- CN207006558U CN207006558U CN201720531490.7U CN201720531490U CN207006558U CN 207006558 U CN207006558 U CN 207006558U CN 201720531490 U CN201720531490 U CN 201720531490U CN 207006558 U CN207006558 U CN 207006558U
- Authority
- CN
- China
- Prior art keywords
- high frequency
- heat pump
- water
- frequency heat
- cold water
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Heat-Pump Type And Storage Water Heaters (AREA)
Abstract
It the utility model is related to a kind of second hot type high frequency heat pump superheated vapor dual purpose unit system, including cold water storage cistern, boiler, master controller, Cold water tap, hot-water valve, water pump, y-type filter, high frequency heat pump assembly, safety valve, hot water temperature's table, Water flow adjusting valve, threeway testing valve of water, cold water inlet pipe and hot water out pipe;The both ends of the cold water inlet pipe are respectively arranged with cold water storage cistern and the high frequency heat pump assembly, and the Cold water tap, water pump and y-type filter are set in turn on the cold water inlet pipe respectively;The utility model is simple in construction, ingenious in design, and this second hot type D type high frequency heat pump superheated vapor dual purpose unit system application is extended to southern and northern each field, can heat, for boiling water, it is reliable, easy to use for steam, this product electricity separation, performance safety.
Description
Technical field
It the utility model is related to the technical field of heat-pump apparatus, and in particular to a kind of second hot type high frequency heat pump superheated vapor two
Use machine set system.
Background technology
Coal and oil gas fired-boiler currently on the market, it is both high energy consumption high pollution and discharges carbon dioxide, sulfur dioxide,
Very big pollution is caused to environment and is not saved.And very big potential safety hazard be present, explosive inflammable easily poisoning and generation fire.And
Cause a principal element of haze.Second hot type D type high frequency heat pump superheated vapor dual purpose unit systems, it is the combustion of high pollution high energy consumption
The substitute products of coal oil-burning gas-fired boiler.
Utility model content
The purpose of this utility model is to be directed to weak point of the prior art, proposes that a kind of second hot type high frequency heat pump is high
Warm water vapour dual purpose unit system.
To use following technical scheme up to this purpose, the utility model:
A kind of second hot type high frequency heat pump superheated vapor dual purpose unit system, including it is cold water storage cistern, boiler, master controller, cold
Penstock, hot-water valve, water pump, y-type filter, high frequency heat pump assembly, safety valve, hot water temperature's table, Water flow adjusting valve, three
Logical testing valve of water, cold water inlet pipe and hot water out pipe;The both ends of the cold water inlet pipe are respectively arranged with cold water storage cistern and the high frequency heat pump
Device, the Cold water tap, water pump and y-type filter are set in turn on the cold water inlet pipe respectively;The high frequency heat pump dress
Put and pump out the mouth of a river, high frequency heat pump water inlet mouth, high frequency heat pump heat generating member and high frequency heat pump body, the high frequency heat pump including high frequency heat
Delivery port and high frequency heat pump water inlet mouth are respectively arranged on the high frequency heat pump body, and the high frequency heat pump heat generating member is arranged at institute
State in high frequency heat pump body;The cold water inlet pipe is connected to the high frequency heat pump water inlet mouth, one end connection of the hot water out pipe
In the boiler, the other end is connected to the high frequency heat and pumps out the mouth of a river;The hot water temperature sensor, safety valve, hot water temperature
Degree table, Water flow adjusting valve, threeway testing valve of water and hot-water valve are set in turn on the hot water out pipe respectively;The main control
Device is run by high frequency heat pump assembly described in high frequency heat pump heat generating member power supply line traffic control.
A more progressive ground, the cold water storage cistern include cold water storage cistern water level observation device, cold water storage cistern ball-cock assembly, cooling water inlet, cold water
Temperature sensor and cold water storage cistern sewage draining exit, cooling water inlet and the cold water storage cistern sewage draining exit are respectively arranged at the one of the cold water storage cistern
Side, cold water storage cistern water level observation device, cold water temperature sensor and the cold water storage cistern ball-cock assembly are respectively arranged in the cold water storage cistern.
A more progressive ground, it is blind that the boiler includes hot water and steam case safety valve, hotwell level's viewer, boiler
Pipe, boiler sewage draining exit, user hot water mouth, hot water outlet and boiler ball-cock assembly, the hot water and steam case safety valve, boiler
Sewage draining exit, hot water outlet and user hot water mouth are respectively arranged in the side wall of the boiler, the boiler blind pipe and hot water
Case ball-cock assembly is respectively arranged in the boiler.
A more progressive ground, the master controller include high frequency upconverter and relay, and the relay passes through the high frequency
Heat pump heat generating member power line is connected with the high frequency heat pump heat generating member.
A more progressive ground, water pipe is additionally provided with, the quantity that the high frequency heat pump assembly is set is several, two-by-two the height
Frequency heat pump assembly is connected by the water pipe.
The beneficial effects of the utility model:1. the utility model is simple in construction, ingenious in design, this second hot type D type high frequency heat
Pump superheated vapor dual purpose unit system application is extended to southern and northern each field, can heat, for boiling water, for steam, this production
Product electricity separation, not scaling, performance safety are reliable, easy to use.
Brief description of the drawings
The utility model is further illustrated with reference to the accompanying drawings and examples.
Fig. 1 is the overall structure of second hot type D types high frequency heat pump superheated vapor dual purpose unit system provided by the utility model
Schematic diagram.
Wherein:High frequency heat pump heat generating member 1, high frequency heat pump assembly 2, safety valve 3, high frequency upconverter 4, relay 5, high frequency heat
Pump water inlet mouth 6, high frequency heat pump heat generating member power line 7, y-type filter 8, water pump 9, Cold water tap 10, cold water storage cistern 11, cold water temperature
Sensor 12, cold water storage cistern sewage draining exit 13, hot water outlet 14, hot water temperature's table 15, hot water temperature sensor 16, Water flow adjusting valve
17th, high frequency heat pumps out the mouth of a river 18, water pipe 19, boiler ball-cock assembly 20, user hot water mouth 21, hot water and steam case safety valve 22, heat
Cistern water level viewer 23, boiler blind pipe 24, boiler sewage draining exit 25, cold water storage cistern ball-cock assembly 26, cooling water inlet 27, boiler
28th, hot water out pipe 29, cold water inlet pipe 30, master controller 31, threeway testing valve of water 32, hot-water valve 33, cold water storage cistern water level observation device
34。
Embodiment
Further illustrate the technical solution of the utility model below in conjunction with the accompanying drawings and by embodiment.
A kind of second hot type high frequency heat pump superheated vapor dual purpose unit system, as shown in figure 1, including cold water storage cistern 11, boiler
28th, master controller 31, Cold water tap 10, hot-water valve 33, water pump 9, y-type filter 8, high frequency heat pump assembly 2, safety valve 3, heat
Coolant-temperature gage table 15, Water flow adjusting valve 17, threeway testing valve of water 32, cold water inlet pipe 30 and hot water out pipe 29;The cold water inlet pipe 30
Both ends be respectively arranged with the cold water storage cistern 11 and high frequency heat pump assembly 2, the Cold water tap 10, water pump 9 and y-type filter 8
It is set in turn in respectively on the cold water inlet pipe 30;The high frequency heat pump assembly 2 pumps out the mouth of a river 18, high frequency heat pump including high frequency heat
Water inlet 6, high frequency heat pump heat generating member 1 and high frequency heat pump body, the high frequency heat pumps out the mouth of a river 18 and high frequency heat pump water inlet mouth 6 divides
It is not arranged on the high frequency heat pump body, the high frequency heat pump heat generating member 1 is arranged in the high frequency heat pump body;It is described cold
Water inlet pipe 30 is connected to the high frequency heat pump water inlet mouth 6, and one end of the hot water out pipe 29 is connected to the boiler 28, another
End is connected to the high frequency heat and pumps out the mouth of a river 18;The hot water temperature sensor 16, safety valve 3, hot water temperature's table 15, water-carrying capacity
Regulating valve 17, threeway testing valve of water 32 and hot-water valve 33 are set in turn on the hot water out pipe 29 respectively;The master controller
31 control the high frequency heat pump assembly 2 to be run by high frequency heat pump heat generating member power line 7.
The high frequency heat pump heat generating member 1 is installed in several heat source bodies of high frequency heat pump heating intracavitary and by high frequency heat pump
Heat generating member power line 7 is connected with relay 5, high frequency upconverter 4, and the high frequency heat pump heating chamber loads high frequency heat pump heat generating member
1 and water and to have high frequency heat pump water inlet mouth 6, high frequency heat to pump out several containers at the mouth of a river 18 and these containers be all that high frequency heat pump enters
The mouth of a river 6, high frequency heat pump out the head and the tail of the mouth of a river 18 and are connected in series, and the safety valve 3, which is fixed on hot water out pipe 29, prevents super-pressure
Pressure release leakage device, the high frequency upconverter 4 are to control the elevated electronic building brick of frequency of high frequency heat pump heat generating member 1, the relay
Device 5 is the electronic component for controlling the on or off of high frequency heat pump heat generating member 1, and the high frequency heat pump water inlet mouth 6 is integrally fixed at high frequency heat pump
The heating chamber right side or left part and offer water enter the port of high frequency heat pump heating intracavitary, the high frequency heat pump heat generating member power line 7
It is the connecting line that high frequency heat pump heat generating member 1 is powered, the y-type filter 8 is integrally fixed on cold water inlet pipe 30 and water is filtered
The device of impurity, the water pump 9 are integrally fixed on cold water inlet pipe 30 and the special-purpose member of water filling are carried out to high frequency heat pump heating chamber,
Valve is integrally fixed at hot water out pipe 29, on cold water inlet pipe 30 and control water by or the switch element that does not pass through, the cold water storage cistern
Ball-cock assembly 26 is integrally fixed at the top correct position control of cold water storage cistern 11 plus water to the element of certain position, and the boiler 28 is dress
The insulation hot water tank for the hot water being heated, the hot water out pipe 29 are dual-purpose by second hot type D type high frequency heat pump superheated vapor
Machine set system heating water heel row removes the siphunculus of hot water, and the threeway testing valve of water 32 is high for excluding second hot type D type high frequencies heat pump
Gas and water temperature in warm water vapour dual purpose unit system exclude the part outside boiler 28 when being not reaching to set water temperature.
The utility model is simple in construction, ingenious in design, and hot type D type high frequency heat pump superheated vapor dual purpose units system should within this second
Be extended to southern and northern each field with scope, can heat, for boiling water, for steam, this product electricity separation, not scaling, performance
Securely and reliably, it is easy to use.
The operation principle of the present invention:Cold water storage cistern 11 is filled into cold water first, boiler 28 is empty water tank, opens master controller
31, under the operating effect of water pump 9, cold water is from cold water storage cistern 11 by Cold water tap 10, water pump 9, y-type filter 8, high frequency heat
Pump water inlet mouth 6 is injected and filled to several high frequency heat pumps heating intracavitary, at this moment electricity heating on high frequency heat pump heat generating member 1 step by step
Frequency reaches setpoint frequency by the gradual raising frequency of setpoint frequency, and experiment proves:The temperature during raising frequency of high frequency heat pump heat generating member 1 is fast
Speed rises to 2000 DEG C ± 100 DEG C, then is gone directly threeway testing valve of water by safety valve 3, hot water temperature's table 15, Water flow adjusting valve 17
32, the bypass pipe at this moment opening threeway testing valve of water 32 is exhausted and excluded the water for not reaching set water temperature, setting water to be achieved
The bypass pipe of three way type water valve 32, which is closed main line and opened, when warm is up to the water of set water temperature and discharges into boiler 28, makes whole
Hot water in individual boiler 28 is entirely the hot water by set water temperature injection.
A more progressive ground, the cold water storage cistern 11 include cold water storage cistern water level observation device 34, cold water storage cistern ball-cock assembly 26, cooling water inlet
27th, cold water temperature sensor 12 and cold water storage cistern sewage draining exit 13, the cooling water inlet 27 and cold water storage cistern sewage draining exit 13 are respectively arranged at
The side of the cold water storage cistern 11, cold water storage cistern water level observation device 34, cold water temperature sensor 12 and the cold water storage cistern ball-cock assembly 26 divide
It is not arranged in the cold water storage cistern 11.
The cold water storage cistern 11 be to high frequency heat pump heating chamber provide water source container filled with water, the cold water temperature sensor 12
The electronic component of cold water temperature is detected, the cold water storage cistern sewage draining exit 13 excludes the port of dirt in cold water storage cistern 11, and the cold water enters
Mouthfuls 27 be one end connection cold water storage cistern ball-cock assembly 26 and port that the other end is connected with water supply, and the cold water inlet pipe 30 is that the second is hot
The siphunculus that formula D type high frequency heat pump superheated vapor dual purpose unit systems are fetched water from cold water storage cistern 11.
A more progressive ground, the boiler 28 include hot water and steam case safety valve 22, hotwell level's viewer 23, hot water
Case blind pipe 24, boiler sewage draining exit 25, user hot water mouth 21, hot water outlet 14 and boiler ball-cock assembly 20, the hot water and steam
Case safety valve 22, boiler sewage draining exit 25, hot water outlet 14 and user hot water mouth 21 are respectively arranged at the side of the boiler 28
On wall, the boiler blind pipe 24 and boiler ball-cock assembly 20 are respectively arranged in the boiler 28.
The hot water outlet 14 is that the water after second hot type D type high frequency heat pump superheated vapor dual purpose unit systems heat water goes out
Mouthful, hot water temperature's table 15 is integrally fixed on hot water out pipe 29 and shows the component of leaving water temperature, and the hot water temperature passes
Sensor 16 is integrally fixed on hot water out pipe 29 and with the line and the electronic component of master control borad connecting detection water temperature of extraordinary resistance, described
Water flow adjusting valve 17 is integrally fixed on hot water out pipe 29 and can adjust the part of hot water flow size, and the high frequency heat pumps out
The mouth of a river 18 is integrally fixed at the port that high frequency heat pump heating top of chamber is gone out for heated water, and the boiler ball-cock assembly 20 is control
Heat water tank 28 plus water or stop the element for adding water, the user hot water mouth 21 is delivery port when user uses hot water, described
Hot water and steam case safety valve 22 is to be scheduled on 3, the safety valve that the top of boiler 28 is used for casing over-pressure over-temperature, the boiler water
Position viewer 23 is with being connected inside the correct position of boiler 28 and holding up transparent pipe fitting and considerable along the parallel vertical of boiler 28
The pipe fitting of the position of the water surface in transparent pipe is examined, the boiler blind pipe 24 is the pipe fitting of one end closing of temperature sensor, described
Boiler sewage draining exit 25 is the supply and discharge opened in the bottom of boiler 28 except the mouth of dirt inside water tank.
A more progressive ground, the master controller 31 include high frequency upconverter 4 and relay 5, and the relay 5 is by described
High frequency heat pump heat generating member power line 7 is connected with the high frequency heat pump heat generating member 1.The master control borad of the master controller 31 is control
During second hot type D types high frequency heat pump superheated vapor dual purpose unit system operation and bolt down procedure and the master control electronics of arrange parameter
Integrated package.
A more progressive ground, water pipe 19 is additionally provided with, the quantity that the high frequency heat pump assembly 2 is set is several, two-by-two institute
High frequency heat pump assembly 2 is stated by the water pipe 19 to be connected.The water pipe 19 is high frequency heat pump on connection high frequency heat pump heating chamber
Water inlet 6 and high frequency heat pump out the pipeline of the Inlet and outlet water of the mouth of a river 18.
Second hot type high frequency heat pump superheated vapor dual purpose unit system is the aggregate of multipole heating generator assembly, is made every
The water temperature of one pole all continues to rise on the basis of the water temperature of a rising, and experiment proves:During 20 DEG C of basic water temperature, the temperature of preceding 1 pole
Difference is all at 40 DEG C, and at 30 DEG C, the temperature difference of rear 1 pole reaches 100 DEG C of setting values at 10 DEG C or is being heated to 120 the temperature difference of middle 1 pole
DEG C steam setting value.Applicator part is added, the thermal efficiency is higher, environmental protection and energy saving significant effect;Experiment proves:Applicator part
The heat discharged during raising frequency is higher than 1.5 times ± 0.2 of the warmware that takes place frequently surely;Threeway testing valve of water is installed additional, has made boiler
Interior hot water is filled by the value of setting and without falseness;Firing rate is exceedingly fast, and is risen with the second no longer with hour or minute but to calculate
Warm speed;Applicator part water power is completely separated;Applicator part never scaling;It is simple in construction, it is not required to after sale.
Technical principle of the present utility model is described above in association with specific embodiment.These descriptions are intended merely to explain this reality
With new principle, and the limitation to scope of protection of the utility model can not be construed in any way.Based on explanation herein,
Those skilled in the art, which would not require any inventive effort, can associate other embodiments of the present utility model,
These modes are fallen within the scope of protection of the utility model.
Claims (5)
- A kind of 1. second hot type high frequency heat pump superheated vapor dual purpose unit system, it is characterised in that:Including cold water storage cistern, boiler, master Controller, Cold water tap, hot-water valve, water pump, y-type filter, high frequency heat pump assembly, safety valve, hot water temperature's table, water-carrying capacity Regulating valve, threeway testing valve of water, cold water inlet pipe and hot water out pipe;The both ends of the cold water inlet pipe be respectively arranged with the cold water storage cistern and High frequency heat pump assembly, the Cold water tap, water pump and y-type filter are set in turn on the cold water inlet pipe respectively;The height Frequency heat pump assembly pumps out the mouth of a river, high frequency heat pump water inlet mouth, high frequency heat pump heat generating member and high frequency heat pump body including high frequency heat, described High frequency heat pumps out the mouth of a river and high frequency heat pump water inlet mouth is respectively arranged on the high frequency heat pump body, the high frequency heat pump heat generating member It is arranged in the high frequency heat pump body;The cold water inlet pipe is connected to the high frequency heat pump water inlet mouth, the hot water out pipe One end is connected to the boiler, and the other end is connected to the high frequency heat and pumps out the mouth of a river;The hot water temperature sensor, safety Valve, hot water temperature's table, Water flow adjusting valve, threeway testing valve of water and hot-water valve are set in turn on the hot water out pipe respectively; The master controller is run by high frequency heat pump assembly described in high frequency heat pump heat generating member power supply line traffic control.
- 2. according to claim 1 second hot type high frequency heat pump superheated vapor dual purpose unit system, it is characterised in that:It is described cold Water tank includes cold water storage cistern water level observation device, cold water storage cistern ball-cock assembly, cooling water inlet, cold water temperature sensor and cold water storage cistern sewage draining exit, Cooling water inlet and the cold water storage cistern sewage draining exit is respectively arranged at the side of the cold water storage cistern, the cold water storage cistern water level observation device, cold Water temperature sensor and cold water storage cistern ball-cock assembly are respectively arranged in the cold water storage cistern.
- 3. according to claim 1 second hot type high frequency heat pump superheated vapor dual purpose unit system, it is characterised in that:The heat Water tank include hot water and steam case safety valve, hotwell level's viewer, boiler blind pipe, boiler sewage draining exit, user hot water mouth, Hot water outlet and boiler ball-cock assembly, hot water and steam case safety valve, boiler sewage draining exit, hot water outlet and the user hot water mouth It is respectively arranged in the side wall of the boiler, the boiler blind pipe and boiler ball-cock assembly are respectively arranged at the boiler It is interior.
- 4. according to claim 1 second hot type high frequency heat pump superheated vapor dual purpose unit system, it is characterised in that:The master Controller includes high frequency upconverter and relay, and the relay passes through the high frequency heat pump heat generating member power line and the high frequency Heat pump heat generating member is connected.
- 5. according to claim 1 second hot type high frequency heat pump superheated vapor dual purpose unit system, it is characterised in that:Also set up There is water pipe, the quantity that the high frequency heat pump assembly is set is several, and the high frequency heat pump assembly passes through the water pipe phase two-by-two Connection.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201720531490.7U CN207006558U (en) | 2017-05-16 | 2017-05-16 | A kind of second hot type high frequency heat pump superheated vapor dual purpose unit system |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201720531490.7U CN207006558U (en) | 2017-05-16 | 2017-05-16 | A kind of second hot type high frequency heat pump superheated vapor dual purpose unit system |
Publications (1)
Publication Number | Publication Date |
---|---|
CN207006558U true CN207006558U (en) | 2018-02-13 |
Family
ID=61443059
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201720531490.7U Expired - Fee Related CN207006558U (en) | 2017-05-16 | 2017-05-16 | A kind of second hot type high frequency heat pump superheated vapor dual purpose unit system |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN207006558U (en) |
-
2017
- 2017-05-16 CN CN201720531490.7U patent/CN207006558U/en not_active Expired - Fee Related
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106927525A (en) | Heating tank and water purifier | |
KR101160795B1 (en) | Water heater with automatic controller | |
CN102538186B (en) | Multi-functional electric hot water boiler | |
CN104728822A (en) | Steam generation device with electromagnetic heating function | |
CN206257640U (en) | A kind of Full-automatic electrical heating steam generator | |
CN204494356U (en) | A kind of electromagnetic heating steam generating means | |
CN202470385U (en) | Instant-heating boiler | |
CN203549770U (en) | Temperature-detector-controlling and automatic-water-adding steam generating device | |
TWI526658B (en) | Storage water heater with instant hot water supply and control method thereof | |
CN207006558U (en) | A kind of second hot type high frequency heat pump superheated vapor dual purpose unit system | |
CN104807171A (en) | Gas-electric combined type water heater | |
CN104873102A (en) | Drinking water system with automatic water adding function and safety control method thereof | |
CN106979616A (en) | A kind of second hot type high frequency heat pump superheated vapor dual purpose unit system | |
CN203857448U (en) | Steam generator | |
CN203489464U (en) | Integrated water-storage gas water heater system | |
CN104180530A (en) | Pressure-bearing hot-water boiler system | |
CN201289151Y (en) | Hot water heating apparatus by utilizing solar | |
CN103411300B (en) | A kind of tandem type multi-stage heats Vertical Heat hydrophone | |
CN203704321U (en) | Gas water boiler with self-circulation function | |
CN207751171U (en) | Hot water boiling water steam all-in-one machine | |
CN207365170U (en) | Rural Families coal and electricity dual-purpose energy-saving micro safety normal-pressure hot water heating boiler | |
CN202485202U (en) | Multifunctional electric water boiler | |
CN206729732U (en) | A kind of duct type intelligence steam engine | |
CN206656492U (en) | Stepping water boiler | |
CN202915322U (en) | Steam generator |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |