CN207003150U - A kind of High Speed Railway Subgrade by karst sinkhole - Google Patents
A kind of High Speed Railway Subgrade by karst sinkhole Download PDFInfo
- Publication number
- CN207003150U CN207003150U CN201720672286.7U CN201720672286U CN207003150U CN 207003150 U CN207003150 U CN 207003150U CN 201720672286 U CN201720672286 U CN 201720672286U CN 207003150 U CN207003150 U CN 207003150U
- Authority
- CN
- China
- Prior art keywords
- sinkhole
- karst
- speed railway
- high speed
- railway subgrade
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 230000003014 reinforcing effect Effects 0.000 claims abstract description 8
- 239000011435 rock Substances 0.000 claims description 5
- 238000005056 compaction Methods 0.000 claims description 2
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 claims 1
- 238000010276 construction Methods 0.000 abstract description 5
- 239000002352 surface water Substances 0.000 abstract description 5
- XEEYBQQBJWHFJM-UHFFFAOYSA-N Iron Chemical compound [Fe] XEEYBQQBJWHFJM-UHFFFAOYSA-N 0.000 description 2
- 230000009286 beneficial effect Effects 0.000 description 2
- 238000010586 diagram Methods 0.000 description 2
- 238000006424 Flood reaction Methods 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 230000029142 excretion Effects 0.000 description 1
- 229910052742 iron Inorganic materials 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 239000002689 soil Substances 0.000 description 1
- 230000006641 stabilisation Effects 0.000 description 1
- 238000011105 stabilization Methods 0.000 description 1
Landscapes
- Railway Tracks (AREA)
Abstract
A kind of High Speed Railway Subgrade by karst sinkhole, can effectively discharge surface water, sinkhole is not blocked, meets the requirement of high-speed railway subgrade, and it is easy for construction.It includes:Rotary churning pile, it is arranged in the earthen foundation on sinkhole periphery, forms occlusion and enclose curtain structure;Reinforcing pile, it is arranged in the earthen foundation outside sinkhole scope;Drainage frame, is arranged at the top of the ground of sinkhole coverage, and roadbed filling body is filled at the top of drainage frame.
Description
Technical field
Geotechnical Engineering is the utility model is related to, more particularly to passes through the high-speed railway subgrade engineering of karst sinkhole.
Background technology
Sinkhole is the common surface water drain passage in karst landform area, and normal conditions are unable to silting, otherwise can influenceed
The excretion of surface water, or even produce floods.When railway can only in the form of roadbed by when, how to accomplish not block sinkhole, again
The requirement of high-speed railway subgrade can be met, just seem increasingly important.It is therefore proposed that a kind of high-speed railway by karst sinkhole
Road structure is significant.
Utility model content
Technical problem to be solved in the utility model is to provide a kind of high-speed railway subgrade knot by karst sinkhole
Structure, can effectively discharge surface water, sinkhole is not blocked, meets the requirement of high-speed railway subgrade, and it is easy for construction.
Technical scheme is as follows used by the utility model solves above technical problem:
A kind of High Speed Railway Subgrade by karst sinkhole of the present utility model, it is characterized in that it includes:Churning
Stake, is arranged in the earthen foundation on sinkhole periphery, forms occlusion and encloses curtain structure;Reinforcing pile, it is arranged on outside sinkhole scope
Earthen foundation in;Drainage frame, is arranged at the top of the ground of sinkhole coverage, and roadbed filling body is filled in drainage frame
Top.
The beneficial effects of the utility model are that solve sinkhole draining and roadbed filling meets the difficulty of high-speed railway requirement
Topic, and have the characteristics that easy for construction, economical and environmentally friendly, there is popularizing application prospect.
Brief description of the drawings
This specification includes following three width accompanying drawing:
Fig. 1 is a kind of sectional schematic diagram of High Speed Railway Subgrade by karst sinkhole of the utility model.
Fig. 2 is a kind of floor map of High Speed Railway Subgrade by karst sinkhole of the utility model.
Fig. 3 is a kind of drainage frame front signal of High Speed Railway Subgrade by karst sinkhole of the utility model
Figure.
Component name and corresponding mark are shown in figure:Rotary churning pile 1, reinforcing pile 2, drainage frame 3, bottom plate 31, side wall
32nd, top plate 33, osculum 34, roadbed filling body 4, sinkhole A, earthen foundation B, rock quality base C.
Embodiment
The utility model is further illustrated with reference to the accompanying drawings and examples:
Reference picture 1, Fig. 2, a kind of High Speed Railway Subgrade by karst sinkhole of the present utility model include:Churning
Stake 1, is arranged in the earthen foundation B on sinkhole A peripheries, forms occlusion and encloses curtain structure;Reinforcing pile 2, it is arranged on sinkhole A scopes
Outside earthen foundation B in;Drainage frame 3, is arranged at the top of the ground of sinkhole A coverages, and roadbed filling body 4 fills
The top of drainage frame 3.
Occlusion is formed in the earthen foundation B on sinkhole A peripheries with rotary churning pile 1 and enclose curtain, avoid sinkhole A bands in draining
The soil property around hole is walked, so as to ensure the stability of earthen foundation.The reinforcing pile 2 being arranged in earthen foundation B solves high-speed iron
The problem of road settlement of foundation, and higher bearing capacity is provided for drainage frame 3, increase the stability of drainage frame 3.With draining frame
Drainage channel of the frame 3 as surface water and sinkhole A, ensures the stabilization of roadbed, and as the bearing structure of roadbed filling body 4,
Bearing structure of the roadbed filling body 4 as train load.The beneficial effect of the structure is that solve sinkhole draining and roadbed is filled out
The problem for meeting high-speed railway requirement is built, and has the characteristics that easy for construction, economical and environmentally friendly, there is popularizing application prospect.
Reference picture 1, rotary churning pile 1 a diameter of 0.8m, the spacing 0.6m, processing depth to rock quality base C bedrock surfaces.It is described
Reinforcing pile 2 is using CFG (CFG stakes) or compaction thread etc., and stake spacing is usually 1.5-1.8m, and processing is deep
Spend to rock quality base C bedrock surfaces.
Reference picture 3, the drainage frame 3 are poured using armored concrete, and it is pre- in the position of bottom plate 31 corresponding to sinkhole A
Osculum 34 is stayed, width is set not less than twice of sinkhole A diameters.The size of osculum 34 is not less than chi of the sinkhole on ground
It is very little.
The utility model a kind of High Speed Railway Subgrade by karst sinkhole described above that simply explains through diagrams
Some principles, be not intended to by the utility model be confined to shown in and described concrete structure and the construction method scope of application
It is interior, therefore every corresponding modification for being possible to be utilized and equivalent, belong to the apllied the scope of the claims of the utility model.
Claims (5)
- A kind of 1. High Speed Railway Subgrade by karst sinkhole, it is characterized in that it includes:Rotary churning pile (1), is arranged on In the earthen foundation (B) on water hole (A) periphery, form occlusion and enclose curtain structure;Reinforcing pile (2), it is arranged on outside sinkhole (A) scope Earthen foundation (B) in;Drainage frame (3), is arranged at the top of the ground of sinkhole (A) coverage, and roadbed filling body (4) is filled out Build at the top of drainage frame (3).
- 2. a kind of High Speed Railway Subgrade by karst sinkhole as claimed in claim 1, it is characterized in that:The churning Stake (1) a diameter of 0.8m, spacing 0.6m, processing depth to rock quality base (C) bedrock surface.
- 3. a kind of High Speed Railway Subgrade by karst sinkhole as claimed in claim 1, it is characterized in that:The reinforcing Stake (2) is using CFG or compaction thread etc., and stake spacing is 1.5-1.8m, processing depth to rock quality base (C) bedrock surface.
- 4. a kind of High Speed Railway Subgrade by karst sinkhole as claimed in claim 1, it is characterized in that:The draining Framework (3) is poured using armored concrete, and it reserves osculum (34) in bottom plate (31) position corresponding to sinkhole (A), is set Width is not less than twice of sinkhole (A) diameter.
- 5. a kind of High Speed Railway Subgrade by karst sinkhole as claimed in claim 4, it is characterized in that:The draining Hole (34) size is not less than size of the sinkhole on ground.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201720672286.7U CN207003150U (en) | 2017-06-10 | 2017-06-10 | A kind of High Speed Railway Subgrade by karst sinkhole |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201720672286.7U CN207003150U (en) | 2017-06-10 | 2017-06-10 | A kind of High Speed Railway Subgrade by karst sinkhole |
Publications (1)
Publication Number | Publication Date |
---|---|
CN207003150U true CN207003150U (en) | 2018-02-13 |
Family
ID=61446380
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201720672286.7U Expired - Fee Related CN207003150U (en) | 2017-06-10 | 2017-06-10 | A kind of High Speed Railway Subgrade by karst sinkhole |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN207003150U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111424685A (en) * | 2020-04-14 | 2020-07-17 | 中国电建集团贵阳勘测设计研究院有限公司 | Deep water falling hole processing structure and method for backfilling foundation in large karst depression |
-
2017
- 2017-06-10 CN CN201720672286.7U patent/CN207003150U/en not_active Expired - Fee Related
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111424685A (en) * | 2020-04-14 | 2020-07-17 | 中国电建集团贵阳勘测设计研究院有限公司 | Deep water falling hole processing structure and method for backfilling foundation in large karst depression |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103758113B (en) | A kind of grid encloses the anti-liquefied foundation reinforcement means of hoop | |
CN207672558U (en) | A kind of railroad embankment Pile slab-wall structure | |
CN105064288B (en) | The mixing structure of dam type and construction method of a kind of concrete dam and earth and rockfill dam | |
CN103410210A (en) | Water-absorbing fiber percolation pipe and dewatering device | |
CN102926328B (en) | Bridge waterside foundation pit excavation and support method and support wall structure | |
CN104480956B (en) | A kind of minor diameter mold-bagged concrete pile composite foundation | |
CN205591066U (en) | Fine grained soil is received sloping embankment and is filled structure | |
CN207944450U (en) | soft foundation reinforcing structure | |
CN207003150U (en) | A kind of High Speed Railway Subgrade by karst sinkhole | |
CN204551510U (en) | A kind of filled-up ground catchments pressure reduction well drop and drainage structure | |
CN202730785U (en) | Anti-floating blind ditch water drainage structure for underground structure | |
CN102817298B (en) | Construction method on permafrost | |
CN103966996A (en) | Gravel pile and manufacturing method thereof | |
CN206916731U (en) | A kind of high-speed railway shallow layer soft soil foundation ruggedized construction | |
CN204491320U (en) | Existing railway station roadbed light supporting structure on filled ground | |
CN102330398A (en) | High-speed railway roadbed structure of unsaturated soil foundation in plain region | |
CN104895008B (en) | The construction method of environmentally friendly ecology wallboard type with ribbing barricade shore protection | |
CN103966997B (en) | The construction method of ground processing is carried out in utilization with the perfusion engineering pile of steel bushing | |
CN102535464A (en) | Construction method for driving pre-stressed hollow pile into thick-layer soft soil | |
CN207003158U (en) | A kind of soft soil foundation pile foundation cantilever barrier wall structure | |
CN208251760U (en) | Flexible barrier leaks reservoir | |
CN106337409A (en) | Method for treating peat soil foundation through preloading in combination with salt piles | |
CN206070257U (en) | A kind of roadbed for improving rail track bearing capacity | |
CN206667432U (en) | A kind of rainfall speed oozes device | |
CN202706046U (en) | Anti-floating drainage structure for underground structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20180213 |