CN207253926U - A kind of chimney rain collection device - Google Patents

A kind of chimney rain collection device Download PDF

Info

Publication number
CN207253926U
CN207253926U CN201720908624.2U CN201720908624U CN207253926U CN 207253926 U CN207253926 U CN 207253926U CN 201720908624 U CN201720908624 U CN 201720908624U CN 207253926 U CN207253926 U CN 207253926U
Authority
CN
China
Prior art keywords
chimney
cyclone
collection device
annular
absorption tower
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201720908624.2U
Other languages
Chinese (zh)
Inventor
邓志伦
殷兴华
胡双双
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
WUHAN HUADE ECOTEK Corp
Original Assignee
WUHAN HUADE ECOTEK Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by WUHAN HUADE ECOTEK Corp filed Critical WUHAN HUADE ECOTEK Corp
Priority to CN201720908624.2U priority Critical patent/CN207253926U/en
Application granted granted Critical
Publication of CN207253926U publication Critical patent/CN207253926U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Cyclones (AREA)

Abstract

It the utility model is related to a kind of chimney rain collection device, including cyclone, annular collection trough, on absorption tower, chimney segment near top installs a cyclone, and lower wall cylinder outer ring to the absorption tower chimney wall installation annular collection trough of cyclone, annular collection trough set a discharge outlet and are connected with exterior fluid collection tube road system.Wet desulfurization system after the utility model is installed, flow velocity of the wet flue gas through chimney segment about 15m/s, in this velocity flows through cyclone, guide functions through swirl vane form spiral-shaped air-flow, collided along chimney wall tangential direction and siding, drop is collected by siding, hereafter after the upward speed of drop can slow down gradually annular collection trough is flowed into along siding, the drop of speed also can be blocked and flowed back by ring baffle in chimney top, solve the important environmental pollution hidden danger of wet desulphurization facility operation.Device provided by the utility model has the advantages that drop collection efficiency is high, simple in structure, system resistance is small, does not increase operating cost.

Description

A kind of chimney rain collection device
Technical field
It the utility model is related to the collection device of " chimney rain " that chimney is discharged in device in a kind of wet desulphurization.
Background technology
At present, in the flue gas desulfurization device (FGD) of domestic thermal power plant coal unit installation, it is most of use it is wet Method sulfur removal technology.The wet desulfurizing process of early stage is mounted with flue gas heat-exchange unit (GGH) to lift the rising height of flue gas so that More than 80 DEG C are heated to from the neat stress (50 DEG C or so) of absorption tower discharge.After 2006, since helicoid GGH is being run During dust stratification, fouling it is serious, have impact on the normal operation of whole desulfurizer, then, the desulfurizer then built is almost GGH is all eliminated, makes 50 DEG C or so of wet saturated flue gas directly from smoke stack emission, namely what is often called " Wet chimney ".Wet saturated flue gas Ground spreads and condenses into the small rain droplets of the slurries containing solid crystal around from chimney top to tower, is exactly " chimney mentioned herein Rain " phenomenon.Slurries in desulfurizer neat stress are mainly derived from the fine drop after the spraying layer nozzle atomization of absorption tower, slurries Fogdrop diameter is most of between 1500-2000 μm after nozzle atomization, and a small amount of diameter can be produced after collision at 15 μm or so Droplet, droplet is after demister, and droplet removal rate of the diameter not less than 22 μm is generally 99.99%, 15-22 μm of diameter Drop removal rate be 50%, less than 15 μm of droplet can not intercept, therefore it is inevitable to have a certain amount of slurries in neat stress. In the thermal power plant using wet desulphurization, much all there is " chimney rain " phenomenon in Wet chimney operation, be usually that unit exists During large load operation, flue gas carries slurries phenomenon and is particularly acute.
" chimney rain " contains a certain amount of SO in acidity2、SO3And slurries etc., can to the equipment in diffusion zone, facility and Building causes certain infringement, and the production, life to surrounding resident have an impact.Continuously " chimney rain " will be to nearby residents Life and power plant's production produce harmful effect." chimney rain " dried mud point, if falling in power plant's nearby residents roof and clothing On, cleaning is very difficult;If falling on power plant's automobile, architectural glazings, device outer surface, while causing environmental pollution, Power plant safety can be influenced to carry out production strictly in line with rules and regulations;Continuously " chimney rain " will produce bad shadow to the growth of power plant periphery plant and crops Ring, " chimney rain " is covered in vegetation and crops blade surface, not only breaks up landscape after falling, and hinders Plant Light cooperation With influencing the normal growths of vegetation and crops;At present, when there is serious " chimney rain " phenomenon in domestic multiple power plant, more by The strong dissatisfaction and protest of neighbouring resident, damages the favorable image of power plant.Due to sensitiveness of the environmental problem in the public, " cigarette Chimney rain " problem has become the important environmental pollution hidden danger of wet desulphurization facility operation.
The content of the invention
The purpose of this utility model is in order to overcome the problems of the above-mentioned prior art, there is provided a kind of Novel chimney rain is collected Device.Device provided by the utility model have drop collection efficiency is high, simple in structure, system resistance is small, do not increase operation into This advantages that.
The technical solution of the utility model is:
A kind of chimney rain collection device, including cyclone, annular collection trough, it is characterised in that:On absorption tower chimney segment top A cyclone is nearby installed in portion, and lower wall cylinder outer ring to the absorption tower chimney wall installation annular collection trough of cyclone, annular are received Collection groove sets a discharge outlet and is connected with exterior fluid collection tube road system.
The utility model further includes ring baffle, and ring baffle is installed on absorption tower chimney top outlet inward flange.
The cyclone is made of some paddle shape blades, top center disk cylinder, lower wall cylinder, top center disk cylinder Supported with lower wall cylinder and fix each paddle shape blade, and some paddle shape blades are along chimney circumference, cyclone monnolithic case Taper fan structure.
The paddle shape width of blade direction of the cyclone tilts 40 °~50 ° arrangements, length of blade direction in the direction of the clock 25 °~35 ° of angle with horizontal plane arranges to top center disk cylinder, and see cannot be seamed for vertical direction between adjacent paddle shape blade Gap.
The top center disk cylinder of the cyclone is equipped with manhole and supporting blind flange.
The groove body circumferential direction inside of the annular collection trough is disposed with some stiffener plates, stiffener plate quantity and paddle shape Blade is identical, and the positioning of stiffener plate arranges that the bottom plate of stiffener plate and annular collection trough leaves one with paddle shape blade pair Determining deviation, flows, whole cyclone is supported by this annular collection trough easy to the slurries of collection.
Wet desulfurization system after the utility model, the wet flue gas about 15m/s of the flow velocity through chimney segment, under this speed are installed Cyclone is flowed through, the guide functions through swirl vane form spiral-shaped air-flow, are collided along chimney wall tangential direction and siding, Drop is collected by siding, and annular collection trough, speed are flowed into along siding after hereafter the upward speed of drop can slow down gradually Drop also can be blocked and be flowed back by ring baffle in chimney top, the important environmental pollution for solving wet desulphurization facility operation is hidden Suffer from.Device provided by the utility model is with drop collection efficiency is high, simple in structure, system resistance is small, does not increase operating cost The advantages that.
Brief description of the drawings
Fig. 1 is the arrangement schematic diagram of the utility model.
Fig. 2 is the hydrocyclone structure schematic diagram of the utility model.
Fig. 3 is that the cyclone of the utility model overlooks intention.
Embodiment
Structure Figure is further described the utility model.
As shown in Figure 1, Figure 2, Figure 3 shows, the utility model mainly includes cyclone 4, ring baffle 7, annular collection trough 8, its It is characterized in that:On absorption tower, chimney segment near top installs a cyclone 4, and the lower wall cylinder 4-3 outer rings of cyclone 4 are extremely inhaled Receive tower chimney wall installation annular collection trough 8, annular collection trough 8 set a discharge outlet 10 and with exterior fluid collection tube road system System 1 is connected;Ring baffle 7 is installed on absorption tower chimney top outlet inward flange;The cyclone 4 is by some paddle shape blades 4-2, top center disk cylinder 4-1, lower wall cylinder 4-3 compositions, top center disk cylinder 4-1 and lower wall cylinder 4-3 are supported And fixed each paddle shape blade 4-2, and some paddle shape blade 4-2, along chimney circumference, cyclone monnolithic case is taper wind Fan structure;Flue gas forms swirling eddy by the water conservancy diversion of paddle shape blade, and the paddle shape blade 4-2 widths of the cyclone are pressed Tilt 45 ° of arrangements clockwise, 32 ° of paddle shape blade 4-2 length directions angle with horizontal plane is to top center disk cylinder 4-1 Arrangement, and vertical direction is seen and cannot be had the gap between adjacent paddle shape blade 4-2, and must have certain overlapping region;Cyclone 4 Top center disk cylinder 4-1 be equipped with the manhole and supporting blind flange 11 of a diameter of 800mm, the upper and lower inspection of for constructing when Repair passage.The 8 groove body circumferential direction inside of annular collection trough that lower wall cylinder 4-3 outer rings to the absorption tower chimney wall of cyclone 4 is installed Some stiffener plates 9 are disposed with, 9 quantity of stiffener plate is identical with paddle shape blade 4-2, and the positioning of stiffener plate 9 and paddle shape leaf Piece 4-2 centerings arrange, the bottom plate of stiffener plate 9 and annular collection trough 8 stay it is at regular intervals, it is whole easy to the slurries flowing of collection A cyclone is supported by this annular collection trough.Allow pipe support to move towards according to trench and absorption tower body, collected in annular Groove, which corresponds to orientation, to be opened a discharge outlet 10 and accesses a set of fluid collection tube road system 1, discharges the slurries of collection.Absorption tower chimney top The ring baffle 7 of portion outlet inward flange installation, predominantly prevents the slurries through the effect of 4 centrifugal force of cyclone from being thrown away along chimney wall, Improve organic efficiency.It is disposed with the scaffold of spacing 800mm in terms of construction and maintenance to lower stack wall 1m or so in cyclone absolute altitude Through hole 5, the upward chimney wall 1m of cyclone or so opens the peace of an a diameter of 800mm manholes 2, upward 2m or so arrangement spacing 1000mm Full band through hole 3, the absorption tower downward 1.5m of chimney top ring baffle or so also arranges the scaffold through hole 5 of spacing 800mm.Former chimney If without broken solar or lunar halo in design, can be uniformly distributed along the circumference 4 broken wind fins 6 in top small range region, increase absorption tower chimney Stability.Whole system material is both needed to meet Corrosion Protection, and main material is fiberglass, PP, 316L or two-phase alloys steel etc., spiral shell The fasteners such as bolt use 316L stainless steels or two-phase alloys steel, and the connection between fiberglass is connected using fiberglass special bonding material Connect.
The operating mechanism of wet desulfurization system is the wet flue gas about 15m/s of the flow velocity through chimney segment, in this velocity flows through rotation Device is flowed, the guide functions of the paddle shape blade 4-2 through cyclone 4 form spiral-shaped air-flow, along chimney wall tangential direction and wall Plate collides, and drop is collected by siding, and annular collection trough 8 is flowed into along siding after hereafter the upward speed of drop can slow down gradually, The drop of speed also can be blocked and flowed back by ring baffle 7 in chimney top.

Claims (6)

1. a kind of chimney rain collection device, including cyclone, annular collection trough, it is characterised in that:At the top of the chimney segment of absorption tower One cyclone of installation nearby, and lower wall cylinder outer ring to the absorption tower chimney wall installation annular collection trough of cyclone, annular are collected Groove sets a discharge outlet and is connected with exterior fluid collection tube road system.
2. chimney rain collection device according to claim 1, it is characterised in that:Further include ring baffle, ring baffle peace Inward flange is exported mounted in absorption tower chimney top.
3. chimney rain collection device according to claim 1 or 2, it is characterised in that:The cyclone is by some paddle shapes Blade, top center disk cylinder, lower wall cylinder composition, top center disk cylinder support with lower wall cylinder and fix each paddle shape leaf Piece, and some paddle shape blades are along chimney circumference.
4. chimney rain collection device according to claim 3, it is characterised in that:The paddle shape width of blade side of the cyclone To 40 °~50 ° arrangements are tilted in the direction of the clock, 25 °~35 ° of length of blade direction angle with horizontal plane is justified along top center disk Cylinder arrangement, and vertical direction is seen and cannot be had the gap between adjacent paddle shape blade.
5. chimney rain collection device according to claim 1 or 2, it is characterised in that:The top center disk of the cyclone Cylinder is equipped with manhole and supporting blind flange.
6. chimney rain collection device according to claim 3, it is characterised in that:Inside the groove body of the annular collection trough Some stiffener plates are circumferentially disposed with, stiffener plate quantity is identical with paddle shape blade, and the positioning of stiffener plate and paddle shape leaf The bottom plate of piece centering arrangement, stiffener plate and annular collection trough stays at regular intervals.
CN201720908624.2U 2017-07-25 2017-07-25 A kind of chimney rain collection device Active CN207253926U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720908624.2U CN207253926U (en) 2017-07-25 2017-07-25 A kind of chimney rain collection device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720908624.2U CN207253926U (en) 2017-07-25 2017-07-25 A kind of chimney rain collection device

Publications (1)

Publication Number Publication Date
CN207253926U true CN207253926U (en) 2018-04-20

Family

ID=61927462

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720908624.2U Active CN207253926U (en) 2017-07-25 2017-07-25 A kind of chimney rain collection device

Country Status (1)

Country Link
CN (1) CN207253926U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108854358A (en) * 2018-07-10 2018-11-23 马鞍山市如松冶金科技有限责任公司 One kind spraying Integral dust catcher by spraying
CN111473351A (en) * 2020-04-24 2020-07-31 北京博纳菲德科技有限公司 Environment-friendly and energy-saving house chimney and using method
CN114775920A (en) * 2022-03-16 2022-07-22 中建二局第一建筑工程有限公司 Roof

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108854358A (en) * 2018-07-10 2018-11-23 马鞍山市如松冶金科技有限责任公司 One kind spraying Integral dust catcher by spraying
CN111473351A (en) * 2020-04-24 2020-07-31 北京博纳菲德科技有限公司 Environment-friendly and energy-saving house chimney and using method
CN114775920A (en) * 2022-03-16 2022-07-22 中建二局第一建筑工程有限公司 Roof

Similar Documents

Publication Publication Date Title
CN104984597B (en) A kind of air swirl parallel combination demister and application
CN207253926U (en) A kind of chimney rain collection device
CN105169818B (en) Double-vane air-swirl parallel-combination demister and application thereof
CN105148623B (en) Rotary blade type dynamic steam-water separator with controllable rotational speeds
JP3269332B2 (en) Spray tower
CN207755876U (en) Double cyclone dedusting demisters
CN204911024U (en) Pneumatic whirl parallel combination defogging device
CN205599335U (en) Tubular pole defogging dust collector
CN204684801U (en) A kind of spiral board dedusting demister
CN205269245U (en) Desulfurizing tower exhaust pass defogging device with guide plate
CN204601836U (en) For the cyclone that wet desulfurization system flue gas drop removes
CA1049924A (en) Cooling tower
CN102444309A (en) Non-corrosive dust-collecting and energy-saving chimney
CN103953937B (en) A kind of Wet chimney inlet guide vance device
CN106111026B (en) A kind of rotating stream tray scrubber producing thiocarbamide
CN204973336U (en) Pneumatic whirl parallel combination defogging device of double leaf
CN210699167U (en) Multistage cyclone dust and mist eliminator
CN100460759C (en) Wind-proof, rain-proof and environmental protection cowl
CN206739339U (en) Smoke discharging device
CN209596735U (en) Tubular type Environmental protection water circulation cyclone dust
CN206027657U (en) Whirl board tower that production thiocarbamide was used
CN102563678A (en) Device used for preventing flue gas at outlet of chimney from carrying droplets after wet desulphurization
CN206755208U (en) A kind of condensation liquor collecting device for fiber glass reinforced plastic chimney inner cylinder
CN202511303U (en) Device for preventing wet desulphurized flue gas at chimney exit from carrying liquid droplets
CN205995156U (en) A kind of wet desulphurization spiral-flow type demister

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant