CN206974777U - A kind of Compaction experiment experiment hoop pier - Google Patents

A kind of Compaction experiment experiment hoop pier Download PDF

Info

Publication number
CN206974777U
CN206974777U CN201720940718.8U CN201720940718U CN206974777U CN 206974777 U CN206974777 U CN 206974777U CN 201720940718 U CN201720940718 U CN 201720940718U CN 206974777 U CN206974777 U CN 206974777U
Authority
CN
China
Prior art keywords
hinge
compaction
big
experiment
small
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201720940718.8U
Other languages
Chinese (zh)
Inventor
林秦辉
林秦娟
沈丽娟
林慧娟
汤丽梅
陈木强
林福宾
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Fujian Prudential Testing Technology Ltd By Share Ltd
Original Assignee
Fujian Prudential Testing Technology Ltd By Share Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Fujian Prudential Testing Technology Ltd By Share Ltd filed Critical Fujian Prudential Testing Technology Ltd By Share Ltd
Priority to CN201720940718.8U priority Critical patent/CN206974777U/en
Application granted granted Critical
Publication of CN206974777U publication Critical patent/CN206974777U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

The utility model discloses a kind of Compaction to test with experiment hoop pier, including cushion block, the top of the cushion block is fixed with the first big hinge, first big hinge is arranged to ironcasting with cushion block, the first big hinge is fixed with second largest hinge by latch and jack, the first big hinge on the inside of second largest hinge with being provided with the first compaction cylinder, the first big hinge is identical with second largest hinge structure, the internal diameter of the first big hinge and second largest hinge is disposed as 16cm, and the diameter of first compaction cylinder is arranged to 16cm.The utility model, the red wine bottle that will conveniently and effectively can be positioned in pad clamp, will not loosen, effectively prevent mutual collision in transit, bottle breakage degree is low.

Description

A kind of Compaction experiment experiment hoop pier
Technical field
Compaction experimental technique field is the utility model is related to, specifically a kind of Compaction experiment experiment hoop pier.
Background technology
JTG E40-2007《Highway earthwork test rule》In light-duty heavy compaction, hit it is real it is complete after sample can be higher by cylinder Face face with sharpener, it is necessary to manually carry out shaving, but because compaction cylinder itself is in light weight very closely knit plus the sample after reality is hit, Cylinder when shaving is caused to be rocked together with sample, it is necessary to which two people are coordinated, and have impact on efficiency and the experiment of experiment Effect.
Utility model content
The purpose of this utility model is to provide a kind of Compaction experiment experiment hoop pier, of the prior art to solve Problem.
To achieve the above object, the utility model provides following technical scheme:A kind of Compaction experiment experiment hoop pier, Including cushion block, the first small hinge, the second small hinge and the second compaction cylinder, the top of the cushion block is fixed with the first big hinge, the One big hinge is arranged to ironcasting with cushion block, and the first big hinge is fixed with second largest hinge by latch and jack, described First big hinge on the inside of second largest hinge with being provided with the first compaction cylinder, the first big hinge and second largest hinge structure phase Together, the internal diameter of the described first big hinge and second largest hinge is disposed as 16cm, and the diameter of first compaction cylinder is arranged to 16cm, the height of the first big hinge and second largest hinge are arranged to 8cm.
Preferably, the length of the cushion block is arranged to 40cm, width is arranged to 16cm, is highly arranged to 1.5cm, and described The diameter of one compaction cylinder is arranged to 15.2cm.
Preferably, the described first big hinge is provided with the first small hinge and the second small hinge with second largest hinge inner side, the The second compaction cylinder is provided with the inside of one small hinge and the second small hinge.
Preferably, the external diameter of the described first small hinge and the second small hinge is arranged to 16cm, the first small hinge and second small The internal diameter of hinge is arranged to 10.6cm, and the height of the first small hinge and the second small hinge is arranged to 6cm.
Preferably, the diameter of second compaction cylinder is arranged to 10cm.
Compared with prior art, the beneficial effects of the utility model are:The utility model accurate positioning.Positioned with hinge, Position is accurate, and can be common to geotechnique hits reality and CBR experiments, has corresponding cushion block, is easy to call different compaction cylinders;Practicality can OK.It is easy to operate, it will not be taken a significant amount of time because of installation compaction cylinder.
Brief description of the drawings
Fig. 1 is structural representation of the present utility model.
Fig. 2 is top view of the present utility model.
Fig. 3 is the structural representation of the compaction cylinder of the utility model second installation.
In figure:1- cushion blocks;The first big hinges of 2-;The second largest hinges of 3-;The compaction cylinders of 4- first;5- latches;6- jacks;7- One small hinge;The second small hinges of 8-;The compaction cylinders of 9- second.
Embodiment
Below in conjunction with the accompanying drawing in the utility model embodiment, the technical scheme in the embodiment of the utility model is carried out Clearly and completely describing, it is clear that described embodiment is only the utility model part of the embodiment, rather than whole Embodiment.Based on the embodiment in the utility model, those of ordinary skill in the art are not under the premise of creative work is made The every other embodiment obtained, belong to the scope of the utility model protection.
Refer to Fig. 1-3, in the utility model embodiment, a kind of Compaction experiment experiment hoop pier, including cushion block 1, First small hinge 7, the second small compaction cylinder 9 of hinge 8 and second, the top of cushion block 1 are fixed with the first big hinge 2, the first big hinge 2 Ironcasting is arranged to cushion block 1, the first big hinge 2 is fixed with second largest hinge 3 by latch 5 and jack 6, the first big hinge 2 The second largest inner side of hinge 3 is provided with the first compaction cylinder 4, the first big hinge 2 is identical with the second largest structure of hinge 3, the first big conjunction The internal diameter of page 2 and second largest hinge 3 is disposed as 16cm, and the height of the first big hinge 2 and second largest hinge 3 is arranged to 8cm, the The diameter of one compaction cylinder 4 is arranged to 15.2cm, and the length of cushion block 1 is arranged to 40cm, width is arranged to 16cm, is highly arranged to 1.5cm, the first big hinge 2 are provided with the first small 7 and second small hinge 8 of hinge, the first small hinge 7 with the second largest inner side of hinge 3 The second small inner side of hinge 8 is provided with the second compaction cylinder 9, the external diameter of the first small 7 and second small hinge 8 of hinge is arranged to 16cm, The internal diameter of first small 7 and second small hinge 8 of hinge is arranged to 10.6cm, and the height of the first small 7 and second small hinge 8 of hinge is set For 6cm, the diameter of the second compaction cylinder 9 is arranged to 10cm.
Operation principle of the present utility model is:When doing heavy compaction, two jacks and first on second largest hinge are big The jack of hinge coincides with the upper and lower and injects latch again, and two are just combined the compaction cylinder of banding first;Doing heavy compaction and soil Carrying ratio(CBR)During experiment, the internal diameter size of the first big hinge and second largest hinge(Diameter=16cm)Admit the first compaction cylinder (Diameter=15.2cm).Do it is light-duty hit in real time, the second small hinge and the second small hinge are connected so that the first small hinge and the Two small hinges(Diameter=10.6cm)It is enclosed in the first big hinge and second largest hinge, then puts the second compaction cylinder into(Diameter= 10cm).The soil body after banding above the convenient shaving compaction cylinder of can scraper.
It is obvious to a person skilled in the art that the utility model is not limited to the details of above-mentioned one exemplary embodiment, and And in the case of without departing substantially from spirit or essential attributes of the present utility model, it can realize that this practicality is new in other specific forms Type.Therefore, no matter from the point of view of which point, embodiment all should be regarded as exemplary, and is nonrestrictive, this practicality is new The scope of type limits by appended claims rather than described above, it is intended that the equivalency fallen in claim is contained All changes in justice and scope are included in the utility model.Any reference in claim should not be considered as limitation Involved claim.

Claims (5)

1. a kind of Compaction experiment experiment hoop pier, including cushion block(1), the first small hinge(7), the second small hinge(8)With Two compaction cylinders(9), it is characterised in that:The cushion block(1)Top be fixed with the first big hinge(2), the first big hinge(2)With pad Block(1)It is arranged to ironcasting, the first big hinge(2)With second largest hinge(3)Pass through latch(5)With jack(6)It is fixed, institute State the first big hinge(2)With second largest hinge(3)Inner side is provided with the first compaction cylinder(4), the first big hinge(2)With second Big hinge(3)Structure is identical, the first big hinge(2)With second largest hinge(3)Internal diameter be disposed as 16cm, first big closes Page(2)With second largest hinge(3)Height be arranged to 8cm, first compaction cylinder(4)Diameter be arranged to 15.2cm.
A kind of 2. Compaction experiment experiment hoop pier according to claim 1, it is characterised in that:The cushion block(1)'s Length is arranged to 40cm, width is arranged to 16cm, is highly arranged to 1.5cm.
A kind of 3. Compaction experiment experiment hoop pier according to claim 1, it is characterised in that:The first big hinge (2)With second largest hinge(3)Inner side is provided with the first small hinge(7)With the second small hinge(8), the first small hinge(7)With second Small hinge(8)Inner side is provided with the second compaction cylinder(9).
A kind of 4. Compaction experiment experiment hoop pier according to claim 1, it is characterised in that:The first small hinge (7)With the second small hinge(8)External diameter be arranged to 16cm, the first small hinge(7)With the second small hinge(8)Internal diameter be arranged to 10.6cm, the first small hinge(7)With the second small hinge(8)Height be arranged to 6cm.
A kind of 5. Compaction experiment experiment hoop pier according to claim 4, it is characterised in that:Second compaction cylinder (9)Diameter be arranged to 10cm.
CN201720940718.8U 2017-07-31 2017-07-31 A kind of Compaction experiment experiment hoop pier Expired - Fee Related CN206974777U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720940718.8U CN206974777U (en) 2017-07-31 2017-07-31 A kind of Compaction experiment experiment hoop pier

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720940718.8U CN206974777U (en) 2017-07-31 2017-07-31 A kind of Compaction experiment experiment hoop pier

Publications (1)

Publication Number Publication Date
CN206974777U true CN206974777U (en) 2018-02-06

Family

ID=61398069

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720940718.8U Expired - Fee Related CN206974777U (en) 2017-07-31 2017-07-31 A kind of Compaction experiment experiment hoop pier

Country Status (1)

Country Link
CN (1) CN206974777U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108519265A (en) * 2018-04-12 2018-09-11 浙江裕立检测科技有限公司 Compaction test apparatus
CN109323882A (en) * 2018-11-23 2019-02-12 同济大学 A kind of combination hammer displacement pier pier body sampler

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108519265A (en) * 2018-04-12 2018-09-11 浙江裕立检测科技有限公司 Compaction test apparatus
CN109323882A (en) * 2018-11-23 2019-02-12 同济大学 A kind of combination hammer displacement pier pier body sampler

Similar Documents

Publication Publication Date Title
CN206974777U (en) A kind of Compaction experiment experiment hoop pier
CN206051446U (en) Lifting machine safety lock and the lifting machine using which
CN204587830U (en) Pressure head translation push pedal positional cylinder
CN205712684U (en) A kind of guide tracked New wall brick
CN206367750U (en) A kind of compression set of vertical-compression type garbage apparatus
CN207608792U (en) A kind of rammer compacter for building with handrail damping
CN202670379U (en) Support for loading and transportation of mineral water barrel
CN204238123U (en) A kind of triangular form section steel pipe regeneration concrete pier stud
CN210196511U (en) Large pneumatic blind plate valve overturning cylinder
CN106217565B (en) A kind of environmental protection recycles compaction apparatus with throwaway chopsticks
CN206677862U (en) A kind of dismantling device for being used for mud slurry pump cylinder jacket and piston
CN206813774U (en) A kind of foot-operated environment-friendly trash can
CN206203830U (en) The large span A type supporting legs of high-altitude operation vehicle
CN203006073U (en) Green brick transporter
CN206141583U (en) Gas cylinder cart
CN205552981U (en) Damping rubber support combination die
CN204500021U (en) Stool
CN204754591U (en) Fixed safe of sucking disc
CN204937977U (en) LNG gas cylinder Foldable bracket
CN204214528U (en) Weighing device
CN206484527U (en) A kind of shackle storing unit
CN203921646U (en) A kind of packaging structure of Novel backlight
CN208775249U (en) A kind of molecular sieve pack arrangement
CN203419449U (en) Vertical short-stroke rubbish compression equipment
CN207152739U (en) A kind of combined type medical pallet

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20180206

Termination date: 20180731