CN207156081U CN201720992020.0U CN201720992020U CN207156081U CN 207156081 U CN207156081 U CN 207156081U CN 201720992020 U CN201720992020 U CN 201720992020U CN 207156081 U CN207156081 U CN 207156081U
Authority
CN
China
Prior art keywords
crossbearer
floating
box
internal model
prefabricated box
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201720992020.0U
Other languages
Chinese (zh)
Inventor
杨云鸿
张春洪
赵绍鹏
陈建冰
黄炳营
崔龙
龙贵宾
贾彦奇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sinohydro Bureau 14 Co Ltd
Original Assignee
Sinohydro Bureau 14 Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sinohydro Bureau 14 Co Ltd filed Critical Sinohydro Bureau 14 Co Ltd
Priority to CN201720992020.0U priority Critical patent/CN207156081U/en
Application granted granted Critical
Publication of CN207156081U publication Critical patent/CN207156081U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Rod-Shaped Construction Members (AREA)

Abstract

The utility model discloses a kind of prefabricated box -beam internal model anti-floating system, it is desirable to provide a kind of good prefabricated box -beam internal model anti-floating system of Forming Quality.It including the use of when be respectively provided with across box beam both sides precast outer die and both ends the crossbearer of connecting hole, the at least two anti-floating steel pipes for being arranged at crossbearer lower end and extending downwardly, two are connected to the shackle in the connecting hole of crossbearer two, and the flower basket bolt that one end is connected with the same side shackle during two uses, the other end and precast outer die connect;The crossbearer is made of I-steel;The anti-floating steel pipe is welded to connect with crossbearer.The utility model can improve the quality of prefabricated box -beam, have great use value.

Description

A kind of prefabricated box -beam internal model anti-floating system
Technical field
Box beam mould technical field is the utility model is related to, is filled more particularly, to a kind of prefabricated box -beam internal model anti-floating Put.
Background technology
At present, as the development of engineering construction, bridge Construction Technology continue to develop, Construction of Precast Box Beam technology is obtained into one Step is promoted, and because prefabricated case beam is hollow-core construction, in prefabricated box -beam, hollow-core construction needs to set inner template, and inner template is ladder Shape structure, during filling concrete, due to the mobility of concrete, there is a upward active force to inner template, make interior Form floating, influence prefabricated box -beam quality.
Utility model content
The purpose of this utility model is intended to overcome the shortcomings of the prior art, there is provided and it is a kind of easy to use, can be effective Prevent internal model from floating, the high prefabricated box -beam internal model anti-floating system of Forming Quality.
In order to solve the above-mentioned technical problem, the utility model is achieved through the following technical solutions:
A kind of prefabricated box -beam internal model anti-floating system, it is across box beam both sides precast outer die and prefabricated outer with box beam both sides during use Mould connects;Including the use of when be respectively provided with across box beam both sides precast outer die and both ends the crossbearer of connecting hole, at least two are arranged at Crossbearer lower end and the anti-floating steel pipe extended downwardly, two are connected to the shackle in the connecting hole of crossbearer two, and one during two uses End is connected with the same side shackle, the flower basket bolt of the other end and precast outer die connection;The crossbearer is made of I-steel;It is described Anti-floating steel pipe is welded to connect with crossbearer.
Preferably, the crossbearer uses I16 I-steel.
Preferably, the anti-floating steel pipe uses the steel pipes of Φ 32.
Preferably, the anti-floating steel pipe lower end is provided with pressing plate.
Preferably, the anti-floating steel pipe is two.
Compared with prior art, the utility model has the following advantages that:
The utility model overcomes the buoyancy of inner template using the active force of precast outer die structure, is filling Inner Moulding Board in Building It will not be floated when noting concrete, improve the quality of prefabricated box -beam, there is great use value.
Brief description of the drawings
, below will be to embodiment in order to illustrate more clearly of the utility model embodiment or technical scheme of the prior art Or the required accompanying drawing used is briefly described in description of the prior art, it should be apparent that, drawings in the following description are only It is some embodiments of the utility model, for those of ordinary skill in the art, is not paying the premise of creative work Under, other accompanying drawings can also be obtained according to these accompanying drawings.
Fig. 1 is the structural representation of the utility model one embodiment.
Fig. 2 is schematic diagram when Fig. 1 is used.
Fig. 3 is the structural representation of second embodiment of the utility model.
Embodiment
Below in conjunction with the accompanying drawing in the utility model embodiment, the technical scheme in the embodiment of the utility model is carried out Clearly and completely describing, it is clear that described embodiment is only the utility model part of the embodiment, rather than whole Embodiment.Based on the embodiment in the utility model, those of ordinary skill in the art are not under the premise of creative work is paid The every other embodiment obtained, belong to the scope of the utility model protection.
Prefabricated box -beam internal model anti-floating system shown in Fig. 1-2, across box beam both sides precast outer die 10 and and box beam during use Both sides precast outer die 10 connects;Including the use of when be respectively provided with across box beam both sides precast outer die 10 and both ends the crossbearer of connecting hole 5 1, two anti-floating steel pipes 2 for being arranged at the lower end of crossbearer 1 and extending downwardly, two are connected to the shackle in 1 liang of connecting hole 5 of crossbearer 4, and the flower basket bolt 3 that one end is connected with the same side shackle 4 during two uses, the other end and precast outer die connect;The crossbearer 1 It is made of I-steel;The anti-floating steel pipe 2 is welded to connect with crossbearer 1.
The crossbearer uses I16 I-steel.
The anti-floating steel pipe 2 uses the steel pipes of Φ 32.
Prefabricated box -beam internal model anti-floating system shown in Fig. 3, wherein, the lower end of anti-floating steel pipe 2 is provided with pressing plate 6, can have Effect avoids prefabricated internal model from floating, and remaining is essentially identical with above-described embodiment.
In use, according to this engineering box beam both sides precast outer die distance suitable for reading, the I16 I-steel of suitable length is intercepted, I-steel is corresponded at inner template both sides, each section of welding two steel pipes of Φ 32, leaves a certain distance between two section steel pipes so that box beam steel Muscle passes through.Two circular apertures are cut open at I-steel both ends again as connecting hole, it is using shackle and flower basket bolt that I-steel is horizontal Frame is connected with the clasp in precast outer die structure, and screwing flower basket bolt can pour.
When in use, multiple anti-floating systems are pressed in inner template for prefabricated box -beam internal model anti-floating system, utilize the gaily decorated basket successively Crossbearer is buckled on the clasp of precast outer die structure and screwed by bolt, and box beam concrete outwards winding flower basket bolt after the completion of pouring, and removes Crossbearer, continue subsequent cycle work.
Preferred embodiment of the present utility model is the foregoing is only, it is all at this not to limit the utility model Within the spirit and principle of utility model, any modification, equivalent substitution and improvements made etc., the utility model should be included in Protection domain within.

Claims (5)

1. a kind of prefabricated box -beam internal model anti-floating system, during use across box beam both sides precast outer die and with box beam both sides precast outer die Connection;It is characterized in that:Including the use of when be respectively provided with across box beam both sides precast outer die and both ends the crossbearer of connecting hole, at least two The anti-floating steel pipe that root is arranged at crossbearer lower end and extended downwardly, two are connected to the shackle in the connecting hole of crossbearer two, and two The flower basket bolt that one end is connected with the same side shackle during use, the other end and precast outer die connect;The crossbearer uses I-steel It is made;The anti-floating steel pipe is welded to connect with crossbearer.
2. prefabricated box -beam internal model anti-floating system according to claim 1, it is characterised in that:The crossbearer uses I16 I-steel.
3. prefabricated box -beam internal model anti-floating system according to claim 1 or claim 2, it is characterised in that:The anti-floating steel pipe uses Φ 32 steel pipes.
4. prefabricated box -beam internal model anti-floating system according to claim 1 or claim 2, it is characterised in that:The anti-floating steel pipe lower end is set It is equipped with pressing plate.
5. prefabricated box -beam internal model anti-floating system according to claim 1 or claim 2, it is characterised in that:The anti-floating steel pipe is two.
CN201720992020.0U 2017-08-09 2017-08-09 A kind of prefabricated box -beam internal model anti-floating system Expired - Fee Related CN207156081U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720992020.0U CN207156081U (en) 2017-08-09 2017-08-09 A kind of prefabricated box -beam internal model anti-floating system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720992020.0U CN207156081U (en) 2017-08-09 2017-08-09 A kind of prefabricated box -beam internal model anti-floating system

Publications (1)

Publication Number Publication Date
CN207156081U true CN207156081U (en) 2018-03-30

Family

ID=61716365

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720992020.0U Expired - Fee Related CN207156081U (en) 2017-08-09 2017-08-09 A kind of prefabricated box -beam internal model anti-floating system

Country Status (1)

Country Link
CN (1) CN207156081U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111496987A (en) * 2019-07-15 2020-08-07 中铁建工集团有限公司 Core mould come-up control system is prevented to hollow core slab

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111496987A (en) * 2019-07-15 2020-08-07 中铁建工集团有限公司 Core mould come-up control system is prevented to hollow core slab

Similar Documents

Publication Publication Date Title
CN202831233U (en) Connected node of protracting inner diaphragm steel girder and concrete-filled steel-tubular columns inscribed a pipe coat
CN206309029U (en) A kind of aluminum alloy mould plate back cord fixing device
CN204098239U (en) The connected node of profile steel concrete column and reinforced concrete beam
CN202627491U (en) Forming template for deformation joint position shear wall of high-rise building
CN204059957U (en) A kind of formwork reinforcement structure
CN206707008U (en) A kind of novel fabricated attachment structure of steel column and steel column
CN207156081U (en) A kind of prefabricated box -beam internal model anti-floating system
CN209040349U (en) A kind of ring muscle fastening shear wall structure being easily installed
CN101806107A (en) Side column connecting node of thin steel plate shear wall
CN208343121U (en) Prefabricated assembled steel structure concrete wallboard mould
CN205046844U (en) Clear water concrete window steel form structure device that wafts
CN207032868U (en) The form clamp of reversed beam is poured after a kind of
CN207048304U (en) A kind of easy-to-mount construction moulding plate
CN110258885B (en) Green energy-conserving two-way atress truss floor carrier plate
CN206967697U (en) A kind of prefabricated bilateral overlapping accurate process units of wall
CN206753038U (en) It is a kind of to wear joist steel sleeve pipe applied in aluminum dipping form
AU2018298511A1 (en) Assembled building wall body and building house with combination of steel structure and concrete structure
CN207245172U (en) A kind of constructional column prefab-form structure
CN206467999U (en) A kind of construction formwork for placing
CN206956711U (en) A kind of pipe fitting for being used to prevent filling pile cage of reinforcement from floating cage
CN207827677U (en) A kind of pre-buried hanging apparatus for concrete prefabricated element
CN207048055U (en) Combine prefabricated components in a kind of web holes cast-type part
CN207003720U (en) A kind of assembled integral concrete shear force wall attachment structure
CN207003828U (en) A kind of reinforced column prefabricated component
CN206513097U (en) A kind of new omnipotent auxiliary cross-arm of " D " composite

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20180330

CF01 Termination of patent right due to non-payment of annual fee