CN207072629U - The preventing clogging up device of back taper funnel - Google Patents

The preventing clogging up device of back taper funnel Download PDF

Info

Publication number
CN207072629U
CN207072629U CN201720901020.5U CN201720901020U CN207072629U CN 207072629 U CN207072629 U CN 207072629U CN 201720901020 U CN201720901020 U CN 201720901020U CN 207072629 U CN207072629 U CN 207072629U
Authority
CN
China
Prior art keywords
funnel
back taper
trap
breach
preventing clogging
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201720901020.5U
Other languages
Chinese (zh)
Inventor
陈吉霄
张�杰
徐琳
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Qingdao Port International Ltd By Share Ltd Former Port Branch
Qingdao Port International Co Ltd
Original Assignee
Qingdao Port International Ltd By Share Ltd Former Port Branch
Qingdao Port International Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Qingdao Port International Ltd By Share Ltd Former Port Branch, Qingdao Port International Co Ltd filed Critical Qingdao Port International Ltd By Share Ltd Former Port Branch
Priority to CN201720901020.5U priority Critical patent/CN207072629U/en
Application granted granted Critical
Publication of CN207072629U publication Critical patent/CN207072629U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Chutes (AREA)

Abstract

The utility model discloses a kind of preventing clogging up device of back taper funnel, it is to overcome the back taper funnel that existing transhipment bulk cargo uses, in the goods that the moment flow of material is excessive or transhipment adhesiveness is strong, easily cause funnel spilling suitable for reading spill Lou or lower mouth block, manual cleaning spill Lou it is low with the work efficiency of bur, labor intensity is big, unsafe shortcoming offer.Breach is provided with the close lower exit site of back taper hopper side walls, on the lateral wall of breach upper end, is connected with the trap that can open or close breach.When transporting different cargo types, operable trap reaches suitable position or completely closed, goods is set to pass through the suitable space exported under funnel, the nothing for realizing transhipment material is spilt Lou and without clogging, without manual cleaning, operating efficiency is high, reduces labor intensity, eliminates the security risk of man-machine mixture operation.

Description

The preventing clogging up device of back taper funnel
Technical field
The utility model belongs to guide facility, specifically a kind of to be used to guide bulk cargo to be transported to from upstream facility The funnel of downstream installation.
Background technology
The bulk cargo unloading transported on harbour, the mode for usually transmitting bulk goods with multilevel device, i.e., sets from upstream It is standby to pour on the belt conveyer in downstream, then transport again and be sent to suitable place storage.To prevent linking of the goods in transhipment Place is spilt, and is mostly to be entered with the small back taper funnel guide of big upper and lower small mouth mouth, goods from the big mouth above funnel, from following Osculum flow on the belt of belt conveyer and transport.The funnel used at present, the size of its upper and lower mouth is immutable solid Fixed pattern.
When the goods of transhipment is the cargo type of good fluidity, goods falls on belt-conveying by lower mouth again into funnel is suitable for reading Just than smoothly on machine;If be fed transhipment directly to funnel in large quantities by equipment such as large-scale cranes, because material falls Moment flow into funnel is very big, and the lower mouth for easily causing funnel has little time to flow out and block, and so, material can be from upper Mouth overflows and spills and spill;Meanwhile the poor viscous wet goods kind of such as ore, coal mobility is also often transported on harbour, easily It is adhered in the side wall of funnel, even if goods is not directly largely to be fed, can also makes material sticks in hopper side walls Accumulation, make to become narrow at its lower mouth and result in blockage.
When material blocks in funnel exit, it is necessary to staff is cleared up using other auxiliary equipment, Influence normal production, cause operating efficiency low, manual cleaning labor intensity is big, while in equipment operation cleaning make it is man-machine not It can separate, unsafe factor be present.
Utility model content
Technical problem to be solved in the utility model is the back taper funnel for overcoming existing transhipment bulk cargo to use, Because lower outlet size is fixed from becoming, the moment flow in material is excessive or mouth blocks up under funnel during transhipment adhesiveness strong goods Plug, easily cause material and spilt Lou or lower mouth does not discharge in funnel spilling suitable for reading, manual cleaning spill Lou it is low with bur work efficiency, work by force Spend big, unsafe shortcoming, there is provided a kind of preventing clogging up device of back taper funnel.
In order to solve above mentioned problem existing for prior art, the utility model is realized using following technical proposals: The close lower exit site of back taper hopper side walls is provided with breach, and on the lateral wall of breach upper end, on or off can be played by being connected with Close the trap of breach.
The utility model also has following technical characteristic:
The connection of the trap, be on the lateral wall of the breach upper end, be fixed with funnel hinged-support, trap it is upper End is rotationally through on funnel hinged-support with shipping and reselling on another market;In the middle and lower part for leaving funnel one side of trap, trap hinge is fixed with Bearing, support are arranged on the scalable push rod in belt conveyer frame, and with shipping and reselling on another market, to be rotationally through trap hinged for its termination On seat;
The stretches push rod is promoted by hydraulic jack, and hydraulic jack support is arranged in belt conveyer frame;
The installation of the hydraulic jack, it is that bearing is fixed with the belt conveyer frame, erects and fix on bearing There is pole, the cylinder body of hydraulic jack is through on pole in which can swing up and down angle with selling through joint efforts;
The breach be located at funnel in the side wall of belt of belt conveyor length direction;
The control circuit of the hydraulic jack electrically connects with electric operation system.
The advantages of the utility model and good effect be, after installing trap additional on funnel side, when running into mobility Suitable position is closed or reached to good cargo type, the trap that operable push rod installs indentation, there on funnel;When run into flow compared with Big or poor mobility cargo type, can open trap to maximum, so as to increase goods by space, realize transhipment material When funnel without blocking, without manual cleaning, substantially increase operating efficiency, reduce labor intensity, eliminate manual cleaning Man-machine mixture operation risk.
Brief description of the drawings
Fig. 1 is a kind of schematic cross-sectional view of working condition of the utility model;
Fig. 2 is the schematic cross-sectional view of Fig. 1 another working condition.
Embodiment
Below in conjunction with the accompanying drawings and embodiment the utility model is described in further detail.
In Fig. 1, back taper funnel 1 is arranged on above belt conveyer 7 with support 1.1, and the lower mouth of the funnel 1 is to downward The vibratory sieve 8 in face, goods scatter from shake of the lower mouth outflow through vibratory sieve 8 from the entrance suitable for reading of funnel 1, fall on belt-conveying Storing place is sent on the belt of machine 7.
In order to prevent the moment flow of material excessive, make material have little time from the outflow of the lower mouth of funnel 1 and from spilling suitable for reading Spill Lou, or during the transhipment strong goods of adhesiveness, material sticks make lower outlet diminish and accumulated plugging in the side wall of funnel 1, Breach 1.3 is provided with the side wall 1.2 in the close lower exit of existing funnel 1, trap is connected with the outside of the upper end of breach 1.3 3, telescopic push rod 4.1 is movably connected in the outside of trap 3, when push rod 4.1 acts outer drawing trap 3(Referring to Fig. 2), breach 1.3 are opened, and material is swimmingly flowed out from the 1 time mouth of funnel for having become big, otherwise 1 time mouth of funnel diminishes until returning to existing Stationary state;
After preventing the lower outlet of funnel 1 from expanding, material is unlikely to spill the width of the belt of belt conveyer 7 Both sides, the breach 1.3 to be located on funnel 1 positioned at belt conveyer 7 Belt Length direction side wall 1.2 on, that is, leak In any one on bucket 1 in two side walls 1.2 perpendicular with Belt Length.
The connection of the trap 3, it is on the lateral wall of the upper end of breach 1.3, is fixed with funnel hinged-support 2, it is living The upper end of plate 3 2.1 is rotationally through on the funnel hinged-support 2 with shipping and reselling on another market, in the right flank for leaving funnel 1 of trap 3 Bottom, trap hinged-support 3.1 is fixed with, support is arranged on the scalable push rod 4.1 in belt conveyer frame, and its left end is used Ship and resell on another market and 3.2 be rotationally through on trap hinged-support 3.1.
The scalable push rod 4.1 is mounted on hydraulic jack 4, is promoted by hydraulic jack 4, the cylinder of hydraulic jack 4 Body support is arranged in belt conveyer frame.
The installation of the cylinder body of hydraulic jack 4, it is to be fixed with bearing 6 in the belt conveyer frame on the right side of funnel 1, props up Erect on seat 6 and be fixed with pole 5, the left end of push rod 4.1 of hydraulic jack 4 is flexibly connected with the middle and lower part of trap 3, hydraulic jack 4 cylinder body 4.2 is through on pole 5 in which can swing up and down angle with selling through joint efforts, so, when the push rod 4.1 of hydraulic jack 4 extends or contracted In short-term, trap 3 is driven to make fan-shaped swing open or the breach 1.3 closed on funnel 1;Meanwhile hydraulic jack 4 can be with push rod 4.1 Length become with being turned into angle accommodation.
In work, when transporting the cargo type of good fluidity, operation hydraulic jack 4 is by push rod 4.1 by breach on funnel 1 The lower end of trap 3 installed at 1.3 is promoted to the left, and trap 3 makees fan-shaped swing to the left, and trap 3 is reached into suitable position or will be lacked Mouth 1.3 completely closes;When running into the cargo type that flow is larger or mobility is poor, the push rod 4.1 of operation hydraulic jack 4 returns to the right Contracting, drive trap 3 to make fan-shaped swing to the right and pull open, until aperture maximum, make being increased by space for goods avoid blocking.
Because hydraulic jack 4 4.2 is rotationally through on pole 5 with selling through joint efforts, when push rod 4.1 stretches, hydraulic jack 4 can Make adaptively angle adjustment on pole 5, make adjustment fluent movements.So, the big I in lower outlet of funnel 1 is according to passing through goods The concrete condition of thing makees accommodation, and transhipment material can be achieved and occur at funnel 1 without flash and without clogging.
In order that the flexible more convenient of the push rod 4.1 is operated, control circuit and the electric operation room electricity of hydraulic jack 4 Connection.Meanwhile can also install monitor and control facility additional on the top of funnel 1, to find the situation of change of material in funnel 1 early, realize Remote monitoring, operation and regulation in the computer room of operating room, it is safe to use, reliable.
Above-described embodiment is only the indicative explaination carried out to the utility model, is not unique technical scheme.It is every The modification carried out using the technical solution of the utility model by purport or equivalent substitution, in the scope of protection of the utility model Within.

Claims (6)

  1. A kind of 1. preventing clogging up device of back taper funnel, it is characterised in that:In the close lower exit site of back taper hopper side walls Provided with breach, on the lateral wall of breach upper end, the trap that can open or close breach is connected with.
  2. 2. the preventing clogging up device of back taper funnel as claimed in claim 1, it is characterised in that:The connection of the trap, be Above the lateral wall of the breach upper end, funnel hinged-support is fixed with, the upper end of trap is rotationally through funnel hinge with shipping and reselling on another market On bearing;In the middle and lower part for leaving funnel one side of trap, trap hinged-support is fixed with, support is arranged on belt conveyer machine Scalable push rod on frame, its termination are rotationally through on trap hinged-support with shipping and reselling on another market.
  3. 3. the preventing clogging up device of back taper funnel as claimed in claim 2, it is characterised in that:The stretches push rod is by hydraulic pressure Oil cylinder pushing, hydraulic jack support is arranged in belt conveyer frame.
  4. 4. the preventing clogging up device of back taper funnel as claimed in claim 3, it is characterised in that:The installation of the hydraulic jack, It is that bearing is fixed with the belt conveyer frame, is erect on bearing and be fixed with pole, the cylinder body of hydraulic jack is with selling through joint efforts It is through on pole while angle can be swung up and down.
  5. 5. the preventing clogging up device of back taper funnel as claimed in claim 1 or 2, it is characterised in that:The breach is located at funnel In the side wall of belt of belt conveyor length direction.
  6. 6. the preventing clogging up device of back taper funnel as claimed in claim 3, it is characterised in that:The control electricity of the hydraulic jack Road electrically connects with electric operation system.
CN201720901020.5U 2017-07-24 2017-07-24 The preventing clogging up device of back taper funnel Expired - Fee Related CN207072629U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720901020.5U CN207072629U (en) 2017-07-24 2017-07-24 The preventing clogging up device of back taper funnel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720901020.5U CN207072629U (en) 2017-07-24 2017-07-24 The preventing clogging up device of back taper funnel

Publications (1)

Publication Number Publication Date
CN207072629U true CN207072629U (en) 2018-03-06

Family

ID=61522897

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720901020.5U Expired - Fee Related CN207072629U (en) 2017-07-24 2017-07-24 The preventing clogging up device of back taper funnel

Country Status (1)

Country Link
CN (1) CN207072629U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112478686A (en) * 2020-11-30 2021-03-12 国家能源集团煤焦化有限责任公司 Conveying device
CN115384951A (en) * 2022-08-31 2022-11-25 扎赉诺尔煤业有限责任公司 Prevent blockking up funnel subassembly and belt feeder conveying system

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112478686A (en) * 2020-11-30 2021-03-12 国家能源集团煤焦化有限责任公司 Conveying device
CN115384951A (en) * 2022-08-31 2022-11-25 扎赉诺尔煤业有限责任公司 Prevent blockking up funnel subassembly and belt feeder conveying system
CN115384951B (en) * 2022-08-31 2024-02-06 扎赉诺尔煤业有限责任公司 Anti-blocking leakage bucket assembly and belt conveyor conveying system

Similar Documents

Publication Publication Date Title
CN207072629U (en) The preventing clogging up device of back taper funnel
CN202498631U (en) High speed stirring pulping bench vehicle
CN203173389U (en) Auger delivery device capable of filtering materials
CN203296813U (en) Winze device with automatic ore drawing and blockage preventing functions
CN204198028U (en) The dual-purpose loading station of a kind of ore coal
CN205616281U (en) Ship unloaders and material recovery unit scatters thereof
CN206309352U (en) Deep-sea mining Hydraulic transportation pilot system
CN209997311U (en) Underground water-coal separation system
CN208948256U (en) A kind of belt conveyor
CN110316482A (en) A kind of novel blockage-clearing device
CN109352870A (en) A kind of waste material recovery device in power supply line production system
CN210289798U (en) Grouting system
CN107444922A (en) Scrapper conveyor feeding device and loading conveyor
CN210480255U (en) Concrete discharge apparatus
CN212558491U (en) Material inlet of bulk machine
CN103910180A (en) Tipping-bucket concrete feeder
CN208183637U (en) A kind of auger type is prewetted distributor
CN207079935U (en) A kind of blanking device of grinding coagulation soil
CN207698643U (en) Lime stone doffer in a kind of desulfurization pulping system
CN207920093U (en) A kind of stirring pusher extruding device for building
CN205441803U (en) Mining material loading machine
CN206939123U (en) A kind of mortar mixing filling equipment easy to operation
CN208150332U (en) Screw conveyor
CN209838475U (en) Underground coal digging machine
CN205112091U (en) Do benefit to mortar exhaust mortar jar

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20180306

Termination date: 20180724