CN207218247U CN201620797947.4U CN201620797947U CN207218247U CN 207218247 U CN207218247 U CN 207218247U CN 201620797947 U CN201620797947 U CN 201620797947U CN 207218247 U CN207218247 U CN 207218247U
Authority
CN
China
Prior art keywords
communication interface
power network
interface end
main frame
output end
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201620797947.4U
Other languages
Chinese (zh)
Inventor
吴军
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
JINGJIANG XUFEI SECURITY ENGINEERING Co Ltd
Original Assignee
JINGJIANG XUFEI SECURITY ENGINEERING Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by JINGJIANG XUFEI SECURITY ENGINEERING Co Ltd filed Critical JINGJIANG XUFEI SECURITY ENGINEERING Co Ltd
Priority to CN201620797947.4U priority Critical patent/CN207218247U/en
Application granted granted Critical
Publication of CN207218247U publication Critical patent/CN207218247U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Remote Monitoring And Control Of Power-Distribution Networks (AREA)

Abstract

The utility model discloses a kind of high voltage electric net device, including the interior power network main frame provided with emergency button, the output end of the power network main frame is connected by 485 buses with multiple power network extension sets;When the power network main frame due to failure can not normal work when, can by the emergency button to the power network extension set carry out emergency service;Wherein, the power network main frame includes CPU processing units, its the first communication interface end is connected with keyboard, its the second communication interface end is connected with LCD MODULE, its the 3rd communication interface end is connected with LED light, its the 4th communication interface end is connected with switching value output module, its the 5th communication interface end is connected with 485 extension set communication modules, its the 6th communication interface end is connected with alarm output module, its the 7th communication interface end is connected with TCP/IP network communication modules, and its 8th communication interface end is connected with 485 dataphone modules;The utility model has abundant communication, remote alarm interface, can be independently operated, also networking and be connected to integrated platform.

Description

A kind of high voltage electric net device
Technical field
It the utility model is related to a kind of high voltage electric net device.
Background technology
At present there is wrong report, rate of failing to report height in some existing power network products, easily be influenceed by factors such as weather, some electricity Subnormal voltage operation can only drop in the rainy day in net device or pause uses, and have that power consumption is big, power utilization rate is low, environment self-adaption Can be poor, Function Extension performance is poor, construction costs is high the shortcomings of.
Utility model content
The purpose of the utility model is to provide the utility model technology that needs solve the defects of for prior art presence to ask Topic is to overcome the shortcomings of existing power network product in technical background, and meets the requirement of GB 25287-2010 national standards.This High voltage electric net device employs a kind of advanced control mode, mainly have managing main frame, extension set control box, high pressure detection resistance, High-voltage booster etc. forms, and has accomplished that strong adaptability, power utilization rate are high, save, has effectively solved above deficiency, reach Excellent performance.
The utility model to achieve the above object, adopts the following technical scheme that:A kind of high voltage electric net device, including interior be provided with The power network main frame of emergency button, the output end of the power network main frame are connected by 485 buses with multiple power network extension sets;When the electricity Host's machine due to failure can not normal work when, can by the emergency button to the power network extension set carry out emergency service;Its In, the power network main frame includes CPU processing units, and its first communication interface end is connected with keyboard, its second communication interface end with LCD MODULE is connected, and its 3rd communication interface end is connected with LED light, and its 4th communication interface end and switching value are defeated Go out module connection, its 5th communication interface end is connected with 485 extension set communication modules, its 6th communication interface end and warning output mould Block is connected, and its 7th communication interface end is connected with TCP/IP network communication modules, its 8th communication interface end and 485 dataphones Module connects;The power network extension set include input exchanged with 220V electrically connect filter circuit, the first of the filter circuit Output end is connected with driving plate, and the second output end of the filter circuit is connected with control panel;Wherein, the output of the driving plate End is connected with step-up transformer, and it is defeated that the first output end of the step-up transformer by high voltage switching device is connected to the first high pressure Go out end, the second output end of the step-up transformer is connected to the second High voltage output portion;The control signal of the control panel It is connected by 485 bus with power network main frame, detection signal detection input and the detection conversion module of the control panel connect Connect, the voltage signal test side of the detection conversion module and the output with the step-up transformer respectively of electric quantity signal test side End connection.
The beneficial effects of the utility model:
1st, the utility model complies fully with GB 25287-2010 national standards;
2nd, the utility model has abundant communication, remote alarm interface, can be independently operated, also networking and be connected to integrated flat Other safety-protection systems such as platform use;
3rd, the utility model adaptivity is strong, there is fine, rain mode of operation, is adapted to various environment to use;
4th, the utility model has tamper-proof, short-circuit function, when main frame can not work, each extension set energy independent operating, most Limits accomplish to run without interruption;Short-circuit between conductors successor so possesses strike effect over the ground;
5th, the distinctive design that polarises of the utility model so that can produce high pressure between every line of outer net.
Brief description of the drawings
Fig. 1 is allomeric function schematic diagram of the present utility model.
Fig. 2 is power network host function schematic diagram of the present utility model.
Embodiment
Shown in Fig. 1 to Fig. 2, it is related to a kind of high voltage electric net device, including the interior power network main frame provided with emergency button, the electricity The output end of host's machine is connected by 485 buses with multiple power network extension sets;When the power network main frame because failure can not normal work When making, emergency service can be carried out to the power network extension set by the emergency button;It is uninterrupted to ensure that high pressure intercepts function;Extension set Can independent operating work, can be also managed collectively by main frame.It can make electric net device not because a certain part occurs in this way Failure and the normal operation for influenceing whole system.
Fig. 2 is the functional schematic of power network main frame, and the power network main frame includes CPU processing units 21, and its first communication connects Mouth end is connected with keyboard 22, and its second communication interface end is connected with LCD MODULE 23, and its 3rd communication interface end refers to LED Show that lamp 24 connects, its 4th communication interface end is connected with switching value output module 25, its 5th communication interface end and extension set 485 Communication module 26 is connected, and its 6th communication interface end is connected with alarm output module 27, its 7th communication interface end and TCP/IP Network communication module 28 is connected, and its 8th communication interface end is connected with 485 dataphone modules 29;
Wherein, running parameter is inputted central processing unit by keyboard and broadcasts to each power network point by central processing unit Machine;LCD MODULE can inquire about various arranges values, and by works such as each power network extension set present operating voltage, electric current, strike electric currents Make state real-time display to come out;LED light can intuitively find out each extension set whether normal work and net-fault, suspension, short circuit, withdraw a garrison Etc. alarm condition;Alarm output module can provide the alarm switch amount signal output of each power network extension set, convenient to be set with other Standby linkage;485 extension set communication modules are responsible for communicating between main frame and extension set;It is defeated that alarm output module provides total alarm switch amount Go out, acoustic-optic alarm can be driven, can know that TCP/IP network communication modules are to pass through in time to there is policeman after alert Main frame access to LAN is realized remote management by TCP/IP modes;485 dataphone modules are to be connect main frame using 485 modes Enter LAN, realize remote management.
The structure combines the management control function for realizing power network main frame by each feature board, gives maintenance, repair band To greatly facilitate;Electric net device will not should be some component malfunction and cause the paralysis of whole host computer system so that be The more stable operation of system;Maintenance cost is reduced, which part goes wrong changes for which part, has accomplished convenience, simple, reality With.User can set different fine day rainy day running parameter according to the weather conditions of locality simultaneously so that electric net device can be Any area uses.
The power network extension set includes the filter circuit that input exchanges electrical connection with 220V, and the first of the filter circuit is defeated Go out end to be connected with driving plate, the second output end of the filter circuit is connected with control panel;Wherein, the output end of the driving plate It is connected with step-up transformer, the first output end of the step-up transformer is connected to the first High voltage output by high voltage switching device End, the second output end of the step-up transformer are connected to the second High voltage output portion;The control signal of the control panel is led to 485 bus to be crossed to be connected with power network main frame, the detection signal detection input of the control panel is connected with detection conversion module, The voltage signal test side of the detection conversion module and the electric quantity signal test side output end with the step-up transformer respectively Connection.
In the system, the generation of high-tension electricity, which employs to tap into 220V alternating current directs after row zero passage detection, is added to extraordinary boosting The input of transformer, required high tension voltage is obtained after directly being boosted by special transformer.Use this scheme Major advantage is:1) electromagnetic interference is very small, does not disturb the normal work of other equipment;2) control accuracy is high, response speed It hurry up, it is possible to achieve timely precision strike;3) double winding output HIGH voltage, voltage between lines reach twice that single channel realizes voltage, The big raising of voltage breakdown ability, improve the effect of protection and tamper-proof ability.4) by Phototube Coupling, control is substantially increased The antijamming capability of system processed, it ensure that user uses the safety of equipment;5) controlled by control system, it is normal in assurance function On the premise of, the power consumption of system is very small, can greatly save using electric energy.
Concrete principle is:After the filtered and anti-interference suppression of 220V alternating currents, power supply is added to driving plate all the way, by driving Plate control 220V is added to the cycle of power supply on high-tension transformer, required for by special transformer, 220V alternating currents are increased to Voltage (presses national standard, the high voltage highest of output can reach 7KV per road, and the voltage highest between two-way high pressure can reach To 14KV);Alternating current provides power supply for control panel all the way in addition, and control panel constantly detects under the control of high-speed microprocessor The voltage and electricity that sampling conversion obtains from high-voltage line, so as to control the work of driving plate, realize high-voltage fence national standard The required various functions reached.
It is understood that work as high pressure one, and after high pressure two is output to outer net, by iron wire or other conductive materials by outer net After short circuit, the high pressure between line-line can disappear, although at this moment system meeting and alarm should be outer net high pressure and disappeared, people Member also can be achieved on what is run away.So we have installed a set of high voltage switching device additional, after being short-circuited between outer netting twine-line, So that still there is high pressure between line-ground.
Operation principle:Main frame sets the running parameters such as strike electricity, alarm trigger current according to practical service environment, passes through Bus broadcast gives each extension set control device.Extension set control device is mainly by power supply, control panel, high pressure detection resistance and high pressure liter Depressor is formed, and the power frequency sine wave of signal period is sent during normal work, and high voltage supply outer net, detection are produced by high-voltage booster The voltage of the high tension loop detected, current value are fed back to high-speed microprocessor processing unit by circuit, and electric current, the electricity preset Pressure is compared, and lasting high-tension current is exported immediately after meeting alert if, until the strike electricity of output meets default mark Untill standard, then detect, if normal recover normal working condition, while real-time voltage, electric current equivalence are sent to master Machine, main frame show various information by liquid crystal display.
Preferred embodiment of the present utility model is the foregoing is only, it is all in this practicality not to limit the utility model Within new spirit and principle, any modification, equivalent substitution and improvements made etc., guarantor of the present utility model should be included in Within the scope of shield.

Claims (1)

  1. A kind of 1. high voltage electric net device, it is characterised in that including the interior power network main frame provided with emergency button, the power network main frame Output end is connected by 485 buses with multiple power network extension sets;When the power network main frame due to failure can not normal work when, can lead to Cross the emergency button and emergency service is carried out to the power network extension set;Wherein, the power network main frame includes CPU processing units, its First communication interface end is connected with keyboard, and its second communication interface end is connected with LCD MODULE, its 3rd communication interface end Be connected with LED light, its 4th communication interface end is connected with switching value output module, its 5th communication interface end with 485 points Machine communication module is connected, and its 6th communication interface end is connected with alarm output module, its 7th communication interface end and TCP/IP nets Network communication module is connected, and its 8th communication interface end is connected with 485 dataphone modules;The power network extension set include input with The filter circuit of 220V exchange electrical connections, the first output end of the filter circuit are connected with driving plate, the filter circuit Second output end is connected with control panel;Wherein, the output end of the driving plate is connected with step-up transformer, the step-up transformer The first output end the first High voltage output end, the second output end of the step-up transformer are connected to by high voltage switching device It is connected to the second High voltage output portion;The control signal of the control panel is connected by 485 bus with power network main frame, described The detection signal detection input of control panel is connected with detection conversion module, the voltage signal test side of the detection conversion module It is connected with output end of the electric quantity signal test side respectively with the step-up transformer.
CN201620797947.4U 2016-07-27 2016-07-27 A kind of high voltage electric net device Active CN207218247U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620797947.4U CN207218247U (en) 2016-07-27 2016-07-27 A kind of high voltage electric net device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620797947.4U CN207218247U (en) 2016-07-27 2016-07-27 A kind of high voltage electric net device

Publications (1)

Publication Number Publication Date
CN207218247U true CN207218247U (en) 2018-04-10

Family

ID=61809029

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620797947.4U Active CN207218247U (en) 2016-07-27 2016-07-27 A kind of high voltage electric net device

Country Status (1)

Country Link
CN (1) CN207218247U (en)

Similar Documents

Publication Publication Date Title
CN203366116U (en) Oil field well site data acquisition system based on Internet of things
CN206684949U (en) The traffic lights that a kind of running status independently additionally monitors
CN206164082U (en) Ore deposit lost circulation electric protection device based on pour into signal method into
CN205681181U (en) A kind of Dual-power automatic switching controller
CN201503462U (en) Dispersion-type fault alarm unit of LED signal controller
CN109802489A (en) A kind of solar energy photovoltaic panel TTC & DT Systems based on power line carrier
CN207218247U (en) A kind of high voltage electric net device
CN209800225U (en) Water pump working condition monitoring instrument
CN106093478A (en) A kind of intelligent electric power data module and split type display
CN206259751U (en) A kind of intelligent lightning protecting power distribution equipment
CN203274837U (en) Water inflow alarm device for cargo hold of ship
CN205725135U (en) Three-phase intelligent seamless auto switching device for dual-electric source
CN202997699U (en) Intelligent breaker controller
CN204272159U (en) A kind of energy source gateway realizing fault electric arc and detect
CN205445987U (en) Water pump controller
CN209709742U (en) Double-CT power taking and supplying device for high-voltage cable monitoring equipment
CN205027847U (en) System for remove power supply ground connection state real -time supervision and fault locating
CN208376783U (en) Minimize the dedicated LED signal machine of rail traffic
CN202256522U (en) Insulating monitor and medical isolating power system
CN206564029U (en) A kind of active filter monitoring system being wirelessly transferred
CN206180693U (en) Box -type substation monitored control system
CN103729958A (en) Periphery high-voltage electrified fence device
CN206004977U (en) Intelligent road-lamp with residual current protecting controls chopper
CN221150966U (en) Electric energy quality comprehensive treatment device based on operation compensation