CN207170960U - A kind of horizontal zinc powder furnace of combustion gas - Google Patents

A kind of horizontal zinc powder furnace of combustion gas Download PDF

Info

Publication number
CN207170960U
CN207170960U CN201720807333.4U CN201720807333U CN207170960U CN 207170960 U CN207170960 U CN 207170960U CN 201720807333 U CN201720807333 U CN 201720807333U CN 207170960 U CN207170960 U CN 207170960U
Authority
CN
China
Prior art keywords
chamber
zinc
pipe
zinc powder
condensation chamber
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201720807333.4U
Other languages
Chinese (zh)
Inventor
陈志强
刘影
谭林
肖安文
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hunan Xinwei Metal New Material Polytron Technologies Inc
Original Assignee
Hunan Xinwei Metal New Material Polytron Technologies Inc
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hunan Xinwei Metal New Material Polytron Technologies Inc filed Critical Hunan Xinwei Metal New Material Polytron Technologies Inc
Priority to CN201720807333.4U priority Critical patent/CN207170960U/en
Application granted granted Critical
Publication of CN207170960U publication Critical patent/CN207170960U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model discloses a kind of horizontal zinc powder furnace of combustion gas, including Heat Room and condensation chamber, the inside of the Heat Room is provided with blast tube, combuster is fixedly mounted in the side of the Heat Room, the side of the combustion chamber is provided with melting chamber, the side of the melting chamber is welded with zinc ingot metal entrance, the bottom of the combustion chamber offers vaporization chamber, the side of the combustion chamber is fixedly connected on zinc fume pipe one end, the other end of the zinc fume pipe is fixedly installed condensation chamber, the side of the condensation chamber is fixedly connected on nitrogen tube one end, the outside of the condensation chamber is provided with condenser, the inside of the condensation chamber is socketed with circulating condensing pipe.By offering melting chamber, for melting zinc ingot metal, zinc solution is formed, by being provided with heat-conducting plate between combustion chamber and vaporization chamber, is made up of the high fire resistance carbofrax material of thermal conductivity, the oxygen completely cut off well in combustion chamber, prevents zinc to be oxidized.

Description

A kind of horizontal zinc powder furnace of combustion gas
Technical field
Zinc powder furnace technical field is the utility model is related to, more particularly to a kind of horizontal zinc powder furnace of combustion gas.
Background technology
Technical field is produced and processed in zinc powder at present, relatively common two kinds of equipment are atomization and the major class of the way of distillation two, Metallurgical furnace mainly has tower-type furnace and horizontal chamber furnace (oven) used by the way of distillation, wherein tower-type furnace typically using cigarette block or coal gas as fuel, its Advantage is that the zinc powder product purity of production is high, can handle the high zinc raw material of impurity content, but tower-type furnace big, the stove that fixed investment be present Service life it is short, the shortcomings of energy consumption is useless larger, and cost is high, therefore be not widely used in actual production, crouch The use of formula zinc powder furnace is relatively broad, still, when being evaporated to zinc liquid, because there is oxygen, easy oxygen in combustion chamber Change zinc, cause the purity of zinc powder not high, also, waste gas is expelled directly out caused by combustion chamber, cause the heat in waste gas no Utilized to good, the heat energy of waste.
Utility model content
The utility model proposes a kind of horizontal zinc powder furnace of combustion gas, solves and is given up caused by existing horizontal zinc powder furnace combustion chamber Gas is expelled directly out, and causes the heat in waste gas not utilized well, the problems such as the heat energy of waste
In order to solve the above-mentioned technical problem, the utility model provides following technical scheme:
A kind of horizontal zinc powder furnace of combustion gas of the utility model, including Heat Room and condensation chamber, the inside installation of the Heat Room There is blast tube, combuster is fixedly mounted in the side of the Heat Room, and the side of the combustion chamber, which is provided with, melts room, described The side for melting room is welded with zinc ingot metal entrance, and the bottom of the combustion chamber offers vaporization chamber, and the side of the combustion chamber is fixed Zinc fume pipe one end is connected to, the other end of the zinc fume pipe is fixedly installed condensation chamber, and the side of the condensation chamber is fixed Nitrogen tube one end is connected to, the outside of the condensation chamber is provided with condenser, and the inside of the condensation chamber is socketed with circulating condensing Pipe, the side of the circulating condensing pipe are provided with water inlet, and the side of the condensation chamber is fixedly connected on zinc powder pipe one end, described The other end of zinc powder pipe is installed with cloth-bag type collector.
As a kind of optimal technical scheme of the present utility model, the external stability of the circulating condensing pipe is provided with a point water Pipe, the distributive pipe have been equidistantly positioned seven.
As a kind of optimal technical scheme of the present utility model, the outside of the nitrogen tube is socketed with pressure-reducing valve, the nitrogen The other end of tracheae is installed with nitrogen cylinder.
As a kind of optimal technical scheme of the present utility model, the side of the blast tube is provided with air duct, institute The opposite side for stating blast tube is provided with burning waste gas passage.
As a kind of optimal technical scheme of the present utility model, the top of the vaporization chamber is installed with heat-conducting plate.
The beneficial effect that the utility model is reached is:The utility model is simple in construction, reasonable in design, is especially suitable for manufacturing Zinc powder, melt room by offering, for melting zinc ingot metal, zinc solution is formed, by being provided between combustion chamber and vaporization chamber Heat-conducting plate, it is made up of the high fire resistance carbofrax material of thermal conductivity, the oxygen completely cut off well in combustion chamber, prevents zinc by oxygen Change, meanwhile, vaporization chamber is being handled using preceding having carried out taking out oxygen, and waste gas caused by combustion chamber is passed through burning waste gas passage, using useless Air of the heat abandoned in the combustion gas and air duct during Heat Room heats blast tube, is exchanged heat in an indirect way, Play a part of waste heat recovery, energy consumption can be reduced, play a part of energy-conservation, by being provided with circulating condensing pipe in condensation chamber, The recycling of condensed water is carried out, has saved water resource, in some distributive pipes of the outside installation of condenser pipe, adds and is steamed with zinc The contact area of vapour, the speed of zinc vapor condensing is accelerated, improve condensation efficiency, nitrogen is passed through into condensation chamber while condensation Gas, it can be very good to play a part of anti-zinc oxidation, practical function, be adapted to be widely popularized.
Brief description of the drawings
Accompanying drawing is used for providing further understanding to of the present utility model, and a part for constitution instruction, with this practicality New embodiment is used to explain the utility model together, does not form to limitation of the present utility model.In the accompanying drawings:
Fig. 1 is overlooking the structure diagram of the present utility model;
Fig. 2 is main structure diagram of the present utility model;
In figure:1st, Heat Room;2nd, air duct;3rd, combustion chamber;4th, zinc fume pipe;5th, condenser;6th, circulating condensing pipe;7、 Water inlet;8th, distributive pipe;9th, zinc powder pipe;10th, cloth-bag type collector;11st, condensation chamber;12nd, pressure-reducing valve;13rd, nitrogen tube;14th, nitrogen Gas cylinder;15th, room is melted;16th, zinc ingot metal entrance;17th, burning waste gas passage;18th, blast tube;19th, heat-conducting plate;20th, vaporization chamber.
Embodiment
Preferred embodiment of the present utility model is illustrated below in conjunction with accompanying drawing, it will be appreciated that described herein excellent Select embodiment to be merely to illustrate and explain the utility model, be not used to limit the utility model.
Embodiment 1
As shown in Figure 1-2, the utility model provides a kind of horizontal zinc powder furnace of combustion gas, including Heat Room 1 and condensation chamber 11, changes The inside in hot cell 1 is provided with blast tube 18, and combuster 3 is fixedly mounted in the side of Heat Room 1, and the side of combustion chamber 3 is set Have and melt room 15, the side for melting room 15 is welded with zinc ingot metal entrance 16, and the bottom of combustion chamber 3 offers vaporization chamber 20, combustion chamber 3 Side be fixedly connected on the one end of zinc fume pipe 4, the other end of zinc fume pipe 4 is fixedly installed condensation chamber 11, condensation chamber 11 Side is fixedly connected on the one end of nitrogen tube 13, and the outside of condensation chamber 11 is provided with condenser 5, and the inside of condensation chamber 11 is socketed with Circulating condensing pipe 6, the side of circulating condensing pipe 6 are provided with water inlet 7, and the side of condensation chamber 11 is fixedly connected on zinc powder pipe 9 One end, the other end of zinc powder pipe 9 are installed with cloth-bag type collector 10.
Further, the external stability of circulating condensing pipe 6 is provided with distributive pipe 8, and distributive pipe 8 has been equidistantly positioned seven, increases Greatly with the contact area of zinc powder, cooling effectiveness is improved.
Further, the outside of nitrogen tube 13 is socketed with pressure-reducing valve 12, and the other end of nitrogen tube 13 is installed with nitrogen cylinder 14, prevent zinc fume to be oxidized.
Further, the side of blast tube 18 is provided with air duct 2, and the opposite side of blast tube 18 is provided with burning and given up Gas passage 17, recovery waste heat, reduce energy waste.
Further, the top of vaporization chamber 20 is installed with heat-conducting plate 19, not only starvation, and has good heat conduction Effect.
Utility model works principle:First, zinc ingot metal is added into thawing room 15 from zinc ingot metal entrance 16, then led in combustion gas Combustion gas is passed through into combustion chamber 3 for road 18 and air duct 2 and air is burnt, and melts room 15 and zinc ingot metal is melted into zinc liquid, and Lead into vaporization chamber 20, heat-conducting plate 19 not only completely cuts off the oxygen in combustion chamber 15 and entered in vaporization chamber 20, and well will combustion The heat transfer burnt in room 3 is evaporated into vaporization chamber 20 to zinc liquid, and the waste gas of burning is heated by burning waste gas passage 17 to be fired The air in combustion gas and air duct 2 in gas passage 18, the zinc fume evaporated in vaporization chamber 20 are entered by zinc fume pipe 4 Cooled down in condensation chamber 11, the nitrogen in nitrogen cylinder 14 is passed through in condensation chamber 11 by pressure-reducing valve 12, prevents zinc from aoxidizing, and circulation is cold Zinc fume is cooled to zinc powder by solidifying pipe 6 and distributive pipe 8, and last zinc powder is passed through in cloth-bag type collector 10 by zinc powder pipe 9 and received Collection.
Finally it should be noted that:Preferred embodiment of the present utility model is these are only, is not limited to this practicality It is new, although the utility model is described in detail with reference to the foregoing embodiments, for those skilled in the art, It can still modify to the technical scheme described in foregoing embodiments, or which part technical characteristic is carried out etc. With replacement.All any modification, equivalent substitution and improvements within the spirit and principles of the utility model, made etc., all should be included Within the scope of protection of the utility model.

Claims (5)

1. a kind of horizontal zinc powder furnace of combustion gas, including Heat Room (1) and condensation chamber (11), it is characterised in that the Heat Room (1) Inside is provided with blast tube (18), and combuster (3) is fixedly mounted in the side of the Heat Room (1), the combustion chamber (3) Side, which is provided with, melts room (15), and the side for melting room (15) is welded with zinc ingot metal entrance (16), the bottom of the combustion chamber (3) End offers vaporization chamber (20), and the side of the combustion chamber (3) is fixedly connected on zinc fume pipe (4) one end, the zinc fume pipe (4) the other end is fixedly installed condensation chamber (11), and the side of the condensation chamber (11) is fixedly connected on nitrogen tube (13) one end, The outside of the condensation chamber (11) is provided with condenser (5), and the inside of the condensation chamber (11) is socketed with circulating condensing pipe (6), The side of the circulating condensing pipe (6) is provided with water inlet (7), and the side of the condensation chamber (11) is fixedly connected on zinc powder pipe (9) one end, the other end of the zinc powder pipe (9) are installed with cloth-bag type collector (10).
2. the horizontal zinc powder furnace of a kind of combustion gas according to claim 1, it is characterised in that outside the circulating condensing pipe (6) Portion is installed with distributive pipe (8), and the distributive pipe (8) has been equidistantly positioned seven.
A kind of 3. horizontal zinc powder furnace of combustion gas according to claim 1, it is characterised in that the outer cover of the nitrogen tube (13) Pressure-reducing valve (12) is connected to, the other end of the nitrogen tube (13) is installed with nitrogen cylinder (14).
A kind of 4. horizontal zinc powder furnace of combustion gas according to claim 1, it is characterised in that the side of the blast tube (18) Air duct (2) is provided with, the opposite side of the blast tube (18) is provided with burning waste gas passage (17).
5. the horizontal zinc powder furnace of a kind of combustion gas according to claim 1, it is characterised in that the top of the vaporization chamber (20) is consolidated Dingan County is equipped with heat-conducting plate (19).
CN201720807333.4U 2017-07-05 2017-07-05 A kind of horizontal zinc powder furnace of combustion gas Active CN207170960U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720807333.4U CN207170960U (en) 2017-07-05 2017-07-05 A kind of horizontal zinc powder furnace of combustion gas

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720807333.4U CN207170960U (en) 2017-07-05 2017-07-05 A kind of horizontal zinc powder furnace of combustion gas

Publications (1)

Publication Number Publication Date
CN207170960U true CN207170960U (en) 2018-04-03

Family

ID=61735576

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720807333.4U Active CN207170960U (en) 2017-07-05 2017-07-05 A kind of horizontal zinc powder furnace of combustion gas

Country Status (1)

Country Link
CN (1) CN207170960U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108426456A (en) * 2018-05-02 2018-08-21 沪如科技南京有限公司 A kind of double shield high molecular material heating room equipment

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108426456A (en) * 2018-05-02 2018-08-21 沪如科技南京有限公司 A kind of double shield high molecular material heating room equipment

Similar Documents

Publication Publication Date Title
CN110081720A (en) Mineral hot furnace forces cooled exhaust gas recycling system
CN106895700B (en) A kind of aluminum alloy melting method
CN207170960U (en) A kind of horizontal zinc powder furnace of combustion gas
CN202182624U (en) Energy-saving aluminium melting conjuncted furnace
CN105339091A (en) Multipurpose centrifugal dust collector
CN207402110U (en) A kind of plating cadmia melting continuously zinc powder furnace
CN201779855U (en) Primary and secondary heat exchange integrated fuel gas condensation heat exchanger
CN107671552A (en) Aluminium sheet circle production line and its construction technology
CN103486871A (en) Melting furnace chimney with waste heat recovery structure
CN103968666B (en) A kind of smelting furnace of aluminum or aluminum alloy production
CN206553599U (en) Reviver saves Shuangzi smelting furnace
CN207871853U (en) A kind of bitumen flue gas comprehensive purifying processing unit
CN202830121U (en) Waste heat recycling device of silver copper smelting furnace
CN207487378U (en) Energy saving and environment friendly totally-enclosed blast-heating cupola
CN207262411U (en) Heat energy recycling steam generator system
CN203083381U (en) Feeding tower capable of recycling waste heat of aluminum alloy melting furnace
CN206670067U (en) A kind of evaporated condensation water and low-nitrogen discharged gas heater
CN213747937U (en) Multipurpose furnace waste heat recycling device
CN218210705U (en) Energy-saving gas crucible furnace
CN209210897U (en) The vacuum regenerative furnace of valuable metal is recycled in a kind of steel plant's flue dust
CN103822479B (en) A kind of crucible furnace with flue gas recovery device
CN107460326A (en) A kind of zinc-nickel skin continuous vacuum smelts retort
CN203771401U (en) Built-in heat exchange burner
CN203625416U (en) Converter mouth fixed-section flue of evaporative cooling flue for steelmaking converter
CN215524154U (en) Energy-saving gas type crucible furnace

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
PE01 Entry into force of the registration of the contract for pledge of patent right

Denomination of utility model: Horizontal zinc powder stove of gas

Effective date of registration: 20190626

Granted publication date: 20180403

Pledgee: China Construction Bank Co., Ltd. Changsha Xiangjiang Branch

Pledgor: Hunan Xinwei metal new material Polytron Technologies Inc

Registration number: 2019430000059

PE01 Entry into force of the registration of the contract for pledge of patent right
EE01 Entry into force of recordation of patent licensing contract

Assignee: Industrial and trade enterprise "instral" Co., Ltd

Assignor: Hunan Xinwei metal new material Polytron Technologies Inc

Contract record no.: X2019990000180

Denomination of utility model: Horizontal zinc powder stove of gas

Granted publication date: 20180403

License type: Common License

Record date: 20191111

EE01 Entry into force of recordation of patent licensing contract
PC01 Cancellation of the registration of the contract for pledge of patent right

Date of cancellation: 20201027

Granted publication date: 20180403

Pledgee: China Construction Bank Co.,Ltd. Changsha Xiangjiang Branch

Pledgor: HUNAN NEW WELLLINK ADVANCED METALLIC MATERIAL Co.,Ltd.

Registration number: 2019430000059

PC01 Cancellation of the registration of the contract for pledge of patent right
PE01 Entry into force of the registration of the contract for pledge of patent right

Denomination of utility model: A gas fired horizontal zinc powder furnace

Effective date of registration: 20201109

Granted publication date: 20180403

Pledgee: China Construction Bank Co.,Ltd. Changsha Xiangjiang Branch

Pledgor: HUNAN NEW WELLLINK ADVANCED METALLIC MATERIAL Co.,Ltd.

Registration number: Y2020980007607

PE01 Entry into force of the registration of the contract for pledge of patent right
PC01 Cancellation of the registration of the contract for pledge of patent right

Date of cancellation: 20211213

Granted publication date: 20180403

Pledgee: China Construction Bank Co.,Ltd. Changsha Xiangjiang Branch

Pledgor: HUNAN NEW WELLLINK ADVANCED METALLIC MATERIAL CO.,LTD.

Registration number: Y2020980007607