CN207032770U - A kind of grating panel of pavement rapid infiltrated - Google Patents
A kind of grating panel of pavement rapid infiltrated Download PDFInfo
- Publication number
- CN207032770U CN207032770U CN201720979850.XU CN201720979850U CN207032770U CN 207032770 U CN207032770 U CN 207032770U CN 201720979850 U CN201720979850 U CN 201720979850U CN 207032770 U CN207032770 U CN 207032770U
- Authority
- CN
- China
- Prior art keywords
- base
- top cover
- articulamentum
- girder
- bearing
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Road Paving Structures (AREA)
Abstract
The utility model discloses a kind of grating panel of pavement rapid infiltrated,Including top cover and base,Girder and crossbeam are provided with the top of the top cover,The girder and crossbeam are disposed through the top cover surface,And the girder and the crossbeam are bolted to connection with the top cover,The girder side is provided with pressure-bearing bar,The pressure-bearing bar insertion is arranged in the girder,The pressure-bearing bar side is provided with splitter box,The splitter box is disposed through on the top cover,Articulamentum is provided with inside the top cover,The articulamentum insertion is arranged in the top cover,And it is fixedly connected with the top cover,Positioning hole is provided with the top of the articulamentum,The positioning hole is disposed through on the articulamentum,The positioning hole side is provided with load-bearing T word beams,The load-bearing T words beam covering is arranged on the articulamentum,The grating panel of such a pavement rapid infiltrated,Installing/dismounting simple and fast,Using flexible,Have broad application prospects.
Description
Technical field
Grating panel technical field is the utility model is related to, specially a kind of grating panel of pavement rapid infiltrated.
Background technology
So-called grating panel, course refer to the floor that surface is provided with grid, be mainly used in the larger place of displacement, with
The use demand of expanding economy, chemical industry, aquaculture, sewage disposal industry, shipbuilding industry, drilling platforms and Public Garden etc. is got over
Come more, so as to cause the demand to floor also increasing, and these local water consumptions are all bigger, if using general
Logical floor, impeded drainage can be caused, the problems such as so as to cause ponding, the production and living to people are made troubles, and grid
Plate is then a kind of floor exclusively for this Environment Design, there is good drainage performance, can ensure that these local drainings are led to
Freely.
But existing grating panel is formed using the spandrel girder and locating rod of I-shaped structure, wherein positioning is worn
The position of bar will be less than the top of spandrel girder, and the grating panel of this structure is less than the top of spandrel girder due to the position of position bar
Portion, so that the position of position bar will be less than the top out-of-flatness of spandrel girder, and it is not easily cleaned, the top of spandrel girder is in
Vacant state, it is easier to be damaged, traditional grating panel structure is complex in addition, and installing/dismounting difficulty is all larger, no
It is easy to use, and cost height is made, increases production cost.
So how to design a kind of grating panel of pavement rapid infiltrated, turning into us will currently solve the problems, such as.
Utility model content
The purpose of this utility model is to provide a kind of grating panel of pavement rapid infiltrated, to solve above-mentioned background skill
The problem of being proposed in art.
To achieve the above object, the utility model provides following technical scheme:A kind of grid of pavement rapid infiltrated
Plate, including top cover and base, the top cover top are provided with girder and crossbeam, and the girder and crossbeam are disposed through the top
Cap surface, and the girder and the crossbeam are bolted to connection with the top cover, the girder side is provided with pressure-bearing bar,
The pressure-bearing bar insertion is arranged in the girder, and the pressure-bearing bar side is provided with splitter box, and the splitter box is disposed through
On the top cover, articulamentum is provided with inside the top cover, the articulamentum is embedded in and is arranged in the top cover, and with the top cover
It is fixedly connected, is provided with positioning hole at the top of the articulamentum, the positioning hole is disposed through in the articulamentum, the positioning hole
Inside is provided with positioning bar, and the positioning bar is disposed through in the positioning hole, and the positioning hole side is provided with load-bearing T words
Beam, the load-bearing T words beam covering are arranged on the articulamentum, are provided with bar groove at the top of the articulamentum, the bar groove is embedding
Entering and be arranged in the articulamentum, the base side is provided with connecting pole, and the connecting pole insertion is arranged in the base, and
The connecting pole is bolted to connection with the base, and described connecting pole one end is provided with attachment cap, the attachment cap covering
The connecting pole surface is arranged at, one end of the base side is provided with connecting hole, and the connecting hole is disposed through the bottom
On seat, the base bottom is provided with support column, and the support column insertion is arranged in the base, and the chassis interior is provided with and held
Pressing plate, the bearing plate top, which is provided with, snaps connection body, and described snap connection is provided with buckle at the top of body, and the buckle insertion is set
Snapped connection in vivo in described, and the buckle is fixedly connected with the body that snaps connection, the buckle side is provided with baffle plate, institute
State baffle plate insertion and be arranged at described snap connection on body.
Further, skid resistance strip is provided with the top of the pressure-bearing bar, the skid resistance strip covering is arranged at the pressure-bearing bar
Surface.
Further, the side of the connection column bottom is provided with anti-abrasion pad, and the anti-abrasion pad nesting is arranged at the connection
On post.
Further, the base side is provided with snib, and the snib covering is arranged on the base, and with the bottom
Seat is bolted to connection, and neck is provided with the top of the snib.
Further, pod apertures and guiding gutter are respectively equipped with the top of the bearing plate, the pod apertures are disposed through institute
State in bearing plate, the guiding gutter insertion is arranged in the bearing plate.
Further, described snap connection is provided with plug connector at the top of body, and plug is provided with the top of the plug connector.
Compared with prior art, the beneficial effects of the utility model are:The grating panel of this kind of pavement rapid infiltrated, is adopted
Designed with layer-stepping, structure is clearly demarcated, and inside uses T word load-bearing beam constructions so that the grating panel top of the pavement rapid infiltrated
Portion is more smooth, does not have seeping phenomenon, and uses hierarchical design, is easy to clear up, in addition, the grating panel is held using multiple
Weight beam interlocks load-bearing, can undertake heavier weight, be hardly damaged, the grating panel of such a pavement rapid infiltrated, installation is torn open
Unload simple and fast, using flexible, it is small to be made cost, has broad application prospects.
Brief description of the drawings
Fig. 1 is overall structure diagram of the present utility model;
Fig. 2 is articulamentum partial structural diagram of the present utility model;
Fig. 3 is bearing plate partial structural diagram of the present utility model;
In figure:1- top covers;2- girders;3- crossbeams;4- pressure-bearing bars;5- splitter boxs;6- skid resistance strips;7- bases;8- abrasionproofs
Pad;9- connecting poles;10- attachment caps;11- connecting holes;12- support columns;13- snibs;14- necks;15- articulamentums;16- is positioned
Hole;17- positions bar;18- load-bearing T word beams;19- bar grooves;20- bearing plates;21- pod apertures;22- guiding gutters;23- buckles connect
Junctor;24- buckles;25- plug connectors;26- baffle plates;27- plugs.
Embodiment
Below in conjunction with the accompanying drawing in the utility model embodiment, the technical scheme in the embodiment of the utility model is carried out
Clearly and completely describing, it is clear that described embodiment is only the utility model part of the embodiment, rather than whole
Embodiment.Based on the embodiment in the utility model, those of ordinary skill in the art are not under the premise of creative work is made
The every other embodiment obtained, belong to the scope of the utility model protection.
Fig. 1-3 are referred to, the utility model provides a kind of technical scheme:A kind of grating panel of pavement rapid infiltrated,
Including top cover 1 and base 7, the top of top cover 1 is provided with girder 2 and crossbeam 3, and the girder 2 and crossbeam 3 are disposed through institute
The surface of top cover 1 is stated, and the girder 2 and the crossbeam 3 are bolted to connection with the top cover 1, the side of girder 2 is set
There is a pressure-bearing bar 4, the insertion of pressure-bearing bar 4 is arranged in the girder 2, and the side of pressure-bearing bar 4 is provided with splitter box 5, described point
Chute 5 is disposed through on the top cover 1, and the inside of top cover 1 is provided with articulamentum 15, and the insertion of articulamentum 15 is arranged at institute
State in top cover 1, and be fixedly connected with the top cover 1, the top of articulamentum 15 is provided with positioning hole 16, and the positioning hole 16 runs through
It is arranged in the articulamentum 15, the inside of positioning hole 16 is provided with positioning bar 17, and the positioning bar 17 is disposed through
In the positioning hole 16, the side of positioning hole 16 is provided with load-bearing T words beam 18, and the covering of load-bearing T words beam 18 is arranged at described
On articulamentum 15, the top of articulamentum 15 is provided with bar groove 19, and the insertion of bar groove 19 is arranged in the articulamentum 15,
The side of base 7 is provided with connecting pole 9, and the insertion of connecting pole 9 is arranged in the base 7, and the connecting pole 9 with it is described
Base 7 is bolted to connection, and described one end of connecting pole 9 is provided with attachment cap 10, and the covering of attachment cap 10 is arranged at described
The surface of connecting pole 9, one end of the side of base 7 are provided with connecting hole 11, and the connecting hole 11 is disposed through the base 7
Interior, the bottom of base 7 is provided with support column 12, and the insertion of support column 12 is arranged in the base 7, inside the base 7
Provided with bearing plate 20, the top of bearing plate 20, which is provided with, snaps connection body 23, and the top of body 23 that snaps connection is provided with buckle 24,
The insertion of buckle 24 is snapped connection in body 23 described in being arranged at, and the buckle 24 fixes company with the body 23 that snaps connection
Connect, the side of buckle 24 is provided with baffle plate 26, and the insertion of baffle plate 26 is arranged at described snap connection on body 23.
Further, the top of pressure-bearing bar 4 is provided with skid resistance strip 6, and the covering of skid resistance strip 6 is arranged at the pressure-bearing
The surface of bar 4, it is safer that the skid resistance strip 6 can allow the grating panel to use.
Further, the side of the bottom of connecting pole 9 is provided with anti-abrasion pad 8, and the nesting of anti-abrasion pad 8 is arranged at the company
Connect on post 9, the anti-abrasion pad 8 is used to protect connecting pole 9.
Further, the side of base 7 is provided with snib 13, and the covering of snib 13 is arranged on the base 7, and with
The base 7 is bolted to connection, and the top of snib 13 is provided with neck 14, and the snib 13 can make two grating panels
Occlusion is closer.
Further, the top of bearing plate 20 is respectively equipped with pod apertures 21 and guiding gutter 22, and the pod apertures 21 run through
It is arranged in the bearing plate 20, the insertion of guiding gutter 22 is arranged in the bearing plate 20, the pod apertures 21 and water conservancy diversion
Groove 22 is used to drain draining.
Further, the top of body 23 that snaps connection is provided with plug connector 25, and the top of plug connector 25 is set
There is plug 27, the plug 27 can make the grating panel structure more firm.
Operation principle:First, the grating panel of the pavement rapid infiltrated is assembled and installed according to structure
In position, when installing the grating panel, connecting pole 9 and attachment cap 10 are nested into connecting hole 11, attachment cap 10
Can sting automatically tight so that be engaged even closer between two grating panels, avoid the occurrence of loosening, in the grating panel in use, because
To be provided with pod apertures 21 and guiding gutter 22 at the top of bearing plate 20, pod apertures 21 and guiding gutter 22 can be guided to current, made
Current are unlikely to scattered, are easy to draining, because being provided with snib 13 in the side of base 7, snib 13 can make to paste between two grating panels
Closing closer, make it more firm, the grating panel is using layer-stepping design in addition, only needs to remove top cover 1 during cleaning,
Cleaning is carried out to top cover 1 can be extremely convenient to complete cleaning use, and is provided with the He of buckle 24 inside the grating panel
Plug 27, using the structure of dual fixation, structure is more stable, and heavy burden ability is stronger.
While there has been shown and described that embodiment of the present utility model, for the ordinary skill in the art,
It is appreciated that these embodiments can be carried out with a variety of changes in the case where not departing from principle of the present utility model and spirit, repaiied
Change, replace and modification, the scope of the utility model are defined by the appended claims and the equivalents thereof.
Claims (6)
1. a kind of grating panel of pavement rapid infiltrated, including top cover (1) and base (7), it is characterised in that:The top cover
(1) top is provided with girder (2) and crossbeam (3), and the girder (2) and crossbeam (3) are disposed through the top cover (1) surface,
And the girder (2) and the crossbeam (3) are bolted to connection with the top cover (1), girder (2) side is provided with and held
Press strip (4), the pressure-bearing bar (4) is embedded to be arranged in the girder (2), and pressure-bearing bar (4) side is provided with splitter box (5),
The splitter box (5) is disposed through on the top cover (1), and articulamentum (15), the articulamentum are provided with inside the top cover (1)
(15) it is embedded to be arranged in the top cover (1), and be fixedly connected with the top cover (1), it is fixed to be provided with the top of the articulamentum (15)
Position hole (16), the positioning hole (16) are disposed through in the articulamentum (15), and positioning is provided with inside the positioning hole (16)
Bar (17), the positioning bar (17) are disposed through in the positioning hole (16), and positioning hole (16) side is provided with and held
Weight T words beam (18), load-bearing T words beam (18) covering are arranged on the articulamentum (15), set at the top of the articulamentum (15)
There is bar groove (19), the bar groove (19) is embedded to be arranged in the articulamentum (15), and base (7) side is provided with connection
Post (9), the connecting pole (9) is embedded to be arranged in the base (7), and the connecting pole (9) passes through spiral shell with the base (7)
Bolt is fixedly connected, and described connecting pole (9) one end is provided with attachment cap (10), and attachment cap (10) covering is arranged at the connecting pole
(9) surface, one end of base (7) side are provided with connecting hole (11), and the connecting hole (11) is disposed through the base
(7) in, base (7) bottom is provided with support column (12), and the support column (12) is embedded to be arranged in the base (7), institute
State and bearing plate (20) is provided with inside base (7), be provided with the top of the bearing plate (20) and snap connection body (23), it is described to snap connection
Be provided with buckle (24) at the top of body (23), the buckle (24) is embedded, and to be arranged at the body (23) that snaps connection interior, and the buckle
(24) it is fixedly connected with the body (23) that snaps connection, buckle (24) side is provided with baffle plate (26), and the baffle plate (26) is embedding
Enter to be arranged at described snap connection on body (23).
A kind of 2. grating panel of pavement rapid infiltrated according to claim 1, it is characterised in that:The pressure-bearing bar
(4) top is provided with skid resistance strip (6), and skid resistance strip (6) covering is arranged at pressure-bearing bar (4) surface.
A kind of 3. grating panel of pavement rapid infiltrated according to claim 1, it is characterised in that:The connecting pole
(9) side of bottom is provided with anti-abrasion pad (8), and anti-abrasion pad (8) nesting is arranged on the connecting pole (9).
A kind of 4. grating panel of pavement rapid infiltrated according to claim 1, it is characterised in that:The base (7)
Side is provided with snib (13), and snib (13) covering is arranged on the base (7), and passes through bolt with the base (7)
It is fixedly connected, neck (14) is provided with the top of the snib (13).
A kind of 5. grating panel of pavement rapid infiltrated according to claim 1, it is characterised in that:The bearing plate
(20) top is respectively equipped with pod apertures (21) and guiding gutter (22), and the pod apertures (21) are disposed through the bearing plate (20)
Interior, the guiding gutter (22) is embedded to be arranged in the bearing plate (20).
A kind of 6. grating panel of pavement rapid infiltrated according to claim 1, it is characterised in that:It is described to snap connection
Plug connector (25) is provided with the top of body (23), plug (27) is provided with the top of the plug connector (25).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201720979850.XU CN207032770U (en) | 2017-08-08 | 2017-08-08 | A kind of grating panel of pavement rapid infiltrated |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201720979850.XU CN207032770U (en) | 2017-08-08 | 2017-08-08 | A kind of grating panel of pavement rapid infiltrated |
Publications (1)
Publication Number | Publication Date |
---|---|
CN207032770U true CN207032770U (en) | 2018-02-23 |
Family
ID=61473649
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201720979850.XU Active CN207032770U (en) | 2017-08-08 | 2017-08-08 | A kind of grating panel of pavement rapid infiltrated |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN207032770U (en) |
-
2017
- 2017-08-08 CN CN201720979850.XU patent/CN207032770U/en active Active
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN203200985U (en) | Light steel structure plant wind-resisting column and roof beam connection structure | |
CN207032770U (en) | A kind of grating panel of pavement rapid infiltrated | |
CN106013632A (en) | Split assembled prefabricated cabin and roof centralized drainage structure thereof | |
CN211421409U (en) | Cross toper box support node | |
CN208638320U (en) | The automatic remover of buck for photovoltaic panel | |
CN204385874U (en) | A kind of rainwater memory module | |
CN210263579U (en) | Flat-to-slope photovoltaic roof structure | |
CN205545120U (en) | Photovoltaic is solar module frame for green house | |
CN205283030U (en) | Assembled low pressure cable distribution box | |
CN204967730U (en) | Photovoltaic solar panel frame | |
CN204531209U (en) | A kind of box-type room back timber being convenient to draining | |
CN207460071U (en) | A kind of integrated roof of green building based on solar panels | |
CN206128267U (en) | Rainwater grate of big displacement | |
CN106013414A (en) | Solar balcony heat collection plate connecting structure and installation method thereof | |
CN207419867U (en) | Steel house panel splicing module | |
CN202248476U (en) | Honeycomb core building shuttering | |
CN215368304U (en) | Drainage channel connects and roof drainage system | |
CN219281069U (en) | Ridge purline structure with drainage function | |
CN206737312U (en) | A kind of high-density plate with water-proof function | |
CN205314384U (en) | Metal roof bracing system with drainage, fender snow subtract gesture function | |
CN211873973U (en) | Sunshade device in gardens | |
CN211908061U (en) | Hua formula box-type substation waterproof construction | |
CN217734276U (en) | Rainwater about sponge city filters collection device | |
CN215368316U (en) | Drainage channel connects and roof drainage system | |
CN108768283A (en) | Buck automatic clearing method for photovoltaic panel |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |