721254861.8U CN201721254861U CN207316236U CN 207316236 U CN207316236 U CN 207316236U CN 201721254861 U CN201721254861 U CN 201721254861U CN 207316236 U CN207316236 U CN 207316236U
- Authority
- CN
- China
- Prior art keywords
- pipe clamp
- connecting rod
- head rod
- rod
- hole
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Abstract
The utility model discloses a kind of combination of Novel pipe clamp, including the first pipe clamp, the second pipe clamp, head rod and the second connecting rod, first pipe clamp and the second pipe clamp are C-shaped configuration, head rod is connected with the first pipe clamp, second connecting rod is detachably connected with the second pipe clamp, head rod is hollow structure, second connecting rod is set in head rod away from one end of the second pipe clamp, the outside diameter of second connecting rod is less than the internal diameter of head rod, and head rod is detachably connected with the second connecting rod;The Novel pipe clamp combination of the utility model, by adjusting head rod and the second connecting rod relative distance and the second pipe clamp relative to the second connecting rod angle, it can realize the distance of the first pipe clamp and the second pipe clamp and the change of relative angle, it can not only realize the change of the centre distance of different pipelines, the opposite trend of different pipelines can also be adjusted, can be adapted for more various and complicated pipeline.
Description
Technical field
The mounting technique field of automobile pipeline is the utility model is related to, particularly a kind of Novel pipe clamp combination.
Background technology
The widely used nylon tube of automobile and rubber pipeline transmit the materials such as vacuum, fuel oil or cooling water, are especially sending out
The numerous and diverse position staggeredly of this various pipelines in motivation cabin position.The position of the respective connector of these pipelines is different, often alternately exists
Together.
In order to prevent each pipeline interfere or because the collision with its Surrounding Parts and caused by wear, it is general at present
Combined using the pipe clamp of the pipe clamp including 2 relative distances and angle fixation and constrain pipeline, to the oil circuit in cabin, water route,
Circuit is fixed or isolates, but since the arrangement of each vehicle is different, it is necessary to the relative distance of the pipe clamp in pipe clamp combination
It is also different with angle, therefore arranged for different pipelines and be required for developing new pipe clamp combination, cause exploitation frequent, in cost
Rise.
The Novel pipe clamp for designing a kind of adjustable pipe clamp relative distance and angle is thus needed to combine, to avoid pipeline from doing
Relate to, while adjacent tubes distance can be adjusted within the specific limits.
Utility model content
The purpose of this utility model is to provide a kind of Novel pipe clamp combination, to solve in pipe clamp combination of the prior art
The technical problem that the relative distance and angle of pipe clamp can not adjust, it can adjust the relative distance and angle of pipe clamp, adapt to compared with
For complicated and various pipeline.
To achieve these goals, the utility model provides following technical solution:
A kind of Novel pipe clamp combination, including the first pipe clamp, the second pipe clamp, head rod and the second connecting rod;Described
One pipe clamp and second pipe clamp are C-shaped configuration, and the head rod is connected with first pipe clamp, second connection
Bar is detachably connected with second pipe clamp;The head rod is hollow structure, and second connecting rod is away from described the
One end of two pipe clamps is set in the head rod, and the outside diameter of second connecting rod is less than the interior of the head rod
Footpath, the head rod are detachably connected with second connecting rod.
Preferably, second connecting rod is equipped with external screw thread, the inner wall of the head rod be equipped with it is described outer
The matched internal thread of screw thread, the head rod are coordinated with second connecting rod by the internal thread and the external screw thread
Connection.
Preferably, second pipe clamp is equipped with convex portion, and the end of second connecting rod opens up fluted, the convex portion
It is contained in the groove and is interference fitted with the groove.
Preferably, the convex portion includes tapering and column structure, and the tapering is equipped with first conical surface in end, in the cone
Portion and the confluce of the column structure are equipped with second conical surface, and the diameter of first conical surface is less than the straight of second conical surface
Footpath, the opening of the groove is equipped with barb, when the convex portion is contained in the groove, the end of the barb and described the
Two conical surfaces abut.
Preferably, pin is further included, the head rod is equipped with first through hole, and the first through hole extends transversely through described
Head rod, second connecting rod are provided in the axial direction with the second through hole, and second through hole extends transversely through described second and connects
Extension bar, the pin connect the head rod through the first through hole and second through hole and are connected with described second
Bar.
Preferably, first pipe clamp is identical with the structure of second pipe clamp.
The beneficial effects of the utility model are:
The utility model provides a kind of combination of Novel pipe clamp, including the first pipe clamp, the second pipe clamp, head rod and the
Two connecting rods, first pipe clamp and second pipe clamp are C-shaped configuration, and the head rod connects with first pipe clamp
Connect, second connecting rod is detachably connected with second pipe clamp, and the head rod is hollow structure, and described second connects
Extension bar is set in the head rod away from one end of second pipe clamp, and the outside diameter of second connecting rod is less than described
The internal diameter of head rod, the head rod are detachably connected with second connecting rod;The New pipe of the utility model
Folder combination, by adjusting head rod and the second connecting rod relative distance and the second pipe clamp relative to the second connecting rod
Angle, it is possible to achieve the change of the relative distance and angle of the first pipe clamp and the second pipe clamp, compared with prior art, this practicality
The change of the new centre distance that can not only realize different pipelines, moreover it is possible to adjust the opposite trend of different pipelines, can be applicable in
It is stronger in more various and complicated pipeline, adaptability.
Brief description of the drawings
Fig. 1 is the first stereogram of the Novel pipe clamp combination of the utility model embodiment;
Fig. 2 is the second stereogram of the Novel pipe clamp combination of the utility model embodiment;
Fig. 3 is second connecting rod of the utility model embodiment and the sectional view of the second pipe clamp;
Fig. 4 is second connecting rod of the utility model embodiment and the stereogram of the second pipe clamp;
Fig. 5 is the head rod of the utility model embodiment and the sectional view of the first pipe clamp;
Fig. 6 is the head rod of the utility model embodiment and the stereogram of the first pipe clamp.
Description of reference numerals:
The first pipe clamps of 1-, the second pipe clamps of 2-, 3- head rods, the second connecting rods of 4-, 5- convex portions, 6- grooves, 7- taperings,
8- column structures, 9- barbs.
Embodiment
The embodiment of the utility model is described below in detail, the example of the embodiment is shown in the drawings, wherein from beginning
Same or similar element is represented to same or similar label eventually or there is same or like element.Below by ginseng
The embodiment for examining attached drawing description is exemplary, and is only used for explaining the utility model, and cannot be construed to the utility model
Limitation.
As depicted in figs. 1 and 2, the embodiment of the utility model provides a kind of Novel pipe clamp and combines, including the first pipe clamp 1,
Second pipe clamp 2,3 and second connecting rod 4 of head rod;First pipe clamp 1 and second pipe clamp 2 are C-shaped configuration, institute
State head rod 3 to be connected with first pipe clamp 1, second connecting rod 4 is detachably connected with second pipe clamp 2;Institute
It is hollow structure to state head rod 3, and second connecting rod 4 is set in described first away from one end of second pipe clamp 2
In connecting rod 3, the outside diameter of second connecting rod 4 is less than the internal diameter of the head rod 3, the head rod 3 and institute
The second connecting rod 4 is stated to be detachably connected.The opening of first pipe clamp 1 and second pipe clamp 2 is preferably provided with symmetrically
Arc panel, such a be provided with are beneficial to be oriented to pipeline.As shown in Figure 5 and Figure 6, the first pipe clamp 1 and head rod 3 are preferred
Injection is structure as a whole.
The utility model embodiment Novel pipe clamp combination application method be:First pipeline is interposed in the first pipe clamp 1
In, then the second pipeline is interposed in the second pipe clamp 2, when needing to adjust the centre distance of the first pipeline and the second pipeline,
The length that the second connecting rod 4 is set in head rod 3 is adjusted, then again by the phase of 3 and second connecting rod 4 of head rod
Position is fixed, the new centre distance of such first pipe clamp, 1 and second pipe clamp 2 is just provided with, the first pipeline and
The distance of second pipeline is also changed therewith;When needing to adjust the relative angle of the first pipeline and the second pipeline, by the
Under two pipe clamps 2 are dismantled from the second connecting rod 4, then according to new angle needs, the second pipe clamp 2 is installed on second again and is connected
On extension bar 4, the new relative angle of such first pipe clamp, 1 and second pipe clamp 2, which just adjusts, to be completed, the first pipeline and the second pipeline
Relative angle also changed therewith;From aforesaid operations step, the Novel pipe clamp of the utility model embodiment combines,
It can not only realize the adjustment of the relative distance of the first pipeline and the second pipeline, moreover it is possible to realize the phase of the first pipeline and the second pipeline
Adjustment to trend, thus can be adapted for increasingly complex and polygon pipeline, versatility is stronger.
On the basis of said structure, as shown in Figure 3 and Figure 4, convex portion 5 is preferably provided with second pipe clamp 2, described
The end of two connecting rods 4 opens up fluted 6, and the convex portion 5 is contained in the groove 6 and is interference fitted with the groove 6.The
Two pipe clamps 2 are detachably connected with the second connecting rod 4 by the interference fit of convex portion 5 and groove 6, and structure is relatively simple, into
This is relatively low.
Further, as shown in figure 3, the convex portion 5 preferably includes tapering 7 and column structure 8, the tapering 7 is in end
Equipped with first conical surface, be equipped with second conical surface in the confluce in the tapering 7 and the column structure 8, first conical surface it is straight
Footpath is less than the diameter of second conical surface, and the opening of the groove 6 is equipped with barb 9, and the convex portion 5 is contained in the groove 6
When middle, the end of the barb 9 is abutted with second conical surface.When being abutted in the end of barb 9 with second conical surface, first conical surface
It is preferred that abutted with the bottom surface of groove 6.After being so contained in convex portion 5 in groove 6, groove 6 can be by barb 9 to second conical surface
Active force, prevents convex portion 5 from coming off from groove 6.Certain tapering 7 also has can be with the structure of selected as sphere or hemisphere etc..
Barb 9 is preferably arranged to even number, and the center line relative to groove 6 is symmetrical, is so conducive to second conical surface and obtains more
Uniform active force.
In a specific embodiment, second connecting rod 4 is equipped with external screw thread, the head rod 3 it is interior
Wall is equipped with passes through the interior spiral shell with the matched internal thread of the external screw thread, the head rod 3 with second connecting rod 4
Line and the external screw thread are connected.So when needing to adjust the relative distance of the first pipe clamp 1 and the second pipe clamp 2, it is only necessary to
Precession or back-out from head rod 3 by the second connecting rod 4, adjustment head rod 3 and the second connecting rod 4 engage
Reach, such a structure is relatively simple, and adjustment is got up also more convenient.
In another specific embodiment, the Novel pipe clamp combination of the utility model embodiment further includes pin, described
Head rod 3 is equipped with first through hole, and the first through hole extends transversely through the head rod 3,4 edge of the second connecting rod
The second through hole is axially offered, second through hole extends transversely through second connecting rod 4, and the pin is logical through described first
Hole connects the head rod 3 and second connecting rod 4 with second through hole.First through hole is preferably symmetrically distributed at
The axis both sides of one connecting rod 3, and the first through hole being oppositely arranged is arranged to concentric, and first through hole could be provided as one
It is right, it may be set to be multipair, and the line in the center of circle for the first through hole being oppositely arranged and the axis of head rod 3 hang down
Directly.Second through hole is arranged to multiple, and the center line of the second through hole is vertical with the axis of the second connecting rod 4.First through hole and second
Through hole is preferably arranged to the identical hole of size.So when needing to be adjusted the distance of the first pipe clamp 1 and the second pipe clamp 2,
Coordinated by using the second different through holes with first through hole, and using pin to the second new through hole and first through hole
Combination be fixed.Tune of 3 and second connecting rod 4 of head rod of such a structure to centre distance and relative angle
Whole scope is wider.
In order to reduce cost, easy to produce in enormous quantities, the structure of first pipe clamp 1 and second pipe clamp 2 is preferably
It is identical.Certain first pipe clamp, 1 and second pipe clamp 2 can also be arranged to other specification according to the difference of the diameter of the pipeline folded up,
To adapt to diversified pipeline.
The structure, feature and effect of the utility model are described in detail based on the embodiments shown in the drawings, with
Upper described is only the preferred embodiment of the utility model, but the utility model is to limit practical range shown in drawing, it is every according to
The change that conception according to the utility model is made, or the equivalent embodiment of equivalent variations is revised as, still without departing from specification and figure
When showing covered spirit, it should be within the protection scope of the present utility model.
Claims (6)
- A kind of 1. Novel pipe clamp combination, it is characterised in that including the first pipe clamp (1), the second pipe clamp (2), head rod (3) and Second connecting rod (4);First pipe clamp (1) and second pipe clamp (2) are C-shaped configuration, the head rod (3) and the described first pipe (1) connection is pressed from both sides, second connecting rod (4) is detachably connected with second pipe clamp (2);The head rod (3) is hollow structure, and second connecting rod (4) deviates from an end cap of second pipe clamp (2) It is located in the head rod (3), the outside diameter of second connecting rod (4) is less than the internal diameter of the head rod (3), institute Head rod (3) is stated to be detachably connected with second connecting rod (4).
- 2. Novel pipe clamp combination according to claim 1, it is characterised in that second connecting rod (4) is equipped with outer spiral shell Line, the inner wall of the head rod (3) be equipped with the matched internal thread of the external screw thread, the head rod (3) with Second connecting rod (4) is connected by the internal thread and the external screw thread.
- 3. Novel pipe clamp combination according to claim 1, it is characterised in that second pipe clamp (2) is equipped with convex portion (5), the end of second connecting rod (4) opens up fluted (6), the convex portion (5) be contained in the groove (6) and with institute State groove (6) interference fit.
- 4. Novel pipe clamp combination according to claim 3, it is characterised in that the convex portion (5) includes tapering (7) and column Structure (8), the tapering (7) are equipped with first conical surface in end, in the tapering (7) and the confluce of the column structure (8) Equipped with second conical surface, the diameter of first conical surface is less than the diameter of second conical surface, and the opening of the groove (6) is equipped with Barb (9), when the convex portion (5) is contained in the groove (6), the end of the barb (9) is abutted with second conical surface.
- 5. Novel pipe clamp combination according to claim 1, it is characterised in that further include pin, the head rod (3) Equipped with first through hole, the first through hole extends transversely through the head rod (3), and second connecting rod (4) is opened vertically Equipped with the second through hole, second through hole extends transversely through second connecting rod (4), the pin through the first through hole and Second through hole connects the head rod (3) and second connecting rod (4).
- 6. Novel pipe clamp combination according to claim 1, it is characterised in that first pipe clamp (1) and the described second pipe The structure for pressing from both sides (2) is identical.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201721254861.8U CN207316236U (en) | 2017-09-27 | 2017-09-27 | A kind of Novel pipe clamp combination |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201721254861.8U CN207316236U (en) | 2017-09-27 | 2017-09-27 | A kind of Novel pipe clamp combination |
Publications (1)
Publication Number | Publication Date |
---|---|
CN207316236U true CN207316236U (en) | 2018-05-04 |
Family
ID=62428083
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201721254861.8U Expired - Fee Related CN207316236U (en) | 2017-09-27 | 2017-09-27 | A kind of Novel pipe clamp combination |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN207316236U (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110926001A (en) * | 2018-09-03 | 2020-03-27 | 青岛海尔空调器有限总公司 | Fixing piece of pipe group and air conditioner |
CN113090821A (en) * | 2021-03-22 | 2021-07-09 | 东风汽车集团股份有限公司 | Universal general pipe clamp |
-
2017
- 2017-09-27 CN CN201721254861.8U patent/CN207316236U/en not_active Expired - Fee Related
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110926001A (en) * | 2018-09-03 | 2020-03-27 | 青岛海尔空调器有限总公司 | Fixing piece of pipe group and air conditioner |
CN110926001B (en) * | 2018-09-03 | 2022-06-14 | 青岛海尔空调器有限总公司 | Fixing piece of pipe group and air conditioner |
CN113090821A (en) * | 2021-03-22 | 2021-07-09 | 东风汽车集团股份有限公司 | Universal general pipe clamp |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN207316236U (en) | A kind of Novel pipe clamp combination | |
CN104514935A (en) | Nut, hose nipple and hose connector for fluid hose | |
CN107023120A (en) | Self-locking clamp pipe type reinforcing bar straight-insert joint | |
CN203670379U (en) | Telescopic rod fixed connecting structure | |
CN205781416U (en) | A kind of attachment structure, Pipeline clip and vehicle | |
CN207454993U (en) | A kind of pipeline joint arrangement | |
KR102291871B1 (en) | Ferrule assembly for fitting | |
CN202521094U (en) | Clamping hoop | |
CN205592504U (en) | Biaxial ferrule device for unmanned aerial vehicle | |
CN209458230U (en) | A kind of Novel pipe connector | |
CN110500460B (en) | Tensile hose sealing connector | |
CN202756806U (en) | Fast double-connector device | |
CN206717380U (en) | A kind of double pressure point fixtures | |
CN205154830U (en) | Fixed staple bolt of using of return bend | |
CN206754608U (en) | A kind of adjustable rotary joint | |
CN206861116U (en) | Pipeline extension is plugged into external member | |
CN207522455U (en) | A kind of oil pipe fixes limiting tool | |
CN207213443U (en) | Three-way pipeline connector | |
CN214556659U (en) | Pipe contracting device | |
CN203175680U (en) | Universal type end cap | |
CN204850262U (en) | Adopt adjusting device of polylinker | |
CN207034382U (en) | A kind of adjustable length valve rod | |
CN215635516U (en) | Adjustable conduit connecting device | |
CN214037278U (en) | Positioning clamp for positioning pipe fitting | |
CN106195472A (en) | A kind of fluid integration hollow bolt |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20180504 Termination date: 20200927 |