CN207246741U CN201721274891.5U CN201721274891U CN207246741U CN 207246741 U CN207246741 U CN 207246741U CN 201721274891 U CN201721274891 U CN 201721274891U CN 207246741 U CN207246741 U CN 207246741U
Authority
CN
China
Prior art keywords
fixed
para
bar
seismic support
sliding
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201721274891.5U
Other languages
Chinese (zh)
Inventor
夏友华
韦小宝
郑诚
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nanjing Eighth Construction And Installation Engineering Co Ltd
Original Assignee
Nanjing Eighth Construction And Installation Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nanjing Eighth Construction And Installation Engineering Co Ltd filed Critical Nanjing Eighth Construction And Installation Engineering Co Ltd
Priority to CN201721274891.5U priority Critical patent/CN207246741U/en
Application granted granted Critical
Publication of CN207246741U publication Critical patent/CN207246741U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

A kind of para-seismic support, including two vertical sunpenders for being fixed on wall top, supporting rod is horizontally fixed between the sunpender, the supporting rod both ends are provided tiltedly with the brace for being fixed on wall top, the supporting rod includes two fixation loop bars for being fixed on sunpender bottom, sliding is equipped with a sliding bar in the every fixed loop bar, and two sliding bar ends close to each other are bolted.When running into earthquake, the stress of horizontal direction and vertical direction is shared by brace and sunpender, to stabilize the electromechanical equipment installed in para-seismic support.In addition, supporting rod is split as being fixed on the fixation loop bar of sunpender bottom and fixes in loop bar the sliding bar being slidably connected, when needing to construct to the electromechanical equipment in para-seismic support, unclamp the bolt fixed between sliding bar, pull open two sliding bars, expose the electromechanical equipment in para-seismic support, facilitate operating personnel to carry out operation.

Description

A kind of para-seismic support
Technical field
A kind of para-seismic support is the utility model is related to, more particularly to a kind of para-seismic support being easily installed.
Background technology
Para-seismic support is that the attached electromechanical engineering facility of limitation produces displacement, control facility vibration, and load is passed on to holding Carry the various components or device in structure.When meet with this area seismic fortification intensity earthquake when, building plumbing system, fire-fighting, The electromechanical engineering facilities such as heating, ventilation, air-conditioning, combustion gas, electric power can reduce the hair of secondary disaster after para-seismic support is reinforced It is raw, so as to reduce casualties and property loss.
At present, the Chinese utility model patent that notification number is CN206458903U discloses a kind of spacing anti-easy to what is adjusted Stent, including master carrier, sunpender, brace and pipe collar are shaken, the sunpender is equipped with two groups, and is mounted by means of bolts on respectively The both ends of master carrier, are installed with oblique pull connecting seat, the oblique pull at the diagonally opposing corner at master carrier upper surface both ends respectively Connecting seat is flexibly connected by hex bolts with the bottom of brace, and the longitudinal center line of the master carrier upper surface is provided with convex Slideway, the pipe collar are slidably connected by screw rod and convex slideway, should be easy to the limiting shock resistant stent of adjusting, at the both ends of sunpender Two groups of braces arranged in a crossed manner are additionally arranged, substantially increase its shock resistance, and the utility model is used for fixed -piping Pipe collar is fixed on master carrier by the way of being slidably connected, after pipeline is fixed, at any time can to the position of pipeline into Row adjustment.
Although this limiting shock resistant stent easy to adjust can be adjusted the position for the pipeline being erected on stent, But to duct orientation make a change or when being replaced to the facility on stent, it is necessary to which para-seismic support is dismantled one by one Getting off to construct, cumbersome.
Utility model content
The purpose of this utility model is to provide a kind of para-seismic support, in the equipment construction on to para-seismic support, need to only beat Spending strut, without whole para-seismic support is disassembled, so that convenient construction.
The above-mentioned technical purpose of the utility model technical scheme is that:A kind of para-seismic support, bag Two vertical sunpenders for being fixed on wall top are included, are horizontally fixed with supporting rod between the sunpender, the supporting rod both ends tilt and set There is the brace for being fixed on wall top, the supporting rod includes two fixation loop bars for being fixed on sunpender bottom, the every fixation Sliding is equipped with a sliding bar in loop bar, and two sliding bar ends close to each other are bolted.
By using above-mentioned technical proposal, the sunpender of vertical direction and the brace being obliquely installed are fixed with wall top, Horizontal supporting rod is fixed by sunpender and brace, the they sup-port being set up in parallel further through several is lived electromechanics and set It is standby.When running into earthquake, the stress of horizontal direction and vertical direction is shared by brace and sunpender, to stabilize para-seismic support The electromechanical equipment of upper installation.In addition, supporting rod is split as being fixed on the fixation loop bar of sunpender bottom and fixed in loop bar to slide The sliding bar of connection, when needing to construct to the electromechanical equipment in para-seismic support, unclamps the bolt fixed between sliding bar, Two sliding bars are pulled open, expose the electromechanical equipment in para-seismic support, facilitate operating personnel to carry out operation.
Further, two steel wire ropes are equipped with the sunpender and sliding bar, described steel wire rope one end is fixed on wall top On, the other end is connected with each other, and the upper surface of the sliding bar is provided with the recessing groove passed through for steel wire rope along glide direction.
By using above-mentioned technical proposal, two steel wire ropes, the connection of steel wire rope one end are set in sunpender and sliding bar In wall top, the other end is connected with each other, in this way, when para-seismic support deforms and distorts under geological process, or even is broken, The steel wire rope being arranged in para-seismic support can play protective action, stop the electromechanical equipment fallen down and para-seismic support body, protect Hinder the safety of personnel in house.In addition, in order to avoid the sliding that the steel wire rope in sunpender hinders sliding bar, in the upper table of sliding bar Face is provided with the recessing groove passed through for steel wire rope.
Further, two steel wire rope ends close to each other are respectively equipped with clasp and buckle mouth.
By using above-mentioned technical proposal, there is clasp in two steel wire rope end sets close to each other and buckle mouth, it is real The connection and separation of existing two steel wire ropes, so as to coordinate the opening and closing of sliding bar, facilitate operating personnel's operation.
Further, hanging ring is fixed with the wall top, the steel wire rope is fixed on hanging ring.
By using above-mentioned technical proposal, be individually for steel wire rope and upper lift ring fixed in wall top, with sunpender and brace with The connecting portion of wall top separates, and ensures after sunpender and brace are separated with wall top, steel wire rope is unaffected remain to play it is anti- Shield acts on.
Further, guide pad is equipped with along fixing sleeve pole length direction, on the fixed loop bar inner wall outside the sliding bar Coordinate on wall along sliding bar length direction and be equipped with guide groove.
By using above-mentioned technical proposal, in order to be oriented to the sliding of sliding bar, guiding is fixed with fixed loop bar inner wall Block, coordinates on sliding bar outer wall and is provided with guide groove, is connected so as to stablize fixed loop bar with the sliding of sliding bar.
Further, the end of two sliding bars is equipped with the limiting plate more than fixing sleeve boom end area.
By using above-mentioned technical proposal, on the one hand, sliding bar excessive slip can be avoided by sliding the limiting plate of boom end And depart from fixing sleeve bar part, on the other hand, the setting of limiting plate can facilitate operating personnel to catch limiting plate to pull slip Bar.
Further, a sliding bar is equipped with groove, another slip close to the end of another sliding bar Bar coordinates close to the end of groove is equipped with convex block, and the screw hole for being provided with and passing through for bolt is penetrated through on the groove and convex block.
By using above-mentioned technical proposal, when sliding bar is only connected with fixed sleeved rod portion position, sliding bar can be in electromechanical equipment Pressure under bend.Therefore, in a sliding bar end set upper groove, it is equipped with the end of another piece of sliding bar There is convex block, convex block is inserted into groove stable stress point is provided to sliding bar.In addition, the company by screw bolt reinforcing sliding bar Connect, prevent sliding bar from sliding, electromechanical equipment is lost support and is threatened personnel safety.
Further, the supporting rod bottom surface is fitted with bearing plate, and described bearing plate one end is rotatably connected on fixing sleeve On bar, the other end is by hasp connection on another fixed loop bar.
By using above-mentioned technical proposal, although sliding bar both ends close to each other are plugged together together to share pressure, It is that after electromechanical equipment is placed on sliding bar, pressure concentrates on the connecting portion of sliding bar, and the easy stress in sliding bar junction becomes Shape.Therefore, the pressure of sliding bar, is shared the sunpender and brace at supporting rod both ends by the bearing plate in the connection of supporting rod bottom On, so as to stabilize para-seismic support.In addition, bearing plate one end is rotatably connected on fixed loop bar, the other end passes through hasp connection On another fixed loop bar, facilitate operating personnel to open bearing plate and carry out operation.
In conclusion the utility model has the advantages that:
1. by the sliding bar being slidably connected in fixed loop bar, the folding of para-seismic support bottom is realized, so that convenient behaviour Supporting rod, which is pulled open, as personnel exposes electromechanical equipment progress operation;
2. by the steel wire rope set in para-seismic support, play the role of secondary protection to the electromechanical equipment in para-seismic support.
Brief description of the drawings
Fig. 1 is a kind of overall structure diagram of para-seismic support of the utility model;
Fig. 2 is sunpender and confined explosion's sectional view of supporting rod part;
Fig. 3 is the enlarged drawing of C portion in Fig. 2;
Fig. 4 is the enlarged drawing of part A in Fig. 1;
Fig. 5 is the enlarged drawing of part B in Fig. 1.
In figure, 1, sunpender;11st, brace;12nd, electromechanical equipment;2nd, supporting rod;21st, fixed loop bar;211st, guide pad;22、 Sliding bar;221st, guide groove;222nd, limiting plate;3rd, groove;31st, convex block;32nd, screw hole;33rd, bolt;4th, bearing plate;41st, rotate Axis;42nd, hasp;5th, hanging ring;51st, steel wire rope;52nd, clasp;53rd, mouth is detained;54th, recessing groove.
Embodiment
The utility model is described in further detail below in conjunction with attached drawing.
Embodiment:
A kind of para-seismic support, as shown in Figure 1, including two sunpenders 1 being fixed on vertically in wall top, and two sunpenders 1 it Between be reserved with installation electromechanical equipment 12 space, be connected with supporting rod 2, and 2 both ends of supporting rod in the lower horizontal of two sunpenders 1 It is connected with brace 11(Sunpender 1, supporting rod 2 and brace 11 all use square channel steel), end of the brace 11 away from supporting rod 2 Portion is fixed in wall top.Here, in order to realize anti seismic efficiency using the stability principle of triangle, set brace 11 is inclined Put, and two braces 11 are fixed with 2 one end of supporting rod.In the utility model this embodiment, 2 folding of supporting rod is set Put, facilitate operating personnel to open supporting rod 2, to carry out operation to the electromechanical equipment 12 on supporting rod 2.In addition, the end of sunpender 1 It is fixed on by connecting seat in wall top, and the end of brace 11 is connected by antidetonation connecting elements with wall top and supporting rod 2.
In order to realize the folding of supporting rod 2, as shown in Fig. 2, supporting rod 2 includes being fixed on two fixations of 1 bottom of sunpender Loop bar 21, and fixed loop bar 21 is hollow setting, supporting rod 2 further includes the sliding bar 22 being slidably connected in fixed loop bar 21, And two sliding bars 22 slide along 2 length direction of supporting rod and set.Two 22 one end of sliding bar are connected with each other, and the other end stretches out solid Determine loop bar 21 to set.As shown in Figure 2, on the one hand, in order to be oriented to the sliding of sliding bar 22, in fixed loop bar 21 at least side inner wall On be fixed with the bar shaped guide pad 211 set along fixed 21 length direction of loop bar, 22 outer wall of sliding bar corresponds to bar shaped guide pad 211 Guide groove 221 is provided with, guide pad 211 is inserted in corresponding guide groove 221;On the other hand, in order to avoid sliding bar 22 is sliding During depart from fixed loop bar 21, the limit more than 21 end area of fixed loop bar is set respectively at the both ends of two sliding bars 22 Position plate 222.
In order to consolidate the connection of two sliding bars 22, as shown in Figures 2 and 3, two sliding bars 22 end close to each other Place, an end, which inwardly collapses, is provided with square groove 3, another end is fixed with the convex block 31 coordinated with groove 3.By two The end of sliding bar 22 is slid onto 2 centre position of supporting rod, and convex block 31 is inserted into groove 3, convex block 31 and groove 3 side wall point Perforation is not corresponded to and is provided with screw hole 32, bolt 33 is fixed in screw hole 32, the fixation of sliding bar 22 can be realized by tightening bolt 33 Connection.
When being placed with electromechanical equipment 12 on sliding bar 22, electromechanical equipment 12 applies pressure, pressure one to sliding bar 22 It is allocated as being used in the connecting portion of two sliding bars 22, another part acts on the connecting portion of sliding bar 22 and fixed loop bar 21 On, the easy stress deformation of connecting portion of two sliding bars 22, influences the normal use of para-seismic support.Therefore, such as Fig. 2, Fig. 4 and figure Shown in 5, the bearing plate 4 for being fitted in 22 bottom of sliding bar is additionally provided between two fixed loop bars 21(At this time, two sliding bars 22 are in connection status), 4 one end of bearing plate is connected to the bottom of a fixed loop bar 21 by rotation axis 41, and the other end passes through Hasp 42 is connected to the bottom of another fixed loop bar 21, is set electromechanics using the bearing plate 4 being connected between fixed loop bar 21 Standby 12 pressure shares 2 both ends of supporting rod, and main pressure is shared by the sunpender 1 and brace 11 for making 2 both ends of supporting rod, carries The security of high anti-seismic stent.In addition, as shown in figures 1 and 3, put to be bonded respectively in 22 upper and lower surface of sliding bar Electromechanical equipment 12 and bearing plate 4 are put, the limiting plate 222 of two 22 junctions of sliding bar is only protruded in 22 two side of sliding bar to be set Put, avoid the limiting plate 222 of the protrusion of upper and lower both sides from hindering the placement of electromechanical equipment 12 and bearing plate 4.
In addition, earthquake is occurring, when sunpender 1 and brace 11 the disengaging wall top of para-seismic support part lose protective action, The para-seismic support of steel can threaten the safety of personnel.Therefore, as depicted in figs. 1 and 2, upper lift ring 5 is fixed in wall top, Hanging ring 5 is located at the connecting portion of sunpender 1 and wall top on one side, connects steel cable 51 respectively on hanging ring 5, and steel wire rope 51 is from hanging For the internal stretch of bar 1 to 2 position of supporting rod, steel wire rope 51 passes through fixed loop bar 21 to enter in sliding bar 22, is grown along sliding bar 22 The connecting portion of two sliding bars 22 is led in degree direction, as shown in figure 3, two steel wire ropes 51 lead in the coupling part of sliding bar 22 The clasp 52 and button mouth 53 for crossing end set connect.On the one hand, it is real by the clasp 52 and button mouth 53 of 22 connecting portion of sliding bar The folding connection of existing steel wire rope 51, coordinates the sliding of sliding bar 22, facilitates operating personnel's operation;On the other hand, such as Fig. 1 and Fig. 2 It is shown, electromechanics can be held after sunpender 1 and brace 11 are ineffective in the steel wire rope 51 of relaxed state under normal condition and set Standby 12, play the role of secondary protection.
Sliding bar 22 can be blocked, therefore, as shown in Fig. 2, in sliding bar 22 in sliding by the steel wire rope 51 of vertical direction Upper surface correspond to 51 position of steel wire rope and be provided with recessing groove 54 along 22 length direction of sliding bar.
The course of work:The para-seismic support being set up in parallel by several supports electromechanical equipment 12, is needing to antidetonation branch Electromechanical equipment 12 on frame safeguarded, is replaced and during deflecting, opens bearing plate 4, loosers a bolt 33, and two sliding bars 22 are drawn Open, then clasp 52 is taken out from button mouth 53, operation can be carried out to the electromechanical equipment 12 exposed;After construction, it will detain Hook 52 buckles into mouth 53, two sliding bars 22 is close to, then screw on bolt 33.
When the sunpender 1, brace 11 or supporting rod 2 of para-seismic support are damaged, and cannot fasten electromechanical equipment 12, 51 stress of steel wire rope in para-seismic support collapses the electromechanical equipment 12 for tightly, holding whereabouts, guarantees personal safety.
The above is only the preferred embodiment of the utility model, and the scope of protection of the utility model is not limited merely to Above-described embodiment, all technical solutions belonged under the utility model thinking belong to the scope of protection of the utility model.It should refer to Go out, for those skilled in the art, some improvement under the premise of the utility model principle is not departed from and Retouching, these improvements and modifications also should be regarded as the scope of protection of the utility model.

Claims (8)

1. a kind of para-seismic support, including two vertical sunpenders for being fixed on wall top(1), the sunpender(1)Between be horizontally fixed with Supporting rod(2), the supporting rod(2)Both ends are provided tiltedly with the brace for being fixed on wall top(11), it is characterised in that:The support Bar(2)Sunpender is fixed on including two(1)The fixation loop bar of bottom(21), the every fixed loop bar(21)Middle sliding is equipped with one Root sliding bar(22), two sliding bars(22)End close to each other passes through bolt(33)Fix.
A kind of 2. para-seismic support according to claim 1, it is characterised in that:The sunpender(1)And sliding bar(22)In wear Equipped with two steel wire ropes(51), the steel wire rope(51)One end is fixed in wall top, and the other end is connected with each other, the sliding bar (22)Upper surface be provided with along glide direction for steel wire rope(51)The recessing groove passed through(54).
A kind of 3. para-seismic support according to claim 2, it is characterised in that:Two steel wire ropes(51)At interconnection It is respectively equipped with clasp(52)With button mouth(53).
A kind of 4. para-seismic support according to claim 3, it is characterised in that:The wall top is fixed with hanging ring(5), the steel Cord(51)It is fixed on hanging ring(5)On.
A kind of 5. para-seismic support according to claim 1, it is characterised in that:The fixed loop bar(21)At least side inner wall On along fixed loop bar(21)Length direction is equipped with guide pad(211), the sliding bar(22)Along sliding bar on outer wall(22)Length Direction, which coordinates, is equipped with guide groove(221).
A kind of 6. para-seismic support according to claim 5, it is characterised in that:Two sliding bars(22)End be equipped with More than fixed loop bar(21)The limiting plate of end area(222).
A kind of 7. para-seismic support according to claim 6, it is characterised in that:A piece sliding bar(22)Close to another Sliding bar(22)End be equipped with groove(3), another sliding bar(22)Close to groove(3)End coordinate be equipped with convex block (31), the groove(3)And convex block(31)Side perforation is provided with screw hole(32).
8. a kind of para-seismic support according to claim 7 is characterized in that:The supporting rod(2)Bottom surface is fitted with load-bearing Plate(4), the bearing plate(4)One end is rotatably connected on fixed loop bar(21)On, the other end passes through hasp(42)It is connected to another Root fixes loop bar(21)On.
CN201721274891.5U 2017-09-29 2017-09-29 A kind of para-seismic support Active CN207246741U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201721274891.5U CN207246741U (en) 2017-09-29 2017-09-29 A kind of para-seismic support

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201721274891.5U CN207246741U (en) 2017-09-29 2017-09-29 A kind of para-seismic support

Publications (1)

Publication Number Publication Date
CN207246741U true CN207246741U (en) 2018-04-17

Family

ID=61889696

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201721274891.5U Active CN207246741U (en) 2017-09-29 2017-09-29 A kind of para-seismic support

Country Status (1)

Country Link
CN (1) CN207246741U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108644549A (en) * 2018-07-25 2018-10-12 深圳易信科技股份有限公司 A kind of machine cabinet load-bearing para-seismic support
CN110332376A (en) * 2019-07-17 2019-10-15 上海柘歆科技集团有限公司 A kind of vertical para-seismic support in water pipe side

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108644549A (en) * 2018-07-25 2018-10-12 深圳易信科技股份有限公司 A kind of machine cabinet load-bearing para-seismic support
CN110332376A (en) * 2019-07-17 2019-10-15 上海柘歆科技集团有限公司 A kind of vertical para-seismic support in water pipe side
CN110332376B (en) * 2019-07-17 2021-05-14 上海柘歆科技集团有限公司 Anti-seismic support is indulged to water pipe side

Similar Documents

Publication Publication Date Title
CN207246741U (en) A kind of para-seismic support
CN205116912U (en) Transformer substation's maintenance is with safe device that blocks
CN211691069U (en) Installation and displacement monitoring structure of spoke type beam string
CN206256704U (en) A kind of umbrella shape high-altitude protection safety net
CN106395605A (en) System for hoisting steel lining module of nuclear power station
CN104638589B (en) Special tool for lifting tubular bus bar
BR102015019922A2 (en) system improvements for horizontal type temporary lifeline assembly
CN214379737U (en) Distribution lines steps on pole operation auxiliary platform
CN207673269U (en) A kind of rope ladder head for high ferro repair
CN201206960Y (en) Bulletproof carrying vest
CN211751942U (en) Building constructor safety arrangement
CN208633574U (en) It is a kind of with preventing people from falling the safety net of effect
CN206081565U (en) Gymnastic training auxiliary protection device
CN208525688U (en) A kind of steel I-beam spraying safety belt suspension protective device
CN206970169U (en) A kind of aerial work platform protection mechanism
CN208272104U (en) Novel three tower
CN106078757A (en) Fire rescue robot of a kind of transformer station Multi-freedom-degreemanipulator manipulator
CN104064984A (en) Double split wire line maintenance pulley
CN206487132U (en) A kind of high-altitude hanging basket safety device
CN211507139U (en) Lead clothing removes subtracts burden and uses auxiliary system
CN213742444U (en) Security protection device for construction
CN104740849B (en) Steep cliff prompt drop bracing frame
CN216091924U (en) Fire escape device
CN206942301U (en) A kind of suspension type tent
CN209324014U (en) A kind of adjustable architectural engineering protective stent