CN207080232U CN201721000160.1U CN201721000160U CN207080232U CN 207080232 U CN207080232 U CN 207080232U CN 201721000160 U CN201721000160 U CN 201721000160U CN 207080232 U CN207080232 U CN 207080232U
Authority
CN
China
Prior art keywords
bentonite
pressure chamber
pressure
case
pressurize equipment
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201721000160.1U
Other languages
Chinese (zh)
Inventor
周骏
张新
朱鸿浦
吴海祥
方园
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tianhe Mechanical Equipment Manufacturing Co Ltd
Original Assignee
Tianhe Mechanical Equipment Manufacturing Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tianhe Mechanical Equipment Manufacturing Co Ltd filed Critical Tianhe Mechanical Equipment Manufacturing Co Ltd
Priority to CN201721000160.1U priority Critical patent/CN207080232U/en
Application granted granted Critical
Publication of CN207080232U publication Critical patent/CN207080232U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Excavating Of Shafts Or Tunnels (AREA)
  • Preparation Of Clay, And Manufacture Of Mixtures Containing Clay Or Cement (AREA)

Abstract

The utility model discloses a kind of EPB shield tunneling bentonite pressurize equipment, it includes bentonite case, the mixer being installed in the bentonite case, and the pressurize equipment also includes bentonite Pressure chamber, the bentonite pump being connected between the bentonite case phase and the bentonite Pressure chamber, gas supply part and control unit for being supplied into bentonite Pressure chamber.The utility model sets up bentonite Pressure chamber between bentonite case and native storehouse, and the pressure and level condition in Tu Cang, bentonite Pressure chamber and bentonite case are monitored by pressure sensor and liquid level sensor moment, using the pressure in the real-time adjustment Tu Cang of gas supply part, bentonite Pressure chamber and bentonite case, the occurrence of gushing can be completely eliminated substantially.

Description

EPB shield tunneling bentonite pressurize equipment
Technical field
Suporting structure field is the utility model is related to, more particularly to a kind of EPB shield tunneling bentonite pressurize equipment.
Background technology
Shield is the main method in constructing metro tunnel, and under Complicated Geologic Condition, can shield machine quickly smoothly pacify Full driving, it is heavily dependent on the use to additive.Conventional additive has foaming agent, bentonite and polymer, And foaming agent and bentonite are then the progress most important additives of sediment improvement in current Shield Construction Method Used.Bentonite is not easy to coagulate Gu intensity is extremely low after solidification, its hygroscopic expansion simultaneously has lubricity, can effectively reduce the permeability of dregs.In easy unstability Stratum in when overhauling shield machine for a long time, inject bentonite to Tu Cang, support pressure can be kept, prevent the water and soil in stratum from entering Bury storehouse and cause surface subsidence;In addition the workability of dregs can be changed, the plasticity of sand soil is improved, be easy to be unearthed, reduce spray Gush.
Existing bentonite pipe-line system includes bentonite case, and bentonite case is connected with bentonite ascending pipe, bentonite note Enter pipe and be provided with bentonite control valve, bentonite pump, pressure gauge, bentonite flowmeter and non-return valve, bentonite inlet position In Tu Cang tops.In shield-tunneling construction, to make the dregs that excavation gets off have certain mobility and a sealing, bentonite is from swelling Bentonite pipeline is pumped into by bentonite pump in native case, so as to be injected into native storehouse, plays the underground water for reducing excavation face to pressure Power is gushed out in cabin, reduces generation of gushing.The problem of boosting or decompression delay be present in the existing bentonite supply unit pressure balance obtained, Generation of gushing can be caused to a certain extent, in order to further reduce generation of gushing, it is necessary to the pressure of moment holding bentonite supply unit Power balances with support pressure, and it is current urgent problem that how the moment, which keeps balance,.
The content of the invention
The purpose of this utility model, which is to provide one kind, can keep Tu Cang and the pressure balanced soil of bentonite supply unit constantly Press shield bentonite pressurize equipment.
In order to solve the above technical problems, the utility model adopts the following technical scheme that:A kind of EPB shield tunneling bentonite pressurize Equipment, it includes bentonite case, the mixer being installed in the bentonite case, and the pressurize equipment also includes swelling soil pressure Storehouse, the bentonite pump being connected between the bentonite case phase and the bentonite Pressure chamber, for into bentonite Pressure chamber The gas supply part and control unit of supply.
Optimization, the liquid level that the pressurize equipment also includes being installed in the bentonite case and bentonite Pressure chamber passes Sensor, the pressure sensor being installed in the bentonite Pressure chamber and native storehouse.
Optimization, the gas supply part include source of the gas, be connected to it is pneumatic between the source of the gas and the bentonite Pressure chamber Ball valve.
Optimization, it is additionally provided with pneumatic ball valve between Tu Cang and the bentonite Pressure chamber.
Further, it is respectively equipped with PID control on the liquid level sensor and pressure sensor in the bentonite Pressure chamber Device.
Further, the pneumatic ball valve between the Tu Cang and the bentonite Pressure chamber is provided with PID controller.
Further, the pneumatic ball valve being connected between the source of the gas and the bentonite Pressure chamber has two and phase It is arranged in parallel.
The beneficial effects of the utility model are:The utility model sets up swelling soil pressure between bentonite case and native storehouse Storehouse, and pass through the pressure in pressure sensor and liquid level sensor moment monitoring Tu Cang, bentonite Pressure chamber and bentonite case Power and level condition, utilize the pressure in the real-time adjustment Tu Cang of gas supply part, bentonite Pressure chamber and bentonite case, base The occurrence of gushing is completely eliminated in instinct.
Brief description of the drawings
Accompanying drawing 1 is structural representation of the present utility model.
Embodiment
Shown embodiment is described in detail below to the utility model below in conjunction with the accompanying drawings.
As shown in figure 1, EPB shield tunneling bentonite pressurize equipment includes bentonite case 1, is installed in the bentonite case 1 Mixer 2, the pressurize equipment also include bentonite Pressure chamber 3, are connected to the phase of bentonite case 1 and the swelling soil pressure Bentonite pump 9 between storehouse 3, the gas supply part for being supplied into bentonite Pressure chamber 3, control unit 10, it is installed on the swelling Native case 1 and liquid level sensor in bentonite Pressure chamber 3, the pressure being installed in the bentonite Pressure chamber 3 and native storehouse 0 Sensor, the pneumatic ball valve between native storehouse 0 and the bentonite Pressure chamber 3, located at native storehouse 0 and the swelling soil pressure The PID controller on pneumatic ball valve between storehouse 3, the liquid level sensor being respectively arranged in the bentonite Pressure chamber 3 and pressure PID controller on sensor.
The liquid level sensor being installed in the bentonite case 1 and bentonite Pressure chamber 3 is respectively the first level sensing The liquid level sensor 42 of device 41 and second.The pressure sensor being installed in the bentonite Pressure chamber 3 is first pressure sensor 51, the pressure sensor being installed in native storehouse 0 have it is multiple, respectively positioned at the upper strata middle level in native storehouse 0 and lower floor, positioned at upper strata Pressure sensor is second pressure sensor 52, and the pressure sensor positioned at middle level is the 3rd pressure sensor 53, positioned at lower floor Pressure sensor be the 4th pressure sensor 54,
The gas supply part includes source of the gas 6, the pneumatic ball valve being connected between the source of the gas 6 and the bentonite Pressure chamber 3, The pneumatic ball valve being connected between the source of the gas 6 and the bentonite Pressure chamber 3 has two and the setting that is in parallel.Wherein one The individual pneumatic ball valve for supply, another is the pneumatic ball valve of exhaust, and the two valves are referred to as the first pneumatic ball valve 71 With the second pneumatic ball valve 72, the pneumatic ball valve between native storehouse 0 and the bentonite Pressure chamber 3 is the 3rd pneumatic ball valve 73, First pneumatic ball valve 71, the second pneumatic ball valve 72 and the 3rd pneumatic ball valve 73 are connected with source of the gas 6 respectively, the first pneumatic ball valve 71 The 5th pressure sensor 55 is additionally provided between source of the gas 6.
The first PID is respectively equipped with first pressure sensor 51, the second liquid level sensor 42 and the 3rd pneumatic ball valve 73 Controller 81, the second PID controller 82 and the 3rd PID controller 83.Second pressure sensor 52, the 3rd pressure sensor 53 And the 4th pressure sensor 54 be connected by adapter 11 with the 3rd PID controllers 83, it is necessary to detect upper strata, middle level or During lower floor's pressure, the gearshift plectrum of adapter 11 is adjusted to corresponding gear.
The soil that will be detected by second pressure sensor 52, the 3rd pressure sensor 53 and the 4th pressure sensor 54 Pressure in pressure shield soil storehouse 0 is contrasted with setting value, when pressure is less than setting value, automatically opens up the 3rd pneumatic ball valve 73, the bentonite in bentonite Pressure chamber 3 is pressed into native storehouse 0 by air pressure, and simultaneously by the first pneumatic ball valve 71 to Supplement air, makes pressure remained steady in bentonite Pressure chamber 3, when pressure rises to setting in native storehouse 0 in bentonite Pressure chamber 3 The 3rd pneumatic ball valve 73 is closed during value.Bentonite liquid level in the second liquid level sensor 42 detection storehouse in bentonite Pressure chamber 3, when When liquid level is less than setting value, automatic start bentonite pump 9 injects bentonite into bentonite Pressure chamber 3, and it is pneumatic to open second Ball valve 72, the air in bentonite Pressure chamber 3 is discharged, makes its interior pressure constant.
For above-described embodiment only to illustrate technical concepts and features of the present utility model, its object is to allow be familiar with technique Personage can understand content of the present utility model and implement according to this, the scope of protection of the utility model can not be limited with this. All equivalent change or modifications made according to the utility model spirit, should all cover within the scope of protection of the utility model.

Claims (7)

1. a kind of EPB shield tunneling bentonite pressurize equipment, it includes bentonite case, the mixer being installed in the bentonite case, It is characterized in that:The pressurize equipment also includes bentonite Pressure chamber, is connected to the bentonite case phase and the swelling soil pressure Bentonite pump between power storehouse, gas supply part and control unit for being supplied into bentonite Pressure chamber.
2. EPB shield tunneling bentonite pressurize equipment according to claim 1, it is characterised in that:The pressurize equipment also includes It is installed on the bentonite case and liquid level sensor in bentonite Pressure chamber, is installed on the bentonite Pressure chamber and soil Pressure sensor in storehouse.
3. EPB shield tunneling bentonite pressurize equipment according to claim 1, it is characterised in that:The gas supply part includes gas Source, the pneumatic ball valve being connected between the source of the gas and the bentonite Pressure chamber.
4. EPB shield tunneling bentonite pressurize equipment according to claim 1, it is characterised in that:Tu Cang and the swelling soil pressure Power is additionally provided with pneumatic ball valve between storehouse.
5. EPB shield tunneling bentonite pressurize equipment according to claim 2, it is characterised in that:In the bentonite Pressure chamber Liquid level sensor and pressure sensor on be respectively equipped with PID controller.
6. EPB shield tunneling bentonite pressurize equipment according to claim 4, it is characterised in that:The Tu Cang and the swelling Pneumatic ball valve between soil pressure storehouse is provided with PID controller.
7. EPB shield tunneling bentonite pressurize equipment according to claim 3, it is characterised in that:It is described to be connected to the source of the gas Pneumatic ball valve between the bentonite Pressure chamber has two and the setting that is in parallel.
CN201721000160.1U 2017-08-11 2017-08-11 EPB shield tunneling bentonite pressurize equipment Active CN207080232U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201721000160.1U CN207080232U (en) 2017-08-11 2017-08-11 EPB shield tunneling bentonite pressurize equipment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201721000160.1U CN207080232U (en) 2017-08-11 2017-08-11 EPB shield tunneling bentonite pressurize equipment

Publications (1)

Publication Number Publication Date
CN207080232U true CN207080232U (en) 2018-03-09

Family

ID=61420058

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201721000160.1U Active CN207080232U (en) 2017-08-11 2017-08-11 EPB shield tunneling bentonite pressurize equipment

Country Status (1)

Country Link
CN (1) CN207080232U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107387105A (en) * 2017-08-11 2017-11-24 中交天和机械设备制造有限公司 EPB shield tunneling bentonite pressurize device and method
CN110306996A (en) * 2019-07-25 2019-10-08 中交天和机械设备制造有限公司 The Pneumatic auxiliary device of shield machine earth pressure balance

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107387105A (en) * 2017-08-11 2017-11-24 中交天和机械设备制造有限公司 EPB shield tunneling bentonite pressurize device and method
CN107387105B (en) * 2017-08-11 2023-12-22 中交天和机械设备制造有限公司 Soil pressure shield bentonite pressure maintaining equipment and method
CN110306996A (en) * 2019-07-25 2019-10-08 中交天和机械设备制造有限公司 The Pneumatic auxiliary device of shield machine earth pressure balance

Similar Documents

Publication Publication Date Title
CN109187925B (en) Gas-liquid countercurrent three-dimensional analog simulation test system for abandoned mine goaf
CN207080232U (en) EPB shield tunneling bentonite pressurize equipment
CN109342274A (en) High polymer crack grouting model test apparatus and test method under pressure-bearing river channels
CN206578131U (en) Soil and groundwater remediation system
CN205444215U (en) Gas drive foundation pit dewatering system
CN113586069A (en) Indoor test device for simulating shield water-rich stratum synchronous grouting construction technology and using method thereof
CN104282214A (en) Pipeline flow tracer test comprehensive device of pressure bearing karst aquifer system
CN105888723B (en) Drainage arrangement from gas pressure measurement to layer-through drilling and method during a kind of lower
CN113125066B (en) Device and method for testing upper floating force of single-ring duct piece
CN206020226U (en) A kind of Multifunctional permeameter
CN107387105A (en) EPB shield tunneling bentonite pressurize device and method
CN110242312A (en) A kind of Anti-blocking structure, a kind of shield machine blowdown anti-block apparatus and its application
CN103195470B (en) Drilling construction Gas gathering-device
CN104695426A (en) Gas lift method based secondary hole cleaning construction process for overlength pile foundations
CN113720994A (en) Device and method for testing stability of shield tunnel excavation surface under spring condition
CN204241322U (en) A kind of assembled duct test device
CN103526769B (en) Replat accumulation body slope intelligent drainage system and water discharge method
CN109164104B (en) Gas-liquid two-phase countercurrent visual simulation test system for abandoned mine goaf
CN106223964B (en) A kind of main shaft seals of shield machine compress control method
CN209247578U (en) High polymer crack grouting model test apparatus under a kind of pressure-bearing river channels
CN204204302U (en) A kind of pipeline stream tracer test integration unit of pressure-bearing karst aquifer system
CN204299513U (en) Drilling well overflow monitoring system
CN203925506U (en) Slurry balance pipe-jacking tunneling machine excavation face automatic pressure-balancing device
CN103114838B (en) High-pressure automatic sand discharge device
CN206246152U (en) Water burst reutilization system in citadel in a kind of tunnel

Legal Events