CN207175539U - A kind of heat power plant boiler make-up water ultrafiltration air purge gas source pipe device - Google Patents

A kind of heat power plant boiler make-up water ultrafiltration air purge gas source pipe device Download PDF

Info

Publication number
CN207175539U
CN207175539U CN201720393074.5U CN201720393074U CN207175539U CN 207175539 U CN207175539 U CN 207175539U CN 201720393074 U CN201720393074 U CN 201720393074U CN 207175539 U CN207175539 U CN 207175539U
Authority
CN
China
Prior art keywords
source
gas
power plant
air purge
branch pipe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201720393074.5U
Other languages
Chinese (zh)
Inventor
陈俊卫
陈仕键
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Electric Power Research Institute of Guizhou Power Grid Co Ltd
Original Assignee
Electric Power Research Institute of Guizhou Power Grid Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Electric Power Research Institute of Guizhou Power Grid Co Ltd filed Critical Electric Power Research Institute of Guizhou Power Grid Co Ltd
Priority to CN201720393074.5U priority Critical patent/CN207175539U/en
Application granted granted Critical
Publication of CN207175539U publication Critical patent/CN207175539U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model discloses a kind of heat power plant boiler make-up water ultrafiltration air purge gas source pipe device, including milipore filter(1), source of the gas branch pipe(2), the first source of the gas supervisor(3), the second source of the gas supervisor(4)And valve(5), described milipore filter(1)With source of the gas branch pipe(2)Connection;Source of the gas branch pipe(2)It is responsible for the first source of the gas(3)Connection;Second source of the gas is responsible for(4)One end is responsible for the first source of the gas(3)Medium position connects, and terminal membrane air inflow differs greatly problem before and after solving ultrafiltration, greatly prolongs milipore filter run time, reduces boiler feedwater workshop operation cost.

Description

A kind of heat power plant boiler make-up water ultrafiltration air purge gas source pipe device
Technical field
It the utility model is related to a kind of ultrafiltration air purge gas source pipe device, particularly a kind of heat power plant boiler make-up water Ultrafiltration air purge gas source pipe device, belong to power plant boiler make-up water water making device technical field.
Background technology
Following construction of fire and electricity is overcritical by mainly development high efficiency high parameter(SC)And ultra supercritical(USC)Thermal motor Group, they have widely been studied and applied in developed country.But supercritical unit is high to boiler feedwater water quality requirement, Therefore boiler feedwater membrane technology will turn into development trend.Ultrafiltration membrance filter precision is far above conventional filter, to suspending Particulate matter, colloid, microorganism, bacterium, viral removal rate are remarkably improved the permeant flux of follow-up film process, saved up to 100% Subsequent film dosage, efficiency and stability that follow-up cleaning frequency membrane improves follow-up film process is greatly lowered.Ultrafiltration belongs to filter membrane Filtering technique, is a kind of pressure-actuated filtering technique, and hydraulic pressure is entered into component with pump, poor by the mould of filter membrane(TMP)Intake To filtering, impurities in water is removed by filter membrane, and impurity is left in influent side, when by except impurity concentration uprise when, in filter membrane table Impurity deposit layers caused by face, sedimentary can change its filtering property and required filter pressure, so as to cause ultrafiltration pressure difference liter Higher position must carry out conventional backwash.Air purge is a most important step in ultrafiltration conventional backwash link, air purge main wash milipore filter The impurity deposit layers thing that the impurity deposit layers thing left, particularly Chemical cleaning are also difficult to clean off.As air purge dynamics not enough if surpass Filter membrane pressure difference can not just be down to runtime value.One end air inlet that the gas source pipe design of ultrafiltration at present uses, causes front and rear terminal membrane air inlet Amount differs greatly, and as long-time air purge dynamics is inadequate, rear terminal membrane impurity deposit layers thing can cumulative blocking film wire.
Utility model content
The technical problems to be solved in the utility model is:A kind of heat power plant boiler make-up water ultrafiltration air purge gas source pipe Device, terminal membrane air inflow differs greatly problem before and after solving ultrafiltration, greatly prolongs milipore filter run time, reduces boiler feedwater Workshop operation cost.
The technical solution of the utility model is:A kind of heat power plant boiler make-up water ultrafiltration air purge gas source pipe device, Including milipore filter, source of the gas branch pipe, the first source of the gas supervisor, the second source of the gas supervisor, source of the gas drier and valve, described milipore filter and Source of the gas branch pipe connects;Source of the gas branch pipe and the supervisor's connection of the first source of the gas;Second source of the gas is responsible for one end and position in the first source of the gas supervisor Put connection.
Described milipore filter at least two.
Described the first source of the gas supervisor is arranged between two milipore filters.
Described source of the gas branch pipe is stainless steel.
Described the first source of the gas supervisor is stainless steel.
Described the second source of the gas supervisor is stainless steel.
Described valve is separately positioned on source of the gas branch pipe, the first source of the gas supervisor and the second source of the gas supervisor, described valve For stainless steel.
Be compared with the prior art, using the technical solution of the utility model by the gas source pipe of ultrafiltration from one end air inlet makes into Portion's air inlet, can quickly solve front and rear terminal membrane air inflow and differ greatly problem, and be easy to transform, improvement cost is relatively low.
Brief description of the drawings
Fig. 1 is the utility model structure drawing of device;
In figure:1st, milipore filter, 2, source of the gas branch pipe, the 3, first source of the gas supervisor, the 4, second source of the gas supervisor, 5, valve.
Embodiment
The utility model is further illustrated below in conjunction with the accompanying drawings
Shown in Fig. 1, a kind of heat power plant boiler make-up water ultrafiltration air purge gas source pipe device, including milipore filter 1, source of the gas Branch pipe 2, the first source of the gas are responsible for the 3, second source of the gas supervisor 4 and valve 5, milipore filter 1 and source of the gas branch pipe 2 connect;Source of the gas branch pipe 2 and The connection of one source of the gas supervisor 3;Second source of the gas is responsible for 4 one end and is connected with the first source of the gas 3 medium positions of supervisor.
Further milipore filter 1 at least two, inside the apparatus structure of multiple milipore filters 1, the reality of the technical program Shi Caineng plays substantial role.
Further first source of the gas supervisor 3 is arranged between two milipore filters, and it is poor quickly to solve front and rear terminal membrane air inflow Different larger problem.
Further source of the gas branch pipe 2 is stainless steel, and stainless steel is not easy to get rusty, and reliability is high, will not be because of pipe Road internal rust causes gas source pipe to block.
Further first source of the gas supervisor 3 is stainless steel, and stainless steel is not easy to get rusty, and reliability is high, Bu Huiyin Gas source pipe is caused to block for pipeline internal rust.
Further second source of the gas supervisor 4 is stainless steel, and stainless steel is not easy to get rusty, and reliability is high, Bu Huiyin Gas source pipe is caused to block for pipeline internal rust.
Further valve 5 is separately positioned on source of the gas branch pipe 2, the first source of the gas supervisor 3 and the second source of the gas supervisor 4, is set Valve 5 is easy to device independently to overhaul, and will not cause to fill a device stoppage in transit because single assembly overhauls
Further valve 5 is stainless steel, and stainless steel is not easy to get rusty, and reliability is high, will not be because of in pipeline Portion, which gets rusty, causes gas source pipe to block.
It can be tested after the installation that each equipment and original paper are carried out according to the technical solution of the utility model connects.

Claims (5)

1. a kind of heat power plant boiler make-up water ultrafiltration air purge gas source pipe device, including milipore filter(1), source of the gas branch pipe(2)、 First source of the gas is responsible for(3), the second source of the gas supervisor(4)And valve(5), it is characterised in that:Described milipore filter(1)With source of the gas branch pipe (2)Connection;Source of the gas branch pipe(2)It is responsible for the first source of the gas(3)Connection;Second source of the gas is responsible for(4)One end is responsible for the first source of the gas(3) Medium position connects, described milipore filter(1)At least two, the first described source of the gas supervisor(3)Installed in two milipore filters Between.
2. a kind of heat power plant boiler make-up water ultrafiltration air purge gas source pipe device according to claim 1, its feature It is:Described source of the gas branch pipe(2)For stainless steel.
3. a kind of heat power plant boiler make-up water ultrafiltration air purge gas source pipe device according to claim 1, its feature It is:Described the first source of the gas supervisor(3)For stainless steel.
4. a kind of heat power plant boiler make-up water ultrafiltration air purge gas source pipe device according to claim 1, its feature It is:Described the second source of the gas supervisor(4)For stainless steel.
5. a kind of heat power plant boiler make-up water ultrafiltration air purge gas source pipe device according to claim 1, its feature It is:Described valve(5)It is separately positioned on source of the gas branch pipe(2), the first source of the gas supervisor(3)It is responsible for the second source of the gas(4)On, institute The valve stated(5)For stainless steel.
CN201720393074.5U 2017-04-14 2017-04-14 A kind of heat power plant boiler make-up water ultrafiltration air purge gas source pipe device Active CN207175539U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720393074.5U CN207175539U (en) 2017-04-14 2017-04-14 A kind of heat power plant boiler make-up water ultrafiltration air purge gas source pipe device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720393074.5U CN207175539U (en) 2017-04-14 2017-04-14 A kind of heat power plant boiler make-up water ultrafiltration air purge gas source pipe device

Publications (1)

Publication Number Publication Date
CN207175539U true CN207175539U (en) 2018-04-03

Family

ID=61732384

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720393074.5U Active CN207175539U (en) 2017-04-14 2017-04-14 A kind of heat power plant boiler make-up water ultrafiltration air purge gas source pipe device

Country Status (1)

Country Link
CN (1) CN207175539U (en)

Similar Documents

Publication Publication Date Title
CN201120256Y (en) Reverse osmosis membrane cleaning apparatus
CN204051456U (en) A kind of rolled membrane module
CN204798975U (en) Vacuum oil filter of secondary filter and high -efficient dehydration
CN204024729U (en) A kind of Novel backwashing bypath system
CN207175539U (en) A kind of heat power plant boiler make-up water ultrafiltration air purge gas source pipe device
CN206996295U (en) A kind of heat power plant boiler make-up water ultrafiltration air purge gas source pipe system
CN201827174U (en) Multistage purifying oil filter
CN202289674U (en) Impurity filter for water supply pipeline
CN204767779U (en) Coalescence vacuum oil purifier
CN209876893U (en) Safe and stable 100% capacity steam pump water supply system of unit system unit
CN210786488U (en) Oil purification device suitable for metallurgical system
CN2701523Y (en) A washing unit with reverse osmosis membrane
CN208169253U (en) Filtration system for hydraulic oil container
CN101865185B (en) Device for cleaning equipment using fluid
CN207237430U (en) By all kinds of means into the clear water tanks of water filtration storage
CN206069785U (en) A kind of oil production filter
CN204986201U (en) Novel exhaust of pipeline fluid device
CN207056069U (en) Self-cleaning filter device
CN201320423Y (en) Mechanical filter
CN209957522U (en) Seawater desalination device
CN205145854U (en) A CO filter for HYCO device
CN204400723U (en) A kind of high purity water treatment system in early stage with on-line cleaning system
CN205742351U (en) A kind of reverse automatic clearing apparatus of water-fetching head
CN203954804U (en) A kind of closed filter
CN204625340U (en) A kind of coating wastewater treatment unit

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant