CN206987197U - A kind of concrete filled steel tube coupled column - Google Patents

A kind of concrete filled steel tube coupled column Download PDF

Info

Publication number
CN206987197U
CN206987197U CN201720882581.5U CN201720882581U CN206987197U CN 206987197 U CN206987197 U CN 206987197U CN 201720882581 U CN201720882581 U CN 201720882581U CN 206987197 U CN206987197 U CN 206987197U
Authority
CN
China
Prior art keywords
steel pipe
concrete
wall
coupled column
stirrup
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201720882581.5U
Other languages
Chinese (zh)
Inventor
殷诗宝
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Wuxi Tongji Steel Structure Project Management Co Ltd
Original Assignee
Wuxi Tongji Steel Structure Project Management Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Wuxi Tongji Steel Structure Project Management Co Ltd filed Critical Wuxi Tongji Steel Structure Project Management Co Ltd
Priority to CN201720882581.5U priority Critical patent/CN206987197U/en
Application granted granted Critical
Publication of CN206987197U publication Critical patent/CN206987197U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Rod-Shaped Construction Members (AREA)

Abstract

The utility model discloses a kind of concrete filled steel tube coupled column, hole is machined with steel pipe wall, stiffener and distributing bar are installed along the longitudinal direction outside steel pipe, steel pipe periphery is arranged at intervals stirrup simultaneously, stirrup is connected or welded with stiffener and distributing bar colligation, and lacing wire is provided at both ends with crotch, through two relative holes after be hooked in respectively on the distributing bar on the outside of hole, and be connected or weld with distributing bar colligation, in steel duct and outer wall casting concrete.The hole of steel pipe side wall can connect the concrete inside and outside steel pipe, at the same lacing wire can also fixing concrete, so as to effectively preventing the concrete shrinkage in steel pipe and cause steel pipe to be separated with concrete, ensure the service behaviour of coupled column.Stiffener is crisscross with stirrup, forms the skeleton of outer wall of steel pipe concrete, concrete is fixed on into outer wall of steel pipe, the concrete of outer wall has heat-blocking action, effectively can prevent heat from directly contacting steel pipe, improves the fire protecting performance of whole coupled column.

Description

A kind of concrete filled steel tube coupled column
Technical field
Building structure field, especially one kind is the utility model is related to avoid concrete from separating with steel pipe and improve fire resisting The concrete filled steel tube coupled column of performance.
Background technology
With the rapid development of China's urban construction and the propulsion of building industrialization, skyscraper and large area plants Demand is more and more.But traditional reinforced concrete structure due to poor seismic behavior the shortcomings of, it is difficult in big load, large span The functional diversities of skyscraper are realized Deng under the conditions of, do not reach saving land, saving required by building industry developing direction more Important indicator, the needs of Development of High-rise Buildings have been not suitable with it.And concrete filled steel tube passes through the fill concrete in steel pipe And formed, the concrete of steel pipe and inside can bear external loads effect jointly, by by the combination of steel pipe and concrete, no The shortcomings that two kinds of materials can only be made up each, and the advantages of the two can be given full play to, therefore concrete filled steel tube is Through a kind of primary structure form as skyscraper.Traditional concrete filled steel tube is directly to pour into concrete in steel pipe Portion, after concrete solidifies in steel pipe, its volume can reduce, and cause the concrete after solidification to be separated with steel pipe internal-surface, reduce The structural behaviour of concrete filled steel tube.Simultaneously there is problem in exposed steel pipe fire line, once fire is run into, exposed steel pipe Deformed under the influence of heat, the reliability of concrete filled steel tube will be directly affected, or even endanger whole building.Especially It is the concrete filled steel tube pillar to play a supportive role, because it is acted on whole building structure for support, the requirement of its fire protecting performance is more It is high.
Utility model content
Separate and cause structural with steel pipe after the concrete setting that the applicant is directed in existing concrete filled steel tube It can reduce, and the problems such as exposed steel pipe fire protecting performance difference, there is provided a kind of concrete filled steel tube coupled column rational in infrastructure, effectively Peeled off with steel pipe after avoiding concrete setting and reduce structural behaviour, while the fire protecting performance of coupled column can be improved.
Technical scheme is as follows used by the utility model:
A kind of concrete filled steel tube coupled column, including steel pipe and concrete, the steel pipe wall are machined with hole, steel pipe outside edge Longitudinal direction installs stiffener and distributing bar, distributing bar are located at the position of hole opening;The steel pipe periphery is arranged at intervals Stirrup, stirrup is welded with stiffener or colligation is connected;Lacing wire is provided at both ends with crotch, through two relative holes after respectively hook It is connected or welds on the distributing bar on the outside of hole, and with distributing bar colligation;Poured in the steel duct and outer wall Concrete.
Further improvement as above-mentioned technical proposal:
The stiffener is welded on outer wall of steel pipe.
The stirrup and distributing bar bind or welding.
The steel pipe is square or rectangular steel pipe, and the position in the hole that the relative wall of steel pipe opens up is relative.
The steel pipe is round steel pipe, and hole is opened in diametric both ends.
The hole is shaped as rectangle, square or circular.
Stiffener, distributing bar and the stirrup of the outer wall of steel pipe are all embedded in concrete.
The stirrup and the material of lacing wire are reinforcing bars.
The diameter of the distributing bar is less than or equal to the diameter of stiffener.
The beneficial effects of the utility model are as follows:
The utility model passes through in outer wall of steel pipe perforate, lacing wire through the distributing bar connection on the outside of relative Kong Bingyu Hole connects the concrete inside and outside steel pipe, meanwhile, the fixed effect of support is played in lacing wire to concrete, effectively prevents from mixing in steel pipe Steel pipe separates with concrete caused by coagulating native solidification shrinkage, ensures the structural behaviour of concrete filled steel tube coupled column.
The utility model installs stiffener along the longitudinal direction in outer wall of steel pipe, and stirrup is connected outside stiffener, indulges The wrong stiffener of traversed by forms the skeleton of outer concrete with stirrup, and effectively solving concrete can not be effectively fixed in outside steel pipe The problem of wall, while the concrete of outer wall has heat-blocking action, effectively can prevent heat from directly contacting steel pipe, improves whole group The fire protecting performance of zygostyle.Stiffener also increases the stress area of section of coupled column simultaneously, and effective compensation steel pipe due to Perforate and caused by structural behaviour lose, while stirrup and lacing wire can also strengthen the structure tension performance of steel pipe.
Brief description of the drawings
Fig. 1 is front view of the present utility model.
Fig. 2 is the profile in Fig. 1 along the horizontal plane.
In figure:1st, steel pipe;2nd, stiffener;3rd, distributing bar;4th, stirrup;5th, lacing wire;6th, concrete;7th, hole.
Embodiment
Below in conjunction with the accompanying drawings, specific embodiment of the present utility model is illustrated.
As depicted in figs. 1 and 2, steel pipe 1 of the present utility model is square or rectangular steel pipe, and the peripheral wall surfaces interval of steel pipe 1 four adds Work has hole 7, and the position in the hole 7 of the relative wall of steel pipe 1 is relative, and hole 7 is shaped as rectangle, square or circular, preferably round Shape.More stiffeners 2 and a distributing bar 3, stiffener 2 are installed along the longitudinal direction in 1 each lateral outer of steel pipe Interruption is welded on the outer wall of steel pipe 1, and distributing bar 3 is located at the position in hole 7.The periphery of steel pipe 1 is arranged at intervals the stirrup 4 of ring-type, stirrup 4 It is connected or welds with stiffener 2 and the colligation of distributing bar 3.Lacing wire 5 is provided at both ends with crotch, through two relative holes 7 It is hooked in respectively afterwards on the distributing bar 3 in the outside of hole 7, and is connected or welds with the colligation of distributing bar 3.In the inside of steel pipe 1 and Outside casting concrete 6, stiffener 2, distributing bar 3 and stirrup 4 are all embedded in the concrete 6 in the outside of steel pipe 1.Stirrup 4 Material with lacing wire 5 is reinforcing bar, and the diameter of distributing bar 3 is less than or equal to the diameter of stiffener 2.
In architectural engineering, first stiffener 2, distributing bar 3, stirrup 4, lacing wire 5 are fixedly mounted with steel pipe 1 and finished, so The concrete 6 inside and outside steel pipe 1 is poured in factory or job site afterwards, completes concrete filled steel tube coupled column of the present utility model. Because steel pipe 1 offers hole 7, therefore can inwardly it be poured from hole 7 when casting concrete, so as to ensure that concrete 6 is uniform It is cast in the inside of steel pipe 1 and outside.Concrete 6 is shunk during solidification, due to the concrete 6 inside and outside steel pipe 1 Connected by hole 7, the concrete 6 inside and outside steel pipe 1 can ensure that the concrete 6 in steel pipe 1 is shrinking simultaneously to contract During will not be separated with the wall of steel pipe 1, can also be to mixed in steel pipe 1 simultaneously because lacing wire 5 is in the interlaced arrangement of steel pipe 1 Solidifying soil 6 plays a part of support, can equally limit the concrete 6 inside steel pipe 1 and be separated with the wall of steel pipe 1, effectively solution The problem of certainly concrete 6 separates with steel pipe 1 and causes the structural behaviour of reinforced concrete combination post to reduce.
Because the outer wall of steel pipe 1 is longitudinally provided with stiffener 2, stirrup 4 is horizontally installed with, stiffener 2 and stirrup 4 are formed Crisscross network, concrete 6 can be fixed on the outer wall of steel pipe 1, had as the skeleton of the outer wall concrete 6 of steel pipe 1 Effect solves the problems, such as that concrete 6 can not be fixed in the smooth outer wall of steel pipe 1.When concrete 6 is fixed on the outer wall of steel pipe 1, By the heat-blocking action of concrete, it can effectively prevent heat from directly contacting steel pipe 1, so as to improve the fire line of whole coupled column Energy.Due to the outer wall perforate 7 of steel pipe 1, the mechanical property of steel pipe 1 is reduced, and the stiffener 2 of the outer wall of steel pipe 1 installation can be mended The reduction of structural behaviour caused by the perforate of steel pipe 1 is repaid, and stiffener 2 also directly increases the stress of steel in coupled column Area of section, the mechanical property of coupled column is improved, while stirrup 4 and lacing wire 5 can also strengthen the structure tension performance of coupled column.
Certainly, steel pipe 1 of the present utility model can also be round steel pipe, round steel pipe periphery install respectively stiffener 2, Distributing bar 3 and stirrup 4, the hole 7 of round steel pipe are opened in diametric both ends, and lacing wire 5 passes through relative hole 7 and and stirrup 4 colligations connect.
Above description is to explanation of the present utility model, is not the restriction to utility model, without prejudice to the utility model In the case of spirit, the utility model can make any type of modification.

Claims (9)

  1. A kind of 1. concrete filled steel tube coupled column, it is characterised in that:Including steel pipe(1)And concrete(6), the steel pipe(1)Wall It is machined with hole(7), steel pipe(1)Outside is installed by stiffener along the longitudinal direction(2)And distributing bar(3), distributing bar(3)It is located at Hole(7)The position of opening;The steel pipe(1)Periphery is arranged at intervals stirrup(4), stirrup(4)With stiffener(2)Welding or colligation Connection;Lacing wire(5)Crotch is provided at both ends with, through two relative holes(7)It is hooked in hole respectively afterwards(7)The distributing bar in outside (3)On, and and distributing bar(3)Colligation connects or welding;In the steel pipe(1)Internal and outer wall casting concrete(6).
  2. 2. according to the concrete filled steel tube coupled column described in claim 1, it is characterised in that:The stiffener(2)It is welded on steel Pipe(1)Outer wall.
  3. 3. according to the concrete filled steel tube coupled column described in claim 1, it is characterised in that:The stirrup(4)With distributing bar(3) Bind or welding.
  4. 4. according to the concrete filled steel tube coupled column described in claim 1, it is characterised in that:The steel pipe(1)For square or rectangle Steel pipe, steel pipe(1)The hole that opens up of relative wall(7)Position it is relative.
  5. 5. according to the concrete filled steel tube coupled column described in claim 1, it is characterised in that:The steel pipe(1)For round steel pipe, hole (7)It is opened in diametric both ends.
  6. 6. according to the concrete filled steel tube coupled column described in claim 1, it is characterised in that:The hole(7)Be shaped as rectangle, side Shape or circle.
  7. 7. according to the concrete filled steel tube coupled column described in claim 1, it is characterised in that:The steel pipe(1)The reinforcement steel of outer wall Muscle(2), distributing bar(3)And stirrup(4)All it is embedded in concrete(6)It is interior.
  8. 8. according to the concrete filled steel tube coupled column described in claim 1, it is characterised in that:The stirrup(4)And lacing wire(5)Material Matter is reinforcing bar.
  9. 9. according to the concrete filled steel tube coupled column described in claim 1, it is characterised in that:The distributing bar(3)Diameter it is small In or equal to stiffener(2)Diameter.
CN201720882581.5U 2017-07-20 2017-07-20 A kind of concrete filled steel tube coupled column Expired - Fee Related CN206987197U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720882581.5U CN206987197U (en) 2017-07-20 2017-07-20 A kind of concrete filled steel tube coupled column

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720882581.5U CN206987197U (en) 2017-07-20 2017-07-20 A kind of concrete filled steel tube coupled column

Publications (1)

Publication Number Publication Date
CN206987197U true CN206987197U (en) 2018-02-09

Family

ID=61415916

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720882581.5U Expired - Fee Related CN206987197U (en) 2017-07-20 2017-07-20 A kind of concrete filled steel tube coupled column

Country Status (1)

Country Link
CN (1) CN206987197U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107237453A (en) * 2017-07-20 2017-10-10 殷诗宝 A kind of concrete filled steel tube coupled column
CN110886153A (en) * 2019-12-11 2020-03-17 中铁第四勘察设计院集团有限公司 Steel pipe concrete long sleeper and construction method thereof

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107237453A (en) * 2017-07-20 2017-10-10 殷诗宝 A kind of concrete filled steel tube coupled column
CN110886153A (en) * 2019-12-11 2020-03-17 中铁第四勘察设计院集团有限公司 Steel pipe concrete long sleeper and construction method thereof

Similar Documents

Publication Publication Date Title
CN105256917B (en) A kind of precast shear wall perps combined connecting structure and its construction method
CN205742613U (en) A kind of prefabricated assembled overlapped shear wall structure connected by high-strength bolt
CN104775516B (en) Field connecting method among prefabricated reinforced concrete columns
CN109372130A (en) The novel full assembly concrete shaped section steel frame node of one kind and its construction method
CN105804241A (en) Single-layer prefabricated assembly type reinforced concrete beam-column joint
CN106567458B (en) Assembled steel-is mixed to combine Beam-post Frame Structure system
CN201339250Y (en) Stiffness structure framework beam preformed steel reinforcement framework structure
CN107246272B (en) Shield tunnel lining glass fiber reinforced concrete segment and manufacturing method thereof
CN107044083A (en) A kind of double-wall corrugated steel pipe reinforced concrete hollow pier post
CN207228316U (en) A kind of prefabricated assembled frame combined using profile steel concrete column and girder steel
CN204959960U (en) Prefabricate prefabricated concrete structure entirely
CN110056092A (en) Bolt plug-in type precast shear wall and superimposed sheet connecting structure and construction method up and down
CN109372129A (en) The novel full assembly concrete frame joint of one kind and its construction method
CN105201071A (en) Totally-prefabricated concrete structure
CN109024915B (en) PVC-FRP pipe constraint steel reinforced concrete column-reinforced concrete beam L-shaped node
CN207794299U (en) A kind of complete assembled steel reinforced concrete frame structure system
CN206987197U (en) A kind of concrete filled steel tube coupled column
CN107237453A (en) A kind of concrete filled steel tube coupled column
CN201406767Y (en) Node for connecting circular concrete-filled tubular column and reinforced concrete floor
CN208918022U (en) Superimposed sheet splicing structure
CN206829416U (en) A kind of prefabricated assembled double steel pipe concrete shear force wall
CN108104263A (en) A kind of novel fabricated steel-regeneration concrete combination frame structural system
CN107938499A (en) A kind of prefabricated assembled bridge pier
CN105649259B (en) A kind of wallboard structural system of the dark framework of band of precast concrete wall panel and its structure
CN209227834U (en) A kind of assembly concrete-filled steel tube frame-shear-wall structure

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20180209