CN207079574U - Marine enrockment area bored concrete pile spillage control device - Google Patents
Marine enrockment area bored concrete pile spillage control device Download PDFInfo
- Publication number
- CN207079574U CN207079574U CN201721037727.2U CN201721037727U CN207079574U CN 207079574 U CN207079574 U CN 207079574U CN 201721037727 U CN201721037727 U CN 201721037727U CN 207079574 U CN207079574 U CN 207079574U
- Authority
- CN
- China
- Prior art keywords
- mud pit
- marine
- control device
- pipeline
- rig
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Abstract
A kind of marine enrockment area bored concrete pile spillage control device is the utility model is related to, the device includes:Small mud pit, big mud pit, the sieves in big mud pit being connected via pipeline and slush pump with small mud pit, the drilling rod hole that big mud pit enters pipeline and rig via mud is connected, and its medium and small mud pit is connected by pipeline with the perforate on the steel pile casting for the rig for being higher by construction time peak level certain distance above.The utility model reduces caused by the head differential pressure spillage at steel pile casting base opening and drift sand formation, reduces the pile foundation pore-forming time and ensure that the quality of pile using head difference inside and outside casing is reduced.
Description
Technical field
It the utility model is related to a kind of marine enrockment area bored concrete pile spillage control device.
Background technology
At sea during the cast-in-situ bored pile of enrockment area, because design stake top absolute altitude differs larger (8 meters or so of the discrepancy in elevation) with sea level
And pile foundation is in marine enrockment area, pile foundation steel pile casting can not buried depth it is oversize, casing coating is relatively thin, in pile foundation construction process
Head difference is excessive inside and outside middle casing, the spillage easily at steel pile casting base opening and drift sand formation, cause slurry coat method proportion reduce, from
Analysis, makes body refuse in hole not exclude normally, bottom hole sediment is blocked up, makes the pile measurement for pouring completion unqualified.Spillage and spillage
Slurry coat method proportion is caused to reduce, isolation.
Utility model content
Based on above mentioned problem, inventor has made intensive studies, as a result find by be higher by construction time peak level with
On steel pile casting on perforate, reduce hole in mud liquid level, so as to reduce head difference inside and outside casing, reduce caused by head differential pressure
Spillage at steel pile casting base opening and drift sand formation, ensures the proportion and denseness of mud in hole, and then ensure that the quality of pile.
A purpose of the present utility model is to provide a kind of marine enrockment area bored concrete pile spillage control device, the device bag
Include:Small mud pit, big mud pit, the sieves in big mud pit being connected via pipeline and slush pump with small mud pit,
The drilling rod hole that big mud pit enters pipeline and rig via mud connects, and its medium and small mud pit is by pipeline and is higher by the construction time most
At a certain distance from above high water mark (for example, peak level above 0.5-3m, more preferably preferably 1-2.5m, 1.2-2m, such as 1.5m
Place) rig steel pile casting on perforate connection.
Further, the volume of small mud pit can be 8-100 cubic meters, preferably 20-80 cubic meters, the body of big mud pit
Product can be 150-1000 cubic meters, preferably 500-800 cubic meters.
Further, mesh size used in step (2) filtering is 30-140 mesh, preferably 50-100 mesh.
Another purpose of the present utility model is to provide marine enrockment area bored concrete pile spillage control method and comprised the following steps:
(1) first be higher by construction time peak level certain distance above (for example, peak level above 0.5-3m, preferably 1-2.5m,
At more preferably 1.2-2m, such as 1.5m) rig steel pile casting on perforate, aperture can be 1-10cm, preferably 3-5cm, by steel
In casing hole mud liquid level reduce (such as to construction time peak level above 0.5-3m, more preferably preferably 1-2.5m, 1.2-2m,
Such as at 1.5m), to reduce head difference inside and outside casing, reduce mud pressure in hole;
(2) one small mud pit is set in tapping, the big mud pit that mud is extracted into construction platform with slush pump enters
Row filtering, oversize feeds back to the drilling rod hole of rig again, to ensure the proportion of mud and denseness, enable in hole body refuse effectively with
Mud is smoothly discharged.Screenings is most water and fine deposit, can be discharged.
This technology mainly reduces head difference inside and outside casing, reduces steel pile casting base opening and drift sand formation caused by head differential pressure
Locate spillage, ensure the proportion and denseness of mud in hole, and then ensure that the quality of pile.
The technology mainly using head difference inside and outside casing is reduced, reduces steel pile casting base opening and stream caused by head differential pressure
Spillage at sand bed, reduce the pile foundation pore-forming time and ensure that the quality of pile.
Brief description of the drawings
Fig. 1 is the structural representation of the utility model sea enrockment area bored concrete pile spillage control device.
Description of reference numerals:
1:Rig;2:Steel pile casting;3:Filling pile construction platform;4:Perforate;5:Small mud pit;6:Mud return duct;7:Greatly
Mud pit;8:Mud enters pipeline;9:Riprap layer;10:Water level.
Embodiment
The utility model is further illustrated below in conjunction with accompanying drawing, it should be understood, however, that the following description is only used for
Exemplary purpose, do not form to any restrictions of the present utility model.
As shown in figure 1, rig 1 is arranged on the filling pile construction platform 3 of riprap layer 9, it is high on the steel pile casting 2 of rig 1
Go out construction time peak level certain distance above (for example, peak level above 0.5-3m, more preferably preferably 1-2.5m, 1.2-
At 2m, such as 1.5m) perforate 4 is set, perforate 4 connects small mud pit 5, and small mud pit 5 is via mud return duct 6 and slush pump
(not shown) is connected with big mud pit 7, in big mud pit set sieves (not shown), big mud pit 7 via
Mud is connected into pipeline 8 with the drilling rod hole of rig 1.
Comprised the following steps using said apparatus sea enrockment area bored concrete pile spillage control method:
(1) construction time peak level certain distance above is being higher by first, for example, peak level above 0.5-3m, excellent
1-2.5m is selected, the steel pile casting of the rig more preferably at 1.2-2m, such as 1.5m opens 1-10cm, preferably 3-5cm diameters hole, by steel
Mud liquid level is reduced for example to construction time peak level above 0.5-3m, more preferably preferably 1-2.5m, 1.2-2m, example in casing hole
At 1.5m), to reduce head difference inside and outside casing, reduce mud pressure in hole;
(2) one small mud pit is set in tapping, the big mud pit that mud is extracted into construction platform with slush pump enters
Row filtering, oversize feeds back to borer drill rod hole again, to ensure the proportion of mud and denseness, enables in hole body refuse effectively with mud
Slurry smoothly discharge.
Embodiment 1
Using the device shown in Fig. 1, opened first in the steel pile casting for the rig being higher by construction time peak level above 1.5m
3cm diametric holes, mud liquid level in steel pile casting hole is reduced for example at construction time peak level above 1.5m, to reduce in casing
Outer head difference, reduce mud pressure in hole;
(2) about 30 cubic metres of small mud pits of one volume are set in tapping, mud is extracted into construction platform with slush pump
On the about 150 cubic metres big mud pit of volume filtered, filtering sieve the mesh of aperture 50, sieves set bottom, oversize
The drilling rod hole of rig rig is fed back to again, to ensure the proportion of mud and denseness, enables body refuse in hole effectively smooth with mud
Discharge.As a result, do not open up hole compared to steel pile casting and in fairlead mud the drilling of conventional bored concrete pile, steel pile casting base opening and drift sand
Spillage significantly reduces at layer, and the pile foundation pore-forming time reduces about 1/3 and ensure that pile quality is excellent.
Embodiment 2
Using the device shown in Fig. 1, opened first in the steel pile casting for the rig being higher by construction time peak level above 1.8m
6cm diametric holes, mud liquid level in steel pile casting hole is reduced for example at construction time peak level above 1.5m, to reduce in casing
Outer head difference, reduce mud pressure in hole;
(2) about 10 cubic metres of small mud pits of one volume are set in tapping, mud is extracted into construction platform with slush pump
On the about 300 cubic metres big mud pit of volume carry out the mesh of aperture 30 of Filtration Filtration sieve, sieves setting bottom, oversize is again
Borer drill rod hole is fed back to, to ensure the proportion of mud and denseness, body refuse in hole is effectively smoothly discharged with mud.Knot
Fruit, does not open up hole compared to steel pile casting and the conventional bored concrete pile of mud drills in fairlead, is leaked at steel pile casting base opening and drift sand formation
Slurry significantly reduces, and the pile foundation pore-forming time reduces about 1/3 and ensure that pile quality is excellent.
Claims (5)
1. a kind of marine enrockment area bored concrete pile spillage control device, the device include:Small mud pit, via pipeline and slush pump with
Big mud pit, the sieves in big mud pit of small mud pit connection, big mud pit enter pipeline and rig via mud
The connection of drilling rod hole, its medium and small mud pit passes through the steel of pipeline and the rig for being higher by construction time peak level certain distance above
Perforate connection on casing.
2. marine enrockment area bored concrete pile spillage control device according to claim 1, it is characterised in that small mud pit passes through
Pipeline is connected with the perforate on the steel pile casting for the rig being higher by construction time peak level above 0.5-3m.
3. marine enrockment area bored concrete pile spillage control device according to claim 1, it is characterised in that small mud pit passes through
Pipeline is connected with the perforate on the steel pile casting for the rig being higher by construction time peak level above 1.5m.
4. marine enrockment area bored concrete pile spillage control device according to claim 1, it is characterised in that the body of small mud pit
Product is 8-100 cubic meters, and the volume of big mud pit is 150-1000 cubic meters.
5. marine enrockment area bored concrete pile spillage control device according to claim 1, it is characterised in that the screen cloth of sieves
Aperture is 30-140 mesh.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201721037727.2U CN207079574U (en) | 2017-08-18 | 2017-08-18 | Marine enrockment area bored concrete pile spillage control device |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201721037727.2U CN207079574U (en) | 2017-08-18 | 2017-08-18 | Marine enrockment area bored concrete pile spillage control device |
Publications (1)
Publication Number | Publication Date |
---|---|
CN207079574U true CN207079574U (en) | 2018-03-09 |
Family
ID=61419574
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201721037727.2U Active CN207079574U (en) | 2017-08-18 | 2017-08-18 | Marine enrockment area bored concrete pile spillage control device |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN207079574U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107447751A (en) * | 2017-08-18 | 2017-12-08 | 新地能源工程技术有限公司 | Marine enrockment area bored concrete pile spillage control device and method |
-
2017
- 2017-08-18 CN CN201721037727.2U patent/CN207079574U/en active Active
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107447751A (en) * | 2017-08-18 | 2017-12-08 | 新地能源工程技术有限公司 | Marine enrockment area bored concrete pile spillage control device and method |
CN107447751B (en) * | 2017-08-18 | 2023-04-14 | 新地能源工程技术有限公司 | Slurry leakage control device and method for cast-in-place pile in offshore riprap area |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN101736732B (en) | Pressure and water reduction construction method of ultra-deep foundation pit confined water | |
US3081828A (en) | Method and apparatus for producing cuts within a bore hole | |
CN105804059B (en) | Drilling pouring pile hole device and method | |
US4134461A (en) | Marine structure and method of drilling a hole by means of said structure | |
US5428908A (en) | Apparatus and method for subsidence deepening | |
CN109736338A (en) | A kind of hydraulic engineering foundation pit pipe well combination light well point Yield rainfall relation method | |
CN108035700B (en) | Simulation system and method for sand carrying rule of shaft of marine natural gas hydrate production well | |
CN103920310B (en) | A kind of underground coal mine gas liquor release separator | |
CN104060621A (en) | Construction method for super vacuum dewatering well and well tube structure used in construction method | |
CN105155606A (en) | Port aeration type sludge clearing method | |
CN109881692A (en) | Pre-assembled dewatering well | |
CN104695879B (en) | A kind of stake holes is rinsed and takes out sand hole method | |
CN115144567B (en) | Upstream type tailing dam accumulation surveying and stability evaluation method and system | |
CN207079574U (en) | Marine enrockment area bored concrete pile spillage control device | |
CN107447751A (en) | Marine enrockment area bored concrete pile spillage control device and method | |
CN110847200B (en) | Dewatering and draining structure and dewatering and draining method for horizontal sand well of annular foundation pit | |
CN109339084A (en) | Underwater big depth open caisson passes through the construction method of the hard soil layer for being difficult to abolish | |
NO173521B (en) | UNDERGRADUATE STOCK CONSTRUCTION FOR PROCESSING AND STORAGE OF DRILL CAKES FROM DRILL OPERATIONS IN THE SEA SOUND, AND PROCEDURE FOR USING SUCH STOCK CONSTRUCTION | |
CN207092997U (en) | A kind of mud circulating system | |
CN112983428B (en) | Method for building underground water environment monitoring well | |
CN203463029U (en) | Well pipe structure | |
CN106284267B (en) | A kind of prospecting of offshore foundation and detection comprehensive platform | |
US2126576A (en) | Apparatus for and method of boring into and treating earth material | |
CN209195306U (en) | Middle-size and small-size drill drilling liquid closed-cycle system | |