CN207102268U - A kind of thermal power generation flue-gas dust-removing and desulfurization device - Google Patents

A kind of thermal power generation flue-gas dust-removing and desulfurization device Download PDF

Info

Publication number
CN207102268U
CN207102268U CN201720487103.4U CN201720487103U CN207102268U CN 207102268 U CN207102268 U CN 207102268U CN 201720487103 U CN201720487103 U CN 201720487103U CN 207102268 U CN207102268 U CN 207102268U
Authority
CN
China
Prior art keywords
pipe
gear
power generation
rotating shaft
primary
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201720487103.4U
Other languages
Chinese (zh)
Inventor
孙琳
梁馨鑫
苗莉云
段翠力
王志娟
秦玲玲
郭晓琳
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hebei Hebei Electric Power Engineering Design Consulting Co Ltd
Original Assignee
Hebei Hebei Electric Power Engineering Design Consulting Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hebei Hebei Electric Power Engineering Design Consulting Co Ltd filed Critical Hebei Hebei Electric Power Engineering Design Consulting Co Ltd
Priority to CN201720487103.4U priority Critical patent/CN207102268U/en
Application granted granted Critical
Publication of CN207102268U publication Critical patent/CN207102268U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Treating Waste Gases (AREA)

Abstract

It the utility model is related to a kind of dust-removing desulfurating apparatus, more particularly to a kind of thermal power generation flue-gas dust-removing and desulfurization device.The technical problems to be solved in the utility model is to provide a kind of thermal power generation flue-gas dust-removing and desulfurization device.In order to solve the above-mentioned technical problem, the utility model provides such a thermal power generation flue-gas dust-removing and desulfurization device, includes the first comb, mounting, escape pipe, desulfurizer, the first breather pipe, deblending slot, lid, filler pipe, the second breather pipe, filtering net, primary miscellaneous groove of filter etc.;Mounting top left side is provided with the primary miscellaneous groove of filter, and the primary miscellaneous groove left bottom of filter is provided with the first comb, and the first comb is provided with the first valve, and primary filters miscellaneous groove left upper portion and is provided with air inlet pipe, and the primary miscellaneous groove internal upper part of filter is provided with filtering net.The utility model has reached that desulphurization reaction speed is fast, and the high effect of efficiency of dust collection, the present apparatus is stable, service behaviour and reliable product quality, safe operation, can be to the sufficient filtering of flue gas.

Description

A kind of thermal power generation flue-gas dust-removing and desulfurization device
Technical field
The present invention relates to a kind of dust-removing desulfurating apparatus, more particularly to a kind of thermal power generation flue-gas dust-removing and desulfurization device.
Background technology
Flue gas is the mixture of gas and flue dust, is the main reason for polluting residential block air.The composition of flue gas is very complicated, Gas includes vapor, SO2, N2, O2, CO, CO2 hydrocarbon and oxynitrides etc., and flue dust includes the ash of fuel Point, coal grain, oil droplet and high-temperature split product etc..Therefore pollution of the flue gas to environment is the combined pollution of a variety of poisonous substances.Flue dust Relevant to the harmfulness of human body and the size of particle, it is floating dust of the diameter less than 10 microns that the mostly of harm are produced to human body, especially It is maximum with the floating dust harmfulness of 1-2.5 microns.
In recent years, developing rapidly with economy, metallurgical steel-smelting electric furnace and the boiler using raw coal as fuel increase a lot, this The atmosphere pollution of a little stove discharges causes very big harm to surrounding environment, so removing particulate matter from dusty gas to reduce The technology that it is discharged to air is more and more important.
Desulfurization, refer to fix the element sulphur in coal with the methods of calcium base prevents from generating SO2 during burning as solid.At present Sulfur method typically has burn before burning in burn after three classes such as desulfurization.
There is the shortcomings that desulphurization reaction speed is slow and efficiency of dust collection is low in existing dust-removing desulfurating apparatus, therefore need research and development one badly The thermal power generation flue-gas dust-removing and desulfurization device that kind desulphurization reaction speed is fast and efficiency of dust collection is high.
The content of the invention
(1) technical problems to be solved
The present invention is in order to overcome the shortcomings that desulphurization reaction speed is slow, efficiency of dust collection is low, the technical problem to be solved in the present invention It is to provide a kind of thermal power generation flue-gas dust-removing and desulfurization device.
(2) technical scheme
In order to solve the above-mentioned technical problem, the invention provides such a thermal power generation flue-gas dust-removing and desulfurization device, Include the first comb, mounting, escape pipe, desulfurizer, the first breather pipe, deblending slot, lid, filler pipe, the second breather pipe, filter Miscellaneous net, primary filter miscellaneous groove, air inlet pipe, the first valve, the second valve and communicating pipe, mounting top left side are provided with the primary miscellaneous groove of filter, Primary filters miscellaneous groove left bottom and is provided with the first comb, and the first comb is provided with the first valve, and primary is filtered miscellaneous groove left upper portion and is provided with Air inlet pipe, primary filter miscellaneous groove internal upper part and are provided with filtering net, and primary filters miscellaneous groove crown center and is provided with the second breather pipe, and primary filters miscellaneous groove Bottom right side be communicated with pipe, communicating pipe be provided with the second valve, mounting crown center is provided with deblending slot, the left side of deblending slot End of the bottom respectively with the second breather pipe and communicating pipe is connected, and is located at the lower section of the second breather pipe communicating pipe, and clean groove top Filler pipe is provided with the left of portion, is provided with lid at the top of filler pipe, deblending slot top right side is provided with the first breather pipe, mounting top right side Provided with desulfurizer, desulfurizer top left side is connected with the first breather pipe, and desulfurizer top right side is provided with escape pipe.
Preferably, first gear, motor, second gear, the second oscillating rod, the second shower nozzle, the second flexible pipe, mistake are also included Filter screen, suction pump, the second rotating shaft, bearing block, first rotating shaft, the first oscillating rod, the first flexible pipe and the first shower nozzle, inside deblending slot Left wall is provided with suction pump, and left wall is provided with screen pack inside deblending slot, and suction pump is located inside screen pack, and suction pump is provided with second Flexible pipe and the first flexible pipe, the second flexible pipe and the first flexible pipe pass through screen pack, and the first flexible pipe is located on the right side of the second flexible pipe, in deblending slot Rear wall top is provided with motor and bearing block, and bearing block is located at the downside of motor, and bearing block is provided with the second rotating shaft, in the second rotating shaft Be provided with the second oscillating rod provided with second gear, on front side of the second rotating shaft, the second oscillating rod end is provided with the second shower nozzle, the second shower nozzle and Second flexible pipe is connected, and is provided with first rotating shaft on front side of motor, first rotating shaft is provided with first gear, and first gear is located at the second tooth Wheel top, first gear are meshed with second gear, are provided with the first oscillating rod on front side of first gear, the first oscillating rod end is provided with First shower nozzle, the first shower nozzle are connected with the first flexible pipe.
Preferably, also include dehydrating unit, dehydrating unit include the 3rd breather pipe, heat conduction dehumidification pipe, dehumidifying chamber and Heating plate, mounting top right side are provided with dehumidifying chamber, and dehumidifying intracavitary left wall is provided with heating plate, and being fixed with heat conduction at the top of dehumidifying intracavitary removes Wet pipe, heat conduction dehumidifying pipe end are provided with the 3rd breather pipe, the 3rd breather pipe through dehumidifying top of chamber right side, heat conduction dehumidification pipe left end End is connected with outlet pipe end, and the 3rd breather pipe passes through dehumidifying chamber left bottom.
Preferably, also include desulfurization net, desulfurization net is provided with escape pipe.
Preferably, the material of escape pipe is plastic-aluminum combined material.
Preferably, the material of first gear and second gear uses No. 45 quality carbon steels.
Preferably, the ratio between the height of dedusting groove and the height of desulfurizer are 5:3.5.
Operation principle:Desulfurizer is built with doctor solution, and when needing to handle flue-gas dust-removing and desulfurization, staff, which opens, to be added Lid at the top of water pipe, appropriate clear water is poured into deblending slot, staff covers the lid at the top of water pipe, and flue gas is from air inlet pipe It flow in the primary miscellaneous groove of filter, in the presence of buoyancy, flue gas rises, and flue gas filters in filtering net, and the part in flue gas is miscellaneous The primary miscellaneous groove inner bottom part of filter is fallen under matter, the flue gas after preliminary filtering flow to deblending slot inner bottom part from the second breather pipe, cleaned The clear water filtering flue gas of groove inner bottom part, carries out dust removal process, the inner bottom part of contaminant filter to deblending slot, the flue gas after filtering again Flow to desulfurizer from the first breather pipe, flue gas fully contacts with doctor solution, carry out desulphurization reaction, reacted clean gas from Escape pipe is discharged, and after processing terminates, staff opens the first valve and the second valve, and filtering remaining impurity can be from communicating pipe The first comb is flowed to, so as to discharge impurity.
Because also include first gear, motor, second gear, the second oscillating rod, the second shower nozzle, the second flexible pipe, filtering Net, suction pump, the second rotating shaft, bearing block, first rotating shaft, the first oscillating rod, the first flexible pipe and the first shower nozzle, deblending slot inside are left Wall is provided with suction pump, and left wall is provided with screen pack inside deblending slot, and suction pump is located inside screen pack, and it is soft that suction pump is provided with second Pipe and the first flexible pipe, the second flexible pipe and the first flexible pipe pass through screen pack, and the first flexible pipe is located on the right side of the second flexible pipe, after deblending slot is interior Wall top is provided with motor and bearing block, and bearing block is located at the downside of motor, and bearing block is provided with the second rotating shaft, set in the second rotating shaft There is a second gear, be provided with the second oscillating rod on front side of the second rotating shaft, the second oscillating rod end is provided with the second shower nozzle, the second shower nozzle and the Two flexible pipes are connected, and are provided with first rotating shaft on front side of motor, first rotating shaft is provided with first gear, and first gear is located at second gear Top, first gear are meshed with second gear, are provided with the first oscillating rod on front side of first gear, and the first oscillating rod end is provided with the One shower nozzle, the first shower nozzle are connected with the first flexible pipe, so before deblending slot is started working, staff starts suction pump first And motor, suction pump are drawn water, the clear water after filter screen filtration is drawn into the second flexible pipe and the first flexible pipe, motor Rotating, first gear is driven to rotate, so as to drive second gear to rotate, first gear drives the first oscillating rod to swing up and down, Second gear drives the second oscillating rod to swing, and then the second shower nozzle and the first shower nozzle uniformly spray clear water, can be abundant Dedusting so that efficiency of dust collection improves, and the gas emitted is cleaner, reduces the pollution to environment.
Because also including dehydrating unit, dehydrating unit includes the 3rd breather pipe, heat conduction dehumidification pipe, dehumidifying chamber and heating Plate, mounting top right side are provided with dehumidifying chamber, and dehumidifying intracavitary left wall is provided with heating plate, heat conduction dehumidifying is fixed with the top of dehumidifying intracavitary Pipe, for heat conduction dehumidifying pipe end through dehumidifying top of chamber right side, heat conduction dehumidification pipe left end is provided with the 3rd breather pipe, the 3rd breather pipe end End is connected with outlet pipe end, and the 3rd breather pipe is through dehumidifying chamber left bottom, so the gas meeting after flue-gas dust-removing and desulfurization The 3rd breather pipe, threeth breather pipe flowing of the gas in dehydrating unit, the endotracheal gas of threeway are flow to from escape pipe Heat conduction dehumidification pipe is flowed to, heating plate heats to the gas in heat conduction dehumidification pipe, can play more preferable exsiccation, be easy to The processing of follow-up work.
Because also including desulfurization net, desulfurization net is provided with escape pipe, so after flue gas desulfurization, desulfurization net can be by gas Body carries out desulfurization again so that the efficiency of desulfurization improves, and desulfurization obtains more thorough.
The control mode of the present invention is automatically controlled by controller, the skill that the control circuit of controller passes through this area Art personnel simple programming can be achieved, and belong to the common knowledge of this area, and the present invention is mainly used to protect mechanical device, institute Control mode is not explained with the present invention to connect with circuit.
(3) beneficial effect
Invention achieves desulphurization reaction speed is fast, the high effect of efficiency of dust collection.The present apparatus is stable, service behaviour and Reliable product quality, safe operation can be to the sufficient filtering of flue gas so that efficiency of dust collection improves, and the gas emitted is more Add totally, reduce the pollution to environment.
Brief description of the drawings
Fig. 1 is the first main structure diagram of the present invention.
Fig. 2 is the main structure diagram of deblending slot of the present invention.
Fig. 3 is second of main structure diagram of the present invention.
Fig. 4 is the main structure diagram of dehydrating unit of the present invention.
Fig. 5 is the third main structure diagram of the present invention.
Mark in accompanying drawing for:The combs of 1- first, 2- mountings, 3- clear water, 4- doctor solutions, 5- escape pipes, 6- desulfurizers, The breather pipes of 7- first, 8- deblending slots, 80- lids, 81- filler pipes, the breather pipes of 9- second, 10- filtering nets, the primary filters of 11- are miscellaneous Groove, 12- air inlet pipe, the valves of 13- first, the valves of 14- second, 15- communicating pipes, 16- first gears, 17- motors, the teeth of 18- second Wheel, the oscillating rods of 19- second, the shower nozzles of 20- second, the flexible pipes of 21- second, 22- screen packs, 23- suction pumps, the rotating shafts of 24- second, 25- Bearing block, 26- first rotating shafts, the oscillating rods of 27- first, the flexible pipes of 28- first, the shower nozzles of 29- first, 30- dehydrating units, 301- Three breather pipes, 302- heat conduction dehumidification pipes, 303- dehumidifying chambers, 304- heating plates, 31- desulfurization nets.
Embodiment
The present invention is further illustrated with reference to the accompanying drawings and examples.
Embodiment 1
A kind of thermal power generation flue-gas dust-removing and desulfurization device, as Figure 1-5, include the first comb 1, mounting 2, outlet Pipe 5, desulfurizer 6, the first breather pipe 7, deblending slot 8, lid 80, filler pipe 81, the second breather pipe 9, filtering net 10, primary filter are miscellaneous Groove 11, air inlet pipe 12, the first valve 13, the second valve 14 and communicating pipe 15, the top left side of mounting 2 are provided with the primary miscellaneous groove 11 of filter, Primary filters the miscellaneous left bottom of groove 11 and is provided with the first comb 1, and the first comb 1 is provided with the first valve 13, and primary filters the miscellaneous left side of groove 11 Top is provided with air inlet pipe 12, and primary filters the miscellaneous internal upper part of groove 11 and is provided with filtering net 10, and primary filters the miscellaneous crown center of groove 11 and is provided with second Breather pipe 9, the bottom right side that primary filters miscellaneous groove 11 are communicated with pipe 15, communicating pipe 15 are provided with the second valve 14, mounting 2 pushes up Deblending slot 8 is provided among portion, the left bottom of deblending slot 8 is connected with the second breather pipe 9 and the end of communicating pipe 15 respectively, even Siphunculus 15 is located at the lower section of the second breather pipe 9, and the top left side of deblending slot 8 is provided with filler pipe 81, and the top of filler pipe 81 is provided with lid 80, the top right side of deblending slot 8 is provided with the first breather pipe 7, and the top right side of mounting 2 is provided with desulfurizer 6, the top left side of desulfurizer 6 with First breather pipe 7 is connected, and the top right side of desulfurizer 6 is provided with escape pipe 5.
Embodiment 2
A kind of thermal power generation flue-gas dust-removing and desulfurization device, as Figure 1-5, include the first comb 1, mounting 2, outlet Pipe 5, desulfurizer 6, the first breather pipe 7, deblending slot 8, lid 80, filler pipe 81, the second breather pipe 9, filtering net 10, primary filter are miscellaneous Groove 11, air inlet pipe 12, the first valve 13, the second valve 14 and communicating pipe 15, the top left side of mounting 2 are provided with the primary miscellaneous groove 11 of filter, Primary filters the miscellaneous left bottom of groove 11 and is provided with the first comb 1, and the first comb 1 is provided with the first valve 13, and primary filters the miscellaneous left side of groove 11 Top is provided with air inlet pipe 12, and primary filters the miscellaneous internal upper part of groove 11 and is provided with filtering net 10, and primary filters the miscellaneous crown center of groove 11 and is provided with second Breather pipe 9, the bottom right side that primary filters miscellaneous groove 11 are communicated with pipe 15, communicating pipe 15 are provided with the second valve 14, mounting 2 pushes up Deblending slot 8 is provided among portion, the left bottom of deblending slot 8 is connected with the second breather pipe 9 and the end of communicating pipe 15 respectively, even Siphunculus 15 is located at the lower section of the second breather pipe 9, and the top left side of deblending slot 8 is provided with filler pipe 81, and the top of filler pipe 81 is provided with lid 80, the top right side of deblending slot 8 is provided with the first breather pipe 7, and the top right side of mounting 2 is provided with desulfurizer 6, the top left side of desulfurizer 6 with First breather pipe 7 is connected, and the top right side of desulfurizer 6 is provided with escape pipe 5.
Also include first gear 16, motor 17, second gear 18, the second oscillating rod 19, the second shower nozzle 20, the second flexible pipe 21st, screen pack 22, suction pump 23, the second rotating shaft 24, bearing block 25, first rotating shaft 26, the first oscillating rod 27, the and of the first flexible pipe 28 First shower nozzle 29, the inside left wall of deblending slot 8 are provided with suction pump 23, and the inside left wall of deblending slot 8 is provided with screen pack 22, suction pump 23 Inside screen pack 22, suction pump 23 is provided with the second flexible pipe 21 and the first flexible pipe 28, the second flexible pipe 21 and the first flexible pipe 28 Through screen pack 22, the first flexible pipe 28 is located at the right side of the second flexible pipe 21, and rear wall top is provided with motor 17 and bearing block in deblending slot 8 25, bearing block 25 is located at the downside of motor 17, and bearing block 25 is provided with the second rotating shaft 24, and the second rotating shaft 24 is provided with the second tooth Wheel 18, the front side of the second rotating shaft 24 are provided with the second oscillating rod 19, and the end of the second oscillating rod 19 is provided with the second shower nozzle 20, the second shower nozzle 20 It is connected with the second flexible pipe 21, the front side of motor 17 is provided with first rotating shaft 26, and first rotating shaft 26 is provided with first gear 16, the first tooth Wheel 16 is meshed positioned at the top of second gear 18, first gear 16 with second gear 18, and the front side of first gear 16 is provided with the first pendulum Lever 27, the end of the first oscillating rod 27 are provided with the first shower nozzle 29, and the first shower nozzle 29 is connected with the first flexible pipe 28.
Embodiment 3
A kind of thermal power generation flue-gas dust-removing and desulfurization device, as Figure 1-5, include the first comb 1, mounting 2, outlet Pipe 5, desulfurizer 6, the first breather pipe 7, deblending slot 8, lid 80, filler pipe 81, the second breather pipe 9, filtering net 10, primary filter are miscellaneous Groove 11, air inlet pipe 12, the first valve 13, the second valve 14 and communicating pipe 15, the top left side of mounting 2 are provided with the primary miscellaneous groove 11 of filter, Primary filters the miscellaneous left bottom of groove 11 and is provided with the first comb 1, and the first comb 1 is provided with the first valve 13, and primary filters the miscellaneous left side of groove 11 Top is provided with air inlet pipe 12, and primary filters the miscellaneous internal upper part of groove 11 and is provided with filtering net 10, and primary filters the miscellaneous crown center of groove 11 and is provided with second Breather pipe 9, the bottom right side that primary filters miscellaneous groove 11 are communicated with pipe 15, communicating pipe 15 are provided with the second valve 14, mounting 2 pushes up Deblending slot 8 is provided among portion, the left bottom of deblending slot 8 is connected with the second breather pipe 9 and the end of communicating pipe 15 respectively, even Siphunculus 15 is located at the lower section of the second breather pipe 9, and the top left side of deblending slot 8 is provided with filler pipe 81, and the top of filler pipe 81 is provided with lid 80, the top right side of deblending slot 8 is provided with the first breather pipe 7, and the top right side of mounting 2 is provided with desulfurizer 6, the top left side of desulfurizer 6 with First breather pipe 7 is connected, and the top right side of desulfurizer 6 is provided with escape pipe 5.
Also include first gear 16, motor 17, second gear 18, the second oscillating rod 19, the second shower nozzle 20, the second flexible pipe 21st, screen pack 22, suction pump 23, the second rotating shaft 24, bearing block 25, first rotating shaft 26, the first oscillating rod 27, the and of the first flexible pipe 28 First shower nozzle 29, the inside left wall of deblending slot 8 are provided with suction pump 23, and the inside left wall of deblending slot 8 is provided with screen pack 22, suction pump 23 Inside screen pack 22, suction pump 23 is provided with the second flexible pipe 21 and the first flexible pipe 28, the second flexible pipe 21 and the first flexible pipe 28 Through screen pack 22, the first flexible pipe 28 is located at the right side of the second flexible pipe 21, and rear wall top is provided with motor 17 and bearing block in deblending slot 8 25, bearing block 25 is located at the downside of motor 17, and bearing block 25 is provided with the second rotating shaft 24, and the second rotating shaft 24 is provided with the second tooth Wheel 18, the front side of the second rotating shaft 24 are provided with the second oscillating rod 19, and the end of the second oscillating rod 19 is provided with the second shower nozzle 20, the second shower nozzle 20 It is connected with the second flexible pipe 21, the front side of motor 17 is provided with first rotating shaft 26, and first rotating shaft 26 is provided with first gear 16, the first tooth Wheel 16 is meshed positioned at the top of second gear 18, first gear 16 with second gear 18, and the front side of first gear 16 is provided with the first pendulum Lever 27, the end of the first oscillating rod 27 are provided with the first shower nozzle 29, and the first shower nozzle 29 is connected with the first flexible pipe 28.
Also include dehydrating unit 30, dehydrating unit 30 includes the 3rd breather pipe 301, heat conduction dehumidification pipe 302, dehumidifying chamber 303 and heating plate 304, the top right side of mounting 2 is provided with dehumidifying chamber 303, and the dehumidifying inner left wall of chamber 303 is provided with heating plate 304, dehumidifying chamber 303 inner tops are fixed with heat conduction dehumidification pipe 302, and the end of heat conduction dehumidification pipe 302 is dehumidified through the dehumidifying top right side of chamber 303, heat conduction The left end of pipe 302 is provided with the 3rd breather pipe 301, and the end of the 3rd breather pipe 301 is connected with the end of escape pipe 5, the 3rd breather pipe 301 Through the dehumidifying left bottom of chamber 303.
Embodiment 4
A kind of thermal power generation flue-gas dust-removing and desulfurization device, as Figure 1-5, include the first comb 1, mounting 2, outlet Pipe 5, desulfurizer 6, the first breather pipe 7, deblending slot 8, lid 80, filler pipe 81, the second breather pipe 9, filtering net 10, primary filter are miscellaneous Groove 11, air inlet pipe 12, the first valve 13, the second valve 14 and communicating pipe 15, the top left side of mounting 2 are provided with the primary miscellaneous groove 11 of filter, Primary filters the miscellaneous left bottom of groove 11 and is provided with the first comb 1, and the first comb 1 is provided with the first valve 13, and primary filters the miscellaneous left side of groove 11 Top is provided with air inlet pipe 12, and primary filters the miscellaneous internal upper part of groove 11 and is provided with filtering net 10, and primary filters the miscellaneous crown center of groove 11 and is provided with second Breather pipe 9, the bottom right side that primary filters miscellaneous groove 11 are communicated with pipe 15, communicating pipe 15 are provided with the second valve 14, mounting 2 pushes up Deblending slot 8 is provided among portion, the left bottom of deblending slot 8 is connected with the second breather pipe 9 and the end of communicating pipe 15 respectively, even Siphunculus 15 is located at the lower section of the second breather pipe 9, and the top left side of deblending slot 8 is provided with filler pipe 81, and the top of filler pipe 81 is provided with lid 80, the top right side of deblending slot 8 is provided with the first breather pipe 7, and the top right side of mounting 2 is provided with desulfurizer 6, the top left side of desulfurizer 6 with First breather pipe 7 is connected, and the top right side of desulfurizer 6 is provided with escape pipe 5.
Also include first gear 16, motor 17, second gear 18, the second oscillating rod 19, the second shower nozzle 20, the second flexible pipe 21st, screen pack 22, suction pump 23, the second rotating shaft 24, bearing block 25, first rotating shaft 26, the first oscillating rod 27, the and of the first flexible pipe 28 First shower nozzle 29, the inside left wall of deblending slot 8 are provided with suction pump 23, and the inside left wall of deblending slot 8 is provided with screen pack 22, suction pump 23 Inside screen pack 22, suction pump 23 is provided with the second flexible pipe 21 and the first flexible pipe 28, and the second flexible pipe 21 and the first flexible pipe 28 are worn Screen pack 22 is crossed, the first flexible pipe 28 is located at the right side of the second flexible pipe 21, and rear wall top is provided with motor 17 and bearing block in deblending slot 8 25, bearing block 25 is located at the downside of motor 17, and bearing block 25 is provided with the second rotating shaft 24, and the second rotating shaft 24 is provided with the second tooth Wheel 18, the front side of the second rotating shaft 24 are provided with the second oscillating rod 19, and the end of the second oscillating rod 19 is provided with the second shower nozzle 20, the second shower nozzle 20 It is connected with the second flexible pipe 21, the front side of motor 17 is provided with first rotating shaft 26, and first rotating shaft 26 is provided with first gear 16, the first tooth Wheel 16 is meshed positioned at the top of second gear 18, first gear 16 with second gear 18, and the front side of first gear 16 is provided with the first pendulum Lever 27, the end of the first oscillating rod 27 are provided with the first shower nozzle 29, and the first shower nozzle 29 is connected with the first flexible pipe 28.
Also include dehydrating unit 30, dehydrating unit 30 includes the 3rd breather pipe 301, heat conduction dehumidification pipe 302, dehumidifying chamber 303 and heating plate 304, the top right side of mounting 2 is provided with dehumidifying chamber 303, and the dehumidifying inner left wall of chamber 303 is provided with heating plate 304, dehumidifying chamber 303 inner tops are fixed with heat conduction dehumidification pipe 302, and the end of heat conduction dehumidification pipe 302 is dehumidified through the dehumidifying top right side of chamber 303, heat conduction The left end of pipe 302 is provided with the 3rd breather pipe 301, and the end of the 3rd breather pipe 301 is connected with the end of escape pipe 5, the 3rd breather pipe 301 Through the dehumidifying left bottom of chamber 303.
Also include desulfurization net 31, desulfurization net 31 is provided with escape pipe 5.
The material of escape pipe 5 is plastic-aluminum combined material.
The material of first gear 16 and second gear 18 uses No. 45 quality carbon steels.
The ratio between the height of dedusting groove and the height of desulfurizer 6 are 5:3.5.
Operation principle:Desulfurizer 6 is built with doctor solution 4, and when needing to handle flue-gas dust-removing and desulfurization, staff opens The lid 80 at the top of filler pipe 81, pours into deblending slot 8, staff covers the lid 80 at the top of water pipe, cigarette by appropriate clear water 3 Gas is flow in the primary miscellaneous groove 11 of filter from air inlet pipe 12, and in the presence of buoyancy, flue gas rises, flue gas mistake in filtering net 10 Filter, the primary miscellaneous inner bottom part of groove 11 of filter is fallen under the partial impurities in flue gas, the flue gas after preliminary filtering flows from the second breather pipe 9 To the inner bottom part of deblending slot 8, the clear water 3 of the inner bottom part of deblending slot 8 filters flue gas, carries out dust removal process, contaminant filter to deblending slot 8 Inner bottom part, the flue gas after filtering again flow to desulfurizer 6 from the first breather pipe 7, and flue gas fully contacts with doctor solution 4, carry out Desulphurization reaction, reacted clean gas is discharged from escape pipe 5, and after processing terminates, staff opens the first valve 13 and the Two valves 14, the first comb 1 can be flowed to from communicating pipe 15 by filtering remaining impurity, so as to discharge impurity.
Because also include first gear 16, motor 17, second gear 18, the second oscillating rod 19, the second shower nozzle 20, Two flexible pipes 21, screen pack 22, suction pump 23, the second rotating shaft 24, bearing block 25, first rotating shaft 26, the first oscillating rod 27, first The shower nozzle 29 of flexible pipe 28 and first, the inside left wall of deblending slot 8 are provided with suction pump 23, and the inside left wall of deblending slot 8 is provided with screen pack 22, taken out Water pump 23 is located inside screen pack 22, and suction pump 23 is provided with the second flexible pipe 21 and the first flexible pipe 28, the second flexible pipe 21 and first Flexible pipe 28 passes through screen pack 22, and the first flexible pipe 28 is located at the right side of the second flexible pipe 21, and rear wall top is provided with motor 17 in deblending slot 8 With bearing block 25, bearing block 25 is located at the downside of motor 17, and bearing block 25 is provided with the second rotating shaft 24, and the second rotating shaft 24 is provided with Second gear 18, the front side of the second rotating shaft 24 are provided with the second oscillating rod 19, and the end of the second oscillating rod 19 is provided with the second shower nozzle 20, and second Shower nozzle 20 is connected with the second flexible pipe 21, and the front side of motor 17 is provided with first rotating shaft 26, and first rotating shaft 26 is provided with first gear 16, First gear 16 is located at the top of second gear 18, and first gear 16 is meshed with second gear 18, and the front side of first gear 16 is provided with First oscillating rod 27, the end of the first oscillating rod 27 are provided with the first shower nozzle 29, and the first shower nozzle 29 is connected with the first flexible pipe 28, so Before the start-up operation of deblending slot 8, staff starts suction pump 23 first and motor 17, suction pump 23 are drawn water, and will pass through Clear water 3 after screen pack 22 filters is drawn into the second flexible pipe 21 and the first flexible pipe 28, the rotating of motor 17, drives first gear 16 rotate, and so as to drive second gear 18 to rotate, first gear 16 drives the first oscillating rod 27 to swing up and down, the band of second gear 18 Dynamic second oscillating rod 19 swings, and then the second shower nozzle 20 and the first shower nozzle 29 uniformly spray clear water 3, can fully remove Dirt so that efficiency of dust collection improves, and the gas emitted is cleaner, reduces the pollution to environment.
Because also including dehydrating unit 30, dehydrating unit 30 includes the 3rd breather pipe 301, heat conduction dehumidification pipe 302, removed Wet chamber 303 and heating plate 304, the top right side of mounting 2 are provided with dehumidifying chamber 303, and the dehumidifying inner left wall of chamber 303 is provided with heating plate 304, removed The wet inner top of chamber 303 is fixed with heat conduction dehumidification pipe 302, and the end of heat conduction dehumidification pipe 302 passes through the dehumidifying top right side of chamber 303, heat conduction The left end of dehumidification pipe 302 is provided with the 3rd breather pipe 301, and the end of the 3rd breather pipe 301 is connected with the end of escape pipe 5, the 3rd ventilation Pipe 301 is through the dehumidifying left bottom of chamber 303, so the gas after flue-gas dust-removing and desulfurization can flow to the 3rd ventilation from escape pipe 5 Pipe 301, threeth breather pipe 301 of the gas in dehydrating unit 30 flow, the gas flow heat conduction dehumidifying in the 3rd breather pipe 301 Pipe 302, heating plate 304 heat to the gas in heat conduction dehumidification pipe 302, more preferable exsiccation can be played, after being easy to The processing of continuous work.
Because also including desulfurization net 31, desulfurization net 31 is provided with escape pipe 5, so after flue gas desulfurization, desulfurization net 31 Gas can be subjected to desulfurization again so that the efficiency of desulfurization improves, and desulfurization obtains more thorough.
The control mode of the present invention is automatically controlled by controller, the skill that the control circuit of controller passes through this area Art personnel simple programming can be achieved, and belong to the common knowledge of this area, and the present invention is mainly used to protect mechanical device, institute Control mode is not explained with the present invention to connect with circuit.
Embodiment described above only expresses the preferred embodiment of the present invention, and its description is more specific and detailed, but simultaneously Therefore the limitation to the scope of the claims of the present invention can not be interpreted as.It should be pointed out that for one of ordinary skill in the art For, without departing from the inventive concept of the premise, some deformations can also be made, improves and substitutes, these belong to this hair Bright protection domain.Therefore, the protection domain of patent of the present invention should be determined by the appended claims.

Claims (7)

1. a kind of thermal power generation flue-gas dust-removing and desulfurization device, it is characterised in that include the first comb (1), mounting (2), go out Tracheae (5), desulfurizer (6), the first breather pipe (7), deblending slot (8), lid (80), filler pipe (81), the second breather pipe (9), Filtering net (10), primary filter miscellaneous groove (11), air inlet pipe (12), the first valve (13), the second valve (14) and communicating pipe (15), seat Frame (2) top left side is provided with the primary miscellaneous groove (11) of filter, and primary filters miscellaneous groove (11) left bottom and is provided with the first comb (1), first row Pipe (1) is provided with the first valve (13), and primary filters miscellaneous groove (11) left upper portion and is provided with air inlet pipe (12), and primary is filtered in miscellaneous groove (11) Top is provided with filtering net (10), and primary filters miscellaneous groove (11) crown center and is provided with the second breather pipe (9), and primary filters the right side of miscellaneous groove (11) Side bottom is communicated with pipe (15), communicating pipe (15) is provided with the second valve (14), mounting (2) crown center is provided with deblending slot (8), end of the left bottom of deblending slot (8) respectively with the second breather pipe (9) and communicating pipe (15) is connected, communicating pipe (15) Positioned at the lower section of the second breather pipe (9), deblending slot (8) top left side is provided with filler pipe (81), and lid is provided with the top of filler pipe (81) Sub (80), deblending slot (8) top right side are provided with the first breather pipe (7), and mounting (2) top right side is provided with desulfurizer (6), desulfurizer (6) top left side is connected with the first breather pipe (7), and desulfurizer (6) top right side is provided with escape pipe (5).
2. a kind of thermal power generation flue-gas dust-removing and desulfurization device according to claim 1, it is characterised in that also include One gear (16), motor (17), second gear (18), the second oscillating rod (19), the second shower nozzle (20), the second flexible pipe (21), mistake Filter screen (22), suction pump (23), the second rotating shaft (24), bearing block (25), first rotating shaft (26), the first oscillating rod (27), first Flexible pipe (28) and the first shower nozzle (29), the internal left wall of deblending slot (8) are provided with suction pump (23), and the internal left wall of deblending slot (8) is provided with Screen pack (22), suction pump (23) are located at screen pack (22) inside, and suction pump (23) is soft provided with the second flexible pipe (21) and first Manage (28), the second flexible pipe (21) and the first flexible pipe (28) pass through screen pack (22), and the first flexible pipe (28) is located at the second flexible pipe (21) Right side, the interior rear wall top of deblending slot (8) are provided with motor (17) and bearing block (25), and bearing block (25) is located under motor (17) Side, bearing block (25) are provided with the second rotating shaft (24), and the second rotating shaft (24) is provided with second gear (18), before the second rotating shaft (24) Side is provided with the second oscillating rod (19), and the second oscillating rod (19) end is provided with the second shower nozzle (20), the second shower nozzle (20) and second soft Pipe (21) is connected, and is provided with first rotating shaft (26) on front side of motor (17), and first rotating shaft (26) is provided with first gear (16), and first Gear (16) is located above second gear (18), and first gear (16) is meshed with second gear (18), before first gear (16) Side is provided with the first oscillating rod (27), and the first oscillating rod (27) end is provided with the first shower nozzle (29), the first shower nozzle (29) and first soft Pipe (28) is connected.
3. a kind of thermal power generation flue-gas dust-removing and desulfurization device according to claim 2, it is characterised in that also include and remove Wet device (30), dehydrating unit (30) include the 3rd breather pipe (301), heat conduction dehumidification pipe (302), dehumidifying chamber (303) and added Hot plate (304), mounting (2) top right side are provided with dehumidifying chamber (303), and dehumidifying chamber (303) inner left wall is provided with heating plate (304), removed Wet chamber (303) inner top is fixed with heat conduction dehumidification pipe (302), and heat conduction dehumidification pipe (302) end passes through dehumidifying chamber (303) top right Side, heat conduction dehumidification pipe (302) left end are provided with the 3rd breather pipe (301), the 3rd breather pipe (301) end and escape pipe (5) end It is connected, the 3rd breather pipe (301) passes through dehumidifying chamber (303) left bottom.
4. a kind of thermal power generation flue-gas dust-removing and desulfurization device according to claim 3, it is characterised in that also include de- Sulphur net (31), escape pipe (5) is interior to be provided with desulfurization net (31).
A kind of 5. thermal power generation flue-gas dust-removing and desulfurization device according to claim 4, it is characterised in that escape pipe (5) Material be plastic-aluminum combined material.
A kind of 6. thermal power generation flue-gas dust-removing and desulfurization device according to claim 5, it is characterised in that first gear (16) and the material of second gear (18) uses No. 45 quality carbon steels.
A kind of 7. thermal power generation flue-gas dust-removing and desulfurization device according to claim 6, it is characterised in that the height of dedusting groove The ratio between height of degree and desulfurizer (6) is 5:3.5.
CN201720487103.4U 2017-05-04 2017-05-04 A kind of thermal power generation flue-gas dust-removing and desulfurization device Expired - Fee Related CN207102268U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720487103.4U CN207102268U (en) 2017-05-04 2017-05-04 A kind of thermal power generation flue-gas dust-removing and desulfurization device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720487103.4U CN207102268U (en) 2017-05-04 2017-05-04 A kind of thermal power generation flue-gas dust-removing and desulfurization device

Publications (1)

Publication Number Publication Date
CN207102268U true CN207102268U (en) 2018-03-16

Family

ID=61592985

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720487103.4U Expired - Fee Related CN207102268U (en) 2017-05-04 2017-05-04 A kind of thermal power generation flue-gas dust-removing and desulfurization device

Country Status (1)

Country Link
CN (1) CN207102268U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110252121A (en) * 2019-07-11 2019-09-20 启明星宇节能科技股份有限公司 A kind of tunnel stove desulfurization and dust removal integrated equipment

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110252121A (en) * 2019-07-11 2019-09-20 启明星宇节能科技股份有限公司 A kind of tunnel stove desulfurization and dust removal integrated equipment

Similar Documents

Publication Publication Date Title
CN107096361A (en) A kind of boiler smoke dedusting and purifying device
CN100999670B (en) Smoke preventing and dust removing for tamping coking oven side filling coal and vehicle for smoke preventing and dust removing
CN112191035B (en) Cascade type treatment device for flue gas desulfurization and treatment method thereof
CN106621664A (en) Cyclone water type dedusting device
CN110280117A (en) It is centrifuged oxidizing process and cooperates with micro-nano steam bubble VOCs processing system
CN207137597U (en) A kind of banbury dust-removing device
CN207102268U (en) A kind of thermal power generation flue-gas dust-removing and desulfurization device
CN209116361U (en) A kind of energy saving and environment friendly coal-burning boiler
CN106925091A (en) A kind of thermal power generation flue-gas dust-removing and desulfurization device
CN209260024U (en) A kind of Biomass Gasification And Power Generation System
CN212819162U (en) Flue gas desulfurization and denitrification treatment system
CN205627465U (en) Bag -type dust remover
CN208320134U (en) A kind of coal ash physical separation means
CN209188471U (en) A kind of out of stock integrated treatment unit of dust-removal and desulfurizing
CN211537006U (en) Wet dust remover
CN204246968U (en) Sack cleaner
CN208230106U (en) A kind of recycling of glass smashes it through filter device
CN208436563U (en) A kind of flue gas desulfurization waste heat recycle device
CN216378077U (en) Blast furnace gas dry desulphurization device
CN2774619Y (en) Smoke dust-removing and desulfurizing system
CN205650113U (en) Sack cleaner smoke and dust processing apparatus
CN108379950A (en) A kind of desulfurating dust removing device for flue gas for field of environment protection
CN218458908U (en) Boiler smoke and dust purifier
CN110013723A (en) A kind of industrial dedusting dust-extraction unit easy to repair with sterilizing function
CN218306779U (en) Environment-friendly bag-type dust collector

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20180316