CN207259100U CN201721059544.0U CN201721059544U CN207259100U CN 207259100 U CN207259100 U CN 207259100U CN 201721059544 U CN201721059544 U CN 201721059544U CN 207259100 U CN207259100 U CN 207259100U
Authority
CN
China
Prior art keywords
plate
motor
reel
bracing wire
bottom plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201721059544.0U
Other languages
Chinese (zh)
Inventor
李德杰
尹彪
李兆宇
杨开毅
刘占强
徐道近
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Yunnan Jian Jian Fourth Construction Co Ltd
Original Assignee
Yunnan Jian Jian Fourth Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Yunnan Jian Jian Fourth Construction Co Ltd filed Critical Yunnan Jian Jian Fourth Construction Co Ltd
Priority to CN201721059544.0U priority Critical patent/CN207259100U/en
Application granted granted Critical
Publication of CN207259100U publication Critical patent/CN207259100U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

It the utility model is related to a kind of maintenance of equipment, more particularly to a kind of constructing tunnel tunnel top maintenance of equipment.The technical problem to be solved by the present invention is to provide a kind of suitable constructing tunnel, the constructing tunnel tunnel top maintenance of equipment that convenient and efficient, operating efficiency is high.In order to solve the above-mentioned technical problem, the utility model provides such a constructing tunnel tunnel top maintenance of equipment, includes bottom plate, side plate, supporting rod, wheel, elevating mechanism, operation post, adjoint mechanism, hanging ring, the first bracing wire, hook, tool box etc.;The bottom of bottom plate is provided with supporting rod, and supporting rod bottom is equipped with wheel, and the top both ends of bottom plate are equipped with side plate, and the madial wall of side plate is provided with elevating mechanism, operation post is provided with the top of elevating mechanism.The utility model has reached suitable constructing tunnel, the effect for the constructing tunnel tunnel top maintenance of equipment that convenient and efficient, operating efficiency is high by elevating mechanism and the mutual cooperation with mechanism.

Description

A kind of constructing tunnel tunnel top maintenance of equipment
Technical field
It the utility model is related to a kind of maintenance of equipment, more particularly to a kind of constructing tunnel tunnel top maintenance of equipment.
Background technology
Constructing tunnel, is the abbreviation of new Austrian method for tunnel construction, it is that Austrian scholar applies in long campaigns tunnel In work practice, a kind of rational construction method of proposition from the viewpoint of rock mechanics, is using spray anchor technology, monitoring parameter Survey etc. and with a system that rock mechanics theory is formed and a kind of new engineering construction method for being formed.
When the facility that worker carries out certain construction or carry out in tunnel to the top in tunnel is safeguarded, due to tunnel The particularity of framework, common maintenance facility can not well adapt to its working environment, thus worker maintenance when there is The problem of operating space is inconvenient, equipment can not work normally, operating efficiency is low, therefore applied there is an urgent need for researching and developing a kind of suitable tunnel Work, the constructing tunnel tunnel top maintenance of equipment that convenient and efficient, operating efficiency is high.
Utility model content
(1)Technical problems to be solved
The utility model in order to overcome worker in maintenance there is operating space is inconvenient, equipment can not work normally, The shortcomings that operating efficiency is low, the technical problem to be solved by the present invention is to provide a kind of suitable constructing tunnel, convenient and efficient, work Industry efficient constructing tunnel tunnel top maintenance of equipment.
(2)Technical solution
In order to solve the above-mentioned technical problem, the utility model provides such a constructing tunnel tunnel top maintenance and sets It is standby, include bottom plate, side plate, supporting rod, wheel, elevating mechanism, operation post, adjoint mechanism, hanging ring, the first bracing wire, hook, work Tool case, the second bracing wire and draw ring, the bottom of bottom plate are provided with supporting rod, and supporting rod bottom is equipped with wheel, the top both ends of bottom plate Equipped with side plate, the madial wall of side plate is provided with elevating mechanism, is provided with operation post at the top of elevating mechanism, operation post and bottom plate It is provided between top and is equipped with hanging ring with mechanism, the bottom centre of operation post, the first bracing wire is wound with hanging ring, the first bracing wire Tail end is connected with hook, and hook is arranged right below tool box, is connected with the second bracing wire on four angles at the top of tool box, and second The tail end of bracing wire is wound on draw ring, is hung on draw ring.
Preferably, elevating mechanism includes the first motor, swingle, first bevel gear, second bevel gear, clutch shaft bearing Seat, screw rod, nut and second bearing seat, the bottom right end of bottom plate are provided with the first motor, and it is logical that first is provided with the middle part of supporting rod Hole, is equipped with the output axis connection of swingle, the right end of swingle and the first motor in first through hole, the swingle two in supporting rod Side is mounted on first bevel gear, and bottom plate on the inside of side plate link position with being mounted on first bearing seat, the medial roof of side plate Portion is mounted on second bearing seat, and for first bearing seat with being mounted on screw rod in second bearing seat, the bottom of screw rod passes through bottom plate And be mounted on second bevel gear, second bevel gear is engaged with first bevel gear, is provided with nut on screw rod, the top of nut with The bottom of operation post is connected.
Preferably, with mechanism include the second motor, the first reel, steel wire rope, N-type slide bar, with plate, spring, Contact block, button, guide sleeve and first gear, the centre at the top of bottom plate are provided with the second motor, connect on the output shaft of the second motor It is connected on the bottom plate of first gear, the second motor or so both sides and the first reel is installed, the right side of the first reel also connects Have a first gear, the first gear on the second motor is engaged with the first gear on the first reel, on the first reel around There is steel wire rope, the bottom of operation post is connected with N-type slide bar, and N-type slide bar is equipped with plate, is provided with the left and right ends of plate Second through hole, the second through hole cooperate with N-type slide bar, and the bottom of N-type slide bar is provided with third through-hole, and the tail end of steel wire rope passes through Third through-hole is simultaneously connected with the bottom of plate, with spring is connected between plate and N-type slide bar, is set with the centre of plate bottom There is a contact block, button is installed on the N-type slide bar immediately below contact block, button has circuit to be connected with the second motor, behind tool box Guide sleeve, steel wire penetrating guide sleeve are respectively connected with left and right sides of side.
Preferably, further included and drawn high device, side plate draws high device with being provided with the top of adjoint mechanism, draws high device bag Included the 3rd bracing wire, montant and electronic reel, be connected with montant at the top of side plate, the top right side of montant be provided with it is electronic around Line wheel, is wound with the 3rd bracing wire on electronic reel, the tail end of the 3rd bracing wire is connected with tool box.
Preferably, babinet has been further included, babinet is installed at the top of the second motor and reel, is provided with the top of babinet Four through holes, the steel wire penetrating fourth hole being wound with the first reel.
Operation principle:When construction personnel needs to carry out maintenance the equipment of tunnel top, required instrument will be first repaired In inserter case, construction personnel stands on operation post, while starts elevating mechanism and carry out height to operation post with mechanism Adjust, allow construction personnel to be in suitable working depth, when starting maintenance, pull with hand the first bracing wire, the first bracing wire, which drives, hangs Hook moves up, and due to hanging on draw ring, draw ring is connected with the second bracing wire again, and the second bracing wire is connected with tool box, so Hook tape power driven tools case moves up, and after tool box is moved upward to certain position, construction personnel will place in tool box Instrument take out, carry out maintenance operation.
Because elevating mechanism includes the first motor, swingle, first bevel gear, second bevel gear, first bearing seat, spiral shell Bar, nut and second bearing seat, the bottom right end of bottom plate are provided with the first motor, first through hole are provided with the middle part of supporting rod, the It is equipped with the output axis connection of swingle, the right end of swingle and the first motor in one through hole, the swingle both sides in supporting rod are equal First bevel gear is installed, for bottom plate with being mounted on first bearing seat on the inside of side plate link position, the inside top of side plate is equal Second bearing seat is installed, first bearing seat is with being mounted on screw rod in second bearing seat, the bottom of screw rod is through bottom plate and equal Second bevel gear is installed, second bevel gear is engaged with first bevel gear, and nut, the top of nut and operation are provided with screw rod The bottom of platform is connected.When worker station is after on operation post, while start the first motor and with mechanism, the first motor drives rotation Bull stick rotates, and swingle rotation drives first bevel gear to rotate, and since first bevel gear is engaged with second bevel gear, first bores tooth Wheel, which rotates, drives second bevel gear to rotate, and second bevel gear, which rotates, drives screw rod to turn in first bearing seat and second bearing seat Dynamic, screw rod, which rotates, drives nut to move up and down, and nut, which moves up and down, drives operation post to move up and down, at the same time, with mechanism Coordinating operation platform moves up and down and makes corresponding adjusting, both cooperate, so as to allow construction personnel to be in suitable construction Position.
Because include the second motor, the first reel, steel wire rope, N-type slide bar, adjoint plate, spring, contact with mechanism Block, button, guide sleeve and first gear, the centre at the top of bottom plate are provided with the second motor, are connected with the output shaft of the second motor First reel is installed, the right side of the first reel is also connected with the bottom plate of first gear, the second motor or so both sides One gear, the first gear on the second motor are engaged with the first gear on the first reel, and steel is wound with the first reel Cord, the bottom of operation post are connected with N-type slide bar, and N-type slide bar is equipped with plate, and second is provided with the left and right ends of plate Through hole, the second through hole cooperate with N-type slide bar, and the bottom of N-type slide bar is provided with third through-hole, and the tail end of steel wire rope passes through the 3rd Through hole is simultaneously connected with the bottom of plate, with spring is connected between plate and N-type slide bar, is equipped with and is connect with the centre of plate bottom Contact block, is provided with button on the N-type slide bar immediately below contact block, button has circuit to be connected with the second motor, tool box trailing flank The left and right sides be respectively connected with guide sleeve, steel wire penetrating guide sleeve.When startup lifting gear is adjusted up workbench, together The second motors of Shi Qidong drive the first reel to put steel wire rope, when needing lifting gear to adjust workbench downwards, open Dynamic second motor drives the first reel to receive steel wire rope, reaches the mesh for allowing workbench to move up and down by cooperation between the two , after movable workbench is to suitable position, elevating mechanism and the second motor are closed, then restart the second motor and drive first Reel receives steel wire rope, and steel wire rope, which is pulled, to be moved down along N-type slide bar with plate, moved down with plate drive contact block to Lower movement, when contact block is pressed into button, since button with the second motor has circuit to be connected, so the second motor is closed, the One reel stops receiving steel wire rope, and steel wire rope is now in tensioned state, can pull with hand the first bracing wire at this time, and tool box leads to Cross guide sleeve to move up along steel wire rope, can so ensure the stability that tool box moves up or down, avoid in tool box Rollover causes instrument to drop, and improves the security of operation indirectly.
Device is drawn high because having further included, side plate draws high device with being provided with the top of adjoint mechanism, and drawing high device includes There are the 3rd bracing wire, montant and electronic reel, montant is connected with the top of side plate, the top right side of montant is provided with electronic coiling Take turns, be wound with the 3rd bracing wire on electronic reel, the tail end of the 3rd bracing wire is connected with tool box.When construction personnel adjusts oneself After working space, start electronic reel and receive the 3rd bracing wire, the 3rd bracing wire drives tool box to move up, when tool box is moved to During suitable position, electronic reel is closed, construction personnel takes out instrument out of tool box and constructs to tunnel top.
Because having further included babinet, babinet is installed at the top of the second motor and reel, the 4th is provided with the top of babinet Through hole, the steel wire penetrating fourth hole being wound with the first reel.Babinet covers gear and reel, protects constructor The safety of member, while also improve the working life of the second motor and reel.
(3)Beneficial effect
Construction personnel is maintained suitable construction by the utility model by elevating mechanism and the mutual cooperation with mechanism Position, and tunnel top is carried out maintenance by construction personnel, reach suitable constructing tunnel, convenient and efficient, operating efficiency is high The effect of constructing tunnel tunnel top maintenance of equipment.
Brief description of the drawings
Fig. 1 is the first main structure diagram of the utility model.
Fig. 2 is second of main structure diagram of the utility model.
Fig. 3 is main structure diagram of the utility model with mechanism.
Fig. 4 is the left view structural representation of the utility model.
Fig. 5 is the third main structure diagram of the utility model.
Mark in attached drawing for:1- bottom plates, 2- side plates, 3- supporting rods, 4- wheels, 5- elevating mechanisms, the first motors of 51-, 52- swingles, 53- first through hole, 54- first bevel gears, 55- second bevel gears, 56- first bearing seats, 57- screw rods, 58- spiral shells Mother, 59- second bearing seats, 6- operation posts, 7- is with mechanism, the second motors of 701-, the first reels of 702-, 703- steel wire ropes, 704-N type slide bars, 705- are pressed with plate, the second through holes of 706-, 707- third through-holes, 708- springs, 709- contact blocks, 710- Button, 711- guide sleeves, 712- first gears, 8- hanging rings, the first bracing wires of 9-, 10- hooks, 11- tool boxes, the second bracing wires of 12-, 13- Draw ring, 14- draw high device, the 3rd bracing wires of 141-, 142- montants, the electronic reels of 143-, 15- babinets, 16- fourth holes.
Embodiment
The utility model is further described with reference to the accompanying drawings and examples.
Embodiment 1
A kind of constructing tunnel tunnel top maintenance of equipment, as shown in Figs. 1-5, include bottom plate 1, side plate 2, supporting rod 3, Wheel 4, elevating mechanism 5, operation post 6, adjoint mechanism 7, hanging ring 8, the first bracing wire 9, hook 10, tool box 11, the second bracing wire 12 With draw ring 13, the bottom of bottom plate 1 is provided with supporting rod 3, and 3 bottom of supporting rod is equipped with wheel 4, and the top both ends of bottom plate 1 are equipped with side Plate 2, the madial wall of side plate 2 are provided with elevating mechanism 5, and the top of elevating mechanism 5 is provided with operation post 6, operation post 6 and bottom plate 1 Top between be provided with mechanism 7, be equipped with hanging ring 8 among the bottom of operation post 6, the first bracing wire 9 be wound with hanging ring 8, the The tail end of one bracing wire 9 is connected with hook 10, links up with 10 and is arranged right below tool box 11, connects on four angles at the top of tool box 11 The second bracing wire 12 is connected to, the tail end of the second bracing wire 12 is wound on draw ring 13, and hook 10 is hung on draw ring 13.
Embodiment 2
A kind of constructing tunnel tunnel top maintenance of equipment, as shown in Figs. 1-5, include bottom plate 1, side plate 2, supporting rod 3, Wheel 4, elevating mechanism 5, operation post 6, adjoint mechanism 7, hanging ring 8, the first bracing wire 9, hook 10, tool box 11, the second bracing wire 12 With draw ring 13, the bottom of bottom plate 1 is provided with supporting rod 3, and 3 bottom of supporting rod is equipped with wheel 4, and the top both ends of bottom plate 1 are equipped with side Plate 2, the madial wall of side plate 2 are provided with elevating mechanism 5, and the top of elevating mechanism 5 is provided with operation post 6, operation post 6 and bottom plate 1 Top between be provided with mechanism 7, be equipped with hanging ring 8 among the bottom of operation post 6, the first bracing wire 9 be wound with hanging ring 8, the The tail end of one bracing wire 9 is connected with hook 10, links up with 10 and is arranged right below tool box 11, connects on four angles at the top of tool box 11 The second bracing wire 12 is connected to, the tail end of the second bracing wire 12 is wound on draw ring 13, and hook 10 is hung on draw ring 13.
Elevating mechanism 5 includes the first motor 51, swingle 52, first bevel gear 54, second bevel gear 55, clutch shaft bearing Seat 56, screw rod 57, nut 58 and second bearing seat 59, the bottom right end of bottom plate 1 are provided with the first motor 51, in supporting rod 3 Portion is provided with first through hole 53, and the output shaft of swingle 52, the right end of swingle 52 and the first motor 51 is equipped with first through hole 53 Connect, 52 both sides of swingle in supporting rod 3 are mounted on first bevel gear 54, and bottom plate 1 and the inner side of 2 link position of side plate are equal First bearing seat 56 is installed, the inside top of side plate 2 is mounted on second bearing seat 59, first bearing seat 56 and second bearing Screw rod 57 is mounted in seat 59, the bottom of screw rod 57 through bottom plate 1 and is mounted on second bevel gear 55, second bevel gear 55 Engaged with first bevel gear 54, nut 58 is installed on screw rod 57, the top of nut 58 is connected with the bottom of operation post 6.
Embodiment 3
A kind of constructing tunnel tunnel top maintenance of equipment, as shown in Figs. 1-5, include bottom plate 1, side plate 2, supporting rod 3, Wheel 4, elevating mechanism 5, operation post 6, adjoint mechanism 7, hanging ring 8, the first bracing wire 9, hook 10, tool box 11, the second bracing wire 12 With draw ring 13, the bottom of bottom plate 1 is provided with supporting rod 3, and 3 bottom of supporting rod is equipped with wheel 4, and the top both ends of bottom plate 1 are equipped with side Plate 2, the madial wall of side plate 2 are provided with elevating mechanism 5, and the top of elevating mechanism 5 is provided with operation post 6, operation post 6 and bottom plate 1 Top between be provided with mechanism 7, be equipped with hanging ring 8 among the bottom of operation post 6, the first bracing wire 9 be wound with hanging ring 8, the The tail end of one bracing wire 9 is connected with hook 10, links up with 10 and is arranged right below tool box 11, connects on four angles at the top of tool box 11 The second bracing wire 12 is connected to, the tail end of the second bracing wire 12 is wound on draw ring 13, and hook 10 is hung on draw ring 13.
Elevating mechanism 5 includes the first motor 51, swingle 52, first bevel gear 54, second bevel gear 55, clutch shaft bearing Seat 56, screw rod 57, nut 58 and second bearing seat 59, the bottom right end of bottom plate 1 are provided with the first motor 51, in supporting rod 3 Portion is provided with first through hole 53, and the output shaft of swingle 52, the right end of swingle 52 and the first motor 51 is equipped with first through hole 53 Connect, 52 both sides of swingle in supporting rod 3 are mounted on first bevel gear 54, and bottom plate 1 and the inner side of 2 link position of side plate are equal First bearing seat 56 is installed, the inside top of side plate 2 is mounted on second bearing seat 59, first bearing seat 56 and second bearing Screw rod 57 is mounted in seat 59, the bottom of screw rod 57 through bottom plate 1 and is mounted on second bevel gear 55, second bevel gear 55 Engaged with first bevel gear 54, nut 58 is installed on screw rod 57, the top of nut 58 is connected with the bottom of operation post 6.
Include the second motor 701, the first reel 702, steel wire rope 703, N-type slide bar 704, adjoint plate with mechanism 7 705th, spring 708, contact block 709, button 710, guide sleeve 711 and first gear 712, the centre at the top of bottom plate 1 are provided with second Motor 701, is connected with first gear 712 on the output shaft of the second motor 701, pacifies on the bottom plate 1 of 701 or so both sides of the second motor Equipped with the first reel 702, the right side of the first reel 702 is also connected with first gear 712, and first on the second motor 701 Gear 712 is engaged with the first gear 712 on the first reel 702, and steel wire rope 703, operation are wound with the first reel 702 The bottom of platform 6 is connected with N-type slide bar 704, and N-type slide bar 704 is equipped with plate 705, is provided with the left and right ends of plate 705 Second through hole 706, the second through hole 706 cooperate with N-type slide bar 704, and the bottom of N-type slide bar 704 is provided with third through-hole 707, The tail end of steel wire rope 703 be connected through third through-hole 707 and with the bottom of plate 705, with plate 705 and N-type slide bar 704 it Between be connected with spring 708, be equipped with contact block 709 with the centre of 705 bottom of plate, the N-type slide bar 704 of the underface of contact block 709 On button 710 is installed, button 710 has circuit to be connected with the second motor 701, and tool box is all connected with left and right sides of 11 trailing flank There is guide sleeve 711, steel wire rope 703 passes through guide sleeve 711.
Embodiment 4
A kind of constructing tunnel tunnel top maintenance of equipment, as shown in Figs. 1-5, include bottom plate 1, side plate 2, supporting rod 3, Wheel 4, elevating mechanism 5, operation post 6, adjoint mechanism 7, hanging ring 8, the first bracing wire 9, hook 10, tool box 11, the second bracing wire 12 With draw ring 13, the bottom of bottom plate 1 is provided with supporting rod 3, and 3 bottom of supporting rod is equipped with wheel 4, and the top both ends of bottom plate 1 are equipped with side Plate 2, the madial wall of side plate 2 are provided with elevating mechanism 5, and the top of elevating mechanism 5 is provided with operation post 6, operation post 6 and bottom plate 1 Top between be provided with mechanism 7, be equipped with hanging ring 8 among the bottom of operation post 6, the first bracing wire 9 be wound with hanging ring 8, the The tail end of one bracing wire 9 is connected with hook 10, links up with 10 and is arranged right below tool box 11, connects on four angles at the top of tool box 11 The second bracing wire 12 is connected to, the tail end of the second bracing wire 12 is wound on draw ring 13, and hook 10 is hung on draw ring 13.
Elevating mechanism 5 includes the first motor 51, swingle 52, first bevel gear 54, second bevel gear 55, clutch shaft bearing Seat 56, screw rod 57, nut 58 and second bearing seat 59, the bottom right end of bottom plate 1 are provided with the first motor 51, in supporting rod 3 Portion is provided with first through hole 53, and the output shaft of swingle 52, the right end of swingle 52 and the first motor 51 is equipped with first through hole 53 Connect, 52 both sides of swingle in supporting rod 3 are mounted on first bevel gear 54, and bottom plate 1 and the inner side of 2 link position of side plate are equal First bearing seat 56 is installed, the inside top of side plate 2 is mounted on second bearing seat 59, first bearing seat 56 and second bearing Screw rod 57 is mounted in seat 59, the bottom of screw rod 57 through bottom plate 1 and is mounted on second bevel gear 55, second bevel gear 55 Engaged with first bevel gear 54, nut 58 is installed on screw rod 57, the top of nut 58 is connected with the bottom of operation post 6.
Include the second motor 701, the first reel 702, steel wire rope 703, N-type slide bar 704, adjoint plate with mechanism 7 705th, spring 708, contact block 709, button 710, guide sleeve 711 and first gear 712, the centre at the top of bottom plate 1 are provided with second Motor 701, is connected with first gear 712 on the output shaft of the second motor 701, pacifies on the bottom plate 1 of 701 or so both sides of the second motor Equipped with the first reel 702, the right side of the first reel 702 is also connected with first gear 712, and first on the second motor 701 Gear 712 is engaged with the first gear 712 on the first reel 702, and steel wire rope 703, operation are wound with the first reel 702 The bottom of platform 6 is connected with N-type slide bar 704, and N-type slide bar 704 is equipped with plate 705, is provided with the left and right ends of plate 705 Second through hole 706, the second through hole 706 cooperate with N-type slide bar 704, and the bottom of N-type slide bar 704 is provided with third through-hole 707, The tail end of steel wire rope 703 be connected through third through-hole 707 and with the bottom of plate 705, with plate 705 and N-type slide bar 704 it Between be connected with spring 708, be equipped with contact block 709 with the centre of 705 bottom of plate, the N-type slide bar 704 of the underface of contact block 709 On button 710 is installed, button 710 has circuit to be connected with the second motor 701, and tool box is all connected with left and right sides of 11 trailing flank There is guide sleeve 711, steel wire rope 703 passes through guide sleeve 711.
Further include and drawn high device 14, side plate 2 draws high device 14 with being provided with the top of mechanism 7, draws high device 14 Include the 3rd bracing wire 141, montant 142 and electronic reel 143, the top of side plate 2 is connected with montant 142, the top of montant 142 Electronic reel 143 is installed on the right side of portion, is wound with the 3rd bracing wire 141 on electronic reel 143, the tail end of the 3rd bracing wire 141 with Tool box 11 connects.
Babinet 15 has been further included, babinet 15 is installed at the top of second motor 701 and reel, the top of babinet 15 is provided with Fourth hole 16, the steel wire rope 703 being wound with the first reel 702 pass through fourth hole 16.
Operation principle:When construction personnel needs to carry out maintenance the equipment of tunnel top, required instrument will be first repaired In inserter case 11, construction personnel stand on operation post 6, while start elevating mechanism 5 and with mechanism 7 to operation post 6 into Row height is adjusted, and allows construction personnel to be in suitable working depth, when starting maintenance, pulls with hand the first bracing wire 9, the first bracing wire 9 drive hook 10 to move up, and since hook 10 is hung on draw ring 13, draw ring 13 is connected with the second bracing wire 12 again, the second bracing wire 12 are connected with tool box 11, so the drive of hook 10 tool box 11 moves up, when tool box 11 is moved upward to certain position Postpone, construction personnel takes out the instrument placed in tool box 11, carries out maintenance operation.
Because elevating mechanism 5 includes the first motor 51, swingle 52, first bevel gear 54, second bevel gear 55, first Bearing block 56, screw rod 57, nut 58 and second bearing seat 59, the bottom right end of bottom plate 1 are provided with the first motor 51, supporting rod 3 Middle part be provided with first through hole 53, is equipped with swingle 52 in first through hole 53, the right end of swingle 52 is defeated with the first motor 51 Go out axis connection, 52 both sides of swingle in supporting rod 3 are mounted on first bevel gear 54, and bottom plate 1 is interior with 2 link position of side plate Side is mounted on first bearing seat 56, and the inside top of side plate 2 is mounted on second bearing seat 59, first bearing seat 56 and second Screw rod 57 is mounted in bearing block 59, the bottom of screw rod 57 through bottom plate 1 and is mounted on second bevel gear 55, the second cone tooth Wheel 55 is engaged with first bevel gear 54, nut 58 is provided with screw rod 57, the top of nut 58 is connected with the bottom of operation post 6 Connect.When worker station is after on operation post 6, while start the first motor 51 and with mechanism 7, the first motor 51 drives swingle 52 Rotation, the rotation of swingle 52 drives first bevel gear 54 to rotate, since first bevel gear 54 is engaged with second bevel gear 55, first Bevel gear 54, which rotates, drives second bevel gear 55 to rotate, and second bevel gear 55, which rotates, drives screw rod 57 in first bearing seat 56 and the Rotated in two bearing bracket 59, screw rod 57, which rotates, drives nut 58 to move up and down, and nut 58 is moved up and down to drive and moved down on operation post 6 Dynamic, at the same time, moving up and down and making corresponding adjusting with 7 coordinating operation platform 6 of mechanism, both cooperate, so as to allow Construction personnel is in suitable construction location.
Because include the second motor 701, the first reel 702, steel wire rope 703, N-type slide bar 704, companion with mechanism 7 With plate 705, spring 708, contact block 709, button 710, guide sleeve 711 and first gear 712, the centre at the top of bottom plate 1 is provided with Second motor 701, is connected with first gear 712, the bottom plate 1 of 701 or so both sides of the second motor on the output shaft of the second motor 701 On the first reel 702 is installed, the right side of the first reel 702 is also connected with first gear 712, on the second motor 701 First gear 712 is engaged with the first gear 712 on the first reel 702, and steel wire rope 703 is wound with the first reel 702, The bottom of operation post 6 is connected with N-type slide bar 704, and N-type slide bar 704 is equipped with plate 705, equal with the left and right ends of plate 705 The second through hole 706 is provided with, the second through hole 706 cooperates with N-type slide bar 704, and the bottom of N-type slide bar 704 is provided with third through-hole 707, the tail end of steel wire rope 703 is connected through third through-hole 707 and with the bottom of plate 705, with plate 705 and N-type slide bar Spring 708 is connected between 704, is equipped with contact block 709 with the centre of 705 bottom of plate, the N-type of the underface of contact block 709 is slided Button 710 is installed, button 710 has circuit to be connected with the second motor 701, the left and right sides of 11 trailing flank of tool box on bar 704 Guide sleeve 711 is respectively connected with, steel wire rope 703 passes through guide sleeve 711.When startup lifting gear is adjusted up workbench, together The second motors of Shi Qidong 701 drive the first reel 702 to put steel wire rope 703, downward when needing lifting gear to carry out workbench During adjusting, start the second motor 701 and drive the first reel 702 to receive steel wire rope 703, reached by cooperation between the two and allow work The purpose moved up and down as platform, after movable workbench is to suitable position, closes 5 and second motor 701 of elevating mechanism, then again Starting the second motor 701 drives the first reel 702 to receive steel wire rope 703, and steel wire rope 703 pulls adjoint plate 705 along N-type slide bar 704 move down, and are moved down with plate 705 and drive contact block 709 to move down, when contact block 709 is pressed into button 710 When, since button 710 with the second motor 701 has circuit to be connected, so the second motor 701 is closed, the first reel 702 stops receiving Steel wire rope 703, steel wire rope 703 are now in tensioned state, can pull with hand the first bracing wire 9 at this time, tool box 11 is by leading Set 711 is moved up along steel wire rope 703, can so be ensured the stability that tool box 11 moves up or down, be avoided in work The tool rollover of case 11 causes instrument to drop, and improves the security of operation indirectly.
Device 14 is drawn high because having further included, side plate 2 draws high device 14 with being provided with the top of mechanism 7, draws high dress Put 14 and include the 3rd bracing wire 141, montant 142 and electronic reel 143, the top of side plate 2 is connected with montant 142, montant 142 Top right side electronic reel 143 is installed, the 3rd bracing wire 141, the tail of the 3rd bracing wire 141 are wound with electronic reel 143 End is connected with tool box 11.After construction personnel adjusts the working space of oneself, start electronic reel 143 and receive the 3rd bracing wire 141, the 3rd bracing wire 141 drives tool box 11 to move up, and when tool box 11 is moved to suitable position, closes electronic reel 143, construction personnel's taking-up instrument out of tool box 11 constructs tunnel top.
Because having further included babinet 15, babinet 15, the top of babinet 15 are installed at the top of second motor 701 and reel Fourth hole 16 is provided with, the steel wire rope 703 being wound with the first reel 702 passes through fourth hole 16.Babinet 15 by gear and around Line wheel covers, and protects the safety of construction personnel, while also improves the working life of the second motor 701 and reel.
Embodiment described above only expresses the preferred embodiment of the utility model, its description is more specific and detailed, But it should not be interpreted as limiting the scope of the present invention.It should be pointed out that for the common of this area For technical staff, without departing from the inventive concept of the premise, some deformations can also be made, improves and substitutes, these are all Belong to the scope of protection of the utility model.Therefore, the protection domain of the utility model patent should be determined by the appended claims.

Claims (5)

1. a kind of constructing tunnel tunnel top maintenance of equipment, it is characterised in that include bottom plate(1), side plate(2), supporting rod (3), wheel(4), elevating mechanism(5), operation post(6), with mechanism(7), hanging ring(8), the first bracing wire(9), hook(10), work Has case(11), the second bracing wire(12)And draw ring(13), bottom plate(1)Bottom supporting rod is installed(3), supporting rod(3)Bottom is set There is wheel(4), bottom plate(1)Top both ends be equipped with side plate(2), side plate(2)Madial wall elevating mechanism is installed(5), lifting Mechanism(5)Top operation post is installed(6), operation post(6)With bottom plate(1)Top between be provided with mechanism(7), make Industry platform(6)Bottom among be equipped with hanging ring(8), hanging ring(8)On be wound with the first bracing wire(9), the first bracing wire(9)Tail end be connected with Hook(10), hook(10)Be arranged right below tool box(11), tool box(11)The second drawing is connected with four angles at top Line(12), the second bracing wire(12)Tail end be wound on draw ring(13)On, hook(10)Hang over draw ring(13)On.
A kind of 2. constructing tunnel tunnel top maintenance of equipment according to claim 1, it is characterised in that elevating mechanism (5)Include the first motor(51), swingle(52), first bevel gear(54), second bevel gear(55), first bearing seat (56), screw rod(57), nut(58)And second bearing seat(59), bottom plate(1)Bottom right end the first motor is installed(51), branch Strut(3)Middle part be provided with first through hole(53), first through hole(53)It is interior to be equipped with swingle(52), swingle(52)Right end with First motor(51)Output axis connection, supporting rod(3)Interior swingle(52)Both sides are mounted on first bevel gear(54), bottom Plate(1)With side plate(2)First bearing seat is mounted on the inside of link position(56), side plate(2)Inside top be mounted on Second bearing seat(59), first bearing seat(56)With second bearing seat(59)Inside it is mounted on screw rod(57), screw rod(57)Bottom Portion passes through bottom plate(1)And it is mounted on second bevel gear(55), second bevel gear(55)With first bevel gear(54)Engagement, screw rod (57)On nut is installed(58), nut(58)Top and operation post(6)Bottom be connected.
3. a kind of constructing tunnel tunnel top maintenance of equipment according to claim 2, it is characterised in that with mechanism (7)Include the second motor(701), the first reel(702), steel wire rope(703), N-type slide bar(704), with plate(705)、 Spring(708), contact block(709), button(710), guide sleeve(711)And first gear(712), bottom plate(1)Peace among top Equipped with the second motor(701), the second motor(701)Output shaft on be connected with first gear(712), the second motor(701)It is left The bottom plate of right both sides(1)On the first reel is installed(702), the first reel(702)Right side be also connected with first gear (712), the second motor(701)On first gear(712)With the first reel(702)On first gear(712)Engagement, the One reel(702)On be wound with steel wire rope(703), operation post(6)Bottom be connected with N-type slide bar(704), N-type slide bar (704)It is equipped with plate(705), with plate(705)Left and right ends be provided with the second through hole(706), the second through hole(706) With N-type slide bar(704)Cooperate, N-type slide bar(704)Bottom be provided with third through-hole(707), steel wire rope(703)Tail end Through third through-hole(707)And with plate(705)Bottom connection, with plate(705)With N-type slide bar(704)Between connect There is spring(708), with plate(705)The centre of bottom is equipped with contact block(709), contact block(709)The N-type slide bar of underface (704)On button is installed(710), button(710)With the second motor(701)There are circuit connection, tool box(11)Trailing flank The left and right sides is respectively connected with guide sleeve(711), steel wire rope(703)Through guide sleeve(711).
4. a kind of constructing tunnel tunnel top maintenance of equipment according to claim 3, it is characterised in that further included drawing Rise device(14), side plate(2)With adjoint mechanism(7)Top be provided with and draw high device(14), draw high device(14)Include Three bracing wires(141), montant(142)With electronic reel(143), side plate(2)Top be connected with montant(142), montant(142) Top right side electronic reel is installed(143), electronic reel(143)On be wound with the 3rd bracing wire(141), the 3rd bracing wire (141)Tail end and tool box(11)Connection.
5. a kind of constructing tunnel tunnel top maintenance of equipment according to claim 4, it is characterised in that further included case Body(15), the second motor(701)With babinet is installed at the top of reel(15), babinet(15)Top be provided with fourth hole (16), the first reel(702)On the steel wire rope that is wound with(703)Through fourth hole(16).
CN201721059544.0U 2017-08-23 2017-08-23 A kind of constructing tunnel tunnel top maintenance of equipment Active CN207259100U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201721059544.0U CN207259100U (en) 2017-08-23 2017-08-23 A kind of constructing tunnel tunnel top maintenance of equipment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201721059544.0U CN207259100U (en) 2017-08-23 2017-08-23 A kind of constructing tunnel tunnel top maintenance of equipment

Publications (1)

Publication Number Publication Date
CN207259100U true CN207259100U (en) 2018-04-20

Family

ID=61922134

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201721059544.0U Active CN207259100U (en) 2017-08-23 2017-08-23 A kind of constructing tunnel tunnel top maintenance of equipment

Country Status (1)

Country Link
CN (1) CN207259100U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109592382A (en) * 2018-11-08 2019-04-09 广州建誉利业建设发展股份有限公司 A kind of novel intelligent architectural engineering feeder equipment

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109592382A (en) * 2018-11-08 2019-04-09 广州建誉利业建设发展股份有限公司 A kind of novel intelligent architectural engineering feeder equipment

Similar Documents

Publication Publication Date Title
CN101972526B (en) Rescue device for small-diameter deep well
CN210508329U (en) Splicing type indoor and outdoor extensible building scaffold
CN203998708U (en) A kind of simple and easy controller switching equipment lifting appliance
CN207259100U (en) A kind of constructing tunnel tunnel top maintenance of equipment
CN204252879U (en) A kind of hydraulic drilling rod box
CN111255403A (en) Fishing device for rope-like falling objects in oil exploitation well
CN104192746A (en) Hand-cranking hoisting device fixed to electric pole
CN106823190B (en) Inverted L-shaped deep well rescue device and method
CN211343235U (en) Maintenance tool on gearbox tower of wind driven generator
CN206688052U (en) A kind of deep well rescue device
CN201862173U (en) Rescue device for small-diameter deep well
CN204927042U (en) Large -scale roll of iron core transformer vertical coil winding machine
CN104150393A (en) Micro power electric equipment rotating and hoisting device
CN106836224B (en) A kind of railway construction Stake head handling machine
CN105645290A (en) Arrangement to hoist wind turbine component
CN202650472U (en) Warning curtain for overhauling of electric cabinet
CN108466938A (en) A kind of transformer on-load voltage regulating tap switch boom hoisting
CN207495493U (en) A kind of height-adjustable manipulator
CN219885562U (en) Material lifting device with stable structure
CN108843032B (en) Umbrella for building
CN218363124U (en) Welding equipment for stainless steel sculpture
CN214091065U (en) High-altitude suspension safety traction device for building construction
CN206384667U (en) Cable fast winding device
CN220265009U (en) Explosion-proof electric hoist
CN212101899U (en) Debugging table

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant