CN207251013U - A kind of buried distribution cabinet - Google Patents
A kind of buried distribution cabinet Download PDFInfo
- Publication number
- CN207251013U CN207251013U CN201721324238.5U CN201721324238U CN207251013U CN 207251013 U CN207251013 U CN 207251013U CN 201721324238 U CN201721324238 U CN 201721324238U CN 207251013 U CN207251013 U CN 207251013U
- Authority
- CN
- China
- Prior art keywords
- distribution cabinet
- power distribution
- fixed setting
- subterranean excavation
- cabinet body
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 claims abstract description 49
- 238000009412 basement excavation Methods 0.000 claims abstract description 33
- 239000003651 drinking water Substances 0.000 claims abstract description 6
- 235000020188 drinking water Nutrition 0.000 claims abstract description 6
- 230000000694 effects Effects 0.000 claims description 6
- 239000011248 coating agent Substances 0.000 claims description 4
- 238000000576 coating method Methods 0.000 claims description 4
- 239000000243 solution Substances 0.000 description 6
- 238000012423 maintenance Methods 0.000 description 4
- 230000007812 deficiency Effects 0.000 description 3
- 230000009286 beneficial effect Effects 0.000 description 1
- 230000007547 defect Effects 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 230000005611 electricity Effects 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 238000002347 injection Methods 0.000 description 1
- 239000007924 injection Substances 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 238000006467 substitution reaction Methods 0.000 description 1
Landscapes
- Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
Abstract
The utility model discloses a kind of buried distribution cabinet, including power distribution cabinet body and subterranean excavation, power distribution cabinet body is embedded in subterranean excavation, the lower end fixed setting buoyancy base of power distribution cabinet body, the left and right sides fixed setting guide block of power distribution cabinet body, guide rail is longitudinally fixedly installed in the side of subterranean excavation, guide rail is engaged with guide block, the pre-buried fixed setting water tank in side of subterranean excavation, the bottom of water tank opens up the water inlet connected with subterranean excavation, fixed setting suction pump in water tank, the bottom of subterranean excavation opens up water outlet, the drinking-water pipe that water outlet fixed setting is connected with suction pump.The utility model is simple in structure, cost is relatively low, the utility model is simple in structure, concealment is strong, and babinet is embedded in underground, and it is small to take ground space, at the same time by using law of connected vessels and the buoyancy of water, power distribution cabinet can be safeguarded, it is easy to operate, it can rationally utilize the useful space of underground, and the scientific utilization in space is optimized, it is more convenient for the upkeep operation of power distribution cabinet.
Description
Technical field
It the utility model is related to power distribution cabinet technical field, and in particular to a kind of buried distribution cabinet.
Background technology
High-low voltage electric power distribution cabinet be exactly as its name suggests connect high voltage power distributing cabinet, low-tension switch cabinet and and the distribution of connection cables set
Standby, general power supply bureau, electric substation are all to use high voltage power distributing cabinet, then arrive low-tension switch cabinet, low tension switch again through transformer pressure-reducing
Cabinet is in the distribution board to each electricity consumption, control cabinet, switch-box, and by switch, breaker, fuse, button, indicator light, instrument,
The controller switching equipment that electric wire etc protection device is assembled integrally.With the continuous development of New-energy electric vehicle, New energy electric
Automobile is more and more to enter into common family, and charging pile is the corollary equipment of electric automobile, and community parking position is supporting
Equipment.If the power distribution cabinet of charging pile is located on wall, much room is necessarily taken, is unfavorable for the Optimum utilization in space.It is based on
The deficiencies in the prior art, need to develop one kind and prevent take up parking space, and technical solution convenient to overhaul, to solve the prior art
Technological deficiency.
Utility model content
The purpose of this utility model is that the defects of being directed to the prior art and deficiency, there is provided a kind of buried distribution cabinet.
To achieve the above object, the technical solution adopted in the utility model is:A kind of buried distribution cabinet, including power distribution cabinet
Body and subterranean excavation, its innovative point are:The power distribution cabinet body is embedded in subterranean excavation, under the power distribution cabinet body
End fixed setting buoyancy base, the left and right sides fixed setting guide block of the power distribution cabinet body, the lateral longitudinal of the subterranean excavation
To fixed setting guide rail, the guide rail is engaged with guide block, and the pre-buried fixed setting water tank in side of the subterranean excavation is described
The bottom of water tank opens up the water inlet connected with subterranean excavation, and suction pump, the underground base is fixedly installed in the water tank
The bottom in hole opens up water outlet, the drinking-water pipe that the water outlet fixed setting is connected with suction pump.
Further, the volume of the water tank is twice of the volume of subterranean excavation, and the volume of power distribution cabinet body is ground
The half of the volume of lower foundation pit.
Further, for the water inlet with solenoid valve is fixedly installed on water outlet, the solenoid valve passes through remote control.
Further, the top fixed setting activity pressure-bearing cover board of the subterranean excavation.
Further, the power distribution cabinet body inner and outer surfaces are equipped with moisture-proof rust-proof coating.
With the above structure, the utility model has the beneficial effect that:
The utility model is simple in structure, cost is relatively low, and the utility model is simple in structure, and concealment is strong, and babinet is embedded in ground
Under, occupancy ground space is small, while by using law of connected vessels and the buoyancy of water, it is possible to power distribution cabinet is safeguarded, is grasped
Facilitate, can rationally utilize the useful space of underground, and optimize the scientific utilization in space, be more convenient for the maintenance of power distribution cabinet
Operation.
Brief description of the drawings
Fig. 1 is the structure diagram of the utility model.
Description of reference numerals:
1 power distribution cabinet body, 2 subterranean excavations, 3 buoyancy bases, 4 guide blocks, 5 guide rails, 6 water tanks, 7 water inlets, 8 suction pumps, 9
Water outlet, 10 drinking-water pipes, 11 solenoid valves, 12 activity pressure-bearing cover boards.
Embodiment
The utility model will be further described below with reference to the accompanying drawings.
In order to make the purpose of the utility model, technical solutions and advantages more clearly understood, below in conjunction with attached drawing and specifically
Embodiment, is further elaborated the utility model.It should be appreciated that the specific embodiments described herein are only used
To explain the utility model, it is not used to limit the utility model.
Referring to Fig. 1, a kind of buried distribution cabinet, including power distribution cabinet body 1 and subterranean excavation 2, power distribution cabinet body 1 are embedded in
In subterranean excavation 2, the lower end fixed setting buoyancy base 3 of power distribution cabinet body 1, the left and right sides fixed setting of power distribution cabinet body 1
Guide block 4, longitudinally fixed setting guide rail 5, guide rail 5 are engaged with guide block 4 for the side of subterranean excavation 2, and the side of subterranean excavation 2 is pre-buried
Water tank 6 is fixedly installed, the bottom of water tank 6 opens up the water inlet 7 connected with subterranean excavation 2, is fixedly installed and takes out in water tank 6
Water pump 8, the bottom of subterranean excavation 2 open up water outlet 9, and the drinking-water pipe 10 connected with suction pump 8 is fixedly installed in water outlet 9.Buoyancy
Base 3 can not only bear the weight of power distribution cabinet body 1, and can possess the ability of floating, power distribution cabinet body 1 is floated.
The volume of water tank 6 is twice of the volume of subterranean excavation 2, and the body that the volume of power distribution cabinet body 1 is subterranean excavation 2
Long-pending half.After power distribution cabinet body 1 floats, the half water in water tank 6 floats power distribution cabinet body 1, and makes power distribution cabinet body 1
On float on ground.
For water inlet 7 with solenoid valve 11 is fixedly installed on water outlet 9, solenoid valve 11 passes through remote control.Pass through solenoid valve
11 can carry out switch control to water inlet 7 and water outlet 9, improve the practicality used and convenience.
The top fixed setting activity pressure-bearing cover board 12 of subterranean excavation 2.Activity pressure-bearing cover board 12 does not influence the work on ground
And activity.
1 inner and outer surfaces of power distribution cabinet body are equipped with moisture-proof rust-proof coating.Moisture-proof rust-proof coating can prevent steam from entering to match somebody with somebody
In electric cabinet body 1, and extend the service life of power distribution cabinet body 1.
The operation principle of the utility model:
When needing to be serviced maintenance, the solenoid valve 11 on water inlet 7 need to be only opened, is made in water injection subterranean excavation 2,
So that power distribution cabinet body 1 slowly rises with the buoyancy of dampening, and since law of connected vessels, power distribution cabinet body 1 float up to ground, work
Maintenance and Repair can be carried out by making personnel;After Maintenance and Repair, the solenoid valve 11 on water outlet 9 is opened, while start and draw water
Pump 12, passes water through drinking-water pipe 10 and is back in water tank 6, power distribution cabinet body 1 sinks down into 2 bottom of subterranean excavation.
The above, is merely intended for describing the technical solutions of the present application, but not for limiting the present application, those of ordinary skill in the art couple
The other modifications or equivalent substitution that the technical solution of the utility model is made, without departing from technical solutions of the utility model
Spirit and scope, should all cover among the right of the utility model.
Claims (5)
1. a kind of buried distribution cabinet, including power distribution cabinet body(1)And subterranean excavation(2), it is characterised in that:The power distribution cabinet sheet
Body(1)It is embedded in subterranean excavation(2)It is interior, the power distribution cabinet body(1)Lower end fixed setting buoyancy base(3), the distribution
Cabinet body(1)The left and right sides fixed setting guide block(4), the subterranean excavation(2)Side longitudinally fixed setting guide rail(5),
The guide rail(5)With guide block(4)It is engaged, the subterranean excavation(2)The pre-buried fixed setting water tank in side(6), the storage
Water tank(6)Bottom open up and subterranean excavation(2)The water inlet of connection(7), the water tank(6)Interior fixed setting suction pump
(8), the subterranean excavation(2)Bottom open up water outlet(9), the water outlet(9)Fixed setting and suction pump(8)Connection
Drinking-water pipe(10).
A kind of 2. buried distribution cabinet according to claim 1, it is characterised in that:The water tank(6)Volume for ground
Lower foundation pit(2)Twice of volume, and power distribution cabinet body(1)Volume be subterranean excavation(2)Volume half.
A kind of 3. buried distribution cabinet according to claim 1, it is characterised in that:The water inlet(7)With water outlet(9)
On solenoid valve is fixedly installed(11), the solenoid valve(11)Pass through remote control.
A kind of 4. buried distribution cabinet according to claim 1, it is characterised in that:The subterranean excavation(2)Top consolidate
Determine setting activity pressure-bearing cover board(12).
A kind of 5. buried distribution cabinet according to claim 1, it is characterised in that:The power distribution cabinet body(1)Inside and outside table
Face is equipped with moisture-proof rust-proof coating.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201721324238.5U CN207251013U (en) | 2017-10-16 | 2017-10-16 | A kind of buried distribution cabinet |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201721324238.5U CN207251013U (en) | 2017-10-16 | 2017-10-16 | A kind of buried distribution cabinet |
Publications (1)
Publication Number | Publication Date |
---|---|
CN207251013U true CN207251013U (en) | 2018-04-17 |
Family
ID=61890138
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201721324238.5U Expired - Fee Related CN207251013U (en) | 2017-10-16 | 2017-10-16 | A kind of buried distribution cabinet |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN207251013U (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110077267A (en) * | 2019-05-21 | 2019-08-02 | 杨涛 | A kind of buried new-energy automobile charging pile with water-proof function |
CN111029919A (en) * | 2019-12-23 | 2020-04-17 | 浙江雷盛电气有限公司 | Power distribution equipment control cabinet |
-
2017
- 2017-10-16 CN CN201721324238.5U patent/CN207251013U/en not_active Expired - Fee Related
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110077267A (en) * | 2019-05-21 | 2019-08-02 | 杨涛 | A kind of buried new-energy automobile charging pile with water-proof function |
CN110077267B (en) * | 2019-05-21 | 2023-01-03 | 温州蓝天能源科技股份有限公司 | Bury formula new energy automobile and fill electric pile with waterproof function |
CN111029919A (en) * | 2019-12-23 | 2020-04-17 | 浙江雷盛电气有限公司 | Power distribution equipment control cabinet |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN202732204U (en) | High-level water-storage power generation device | |
CN207251013U (en) | A kind of buried distribution cabinet | |
CN102852189A (en) | Totally closed negative-pressure-free additive pressure water supply device | |
CN106223407B (en) | Air bag two-chamber is pressurized pipe network Pressure-superposed water supply equipment | |
CN203456935U (en) | Integrated solar energy micro-power rainwater pumping station | |
CN104993408B (en) | Offshore boosting station | |
CN206988115U (en) | A kind of waste heat recovery system of air compressor | |
CN205000412U (en) | Intelligent double mode pipe network pressure -superposed water supply equipment | |
CN202324068U (en) | Integrated fire-fighting pump house | |
CN208209533U (en) | A kind of compact offshore wind farm unit dynamic reactive compensation device | |
CN201276721Y (en) | Non-negative pressure water supply equipment with flow regulation function | |
CN206737040U (en) | Rise residential non-negative pressure method of water supply device | |
CN203428903U (en) | Environment-friendly integrated type skid-mounted gas station | |
CN201500635U (en) | Gas explosion fountain device | |
CN206015800U (en) | Vertical fit water tank secondary pressurized Based Intelligent Control supply equipment | |
CN203613606U (en) | Automatic water feeder | |
CN201241355Y (en) | Water-saving equipment | |
CN201167250Y (en) | Power supply for electric control valve for controlling liquid flow | |
CN202386581U (en) | Portable shower | |
CN205242492U (en) | Multichannel water supply system | |
CN201024438Y (en) | Superposed pipe pressurizing water supply device | |
CN204418277U (en) | Box one water supply pumping plant | |
CN108517922A (en) | A kind of energy-saving water supply system | |
JP4597257B1 (en) | Hydroelectric power generation system | |
CN203113433U (en) | Automatic air-compensating type air pressure tank |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CB03 | Change of inventor or designer information |
Inventor after: Niu Dongwei Inventor after: Chen Cheng Inventor after: Li Zhi Inventor after: Chen Xiulin Inventor before: Niu Weidong Inventor before: Chen Cheng Inventor before: Li Zhi Inventor before: Chen Xiulin |
|
CB03 | Change of inventor or designer information | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20180417 |