CN207277657U - A kind of ceiling keel installation structure - Google Patents
A kind of ceiling keel installation structure Download PDFInfo
- Publication number
- CN207277657U CN207277657U CN201721363464.4U CN201721363464U CN207277657U CN 207277657 U CN207277657 U CN 207277657U CN 201721363464 U CN201721363464 U CN 201721363464U CN 207277657 U CN207277657 U CN 207277657U
- Authority
- CN
- China
- Prior art keywords
- shaped hook
- hook plate
- main joist
- installation structure
- keel
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Joining Of Building Structures In Genera (AREA)
Abstract
A kind of ceiling keel installation structure is the utility model is related to, its drip irrigation device:Including one end fix indoors on roof, the sunpender that the other end is mutually assembled with main joist;And, it is assemblied in false keel perpendicular with the main joist on the main joist, on the outer wall of the main joist both sides symmetrical sliding block is connected with along the equal slidingtype of main joist extending direction, L-shaped hook plate is fixed with the sliding block, false keel both sides outer wall offers the through hole to match with the L-shaped hook plate, is connected between the sliding block for driving the sliding block to do relative motion so that the L-shaped hook plate passes through the first spring of the through hole.The keel installation structure of the utility model when in use, can very easily install or remove keel, so as to save the time, improve work efficiency.
Description
Technical field
It the utility model is related to building decoration engineering technology field, more particularly to a kind of ceiling keel installation structure.
Background technology
With the development of decorative engineering furred ceiling technology, indoor suspended ceiling uses keel and gypsum board structure system more, in general, imperial
Bone is hollow strip alloy or plate in itself, is primarily used to support moulding, a kind of construction material of fixed structure, indoors
Using very universal in furred ceiling.
Main joist in use, is typically fixed on the top of Indoor environment by keel by sunpender, and secondary imperial
Bone, is directly anchored on main joist by bolt or screw sometimes, although the mode of this fixation is firm, if work
Journey amount is larger, this mounting means tedious process, can be pretty troublesome, can expend a large amount of manpowers.
Utility model content
To be tied in view of the deficienciess of the prior art, the purpose of this utility model is to provide a kind of installation of ceilings keel
Structure, to solve tedious process, time-consuming and laborious technical problem during keel installation.
The above-mentioned purpose of the utility model technical scheme is that:
A kind of ceiling keel installation structure, including one end fix indoors on roof, the other end mutually assembles with main joist
Sunpender;And false keel perpendicular with the main joist on the main joist is assemblied in, on the outer wall of the main joist both sides
Symmetrical sliding block is connected with along the equal slidingtype of main joist extending direction, L-shaped hook plate, the pair are fixed with the sliding block
Keel both sides outer wall offers the through hole to match with the L-shaped hook plate, is connected between the sliding block described for driving
Sliding block does relative motion so that the L-shaped hook plate passes through the first spring of the through hole.
Using above-mentioned technical proposal, when needing to install false keel, can first sliding slider, drive symmetrical L-shaped hook
Plate is moved to both sides so that false keel may be between symmetrical L-shaped hook plate, by the through-hole alignment L-shaped hook on false keel
The end of plate, unclamps hand, and the first spring can automatically drive L-shaped hook plate relative motion using the restoring force of itself so that L-shaped hook
The end of plate penetrates in through hole and hooks false keel, and at this time, the first spring can drive L-shaped hook plate to be close to the outer wall of false keel, from
And easily false keel can be fixed on main joist, so as to simplify installation procedure, the time is saved, improves work effect
Rate.
The utility model is further set:Some grooves, the groove activity are offered on the outside of the L-shaped hook plate end
Fixture block is equipped with, is equipped with the groove between described fixture block the inner and is used to drive the fixture block to slide along the groove inner wall
Second spring, described fixture block the inner is fixed with the bracing wire for being pierced by the L-shaped hook plate.
Using above-mentioned technical proposal, bracing wire is pulled, fixture block can be driven to be contracted in groove, treat that L-shaped hook plate passes through through hole
Afterwards, after unclamping bracing wire, second spring automatically can drive fixture block to be ejected out of groove so that fixture block can contradict false keel
On inner wall, the situation that false keel rocks shakiness can be thus reduced, further increases the fastness of false keel.
The utility model is further set:The bracing wire end is fixed with draw ring, be fixed with the outside of the L-shaped hook plate with
The hook that the draw ring matches.
Using above-mentioned technical proposal, when needing to pull down false keel, bracing wire can be pulled so that draw ring is with linking up with phase
Match somebody with somebody, so as to keep away this process that manual-free holds bracing wire always;When L-shaped hook plate insertion through hole in after, only need to by draw ring from
Removed on hook, second spring automatically will drive fixture block to be ejected out of groove.
The utility model is further set:The fixture block is equipped with and the through hole edge close to the side of the false keel
The inclined plane being in contact.
Using above-mentioned technical proposal, the inclined plane of setting, when the first spring drives L-shaped hook plate relative motion, fixture block
Inclined plane can be inconsistent with the edge of through hole so that fixture block can be automatically compressed in groove, and it is logical to treat that L-shaped hook plate penetrates completely
After in hole, second spring can drive fixture block automatically to eject, and be drawn in this manner it is possible to save and pulled before the new hook plates of L pass through through hole
This link of line.
The utility model is further set:The symmetrical L-shaped hook plate end is fixed with the magnetic patch to attract each other.
Using above-mentioned technical proposal, after symmetrical L-shaped hook plate passes through through hole, the magnetic patch to attract each other can utilize certainly
The attraction of body so that L-shaped hook plate attracts each other, and thus can further reinforce false keel, fixes it more firm.
The utility model is further set:The main joist movable sleeve is equipped with U-board, and the U-board end is fixed with convex
Block, the sunpender pass through the convex block, and the boom end is threadedly coupled the nut for being useful for clamping the convex block.
Using above-mentioned technical proposal, when needing main joist being fixed on sunpender, U-board first can be set in main dragon
On bone, sunpender is then clamped in the both sides of convex block through the convex block in U-board, then tightening nut so that sunpender holds U-shaped
Plate, so as to very easily sling main joist, this mounting means is easy to operate, can save the time, improves work efficiency.
The utility model is further set:The U-board inboard, upright slidingtype is connected with briquetting, the convex block and institute
State the 3rd spring for being equipped between briquetting and being used for driving the briquetting to be pressed on the false keel.
Using above-mentioned technical proposal, it is necessary to when false keel is installed, briquetting is stirred, makes its compression, false keel is installed on U-shaped
After plate, hand is unclamped, the 3rd spring can automatically drive briquetting to be pressed on false keel, so that false keel be compressed, fix it
It is more firm.
In conclusion the utility model has the advantages that;
, can be first to two Slideslip L when needing fixed false keel by setting L-shaped hook plate, the first spring and through hole
Shape hook plate, makes the end of the through-hole alignment L-shaped hook plate on false keel, and after unclamping hand, the first spring can automatically drive L-shaped hook plate
False keel is fixed on main joist through through hole.
The second spring and fixture block of setting, can be after L-shaped hook plate passes through through hole, and second spring can automatically drive fixture block
Eject out of groove, can be contradicted after fixture block pop-up on the inner wall of false keel, so as to further strengthen the firm of false keel
Property, through the above scheme, Fast Installation and the dismounting of keel just can be very easily realized, so as to improve work efficiency.
Brief description of the drawings
Fig. 1 is the overall structure diagram of the utility model embodiment;
Fig. 2 is the enlarged drawing at A in Fig. 1;
Fig. 3 is the partial sectional view of L-shaped hook plate in the utility model embodiment.
Reference numeral:1st, main joist;11st, sliding block;12nd, L-shaped hook plate;13rd, the first spring;2nd, sunpender;3rd, false keel;31、
Through hole;4th, groove;41st, fixture block;42nd, second spring;43rd, bracing wire;44th, inclined plane;5th, draw ring;51st, link up with;6th, magnetic patch;7th, U-shaped
Plate;71st, convex block;8th, nut;9th, briquetting;10th, the 3rd spring.
Embodiment
The utility model is described in further detail below in conjunction with attached drawing.
This specific embodiment is only explanation to the utility model, it is not the limitation to the utility model, ability
Field technique personnel as needed can make the present embodiment the modification for not creating contribution after this specification is read, but only
All to be protected in the right of the utility model be subject to Patent Law.
The present embodiment:A kind of ceiling keel installation structure, as shown in Figure 1 to Figure 3, including:Room indoors is fixed in one end
On top, the sunpender 2 that the other end is assembled with 1 phase of main joist;And it is assemblied in false keel perpendicular with main joist 1 on main joist 1
3, wherein, slidingtype is connected with symmetrical sliding block 11, and the prolonging along main joist 1 of sliding block 11 on the both sides outer wall of main joist 1
Direction slip is stretched, L-shaped hook plate 12 straight down is fixed with sliding block 11, and the both sides outer wall in false keel 3 offers
The through hole 31 to match with L-shaped hook plate 12 so that the end of L-shaped hook plate 12 may be inserted into through hole 31, in addition, sliding block 11 it
Between be additionally provided with the first spring 13, the end of the first spring 13 is connected with sliding block 11, the first spring 13 be mainly used for drive phase
Symmetrical sliding block 11 does relative motion.
When needing false keel 3 being installed on main joist 1, can first sliding slider 11, drive symmetrical L-shaped hook plate
12 move to both sides so that between symmetrical L-shaped hook plate 12, mobile false keel 3 simultaneously makes on false keel 3 false keel 3
Through hole 31 is directed at the end of L-shaped hook plate 12, waits after the completion of being aligned, and unclamps hand, and the first spring 13 can utilize the restoring force of itself certainly
Dynamic 12 relative motion of driving L-shaped hook plate so that the end of L-shaped hook plate 12 penetrates in through hole 31 and hooks false keel 3, this
When, L-shaped hook plate 12 can be close to the outer wall of false keel 3, pass through above-mentioned mounting means, it is possible to easily fix false keel 3
On main joist 1, so as to simplify installation procedure, the time is saved, improves work efficiency.
Symmetrical groove 4 is further opened with the outside of end of the L-shaped hook plate 12 through through hole 31,4 activity of groove is equipped with
Fixture block 41, and second spring 42 is fixed with 4 bottom wall of groove, the other end of second spring 42 is connected with the inner of fixture block 41,
Bracing wire 43 is further fixed in the inner of fixture block 41, bracing wire 43 is pierced by from the outside of L-shaped hook plate 12.
When needing L-shaped hook plate 12 being inserted into through hole 31, bracing wire 43 can be pulled, drives fixture block 41 to be contracted to groove 4
It is interior, after L-shaped hook plate 12 is interior through through hole 31, bracing wire 43 is unclamped, second spring 42 can automatically drive fixture block 41 out of groove 4
Pop-up so that fixture block 41 is contradicted on the inner wall of false keel 3, so as to further strengthen the stability of false keel 3, is reduced secondary
The situation that keel 3 rock.
Draw ring 5 is further fixed in the end that is pierced by of bracing wire 43, and is fixed with the outside of L-shaped hook plate 12 and 5 phase of draw ring
The hook 51 matched somebody with somebody, in addition, fixture block 41 is provided with the inclined plane 44 touched with 31 side edge of through hole close to the side of false keel 3.
When without using L-shaped hook plate 12, hook 51 hooks draw ring 5, when needing to use L-shaped hook plate 12, in through hole 31
After the end alignment of L-shaped hook plate 12, draw ring 5 can be taken away from hook 51, the first spring 13 will automatically drive L-shaped
In the end insertion through hole 31 of hook plate 12, during L-shaped hook plate 12 moves, the inclined plane 44 on fixture block 41 can be with through hole 31
Edge it is inconsistent so that fixture block 44 can be automatically compressed in groove 4, after L-shaped hook plate 12 passes completely through through hole 31,
Two springs 42 will automatically drive fixture block 41 to eject out of groove 4 and contradict on the inner wall of false keel 3, so as into one
Step reinforces the stability of false keel 3.
In addition, being further fixed on the magnetic patch 6 to attract each other in the end of L-shaped hook plate 12, passed through in symmetrical L-shaped hook plate 12
After through hole 31, the magnetic patch 6 to attract each other can utilize the attraction of itself so that L-shaped hook plate 12 attracts each other, so as into
One step reinforces false keel 3, fixes it more firm.
Wherein, movable sleeve is equipped with U-board 7 on main joist 1, and the upper end of U-board 7 is fixed with convex block 71, and sunpender 2 can be with
End thread through convex block 71, and sunpender 2 is connected with symmetrical nut 8;And the inboard, upright slidingtype in U-board 7 connects
Briquetting 9 is connected to, is further fixed on the 3rd spring 10 at the top of briquetting 9, one end of the 3rd spring 10 is fixed on convex block 71.
When needing main joist 1 being installed on sunpender 2, it can first slide and compress briquetting 9, then U-board 7 is set in
On main joist 1, hand is unclamped, the 3rd spring 10 can automatically driving briquetting 9 be pressed on main joist 1, so as to further carry
The fastness that high main joist 1 is installed;Then one of nut 8 is first threaded in the end of sunpender 2, then sunpender 2 is worn
Convex block 71 is crossed, remaining nut 8 is threaded onto to the end of sunpender 2, passes through the clamping of two nuts 8, it is possible to firmly will very much
Main joist 1 is fixed on sunpender 2, so as to save the time, improves the whole efficiency of installation.
Claims (7)
- A kind of 1. ceiling keel installation structure, it is characterised in that including:One end fix indoors on roof, the other end and master Keel(1)The mutually sunpender of assembling(2);And it is assemblied in the main joist(1)The upper and main joist(1)Perpendicular pair dragon Bone(3), the main joist(1)Along the main joist on the outer wall of both sides(1)The equal slidingtype of extending direction is connected with symmetrical cunning Block(11), the sliding block(11)On be fixed with L-shaped hook plate(12), the false keel(3)Both sides outer wall offers and the L-shaped Hook plate(12)The through hole to match(31), the sliding block(11)Between be connected with for driving the sliding block(11)Do relative motion So that the L-shaped hook plate(12)Through the through hole(31)The first spring(13).
- A kind of 2. ceiling keel installation structure according to claim 1, it is characterised in that the L-shaped hook plate(12)End Some grooves are offered on the outside of portion(4), the groove(4)Activity is equipped with fixture block(41), the groove(4)The interior and fixture block (41)It is equipped between the inner and is used to drive the fixture block(41)Along the groove(4)The second spring that inner wall slides(42), it is described Fixture block(41)The inner, which is fixed with, is pierced by the L-shaped hook plate(12)Bracing wire(43).
- A kind of 3. ceiling keel installation structure according to claim 2, it is characterised in that the bracing wire(43)End is consolidated Surely there is draw ring(5), the L-shaped hook plate(12)Outside is fixed with and the draw ring(5)The hook to match(51).
- A kind of 4. ceiling keel installation structure according to claim 2, it is characterised in that the fixture block(41)Close to institute State false keel(3)Side be equipped with and the through hole(31)The inclined plane that side edge is touched(44).
- A kind of 5. ceiling keel installation structure according to claim 3, it is characterised in that the symmetrical L-shaped hook Plate (12) end is fixed with the magnetic patch to attract each other(6).
- A kind of 6. ceiling keel installation structure according to claim 1, it is characterised in that the main joist(1)Activity It is arranged with U-board(7), the U-board(7)End is fixed with convex block(71), the sunpender(2)Through the convex block(71), institute State sunpender(2)End thread is connected with for clamping the convex block(71)Nut(8).
- A kind of 7. ceiling keel installation structure according to claim 6, it is characterised in that the U-board(7)Medial shaft Straight slidingtype is connected with briquetting(9), the convex block(71)With the briquetting(9)Between be equipped be used for drive the briquetting(9)Support It is pressed in the false keel(3)On the 3rd spring(10).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201721363464.4U CN207277657U (en) | 2017-10-20 | 2017-10-20 | A kind of ceiling keel installation structure |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201721363464.4U CN207277657U (en) | 2017-10-20 | 2017-10-20 | A kind of ceiling keel installation structure |
Publications (1)
Publication Number | Publication Date |
---|---|
CN207277657U true CN207277657U (en) | 2018-04-27 |
Family
ID=61981052
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201721363464.4U Expired - Fee Related CN207277657U (en) | 2017-10-20 | 2017-10-20 | A kind of ceiling keel installation structure |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN207277657U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110439169A (en) * | 2019-08-20 | 2019-11-12 | 浙江天元十杰装饰股份有限公司 | A kind of Thistle board ceiling construction process |
-
2017
- 2017-10-20 CN CN201721363464.4U patent/CN207277657U/en not_active Expired - Fee Related
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110439169A (en) * | 2019-08-20 | 2019-11-12 | 浙江天元十杰装饰股份有限公司 | A kind of Thistle board ceiling construction process |
CN110439169B (en) * | 2019-08-20 | 2020-10-27 | 浙江天元十杰装饰股份有限公司 | Construction process of gypsum plaster board ceiling |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN207277657U (en) | A kind of ceiling keel installation structure | |
CN112593656A (en) | Suspended ceiling assembling structure of hardcover room | |
CN112392194A (en) | Quick joint structure of assembled furred ceiling fossil fragments | |
CN110306713A (en) | A kind of decorative ceiling structure and its construction method | |
CN207211480U (en) | Corridor ceiling system | |
CN207582782U (en) | A kind of keel installation structure | |
CN206174265U (en) | A furred ceiling fixing device for gypsum board | |
CN108708493A (en) | A kind of hanging grid of entirety | |
CN207647002U (en) | A kind of ceiling combination mounting structure | |
CN202990346U (en) | Fastener for external wall decorating panel | |
CN204225335U (en) | A kind of aluminium alloys ceiling system | |
CN212866445U (en) | Plugging device for indoor decorative wall and veneer | |
CN212026806U (en) | Ceiling assembly capable of preventing abnormal sound | |
CN206299019U (en) | A kind of large span ceiling decoration board mounting structure | |
CN209703816U (en) | A kind of large span screen aluminum alloy structure | |
CN207228536U (en) | A kind of dry-hanging installation structure for vertical faces of stone materials | |
CN205917951U (en) | Light trough furred ceiling falls a grade device | |
CN114319768B (en) | Environment-friendly dry-hanging structure for decorative veneer and mounting method | |
CN205421668U (en) | Keel hanging piece | |
CN208983283U (en) | A kind of mounting structure for annular roof lamp | |
CN215107060U (en) | Indoor decoration line board auxiliary fixture | |
CN206016033U (en) | Adjustable lifting is held court from behind a screen variola | |
CN206800721U (en) | A kind of light steel wall surface keel of c-type for being easy to freely dismantle | |
CN117513641B (en) | Suspended ceiling installation structure and method for interior decoration | |
CN220580313U (en) | Indoor furred ceiling aluminium veneer structure convenient to dismantle |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20180427 Termination date: 20191020 |