CN207017505U - A kind of Split sink constructing structure on unit type energy-saving curtain wall - Google Patents
A kind of Split sink constructing structure on unit type energy-saving curtain wall Download PDFInfo
- Publication number
- CN207017505U CN207017505U CN201621318763.1U CN201621318763U CN207017505U CN 207017505 U CN207017505 U CN 207017505U CN 201621318763 U CN201621318763 U CN 201621318763U CN 207017505 U CN207017505 U CN 207017505U
- Authority
- CN
- China
- Prior art keywords
- crossbeam
- unit
- tank material
- curtain wall
- column
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Finishing Walls (AREA)
Abstract
The Split sink constructing structure on a kind of unit type energy-saving curtain wall is the utility model is related to, is related to curtain buildingses construction applications, including crossbeam unit, column unit, tank material and cell curtain wall plate;More crossbeam units dock to form whole crossbeam successively, and more root post units dock to form whole root post successively;On the framework surface that whole crossbeam docks with whole root post with suspension member come fixed cell curtain wall plate;The mounting groove for installing tank material is equipped with crossbeam unit;Tank material is installed on the joint of adjacent two crossbeam units;Tank material is divided into the first tank material and the second tank material;Tank material slides into specified location in mounting groove, and is packaged fixation by fluid sealant.The cell curtain wall Split sink structure is by tank material decomposition technique with realizing during practice of construction to the rigors of sequence of construction.Important contribution has been made to save the construction period, while ensure that the change because of sequence of construction, has produced mounting process common quality defect not in place.
Description
Technical field
Curtain buildingses construction applications are the utility model is related to, more particularly to split type on a kind of unit type energy-saving curtain wall
Tank constructing structure.
Background technology
State's socio-economic development comes into urbanization and industrial age, the construction industry as pillar industry in national economy
There is an urgent need to industry modernization transition and upgrade.Building industry modernization is to substitute labor with the scale plant produced of Integration ofTechnology type
Intensive manual production mode is moved, to industrialize product assembled in situ substitution field operation Construction Mode, realizes house components
The batch production of part production, the green construction of the assembling of job site.Labor productivity can be effectively improved, reduces raw material
With the waste of the energy, cost of construction is reduced, realizes economies of scale.The exploration existing more than ten years of building industry modernization
Course, firmly the portion of building advocate always implement housing industrialization work, Industrialization technical research with exchange on the basis of, group
The establishment revision of standard criterion is knitted, while builds up a collection of housing industrialization Demonstration Base successively, including housing development, construction
The related industry chain such as installation, structural elements, house components enterprise, to promoting being widely implemented for China's housing industrialization to establish base
Plinth.This simultaneously, all parts of the country build authorities by putting into effect housing industrialization encouragement policy equal excitation measure, Industrialization
Pilot and demonstration project construction, either still all have made great progress, have accumulated in terms of engineering management in technical research
Many successful experiences.
Building curtain wall is an important part of architectural industrialization, the building curtain wall under such policy, environment
The industrialization of industry causes the business of type unitized curtain wall significantly to enhance, market prospects are fabulous also with flourishing.Unit
Formula building curtain wall is to integrate design standard, processing factory, the product of Construction Operating Machinery, is to be best suitable for building production
The product of industryization requirement.For many years with the market demands of modular building curtain wall, matched construction technology is gradually perfect,
Fixed Construction Mode is basically formed.
Utility model content
The utility model is mainly solving the technical problems that the Split sink provided on a kind of unit type energy-saving curtain wall is applied
Work structure, solve conventional curtain wall mounting structure causes order fixed because of underaction, and the sealing installed is undesirable
The problem of.
In order to solve the above technical problems, the technical scheme that the utility model uses is to provide a kind of unit type energy-saving curtain
Split sink constructing structure on wall, including crossbeam unit, column unit, tank material and cell curtain wall plate;More crossbeam lists
Docking forms whole crossbeam to member successively, and more root post units dock to form whole root post successively;In whole crossbeam and whole root post
The framework surface formed is docked with suspension member come fixed cell curtain wall plate;It is equipped with the crossbeam unit for installing the tank
The mounting groove of material;The tank material is installed on the joint of adjacent two crossbeam units;The tank material is divided into the first tank material
With the second tank material;The tank material slides into specified location in mounting groove, and is packaged fixation by fluid sealant.
Preferably, the crossbeam unit includes female crossbeam unit and male crossbeam unit;Female crossbeam unit and male crossbeam list
First matched moulds docking;Female crossbeam unit is provided with buckling groove, and prominent crossbeam latch is provided with buckling groove;In public crossbeam list
Member is provided with the crossbeam installation portion being matched with buckling groove;The transverse direction coordinated with crossbeam latch is provided with crossbeam installation portion to insert
Mouthful;The male crossbeam unit is with forming a mounting groove for being used to install the tank material after female crossbeam unit matched moulds.
Preferably, glue is filled with the buckling groove in female crossbeam unit, and glue is filled in crossbeam installation portion
Between buckling groove;Glue is also filled between tank material and mounting groove.
Preferably, the column unit includes public pole unit and female column unit;Female column unit is provided with
Column latch;The longitudinal socket coordinated with the column latch is then provided with the public pole unit.
Preferably, hanging device is connected with by fastener on the column unit;The hanging device is connected in wall
On built-in fitting on wall.
The beneficial effects of the utility model are:A kind of Split sink constructing structure on unit type energy-saving curtain wall is provided,
By tank material decomposition technique with realizing during practice of construction to the rigors of sequence of construction.To save work of constructing
Phase has made important contribution, while ensure that the change because of sequence of construction, produces mounting process common quality defect not in place.This
One technology with the checking put into practice, obtain good effect.
Brief description of the drawings
Fig. 1 is the structural representation of the Split sink constructing structure on a kind of unit type energy-saving curtain wall of the utility model;
Fig. 2 is the structural representation of crossbeam unit docking;
Fig. 3 is the structural representation at the node of crossbeam unit;
Fig. 4 is the partial structurtes zoomed-in view in Fig. 3;
Fig. 5 is the structural representation of column unit docking;
Fig. 6 is the structural representation at the node of column unit;
Fig. 7 is the partial structurtes zoomed-in view in Fig. 6;
Fig. 8 is installment state schematic diagram of the tank material in crossbeam unit joint;
Fig. 9 is installation accurate status schematic diagram of the tank material in crossbeam unit joint;
The mark of each part is as follows in accompanying drawing:1st, crossbeam unit;2nd, column unit;3rd, tank material;4th, cell curtain wall plate;5、
Hanging device;6th, built-in fitting;7th, glue;11st, female crossbeam unit;12nd, public crossbeam unit;13rd, crossbeam installation portion;14th, laterally insert
Mouthful;15th, crossbeam latch;21st, public pole unit;22nd, female column unit;23rd, column latch;24th, longitudinal socket;31st, the first water
Groove material;32nd, the second tank material.
Embodiment
Preferred embodiment of the present utility model is described in detail below in conjunction with the accompanying drawings, so that the advantages of the utility model
It can be easier to be readily appreciated by one skilled in the art with feature, it is apparent clear and definite so as to be made to the scope of protection of the utility model
Define.
Accompanying drawing 1 to 9 is referred to, the utility model embodiment includes:
A kind of Split sink constructing structure on unit type energy-saving curtain wall, including crossbeam unit 1, column unit 2, tank
Material 3 and cell curtain wall plate 4.More crossbeam units 1 are docked successively forms whole crossbeam, and more root post units 2 dock formation successively
Whole root post.Crossbeam unit 1 includes female crossbeam unit 11 and male crossbeam unit 12, and female crossbeam unit 11 is closed with male crossbeam unit 12
Mould docks, and forms a mounting groove for being used to install tank material 3.Female crossbeam unit is provided with buckling groove, is set in buckling groove
There is prominent crossbeam latch 15;The crossbeam installation portion 13 being matched with buckling groove is provided with public crossbeam unit 12;Pacify in crossbeam
Dress portion 13 is provided with the horizontal socket 14 coordinated with crossbeam latch 15.Crossbeam installation portion 13 is inserted in buckling groove, by laterally inserting
Mouth 14 is realized with the grafting of crossbeam latch 15 docks matched moulds installation between male crossbeam unit 12 and female crossbeam unit 11.In clamping
Glue is also filled with groove, and glue is filled in the gap between crossbeam installation portion and buckling groove.Equally, column unit includes
Public pole unit 21 and female column unit 22, female column unit 22 are provided with column latch 23, are then provided with public pole unit 21
The longitudinal socket 24 coordinated with column latch 23.Public pole unit is realized using the cooperation of longitudinal socket 24 and column latch 23
21 and female column unit 22 matched moulds installation.Hanging device 5 is connected with by fastener on column unit 2, hanging device 5 is connected
On built-in fitting 6 on wall.
On the framework surface that whole crossbeam docks with whole root post with suspension member come fixed cell curtain wall plate 4, most end form
Integral curtain wall.The mounting groove for installing tank material 3 is equipped with crossbeam unit 1, tank material is arranged on adjacent two
The joint of root crossbeam unit 1, tank material 3 can be installed and carried out at necessary sealing simultaneously when type unitized curtain wall plate is installed
Reason, is also filled with glue 7 between tank material 3 and mounting groove.In the mounting structure of prior art, when running into reserved opening,
The installation of lastblock plate must be carried out in the case where no completion tank material 3 is installed., must so after lastblock plate is in place
So lead to not the sealing technology for completing the one end of tank material 3.Rainwater in infiltration system will flow along the bottom of tank material 3
Into perps, the possibility of seepage is added.Common processing method be this position inject by scene it is substantial amounts of close
The problem of sealing is to overcome the change because of sequence of construction to bring.According to experience for many years and to maintenance of works information response, occur
It is more in the situation of the part leakage, and repair extremely difficult.
Tank material 3 in cell curtain wall is to carry out a pinpoint component to the cell curtain wall plate of left and right, is added simultaneously
Gu the rigidity of crossbeam notch, the most important cell curtain wall plate that blocked is in a square hole caused by splicing.Pass through tank
Expect that the injecting glue at 3 both ends seals the vertical socket position that the rainwater blocked in infiltration system flows to cell curtain wall plate 4, tank material 3
It is the composition component of crucial importance of cell curtain wall.It is to ensure cell curtain wall watertightness performance, the indispensable component of air-tightness.Cause
This, it is correct that the important in inhibiting of tank material 3 is installed.
When extraordinary change occurs for sequence of construction, then need to carry out one in the case where tank material 3 is fitted without and finished
The installation of plate.Rear tank material can not just meet its technological requirement to a plate in place in completion, therefore we use tank material
The technology of decomposition, tank material 3 is decomposed into two parts to realize complete tank material function.Tank material point in this programme
For the first tank material 31 and the second tank material 32, tank material 3 can slide into specified location in mounting groove.
When the position of no mounting process requirement of completion tank material 3, its top can not installation unit curtain wall panel 4.If run into
Before reserved opening is, it is necessary to install a plate, it is necessary to the peace of the first tank material 31 is carried out by the split construction technical requirement of tank material 3
Dress, as shown in Figure 8.If the second tank material 32 is moved on into position shown in Fig. 9 after repairing reserved opening jigsaw completes injection process i.e.
Can.Only complete just install a cell curtain wall plate after requiring shown in Fig. 9.
Embodiment of the present utility model is the foregoing is only, not thereby limits the scope of the claims of the present utility model, it is every
The equivalent structure or equivalent flow conversion made using the utility model description, or directly or indirectly it is used in other phases
The technical field of pass, similarly it is included in scope of patent protection of the present utility model.
Claims (5)
- A kind of 1. Split sink constructing structure on unit type energy-saving curtain wall, it is characterised in that:Including crossbeam unit, column list Member, tank material and cell curtain wall plate;More crossbeam units dock to form whole crossbeam successively, and more root post units dock shape successively Into whole root post;On the framework surface that whole crossbeam docks with whole root post with suspension member come fixed cell curtain wall plate;It is described The mounting groove for installing the tank material is equipped with crossbeam unit;The tank material is installed on adjacent two crossbeam units Joint;The tank material is divided into the first tank material and the second tank material;The tank material slides into specific bit in mounting groove Put, and fixation is packaged by fluid sealant.
- 2. the Split sink constructing structure on a kind of unit type energy-saving curtain wall according to claim 1, it is characterised in that: The crossbeam unit includes female crossbeam unit and male crossbeam unit;Female crossbeam unit is docked with male crossbeam unit matched moulds;The mother Crossbeam unit is provided with buckling groove, and prominent crossbeam latch is provided with buckling groove;It is provided with public crossbeam unit and is matched with card Crossbeam installation portion in access slot;The horizontal socket coordinated with crossbeam latch is provided with crossbeam installation portion;The public crossbeam unit With forming a mounting groove for being used to install the tank material after female crossbeam unit matched moulds.
- 3. the Split sink constructing structure on a kind of unit type energy-saving curtain wall according to claim 2, it is characterised in that: Glue is filled with buckling groove in female crossbeam unit, and glue is filled between crossbeam installation portion and buckling groove;In water Glue is also filled between groove material and mounting groove.
- 4. the Split sink construction knot on a kind of unit type energy-saving curtain wall as claimed in any of claims 1 to 3 Structure, it is characterised in that:The column unit includes public pole unit and female column unit;Female column unit is provided with column Latch;The longitudinal socket coordinated with the column latch is then provided with the public pole unit.
- 5. the Split sink constructing structure on a kind of unit type energy-saving curtain wall according to claim 4, it is characterised in that: Hanging device is connected with by fastener on the column unit;The hanging device is connected on the built-in fitting on wall.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201621318763.1U CN207017505U (en) | 2016-12-02 | 2016-12-02 | A kind of Split sink constructing structure on unit type energy-saving curtain wall |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201621318763.1U CN207017505U (en) | 2016-12-02 | 2016-12-02 | A kind of Split sink constructing structure on unit type energy-saving curtain wall |
Publications (1)
Publication Number | Publication Date |
---|---|
CN207017505U true CN207017505U (en) | 2018-02-16 |
Family
ID=61460399
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201621318763.1U Active CN207017505U (en) | 2016-12-02 | 2016-12-02 | A kind of Split sink constructing structure on unit type energy-saving curtain wall |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN207017505U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106760086A (en) * | 2016-12-02 | 2017-05-31 | 苏州金螳螂幕墙有限公司 | A kind of Split sink construction technology on unit type energy-saving curtain wall |
-
2016
- 2016-12-02 CN CN201621318763.1U patent/CN207017505U/en active Active
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106760086A (en) * | 2016-12-02 | 2017-05-31 | 苏州金螳螂幕墙有限公司 | A kind of Split sink construction technology on unit type energy-saving curtain wall |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN207017505U (en) | A kind of Split sink constructing structure on unit type energy-saving curtain wall | |
US20200308798A1 (en) | Modular Building for Civil Use | |
CN204199499U (en) | A kind of hyperboloid type unitized curtain wall system | |
CN203514793U (en) | Equipment reserved formwork | |
CN102587665B (en) | Pouring method of coupled shear wall structure | |
CN106760086A (en) | A kind of Split sink construction technology on unit type energy-saving curtain wall | |
CN216230006U (en) | Wear-resisting formula coincide board mould | |
CN203808316U (en) | Structure of concave-convex glass curtain wall | |
CN204152280U (en) | The water leak preventing structure of pin-connected panel collecting-tank | |
CN105672496A (en) | CLT (Cross Laminated Timber) wall-board connecting structure and connecting method thereof | |
CN203412143U (en) | Wall body structure of integrally poured building house | |
CN102041856A (en) | Unit curtain wall system with cantilevered glass flank and opening window | |
CN203791687U (en) | Positioning tool set for horizontal adjustable hinge base drill hole | |
CN105844016B (en) | A method of the proposed building quantity of acquisition based on buildings model cutting | |
CN204476179U (en) | Auxiliary frame construction and installation fixture | |
CN207402949U (en) | A kind of prefabricated panel for concrete prefabricated element production line positions hole tool | |
CN201962980U (en) | Integrated anti-theft communication room | |
Sun | The Common Quality Problems and Preventive Measures of Prefabricated Building Construction | |
CN216465254U (en) | Inner die for steel door and window opening of assembled concrete wall | |
CN205935312U (en) | Panel house wall's reinforced concrete frame structure | |
CN214671504U (en) | Safety management device for construction engineering site construction | |
CN203701382U (en) | Unit type and component type combined curtain wall system | |
CN203977908U (en) | A kind of fast assembling operating room | |
CN210857632U (en) | High-performance unit curtain wall | |
CN204252608U (en) | Assembling movable pond |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |