CN207175213U - A kind of bearing box cover hoisting auxiliary device in the maintenance for turbine bearing pad - Google Patents

A kind of bearing box cover hoisting auxiliary device in the maintenance for turbine bearing pad Download PDF

Info

Publication number
CN207175213U
CN207175213U CN201720853310.7U CN201720853310U CN207175213U CN 207175213 U CN207175213 U CN 207175213U CN 201720853310 U CN201720853310 U CN 201720853310U CN 207175213 U CN207175213 U CN 207175213U
Authority
CN
China
Prior art keywords
lifting
arm
linking arm
box cover
auxiliary device
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201720853310.7U
Other languages
Chinese (zh)
Inventor
唐震
王志鸿
郭伟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
DATANG TAIYUAN CO-GENERATION POWER PLANT
Original Assignee
DATANG TAIYUAN CO-GENERATION POWER PLANT
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by DATANG TAIYUAN CO-GENERATION POWER PLANT filed Critical DATANG TAIYUAN CO-GENERATION POWER PLANT
Priority to CN201720853310.7U priority Critical patent/CN207175213U/en
Application granted granted Critical
Publication of CN207175213U publication Critical patent/CN207175213U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Load-Engaging Elements For Cranes (AREA)

Abstract

The utility model discloses the bearing box cover hoisting auxiliary device in a kind of maintenance for turbine bearing pad, it includes linking arm, is fixed in first lifting arm of described linking arm one end, and is fixed in the second lifting arm of the linking arm other end;At least two first lifting eyes are offered on first lifting arm, at least two second lifting eyes are offered on second lifting arm, first lifting arm, the linking arm and second lifting arm form closed-in construction, and the hollow position of the closed-in construction forms the avoiding space of communicating pipe.The servicing unit can avoid communicating pipe during lifting so that need not be dismantled communicating pipe in maintenance, so as to simplify maintenance process, reduce overhaul of the equipments difficulty, reduce overhaul of the equipments and maintenance cost.

Description

A kind of bearing box cover hoisting auxiliary device in the maintenance for turbine bearing pad
Technical field
Power plant's repair apparatus technical field is the utility model is related to, is used for more particularly, to one kind in turbine bearing pad maintenance Bearing box cover hoisting auxiliary device.
Background technology
It is a common and important overhauling project in overhaul of steam turbine to check bearing shell, for 330MW unit mesolows For communicating pipe, it is typically adopted the mode connected with Unit valves and is arranged in above steam turbine #4, #5 bearing shell, and 300MW units are same Cai is arranged in above #2, #3 bearing shell Yong Unit valve forms.Such arrangement can improve the economy of unit operation and reliable Property, but certain difficulty is brought to maintenance simultaneously, when checking bearing shell below cross over pipe, driving can not be lifted by crane directly, it is necessary to by even Siphunculus is removed, and causes overhaul of the equipments difficult, maintenance process is cumbersome, and cost is higher.
Therefore it provides the bearing box cover hoisting auxiliary device in a kind of maintenance for turbine bearing pad, to lift by crane Communicating pipe can be avoided in journey so that need not be dismantled communicating pipe in maintenance, so as to simplify maintenance process, reduce overhaul of the equipments hardly possible Degree, overhaul of the equipments and maintenance cost are reduced, just turns into those skilled in the art's urgent problem to be solved.
The content of the invention
The purpose of this utility model is to provide the bearing box cover hoisting auxiliary device in a kind of maintenance for turbine bearing pad, To which communicating pipe can be avoided during lifting so that need not be dismantled communicating pipe in maintenance, so as to simplify maintenance process, reduce Overhaul of the equipments difficulty, reduce overhaul of the equipments and maintenance cost.
In order to solve the above-mentioned technical problem, the utility model provides the bearing box cover in a kind of maintenance for turbine bearing pad Hoisting auxiliary device, including linking arm, be fixed in first lifting arm of described linking arm one end, and to be fixed in the linking arm another Second lifting arm of one end;At least two first lifting eyes are offered on first lifting arm, are opened on second lifting arm Provided with least two second lifting eyes, first lifting arm, the linking arm and second lifting arm form closed-in construction, And the hollow position of the closed-in construction forms the avoiding space of communicating pipe.
In hoisting process, by bearing box cover to be lifted fix on the connecting arm or the device other appropriate positions, The suspension hook of lifting appliance catches on the first lifting eye and the second lifting eye, so that by lifting by crane the first lifting arm and the second lifting arm, Sling the servicing unit and bearing box cover to be lifted;During lifting, because two lifting arms and linking arm form closed-in construction, Top communicating pipe can be passed through by the avoiding space in the middle part of closed-in construction, then communicating pipe can be avoided during lifting, is made Need not be dismantled communicating pipe in must overhauling, so as to simplify maintenance process, reduce overhaul of the equipments difficulty, reduce overhaul of the equipments and Maintenance cost.
Further, first lifting arm includes the first supporting plate and be installed on the outside of first supporting plate first Plate is lifted, first supporting plate is fixed in the linking arm, and first lifting eye is opened in the first lifting plate.
Further, the quantity of first lifting eye is five, and each first lifting eye lifts plate along described first Length direction open up, and be uniformly distributed on the length direction.
Further, it is provided with the first reinforcement between first supporting plate and the linking arm.
Further, second lifting arm includes the second supporting plate and be installed on the outside of second supporting plate second Plate is lifted, second supporting plate is fixed in the linking arm, and second lifting eye is opened in the second lifting plate.
Further, the quantity of second lifting eye is three, and each second lifting eye lifts plate along described second Length direction open up, and be uniformly distributed on the length direction.
Further, it is provided with the second reinforcement between second supporting plate and the linking arm.
Brief description of the drawings
, below will be right in order to illustrate more clearly of the utility model embodiment or technical scheme of the prior art The required accompanying drawing used is briefly described in embodiment or description of the prior art, it should be apparent that, describe below In accompanying drawing be some embodiments of the present utility model, for those of ordinary skill in the art, do not paying creativeness On the premise of work, other accompanying drawings can also be obtained according to these accompanying drawings.
Fig. 1 is a kind of structural representation of embodiment of hoisting auxiliary device provided by the utility model.
Description of reference numerals:
The first support arms of 11- 12- first lifts plate the first lifting eyes of 121-
The second support arms of 21- 22- second lifts plate the second lifting eyes of 221-
3- linking arms
The reinforcements of 4- first
The reinforcements of 5- second
100- communicating pipes
Embodiment
The technical solution of the utility model is clearly and completely described below in conjunction with accompanying drawing, it is clear that described Embodiment is the utility model part of the embodiment, rather than whole embodiments.Based on the embodiment in the utility model, sheet The every other embodiment that field those of ordinary skill is obtained under the premise of creative work is not made, belongs to this practicality Novel protected scope.
Fig. 1 is refer to, Fig. 1 is that a kind of structure of embodiment of hoisting auxiliary device provided by the utility model is shown It is intended to.
In a kind of embodiment, bearing box cover hoisting auxiliary device provided by the utility model is used for turbine shaft In watt maintenance, the lifting servicing unit includes linking arm 3, is fixed in first lifting arm of described one end of linking arm 3, and is fixed in Second lifting arm of the other end of linking arm 3;At least two first lifting eyes 121, institute are offered on first lifting arm State and at least two second lifting eyes 221 are offered on the second lifting arm, first lifting arm, the linking arm 3 and described Two lifting arms form closed-in construction, and the hollow position of the closed-in construction forms the avoiding space of communicating pipe 100.
In hoisting process, bearing box cover to be lifted is fixed on linking arm 3 or other appropriate positions of the device, The suspension hook of lifting appliance catches on the first lifting eye 121 and the second lifting eye 221, so as to by lifting by crane the first lifting arm and second Arm, sling the servicing unit and bearing box cover to be lifted;During lifting, because two lifting arms and linking arm 3 form frame Formula structure, top communicating pipe 100 can be passed through by the avoiding space in the middle part of closed-in construction, then can be avoided during lifting Communicating pipe 100 so that communicating pipe 100 need not be dismantled in maintenance, so as to simplify maintenance process, reduce overhaul of the equipments difficulty, Reduce overhaul of the equipments and maintenance cost.Also, because the first lifting eye 121 and the second lifting eye 221 are all at least two, also Adjustment lifting center, stability can be ensured by selecting the lifting eye of diverse location;In addition, by controlling and adjusting two The lifting speed and height of lifting arm, device pitching can be achieved, to ensure optimal lifting position.
In order to ensure structural strength, intensity decreases caused by perforate are avoided, two lifting arms can be designed as double-decker, are had Body, the first lifting arm includes the first supporting plate 11 and is installed on the first lifting plate 12 in the outside of the first supporting plate 11, institute State the first supporting plate 11 and be fixed in the linking arm 3, first lifting eye 121 is opened in the first lifting plate 12;Second Lifting arm includes the second supporting plate 21 and is installed on the second lifting plate 22 in the outside of the second supporting plate 21, second support Plate 21 is fixed in the linking arm 3, and second lifting eye 221 is opened in the second lifting plate 22.
Specifically, the quantity of the first lifting eye 121 is five, and each first lifting eye 121 lifts plate along described first 12 length direction opens up, and is uniformly distributed on the length direction, and the quantity of the second lifting eye 221 is three, and each described the Length direction of two lifting eyes 221 along the described second lifting plate 22 opens up, and is uniformly distributed on the length direction to ensure Hanging position has larger adjusting range.It is apparent that the quantity of the first lifting eye 121 is not limited to five, it can also be three It is individual, four, six or more, the quantity of the second lifting eye 221 is not limited to three, or four or more It is individual.
The first reinforcement 4 is provided between above-mentioned first supporting plate 11 and the linking arm 3, the second supporting plate 21 with The second reinforcement 5 is provided between the linking arm 3, to improve structural strength.
Above-mentioned first lifting plate 12 and second is lifted plate 22 and is made of 20mm thickness steel plates, and the length for lifting plate is 1m, the aperture of the first lifting eye 121 is 40mm, and the pitch-row of the adjacent support of two first lifting eye 121 is 120mm, and first lifts plate 12 are welded in the first supporting plate 11, and the second lifting plate 22 is welded in the second supporting plate 21, and the both ends of linking arm 3 are respectively welded in the One supporting plate 11 and the second supporting plate 21;Two supporting plates use No. 20 channel-section steels of the length for 2m, to increase component strength, mitigate Construction weight;Linking arm 3 uses 133*15 steel pipes, and length is 4.5 meters, meets sling height, ensures component strength;The linking arm 3 can be the structure of the flexible joint arm of socket, so as to adapt to different length requirements.First reinforcement 4 and the second reinforcement 5 are 20mm is thick, right angle length of side 300mm set square, is welded between linking arm 3 and support arm, the aperture of the second lifting eye 221 is 40mm, the pitch-row of adjacent two second lifting eye 221 are 120mm.
Although embodiment of the present utility model has been shown and described above, it is to be understood that above-described embodiment is Exemplary, it is impossible to it is interpreted as to limitation of the present utility model, one of ordinary skill in the art is in the scope of the utility model It is interior above-described embodiment to be changed, changed, replaced and modification.

Claims (7)

1. the bearing box cover hoisting auxiliary device in a kind of maintenance for turbine bearing pad, it is characterised in that including linking arm (3) first lifting arm of the linking arm (3) one end, is fixed in, and is fixed in second lifting of the linking arm (3) other end Arm;At least two first lifting eyes (121) are offered on first lifting arm, at least two are offered on second lifting arm Individual second lifting eye (221), first lifting arm, the linking arm (3) and second lifting arm form closed-in construction, and The hollow position of the closed-in construction forms the avoiding space of communicating pipe (100).
2. bearing box cover hoisting auxiliary device according to claim 1, it is characterised in that first lifting arm includes the One supporting plate (11) and the first lifting plate (12) being installed on the outside of first supporting plate (11), first supporting plate (11) The linking arm (3) is fixed in, first lifting eye (121) is opened in the first lifting plate (12).
3. bearing box cover hoisting auxiliary device according to claim 2, it is characterised in that first lifting eye (121) Quantity be five, length direction of each first lifting eye (121) along the described first lifting plate (12) opens up, and in the length Degree is uniformly distributed on direction.
4. bearing box cover hoisting auxiliary device according to claim 2, it is characterised in that first supporting plate (11) with The first reinforcement (4) is provided between the linking arm (3).
5. bearing box cover hoisting auxiliary device according to claim 1, it is characterised in that second lifting arm includes the Two supporting plates (21) and the second lifting plate (22) being installed on the outside of second supporting plate (21), second supporting plate (21) The linking arm (3) is fixed in, second lifting eye (221) is opened in the second lifting plate (22).
6. bearing box cover hoisting auxiliary device according to claim 5, it is characterised in that second lifting eye (221) Quantity be three, length direction of each second lifting eye (221) along the described second lifting plate (22) opens up, and in the length Degree is uniformly distributed on direction.
7. bearing box cover hoisting auxiliary device according to claim 5, it is characterised in that second supporting plate (21) with The second reinforcement (5) is provided between the linking arm (3).
CN201720853310.7U 2017-07-14 2017-07-14 A kind of bearing box cover hoisting auxiliary device in the maintenance for turbine bearing pad Expired - Fee Related CN207175213U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720853310.7U CN207175213U (en) 2017-07-14 2017-07-14 A kind of bearing box cover hoisting auxiliary device in the maintenance for turbine bearing pad

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720853310.7U CN207175213U (en) 2017-07-14 2017-07-14 A kind of bearing box cover hoisting auxiliary device in the maintenance for turbine bearing pad

Publications (1)

Publication Number Publication Date
CN207175213U true CN207175213U (en) 2018-04-03

Family

ID=61735829

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720853310.7U Expired - Fee Related CN207175213U (en) 2017-07-14 2017-07-14 A kind of bearing box cover hoisting auxiliary device in the maintenance for turbine bearing pad

Country Status (1)

Country Link
CN (1) CN207175213U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110451397A (en) * 2019-05-31 2019-11-15 浙江大唐国际绍兴江滨热电有限责任公司 A kind of turbine bearing pad lifting device
CN111943104A (en) * 2020-08-13 2020-11-17 大唐山东电力检修运营有限公司 Auxiliary lifting equipment for overhauling rotating part of steam turbine and using method thereof

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110451397A (en) * 2019-05-31 2019-11-15 浙江大唐国际绍兴江滨热电有限责任公司 A kind of turbine bearing pad lifting device
CN111943104A (en) * 2020-08-13 2020-11-17 大唐山东电力检修运营有限公司 Auxiliary lifting equipment for overhauling rotating part of steam turbine and using method thereof
CN111943104B (en) * 2020-08-13 2021-11-05 大唐山东电力检修运营有限公司 Auxiliary lifting equipment for overhauling rotating part of steam turbine and using method thereof

Similar Documents

Publication Publication Date Title
CN207175213U (en) A kind of bearing box cover hoisting auxiliary device in the maintenance for turbine bearing pad
CN103832933B (en) A kind of group tower tower crane with auxiliary
CN206970011U (en) A kind of stainless steel tube suspension bracket
CN206511847U (en) A kind of anti-roll device of ship's crane
CN201301167Y (en) Novel pipe hoisting device
CN209940310U (en) Lifting sling for segmental beam
CN206088728U (en) Novel large -scale gallows of taking a trial run
CN208869174U (en) A kind of hydraulic self-adjustable lifting balance fine strain of millet
CN201999622U (en) Hoisting device for working roller or intermediate roller
CN202245808U (en) Crane device for container
CN203513083U (en) Combined hanger special for bundled slender materials
CN105540414A (en) Telescopic lifting frame for box transformer substation
CN204689351U (en) A kind of H profile steel structural elements suspender
CN210133807U (en) Shoulder pole beam assembly for unloading engine room of wind generating set and engine room unloading device
CN210480628U (en) Rotatory hoist of two-way self-balancing
CN203067942U (en) Cable bridge frame for pressurized water reactor top structure
CN208475983U (en) Whole fiber bell-type resistance furnace
CN209259473U (en) Lifting device and hanging component
CN207108324U (en) Pressure-bearing stiffening device is used in a kind of single crystal growing furnace assembling
CN205616481U (en) Counterweight hanging device and crane
CN205061366U (en) Gallows is exchanged in hydraulic pressure translation
CN205061329U (en) Lifting tool for steel plate
CN205346600U (en) Big plate -girder hoist and mount specialized tool
CN204643675U (en) A kind of be applicable to suspension rod after the bont that fills
CN203917888U (en) Ladle for both direction operation ladle adds de-lid arrangement

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20180403

Termination date: 20180714