CN207087160U - The adjustable para-seismic support of cable wire melting welding - Google Patents
The adjustable para-seismic support of cable wire melting welding Download PDFInfo
- Publication number
- CN207087160U CN207087160U CN201720972447.4U CN201720972447U CN207087160U CN 207087160 U CN207087160 U CN 207087160U CN 201720972447 U CN201720972447 U CN 201720972447U CN 207087160 U CN207087160 U CN 207087160U
- Authority
- CN
- China
- Prior art keywords
- cable wire
- connector
- cross arm
- arm support
- adjustable
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Wire Processing (AREA)
Abstract
A kind of adjustable para-seismic support of cable wire melting welding is the utility model is related to, is characterised by:Including upper cross arm support, lower cross arm support, airduct, four in the cable wire of oblique pull shape, to holding card, the first connector and the second connector, cross arm support is fixed at the top of airduct, cross arm support is fixed in the bottom of airduct;Upper cross arm support connects cable wire close to both ends, and cable wire the other end is affixed by the first connector, the second connector and to holding card and fixed part;Be respectively connected with every cable wire it is adjustable it is bicyclic spend blue connector, cable wire and the second connector use sweat soldering attachment structure, and cable wire bicyclic spends blue connector to use sweat soldering attachment structure with adjustable.Advantage is:Without perforate, welding on steel construction, construction and installation are flexible;The construction of superelevation space is time saving and energy saving, reduces construction cost;It can directly control rope length manually, eliminate error, for control cable wire to the fixed force of electromechanical pipeline, horizontal when making the pipeline fully resist earthquake carries power.
Description
Technical field
The utility model belongs to building interior mechanical and electric equipment installation field, adjustable more particularly to a kind of cable wire melting welding
Para-seismic support.
Background technology
Para-seismic support is mainly used in the destruction that reduction is built and the pipeline of industrial electromechanical engineering occurs when by earthquake.It is anti-
Shake stent applications principle:1st, air-conditioning, air pipeline system:All diameters are more than or equal to 0.7m air-line system;All rectangles are cut
Area is more than or equal to 0.38 ㎡ rectangular air duct.2nd, cable testing bridge system:Cable testing bridge of all gravity more than or equal to 150N/m,
Cable ladder, cable line box, bus duct.
Traditional support bracket system is the support system using gravity as primary load, when by larger earthquake, is lacked
Supporting construction, sideshake is big, and destruction closes on facility, or even comes off.It is domestic in recent years to introduce and have developed para-seismic support, can be very
The good load for undertaking pipeline horizontal direction, reduces the infringement that horizontal earthquake carries the masterpiece used time, but above-mentioned para-seismic support structure and
Fixed form is more single, for performance difficulty in special steel construction or superelevation space engineering:1st, design is not on steel construction
Any perforate, welding, easily occur that cable wire clamp junction is easily slided, clamp mechanical fatigue and fixed insecure be scattered etc. are asked
Topic;2nd, provide that para-seismic support suspension rod slenderness ratio is more than 100 or diagonal brace rod member slenderness ratio when being more than 200, palpus in GB50981-2014
Reinforcement measure is taken, common para-seismic support can not meet construction and design requirement;3rd, the rigid design due to cable wire and installation, but
Because of the winter and summer temperature difference problem and the long-term stress of itself of cable wire (cable wire containing stainless steel), cable wire fatigue stretching is occurred and extend
Property and produce elongation Problem of Failure, generally result in using after 3 to five years, easily making originally to be the default cable wire para-seismic support pine tensed
Relax, while accurate antidetonation pretightning force can not be provided apparatus structure and antidetonation pretightning force regulatory function are set, cause cable wire antidetonation branch
Frame, which loses, reaches expected antiseismic engineering effect, therefore its application is very limited, and make its fail to play it is due
Antihunt action.
Utility model content
To there is provided a kind of cable wire melting welding adjustable anti-to solve technical problem present in known technology for the utility model
Shake support and construction method of installation
Using the adjustable para-seismic support of this cable wire melting welding without perforate, welding on steel construction, construction and installation are flexible, nothing
Special tool(s) need to be used, it is time saving and energy saving to be constructed in superelevation space, and can reduce construction cost;Cable wire is easy for installation, flexibility is strong,
Steel construction can be made full use of to be fixed;Using the adjustable bicyclic length for spending blue connector directly to control cable wire manually, disappear
Except error, and then cable wire is controlled to the fixed force of electromechanical pipeline, horizontal when making the pipeline fully resist earthquake carries power.
The utility model is adopted the technical scheme that to solve technical problem present in known technology:
The adjustable para-seismic support of cable wire melting welding, it is characterised in that:Including upper cross arm support, lower cross arm support, airduct, four
Root is in the cable wire of oblique pull shape, to holding card, the first connector and the second connector, and cross arm support is fixed at the top of airduct,
Lower cross arm support is fixed in the bottom of the airduct;The upper cross arm support is connected close to both ends by the first connector and second
Part connects cable wire, and described cable wire the other end is consolidated by the first connector, the second connector and to holding card and building roof
It is affixed to determine portion;It is respectively connected with the every cable wire and adjustable bicyclic spends blue connector, the every cable wire and the second connector
Using sweat soldering attachment structure, the every cable wire bicyclic spends blue connector to use sweat soldering attachment structure with adjustable.
The utility model can also adopt the following technical scheme that:
It is described it is adjustable it is bicyclic to spend blue connector be made up of straight-flanked ring and regulating bolt, the both ends of the straight-flanked ring are formed with
The protuberance being connected as a single entity with it, the protuberance are formed with the internal thread hole with regulating bolt assembling, and the straight-flanked ring both ends are convex
Go out portion and regulating bolt is equipped with by internal thread hole.
The C-channel steel that the upper cross arm support and lower cross arm support are formed with multiple elongated holes using one side makes.
The upper cross arm support and lower cross arm support are fixedly mounted with by all-teeth screw and airduct.
The utility model has the advantages and positive effects of:Because the utility model uses above-mentioned technical proposal, that is, prop up
The cable wire of frame is connected with cable wire uses hot melten type welding connection structure, can solve cable wire clamp junction easily slide, clamp machine
Tool fatigue, fixed insecure the problems such as being scattered;Between cable wire using it is adjustable it is bicyclic spend blue connector, directly can so adjust manually
Whole control rope length, error is eliminated, and then control cable wire to the fixed force of electromechanical pipeline, when the pipeline is fully resisted earthquake
Level carry power, improve cable wire para-seismic support anti seismic efficiency, and then solve cable wire can not fasten manually with two problems of error,
Therefore the application of cable wire para-seismic support can be expanded, in the case where running into macroseism situation, adjustable para-seismic support can effectively play
The accurate antidetonation to quantize and the effect of shock absorbing.In the case where running into macroseism situation, adjustable para-seismic support can effectively play numerical value
The accurate antidetonation changed and the effect of shock absorbing.
Brief description of the drawings
Fig. 1 is front view of the present utility model;
Fig. 2 is Fig. 1 left view;
Fig. 3 is Fig. 1 top view;
Fig. 4 is that the utility model can adjust and bicyclic spend blue connecting-piece structure schematic diagram;
Fig. 5 is the assembling structure schematic diagram of the connector of the utility model first and the second connector.
In figure:1st, to holding card;1-1, fishbolt;1-2, pad;1-3, binding nut;1-4, semicircle steel ring;2nd,
A connection piece;3rd, the second connector;4th, safety pin;5th, cable wire;6th, it can adjust and bicyclic spend blue connector;6-1, straight-flanked ring;6-2、
Regulating bolt;7th, all-teeth screw;8th, upper cross arm support;9th, lower cross arm support;10th, building roof fixed part;11st, airduct;12、
Heat solder joint.
Embodiment
For utility model content, feature and effect of the present utility model can be further appreciated that, following examples are hereby enumerated, and
Accompanying drawing is coordinated to describe in detail as follows:
Refer to Fig. 1-Fig. 5, the adjustable para-seismic support of cable wire melting welding, including upper cross arm support 8, lower cross arm support 9, wind
Pipe 11, four is in the cable wire 5 of oblique pull shape, to holding card 1, the first connector 2 and the second connector 3.Fixed at the top of airduct
Lower cross arm support is fixed in upper cross arm support, the bottom of the airduct;The upper cross arm support passes through the first connection close to both ends
The connector 3 of part 2 and second connects cable wire 5, and described cable wire the other end is by the first connector, the second connector and to holding card
1 is affixed with top of building fixed part 10;Be respectively connected with the every cable wire it is adjustable it is bicyclic spend blue connector 6, it is described every
Root cable wire and the second connector use sweat soldering attachment structure, and the every cable wire bicyclic spends blue connector to use with adjustable
Sweat soldering attachment structure.
In the present embodiment, it is described it is adjustable it is bicyclic to spend blue connector 6 be made up of straight-flanked ring 6-1 and regulating bolt 6-2, institute
The both ends for stating straight-flanked ring are formed with the protuberance being connected as a single entity with it, and the protuberance is formed with the internal thread with regulating bolt assembling
Hole, straight-flanked ring both ends protuberance are equipped with regulating bolt by internal thread hole, and the regulating bolt can use M12 or M16 types.
In the present embodiment, the upper cross arm support and lower cross arm support are formed with multiple length using the zinc-plated one sides of 41x41x2
The C-channel steel in hole makes.
In the present embodiment, the upper cross arm support and lower cross arm support are fixedly mounted with by all-teeth screw and airduct.
In the present embodiment, the connector 3 of the first connector 2 and second is made using Q235 steel plates, described first
The connection wing being connected as a single entity with it is equipped with the connector 3 of connector 2 and second, screw is provided with the connection wing.Applying
When work is installed, the first connector 2 and the second connector 3 need to be attached by bolt.
Operation principle of the present utility model is:
Also need to match somebody with somebody union-melt weld fixture and melting welding mould in installation is applied described in the adjustable para-seismic support of this cable wire melting welding
Operated, the melting welding mould includes upper lid, die main body and bottom, and cable wire anchor is formed with the bottom of melting welding mould
Groove, rectangular cable wire weld portion groove is provided with the middle position of cable wire fixed groove, melting welding hole is formed with die main body center,
The melting welding hole should be directed at cable wire weld portion groove, in use, the melting welding fixture passes through melting welding clamp-securing bore and melting welding mould
It is fixedly mounted with.
The installation specific steps include:
S1, accurate measurement, accurate measurement are pressed to holding the fixing point of card 1 to the distance of the mount point of the second connector 3 of airduct
According to the composition of the second connector, extrapolate two sections of every cable wire 5 needed for length, surplus capacity 100mm is reserved, finally by can adjust
It is bicyclic to spend blue connector 6 to be adjusted.
S2, cable wire melting welding,
(a) melting welding mould, is cleaned with hairbrush, then consolidates the cable wire that cable wire needs to be put into melting welding mould at join by fusion after doubling
Determine in groove, cable wire 5 is stretched out melting welding mould 30mm to folding part, mark is carried out on cable wire, and cut at mark with wallpaper knife
Cut, remove the plastics outsourcing of cable wire.
(b), cable wire is penetrated by can adjust the bicyclic regulating bolt 6-2 circular holes for spending blue connector 6, then by cable wire doubling,
The closed end of cable wire is fixed with band, ensures that cable wire 5 is horizontal, cable wire is put into the cable wire fixed groove of melting welding mold bottom, looked for
Quasi- mark position, melting welding mould is closed, the melting welding clamp-securing bore that melting welding fixture is inserted on melting welding mould, and by melting welding fixture
Tightened with melting welding mould.
(c), melting welding hole pad is put into the center hole in the melting welding hole at die main body center by melting welding die tip, then
Quantitative Thermofusion welding agent is poured into the melting welding hole of melting welding mould, the reserved part Thermofusion welding agent at the pilot bore of melting welding mould, then
Detonator is poured into melting welding mould, reserved part detonator at same pilot bore, finally close the upper lid of melting welding mould.
(d), struck sparks with the detonator and Thermofusion welding agent reserved at lighter alignment pilot bore, until detonator and thermofussion welding
Agent is ignited.
(e), make detonator and after Thermofusion welding agent ignites 1 minute, open the die cover of melting welding mould, at observation melting welding hole,
Whether Thermofusion welding agent is completely melt, after errorless, opens the upper lid of melting welding mould, takes out cable wire 5, completes melting welding.
(f) operation of (b) step, is repeated, completes the melting welding of remaining each cable wire hot melt solder joint;
S3, upper cross arm support 8 and all-teeth screw 7 fixation, are screwed into all-teeth screw 7 by 1 nut first, make all-teeth screw
The elongated hole of cross arm support is penetrated, the second connector 3 is penetrated into all-teeth screw, then is screwed into the 2nd nut and is pre-fixed, can not
Tighten, be easy to cable wire to carry out the regulation of angle and direction when installing.
S4, lower cross arm support 9 and all-teeth screw fixation, in correspondence cross arm support airduct installation site, in airduct
Bottom penetrates lower cross arm support, adjusts lower cross arm support, and cross arm support 8, lower cross arm support and the horizontal of all-teeth screw are put down in guarantee
Vertically, then fixing nut.
S5, to holding the affixed of card 1 and building roof fixed part 10, according to the shape of project fixed part, choose corresponding
Fixed form, this project structure is circular steel structure column, therefore the half rounds bent to holding card 1 using two zinc-coated flat steel sheets
Two semicircle steel ring 1-4 for holding card will be closed on building roof fixed part, folder are being penetrated to holding card opening by circle
Tight bolt 1-1 and pad 1-2, then penetrates fishbolt 1-1 by the second connector 3, then penetrates pad 1-2, then is screwed into clamping
Nut 1-3, finally the circular hole of the circular hole of the second connector and the first connector 2 is aligned, penetrates bolt, and insert safety pin 4.
S6, end the first connector 2 of airduct 11 and the second connector 3 connection, by the circular hole of the first connector 2 and upper cross-arm
The circular hole of the second connector 3 at support aligns, and penetrates fishbolt 1-1, then is screwed into binding nut 1-3, is finally inserted safety
Pin 4.
S7, cable wire 5 fastening, workmen using it is adjustable it is bicyclic spend blue connector 6 to be adjusted cable wire, turn manually
It is dynamic to can adjust the bicyclic regulating bolt 6-2 for spending blue connector, cable wire 5 is carried out mechanical fasteners, until cable wire is completely exceptionally straight, pulling force
Act on to pipeline.
The specification of the adjustable para-seismic support of cable wire melting welding in the present embodiment should be according to ventiduct system, crane span structure
Diameter, sectional area, the gravity factor of system determine that the wirerope 5 can use Φ 8, Φ 10, Φ 12 etc., the upper cross-arm jointly
Support and lower cross arm support, need to carry out calculating Deepen Design according to the situation at scene to holding the actual sizes such as card.
Answered at cable wire sweat soldering joint it is bright and clean uniformly, flawless, residue, stomata phenomena such as, weld strength meets the requirements.
Embodiment described in the utility model accompanying drawing is exemplary, is only used for explaining the utility model, and can not be managed
Solve as to limitation of the present utility model.
Claims (4)
- A kind of 1. adjustable para-seismic support of cable wire melting welding, it is characterised in that:Including upper cross arm support (8), lower cross arm support (9), airduct (11), four in oblique pull shape cable wire (5), to holding card (1), the first connector (2) and the second connector (3), Cross arm support is fixed at the top of airduct, lower cross arm support is fixed in the bottom of the airduct;The upper cross arm support is close to two By the first connector (2) and the second connector (3) connection in the cable wire (5) of oblique pull shape, described cable wire the other end leads to for end Cross the first connector, the second connector and affixed to holding card (1) and fixed part (10);Being respectively connected with the every cable wire can Adjust it is bicyclic spend blue connector (6), the every cable wire and the second connector use sweat soldering attachment structure, the every steel Rope bicyclic spends blue connector to use sweat soldering attachment structure with adjustable.
- 2. the adjustable para-seismic support of cable wire melting welding according to claim 1, it is characterised in that:It is described to can adjust bicyclic flower Blue connector (6) is made up of straight-flanked ring (6-1) and regulating bolt (6-2), and the both ends of the straight-flanked ring are formed with is linked as one with it The protuberance of body, the protuberance are formed with the internal thread hole with regulating bolt assembling, and straight-flanked ring both ends protuberance passes through interior Screwed hole is equipped with regulating bolt.
- 3. the adjustable para-seismic support of cable wire melting welding according to claim 1, it is characterised in that:The upper cross arm support and The C-channel steel that lower cross arm support is formed with multiple elongated holes using one side makes.
- 4. the adjustable para-seismic support of cable wire melting welding according to claim 1, it is characterised in that:The upper cross arm support and Lower cross arm support is fixedly mounted with by all-teeth screw (7) with airduct.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201720972447.4U CN207087160U (en) | 2017-08-04 | 2017-08-04 | The adjustable para-seismic support of cable wire melting welding |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201720972447.4U CN207087160U (en) | 2017-08-04 | 2017-08-04 | The adjustable para-seismic support of cable wire melting welding |
Publications (1)
Publication Number | Publication Date |
---|---|
CN207087160U true CN207087160U (en) | 2018-03-13 |
Family
ID=61544180
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201720972447.4U Active CN207087160U (en) | 2017-08-04 | 2017-08-04 | The adjustable para-seismic support of cable wire melting welding |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN207087160U (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107243703A (en) * | 2017-08-04 | 2017-10-13 | 天津天建设集团有限公司 | The adjustable para-seismic support of cable wire melting welding and construction method of installation |
CN108825873A (en) * | 2018-08-15 | 2018-11-16 | 苏州泰盛新绿节能环保科技有限公司 | A kind of antidetonation suspension and support diagonal brace and its connecting elements |
US11704852B2 (en) | 2016-11-30 | 2023-07-18 | Gopro, Inc. | Aerial vehicle map determination |
-
2017
- 2017-08-04 CN CN201720972447.4U patent/CN207087160U/en active Active
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US11704852B2 (en) | 2016-11-30 | 2023-07-18 | Gopro, Inc. | Aerial vehicle map determination |
CN107243703A (en) * | 2017-08-04 | 2017-10-13 | 天津天建设集团有限公司 | The adjustable para-seismic support of cable wire melting welding and construction method of installation |
CN108825873A (en) * | 2018-08-15 | 2018-11-16 | 苏州泰盛新绿节能环保科技有限公司 | A kind of antidetonation suspension and support diagonal brace and its connecting elements |
CN108825873B (en) * | 2018-08-15 | 2024-03-08 | 苏州泰盛新绿节能环保科技有限公司 | Diagonal bracing for anti-seismic support and hanger and connecting component thereof |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN207087160U (en) | The adjustable para-seismic support of cable wire melting welding | |
US20130091787A1 (en) | Roof Mounting Standoff | |
CN207547984U (en) | A kind of fixed support device for pipeline butt welding | |
CN205226634U (en) | Flexible cable antidetonation support with adjustable simply | |
CN111255950B (en) | Pipe connection structure and antidetonation support that antidetonation support was used | |
CN208010868U (en) | Rope clamp formula cord clip | |
CN205421005U (en) | Viscous damper of installation adjustable length | |
CN103382740B (en) | String branch portal frame structure with adjustable support rod | |
CN107243703A (en) | The adjustable para-seismic support of cable wire melting welding and construction method of installation | |
CN110388017B (en) | Decorative outer wall dry hanging structure and mounting method thereof | |
CN207442409U (en) | A kind of cable bearer for municipal works | |
CN107503456B (en) | A glass claw of plugging into for super large hidden glass curtain wall and mounting structure thereof | |
CN110512734A (en) | A kind of connection structure of steel pipe column and girder steel | |
CN211228140U (en) | High-strength connecting device for top plate construction bracket | |
CN211398769U (en) | Pipe connection structure that antidetonation support was used | |
CN210421443U (en) | Non-welding flat plate fixing embedded part | |
CN211143454U (en) | Suspended ceiling board fixing structure | |
CN203686370U (en) | Structure for installing air duct of hanging belt type | |
CN208221768U (en) | A kind of heavy type support of pipelines | |
CN207277633U (en) | Glass for the concealed glass curtain wall of super large is plugged into pawl and its mounting structure | |
CN206252795U (en) | Backboard frame | |
CN205857789U (en) | A kind of pre-stretch-draw carbon fiber board reinforced concrete beam panel assembly | |
DE202006014470U1 (en) | Fastening equipment for photovoltaic on tiled roofs includes element which can be fitted into existing roof, through which passes anchored threaded rod, or boring screw for water-tight screwing and taking up any type of forces | |
CN205206100U (en) | One -way steel cable point of superelevation supporting ARC unit glass curtain wall | |
CN204531414U (en) | Building pipe hole to be provided special tool |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |