CN206999084U - A kind of workpiece cools down cleaning device - Google Patents

A kind of workpiece cools down cleaning device Download PDF

Info

Publication number
CN206999084U
CN206999084U CN201720927281.4U CN201720927281U CN206999084U CN 206999084 U CN206999084 U CN 206999084U CN 201720927281 U CN201720927281 U CN 201720927281U CN 206999084 U CN206999084 U CN 206999084U
Authority
CN
China
Prior art keywords
workpiece
valve
reservoir
reserve tank
shower nozzle
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201720927281.4U
Other languages
Chinese (zh)
Inventor
陈凌
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
KPS Wuxi Machinery Technology Co Ltd
Original Assignee
KPS Wuxi Machinery Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by KPS Wuxi Machinery Technology Co Ltd filed Critical KPS Wuxi Machinery Technology Co Ltd
Priority to CN201720927281.4U priority Critical patent/CN206999084U/en
Application granted granted Critical
Publication of CN206999084U publication Critical patent/CN206999084U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Cleaning By Liquid Or Steam (AREA)

Abstract

The utility model discloses a kind of workpiece to cool down cleaning device, including cooling liquid water inlet pipe, the first valve, liquid reserve tank, outlet pipe, the second valve, switch element, water pump, the 3rd valve, shower nozzle, the head for controlling sprinkler rotation, reservoir and screen pack;Cooling liquid water inlet pipe is located at the side of liquid reserve tank, first valve is arranged in cooling liquid water inlet pipe, outlet pipe is arranged on the opposite side of liquid reserve tank, second valve is arranged on outlet pipe, switch element is connected with water pump, liquid reserve tank is connected with water pump by conduit, water pump is connected with shower nozzle by conduit, 3rd valve is arranged on the conduit that water pump is connected with shower nozzle, shower nozzle is arranged on head, and shower nozzle is located at the surface of workpiece, and reservoir is located at the underface of workpiece, screen pack is arranged on reservoir, and reservoir is connected by conduit with liquid reserve tank.The present apparatus is cooled down to workpiece, cleaned, and cooling effectiveness is high and simple in construction.

Description

A kind of workpiece cools down cleaning device
Technical field
Industry cooling cleaning technique field is the utility model is related to, particularly a kind of workpiece cooling cleaning device.
Background technology
Along with the rapid development of China's economy, industry cleaning link industry also obtains as the important component of Chinese industrial economy Flourish.Data show that 2011, which are only Chinese industrial cleaning equipment and industrial cleaning agent market, will just reach 20,000,000,000 Member.Various cleaning equipments manufacture distributors up to family more than 1000, wherein, supersonic wave cleaning machine manufacturing enterprise is from 20 generation The family more than 200 till now of several families to record the beginning of the nineties;Also there is family more than 1000 in cleaning agent production distributing business, has formed one Huge industry.
China's industry cleaning link industry is only initially that petrochemical industry and electricity power industry provide cleaning technique service, the master of cleaning Syllabus is energy-saving, raising equipment heat transfer efficiency.Nowadays, cleaning industry is from priority industry city gradually to middle-size and small-size city City's scattering and permeating, and then the gesture to cities and towns, rural area extension popularization is formed, compartmentalization feature is more and more substantially changed, and it has changed into The service trade of socialization, this indicates China's industry cleaning link already through foring wide market atmosphere.
Industrial washer is widely used in field of industrial production, work particularly higher to technological requirements such as the pump housing, valve bodies Part.In production, it is necessary to which to workpiece surface, inner chamber decontaminated, cleaned, and it is dried, cooled down again after cleaning. In workpiece process, workpiece produces substantial amounts of heat with cutter friction, in order to avoid the workpiece caused by heat increase becomes Shape influences processing progress, it is necessary to be cooled down in time to workpiece.Conventional cooling means is that coolant is poured on workpiece, no Only cooling effect is poor, and the liquid after cooling down easily causes environmental pollution, also deposit residue in liquid after the cooling period and The problems such as container is inconvenient to clear up.
The content of the invention
Technical problem to be solved in the utility model is overcome the deficiencies in the prior art and to provide a kind of workpiece cooling clear Cleaning device, the present apparatus are cooled down to workpiece, cleaned, and cooling effectiveness is high and simple in construction.
The utility model uses following technical scheme to solve above-mentioned technical problem:
According to the utility model proposes a kind of workpiece cool down cleaning device, including cooling liquid water inlet pipe, the first valve, storage Liquid case, outlet pipe, the second valve, switch element, water pump, the 3rd valve, shower nozzle, the head for controlling sprinkler rotation, liquid storage Groove and screen pack;Wherein,
Cooling liquid water inlet pipe is located at the side of liquid reserve tank, and the first valve is arranged in cooling liquid water inlet pipe, and outlet pipe is set In the opposite side of liquid reserve tank, the second valve is arranged on outlet pipe, and switch element is connected with water pump, and liquid reserve tank is with water pump by leading Pipe is connected, and water pump is connected with shower nozzle by conduit, and the 3rd valve is arranged on the conduit that water pump is connected with shower nozzle, and shower nozzle is set On head, shower nozzle is located at the surface of workpiece, and reservoir is located at the underface of workpiece, and screen pack is arranged on reservoir, storage Liquid bath is connected by conduit with liquid reserve tank.
As a kind of workpiece cooling further prioritization scheme of cleaning device described in the utility model, in addition to blowing group Part, blowing component are arranged on the upper side and lower side of workpiece, and blowing component includes air blower, the sky being arranged at fan inlet Air filter and the blower being arranged at air blower gas outlet.
As a kind of workpiece cooling further prioritization scheme of cleaning device described in the utility model, blower outlet port It is provided with horn-like blowing mouth, blowing mouth face workpiece.
As a kind of workpiece cooling further prioritization scheme of cleaning device described in the utility model, scribbled on the inside of reservoir Anticorrosion material.
As a kind of workpiece cooling further prioritization scheme of cleaning device described in the utility model, set on the inside of liquid reserve tank There is insulation material.
As a kind of workpiece cooling further prioritization scheme of cleaning device described in the utility model, reservoir is ship shape knot Structure.
The utility model compared with prior art, has following technique effect using above technical scheme:
(1)Present apparatus cycling use of water, water consumption are few and workpiece can be carried out to blow cooling wind, and it is cooled, cools down cleaning;
(2)The utility model is simple in construction, cooling effect is good and environment friendly and pollution-free, cheap, practical and section Can significant effect.
Brief description of the drawings
Fig. 1 is operating diagram of the present utility model.
Reference in figure is construed to:1- cooling liquid water inlet pipes, the valves of 2- first, 3- liquid reserve tanks, 4- outlet pipes, 5- Two valves, 6- switch elements, 7- water pumps, the valves of 8- the 3rd, 9- shower nozzles, 10- heads, 11- reservoirs, 12- screen packs, 13- works Part.
Embodiment
The technical solution of the utility model is described in further detail below in conjunction with the accompanying drawings:
As shown in figure 1, a kind of workpiece cooling cleaning device, including cooling liquid water inlet pipe 1, the first valve 2, liquid reserve tank 3, go out Water pipe 4, the second valve 5, switch element 6, water pump 7, the 3rd valve 8, shower nozzle 9, head 10, liquid storage for controlling sprinkler rotation Groove 11 and screen pack 12;Wherein,
Cooling liquid water inlet pipe is located at the side of liquid reserve tank, and the first valve is arranged in cooling liquid water inlet pipe, and outlet pipe is set In the opposite side of liquid reserve tank, the second valve is arranged on outlet pipe, and switch element is connected with water pump, and liquid reserve tank is with water pump by leading Pipe is connected, and water pump is connected with shower nozzle by conduit, and the 3rd valve is arranged on the conduit that water pump is connected with shower nozzle, and shower nozzle is set On head, shower nozzle is located at the surface of workpiece 13, and reservoir is located at the underface of workpiece, and screen pack is arranged on reservoir, Reservoir is connected by conduit with liquid reserve tank.
The present apparatus also includes blowing component, and blowing component is arranged on the upper side and lower side of workpiece, and blowing component includes air blast Machine, the air cleaner being arranged at fan inlet and the blower being arranged at air blower gas outlet.Blower goes out Gas port end is provided with horn-like blowing mouth, blowing mouth face workpiece.
Anticorrosion material is scribbled on the inside of reservoir, can make it that reservoir is durable in use.
The inner side of liquid reserve tank is provided with insulation material so that the fluid temperature of the inside will not raise.
Reservoir is ship shape structure, and bottom is not easy dead angle be present, is easy to brush bottom cleaning, easy to clean.
The present apparatus can not only realize the cooling in cutting to workpiece, after machining, can also realize to workbench Cleared up with workpiece, the flow velocity of the open and close coolants of water pump is controlled with switch element can pass through valve setpoint.It is cold But the coolant after workpiece is reclaimed by reservoir, then is back to liquid reserve tank by conduit and is recycled.Lead in reservoir Cross filter screen filtration and fall chip, some small residues, which enter reservoir, can also deposit to bottom, easy cleaning.
Above content is to combine specific preferred embodiment further detailed description of the utility model, it is impossible to Assert that specific implementation of the present utility model is confined to these explanations.For the ordinary skill of the utility model art For personnel, without departing from the concept of the premise utility, some simple deductions can also be made or substituted, should all be regarded To belong to the scope of protection of the utility model.

Claims (6)

1. a kind of workpiece cools down cleaning device, it is characterised in that including cooling liquid water inlet pipe, the first valve, liquid reserve tank, water outlet Pipe, the second valve, switch element, water pump, the 3rd valve, shower nozzle, the head for controlling sprinkler rotation, reservoir and filtering Net;Wherein,
Cooling liquid water inlet pipe is located at the side of liquid reserve tank, and the first valve is arranged in cooling liquid water inlet pipe, and outlet pipe is arranged on storage The opposite side of liquid case, the second valve are arranged on outlet pipe, and switch element is connected with water pump, and liquid reserve tank is connected with water pump by conduit Connect, water pump is connected with shower nozzle by conduit, and the 3rd valve is arranged on the conduit that water pump is connected with shower nozzle, and shower nozzle is arranged on cloud On platform, shower nozzle is located at the surface of workpiece, and reservoir is located at the underface of workpiece, and screen pack is arranged on reservoir, reservoir Connected by conduit with liquid reserve tank.
2. a kind of workpiece cooling cleaning device according to claim 1, it is characterised in that also include blowing component, blowing Component is arranged on the upper side and lower side of workpiece, and blowing component includes air blower, the air filtration being arranged at fan inlet Device and the blower being arranged at air blower gas outlet.
3. a kind of workpiece cooling cleaning device according to claim 2, it is characterised in that blower outlet port is provided with Horn-like blowing mouth, blowing mouth face workpiece.
4. a kind of workpiece cooling cleaning device according to claim 1, it is characterised in that scribble anticorrosion on the inside of reservoir Material.
5. a kind of workpiece cooling cleaning device according to claim 1, it is characterised in that the inner side of liquid reserve tank is provided with insulation Material.
6. a kind of workpiece cooling cleaning device according to claim 1, it is characterised in that reservoir is ship shape structure.
CN201720927281.4U 2017-07-28 2017-07-28 A kind of workpiece cools down cleaning device Expired - Fee Related CN206999084U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720927281.4U CN206999084U (en) 2017-07-28 2017-07-28 A kind of workpiece cools down cleaning device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720927281.4U CN206999084U (en) 2017-07-28 2017-07-28 A kind of workpiece cools down cleaning device

Publications (1)

Publication Number Publication Date
CN206999084U true CN206999084U (en) 2018-02-13

Family

ID=61457287

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720927281.4U Expired - Fee Related CN206999084U (en) 2017-07-28 2017-07-28 A kind of workpiece cools down cleaning device

Country Status (1)

Country Link
CN (1) CN206999084U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110834222A (en) * 2019-10-23 2020-02-25 常州固高智能装备技术研究院有限公司 Device for machining workpiece by numerical control equipment and working method thereof

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110834222A (en) * 2019-10-23 2020-02-25 常州固高智能装备技术研究院有限公司 Device for machining workpiece by numerical control equipment and working method thereof

Similar Documents

Publication Publication Date Title
CN203244879U (en) Waste gas absorption tower
CN203216310U (en) Atomization cooling tower
CN210613217U (en) Industrial waste gas purification scrubbing tower
CN201200979Y (en) Online spraying and cleaning equipment
CN206999084U (en) A kind of workpiece cools down cleaning device
CN107952317A (en) A kind of dust pelletizing system
CN206081991U (en) Flue gas dust removal equipment
CN206857411U (en) A kind of multifunction storage water pot
CN207307478U (en) A kind of explosion-proof oil-burning machine exhaust gas purification water tank
CN216295745U (en) Based on dust keeper for desulfurization processing
CN206823505U (en) A kind of efficient desulfurizing tower for smoke gas treatment
CN208320325U (en) A kind of novel tail gas desulfurization processing unit
CN204073769U (en) Fertilizer tail gas dust cleaning apparatus
CN211245922U (en) Humidification formula industrial dust collector
CN206198911U (en) A kind of wet dust separater
CN207899172U (en) A kind of water film dust removal device of practicality
CN203687663U (en) Wet desulphurization smoke inlet guiding cooling device
CN207102246U (en) Fountain high-temperature smoke purifier
CN206208056U (en) The dry colling device of dual countercurrent treatment high-temp waste gas
CN206399222U (en) A kind of heat recovery system for organic particulate matter air draft
CN202700299U (en) Water film dust-removing and benzene-removing device
CN207112848U (en) Zero waste gas emission comprehensive treatment device
CN206793278U (en) Granulation tower dust reclaiming clean device
CN206262306U (en) Wet method, half wet process eddy flow remove haze equipment
CN205241250U (en) Silicon tetrachloride rectification tail gas recovery system

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20180213

Termination date: 20180728

CF01 Termination of patent right due to non-payment of annual fee