CN206958478U - A kind of pipeline compensator - Google Patents

A kind of pipeline compensator Download PDF

Info

Publication number
CN206958478U
CN206958478U CN201720644118.7U CN201720644118U CN206958478U CN 206958478 U CN206958478 U CN 206958478U CN 201720644118 U CN201720644118 U CN 201720644118U CN 206958478 U CN206958478 U CN 206958478U
Authority
CN
China
Prior art keywords
pipe
deformation
plate
compensated
connecting tube
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201720644118.7U
Other languages
Chinese (zh)
Inventor
龚预强
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhongye Changtian International Engineering Co Ltd
Original Assignee
Zhongye Changtian International Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhongye Changtian International Engineering Co Ltd filed Critical Zhongye Changtian International Engineering Co Ltd
Priority to CN201720644118.7U priority Critical patent/CN206958478U/en
Application granted granted Critical
Publication of CN206958478U publication Critical patent/CN206958478U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Joints Allowing Movement (AREA)

Abstract

The utility model discloses a kind of pipeline compensator, and for the connection of two pipes, described two pipes are the first pipe and the second pipe.The inwall of first pipe is embedded to be welded with connecting tube, and connecting tube extends to the second pipe, and grafting enters in the second pipe pipe;Also include deformation-compensated plate, deformation-compensated plate includes the first deformation-compensated plate with the welding of the first pipe port, and the second deformation-compensated plate being welded at second pipe port;First deformation-compensated plate is with being connected pipe outer wall welding;Second compensating plate is close to the outer wall of connecting tube;Also include sealing plate;Sealing plate is welded between the described first deformation-compensated plate and the second deformation-compensated plate.Pipeline compensator disclosed in the utility model can substitute the FlexbleJoint being made up of parts such as bellows, flanges, and the compensation expanded with heat and contract with cold to pipeline is realized when two pipes connect.The utility model is simple in construction, and the surplus material of field pipes can be utilized to make, the cost of effectively save pipeline connection.

Description

A kind of pipeline compensator
Technical field
Pipeline engineering design field is the utility model is related to, more specifically, more particularly to a kind of pipeline compensator.
Background technology
Pipeline compensator is also known as expansion bend or telescopic joint, expansion joint, is mainly used in compensation pipeline and is produced by temperature change Raw expands with heat and contract with cold.If during temperature change pipeline can not completely freely expansion or shrinkage, thermal stress will be produced in pipeline. This stress is must take into consideration in pipe design, otherwise it may cause the rupture of pipeline, influence the progress normally produced.As pipe One important component of road engineering, pipeline compensator play important work in terms of the long-term normal operation of pipeline is ensured With.
In the prior art, industry in most widely used pipeline compensator be FlexbleJoint, its mainly by bellows, The annexes such as end pipe, support, flange, conduit form.Using effective dilatation of bellows when FlexbleJoint works, to absorb Pipeline, conduit, container etc. by the reason such as expand with heat and contract with cold and caused change in size.But the price of bellows is universal higher, and And when pipeline is the larger non-standard of internal diameter, the parts such as flange being related to are both needed to carry out particularly customized, cause large-scale work Industry pipeline link cost remains high.
Utility model content
The utility model provides a kind of pipeline compensator to solve technical problem.The pipeline compensator is set by its structure Meter, pipeline is can compensate for by the reason such as expanding with heat and contract with cold and caused change in size, and the utility model can be realized and gathered materials on the spot, Effectively reduce the cost of pipeline connection.
A kind of pipeline compensator, for the connection of two pipes, described two pipes are managed for the first pipe and second, first pipe Inwall is embedded to be welded with connecting tube, and described connecting tube extends to the second pipe, and grafting enters in the second pipe pipe;The pipeline compensator Also include deformation-compensated plate, the deformation-compensated plate includes the first deformation-compensated plate with the welding of the first pipe port, and is welded on The second deformation-compensated plate at second pipe port;The first deformation-compensated plate is with being connected pipe outer wall welding;Described second Compensating plate is close to the outer wall of connecting tube.
Preferably, in addition to sealing plate;The sealing plate is welded on the described first deformation-compensated plate and second deformation-compensated Between plate.
Preferably, the connecting tube, the first deformation-compensated plate, the first pipe can be used as welding overall, along parallel to second The direction movement of pipe.
Preferably, the connecting tube one or it is welded to form successively by multiple connection sheets.
Preferably, the connecting tube includes support tube and reinforced pipe;The support tube is embedded in the first pipe, the support Pipe one end is welded with the first pipe, and the other end is close to the first deformation-compensated plate;Described reinforced pipe one end is embedded to be welded on support tube Interior, other end grafting enters in the second pipe, and the outer wall of the outer wall of the reinforced pipe and the described first deformation-compensated plate welds, and described The outer wall of second deformation-compensated plate is close to.
Preferably, the described first deformation-compensated plate is circular ring.The second deformation-compensated plate is circular ring.
Preferably, first pipe, the second pipe, connecting tube, the first deformation-compensated plate, the second deformation-compensated plate, sealing plate The material used is identical, is steel plate.
The beneficial effects of the utility model are:A kind of pipeline compensator provided by the utility model, for the connection of two pipes, Two described pipes are the first pipe and the second pipe.The inwall of first pipe is embedded to be welded with connecting tube, and connecting tube extends to the second pipe inserts Access in the second pipe pipe;Also include deformation-compensated plate and sealing plate, deformation-compensated plate includes first with the welding of the first pipe port Deformation-compensated plate, and the second deformation-compensated plate being welded at the second pipe port;First deformation-compensated plate is with being connected pipe outer wall weldering Connect;Second compensating plate is close to the outer wall of connecting tube;Sealing plate is welded on the described first deformation-compensated plate and second deformation-compensated Between plate.Pipeline compensator provided by the utility model enables connecting tube, the first pipe, the first deformation-compensated plate whole as one Body moves left and right.When the first pipe, the second pipe due to expand with heat and contract with cold and internal diameter become big when, it is connecting tube, the first pipe, first deformation-compensated Plate will be used as overall be moved to the left;When being integrally moved to the left more, the part that connecting tube inserts the second pipe also will be more;This When, sealing plate, first it is deformation-compensated change, the second deformation-compensated plate due to by first pipe and the second pipe extruding and clamp.When Due to expanding with heat and contract with cold and internal diameter change hour, connecting tube, the first pipe, the first deformation-compensated plate will be used as overall for first pipe, the second pipe Move right;When integrally moving right more, the part that connecting tube inserts the second pipe also will be fewer;Now, sealing plate, first It is deformation-compensated change, the second deformation-compensated plate due to by first pipe and the second pipe pulling force and deform expansion.Therefore, sealing plate, The structure design of first compensating plate and the second compensating plate, it instead of in traditional design using the parts such as bellows, flange composition Ripple compensation pipe, realize that pipeline is caused by temperature change expands with heat and contract with cold for compensation.Also, pipeline provided by the utility model Compensator structure design is simple, and when industrial pipeline causes pipe diameter oversized because of purposes difference, pipeline compensator can lead to Cross gather materials on the spot field fabrication complete, the element size such as flange, bellows is not limited in by traditional handicraft, effectively reduce into This.
Brief description of the drawings
, below will be to embodiment in order to illustrate more clearly of the utility model embodiment or technical scheme of the prior art Or the required accompanying drawing used is briefly described in description of the prior art, it should be apparent that, drawings in the following description are only It is embodiment of the present utility model, for those of ordinary skill in the art, on the premise of not paying creative work, also Other accompanying drawings can be obtained according to the accompanying drawing of offer.
Fig. 1 is the profile of the pipeline compensator disclosed in the utility model embodiment.
Fig. 2 is the partial enlarged drawing at Figure 1A.
Embodiment
In order that those skilled in the art more fully understand the technical scheme in the application, it is real below in conjunction with the application The accompanying drawing in example is applied, the technical scheme in the embodiment of the present application is clearly and completely described, it is clear that described implementation Example only some embodiments of the present application, rather than whole embodiments.
Based on the embodiment in the application, those of ordinary skill in the art are obtained under the premise of creative work is not made The every other embodiment obtained, it should all belong to the scope of the application protection.
Referring to Fig. 1 and Fig. 2, Fig. 1 provides a kind of specific embodiment of pipeline compensator of the utility model, wherein, Fig. 1 is The profile of pipeline compensator disclosed in the utility model embodiment, Fig. 2 are the partial enlarged drawing at Figure 1A.
As shown in figure 1, the utility model provides a kind of pipeline compensator, the pipeline compensator is used for two pipes of left and right Connection, two pipe is the first pipe 11 positioned at right side and the second pipe 12 positioned at left side.
In traditional technique, it is most widely used that and is attached between two pipes using ripple compensation pipe.Ripple is mended Repaying pipe mainly includes the annexes such as bellows, flange, because bellows manufacture craft is complex, so cost is high.And in face During to industrial pipeline connectivity problem, industrial pipeline has special want often according to the difference of industrial use to the internal diameter of pipeline Ask, cause the annexes such as the bellows in the ripple compensation pipe supporting with it, flange also to turn into non-standard component, need particularly customized.This And one of the reason for causing industrial pipeline link cost high.
In this programme, connecting tube 2 is embedded with the inwall of first pipe 11, the connecting tube 2 is interior with the first pipe 11 Wall welds;Described connecting tube 2 extends to the second pipe 12, and grafting enters in the second pipe 12 manages.Pipeline compensator described in this programme Also include deformation-compensated plate 3 and sealing plate 4, the deformation-compensated plate include with it is the first of the welding of the port of the first pipe 11 deformation-compensated Plate 31, and the second deformation-compensated plate 32 being welded at the port of the second pipe 12;The first deformation-compensated plate 31 is with being connected The outer wall of pipe 2 welds;The second deformation-compensated plate 32 is close to the outer wall of connecting tube 2.
Fig. 2 is refer to, in the present embodiment, circle is all provided with the first deformation-compensated 31 and second deformation-compensated plate 32 of plate Hole, the diameter of circular hole is roughly the same with the external diameter of connecting tube 2, wherein, the port weldering of the first deformation-compensated pipe 11 of plate 31 and first Connect, the second deformation-compensated plate 32 is close to the outer wall of connecting tube 2.At B in Fig. 2, show the second deformation-compensated plate 32 with connecting Annexation between the outer wall of adapter 2.
In order to improve the air-tightness of whole device, it is further preferred that becoming in the described first deformation-compensated plate 31 and second Sealing plate 4 is welded between shape compensating plate 32.
It can be seen that connecting tube 2 is welded to connect with the inwall of the first pipe 11 in this programme, the first deformation-compensated plate 31 and connecting tube 2 outer wall welding, the second deformation-compensated port of 32 and second pipe of plate 12 welding, the second deformation-compensated plate 32 and the outer wall of connecting tube 2 It is close to, sealing plate 4 has been welded to connect between the first deformation-compensated 31 and second deformation-compensated plate 32 of plate.Such a structure design and welding Connected mode so that connecting tube 2, the first pipe 11, the first deformation-compensated plate 31 can move left and right as an entirety.When the first pipe 11st, the second pipe 12 due to expand with heat and contract with cold and internal diameter become it is big when, connecting tube 2, the first pipe 11, the first deformation-compensated plate 31 will be used as whole Body is moved to the left;When being integrally moved to the left more, the part that connecting tube 2 inserts the second pipe 12 also will be more;Now, sealing plate 4th, first it is deformation-compensated change, the second deformation-compensated plate 32 is clamped due to the extruding by the first pipe 11 and the second pipe 12.When Due to expanding with heat and contract with cold and internal diameter change hour, connecting tube 2, the first pipe 11, the first deformation-compensated plate 31 will be made for one pipe 11, the second pipe 12 Moved right to be overall;When integrally moving right more, the part that connecting tube 2 inserts the second pipe 12 also will be fewer;Now, it is close Shrouding 4, first is deformation-compensated to be changed, the second deformation-compensated plate 32 by the pulling force of the first pipe 11 and the second pipe 12 due to being deformed expansion .Therefore, the structure design of sealing plate 4, the first compensating plate and the second compensating plate, instead of in traditional design using bellows, The ripple compensation pipe of the parts such as flange composition, is realized to pipeline caused compensation expanded with heat and contract with cold by temperature change.
In the present embodiment, during the practical operation of large scale industry pipeline connection, gathered materials on the spot to realize, reduce material Cost, the first pipe 11, the second pipe 12, deformation-compensated plate 3, sealing plate 4 can be made using identical steel plate Site Welding Into.In this programme, described connecting tube 2 can be welded to form successively by one or by multiple connection sheets.In practice operates, Because the diameter of connecting tube 2 is less than the diameter of the first pipe 11 and the second pipe 12, so the material for making pipeline can be used directly, will It cuts away a part along pipe side wall makes its diameter be welded into required connecting tube 2 again after reducing.
It can be seen that using the pipeline compensator described in the present embodiment, its is simple in construction, without using bellows, flange etc. zero Part, therefore whether be not that standard component is limited by line size;This structure can also be used directly in manufacturing process simultaneously The material of pipeline in itself is made, realization is gathered materials on the spot, cost-effective.
In the present embodiment, in order to strengthen the bonding strength of the first pipe 11 and the second pipe 12, connecting tube 2 is designed to by propping up Stay tube 21 and reinforced pipe 22 form.The support tube is embedded in the first pipe 11, and port one end of the support tube is welded on In one pipe 11, the other end is close to the first deformation-compensated plate;Described one end of reinforced pipe 22 is embedded to be welded in support tube, the other end Grafting enters in the second pipe 12, and the outer wall of the outer wall of the reinforced pipe 22 and the described first deformation-compensated plate welds, with described second The outer wall of deformation-compensated plate is close to.
A kind of pipeline compensator provided by the utility model is described in detail above.It is used herein specifically Individual example is set forth to principle of the present utility model and embodiment, and the explanation of above example is only intended to help and understands this The method and its core concept of utility model.It should be pointed out that for those skilled in the art, do not departing from On the premise of the utility model principle, some improvement and modification can also be carried out to the utility model, these are improved and modification Fall into the protection domain of the utility model claims.

Claims (8)

1. a kind of pipeline compensator, for the connection of two pipes, described two pipes are the first pipe and the second pipe, it is characterised in that:Institute State the first pipe inwall it is embedded be welded with connecting tube, described connecting tube extends to the second pipe, and grafting enters in the second pipe pipe;Also wrap Deformation-compensated plate is included, the deformation-compensated plate includes the first deformation-compensated plate with the welding of the first pipe port, and is welded on described The second deformation-compensated plate at second pipe port;The first deformation-compensated plate is with being connected pipe outer wall welding;Second compensation Plate is close to the outer wall of connecting tube.
A kind of 2. pipeline compensator as claimed in claim 1, it is characterised in that:Also include sealing plate;The sealing plate weld Between the described first deformation-compensated plate and the second deformation-compensated plate.
A kind of 3. pipeline compensator as claimed in claim 2, it is characterised in that:The connecting tube, the first deformation-compensated plate, One pipe can be used as welding overall, be moved along the direction parallel to the second pipe.
A kind of 4. pipeline compensator as claimed in claim 1, it is characterised in that:The connecting tube one or by multiple connection sheets It is welded to form successively.
A kind of 5. pipeline compensator as described in Claims 1-4 is any, it is characterised in that:The connecting tube includes support tube And reinforced pipe;The support tube is embedded in the first pipe, and described support tube one end is welded with the first pipe, the other end and the first deformation Compensating plate is close to;Described reinforced pipe one end is embedded to be welded in support tube, and other end grafting enters in the second pipe, the reinforced pipe The outer wall of outer wall and the described first deformation-compensated plate welds, and is close to the outer wall of the described second deformation-compensated plate.
A kind of 6. pipeline compensator as claimed in claim 5, it is characterised in that:The first deformation-compensated plate is around described The circular ring of first pipe port.
A kind of 7. pipeline compensator as claimed in claim 5, it is characterised in that:The second deformation-compensated plate is around described The circular ring of second pipe port.
A kind of 8. pipeline compensator as claimed in claim 5, it is characterised in that:First pipe, the second pipe, connecting tube, The material that one deformation-compensated plate, the second deformation-compensated plate, sealing plate use is identical, is steel plate.
CN201720644118.7U 2017-06-05 2017-06-05 A kind of pipeline compensator Active CN206958478U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720644118.7U CN206958478U (en) 2017-06-05 2017-06-05 A kind of pipeline compensator

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720644118.7U CN206958478U (en) 2017-06-05 2017-06-05 A kind of pipeline compensator

Publications (1)

Publication Number Publication Date
CN206958478U true CN206958478U (en) 2018-02-02

Family

ID=61378242

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720644118.7U Active CN206958478U (en) 2017-06-05 2017-06-05 A kind of pipeline compensator

Country Status (1)

Country Link
CN (1) CN206958478U (en)

Similar Documents

Publication Publication Date Title
CN105240640B (en) A kind of Control rod drive line displacement compensation device, shaping dies and its manufacturing process
CN105178443A (en) Bolt connecting joint suitable for single-layer latticed shell with rectangular steel pipes
CN201129586Y (en) Polyethylene, steel bushing flange and pipeline connecting structure
CN206958478U (en) A kind of pipeline compensator
CN104315277A (en) Pipeline connector
CN102287589A (en) Steel plastic composite pipe for spirally-wound steel wire reinforcing body and pipe network
CN201428888Y (en) Pipeline communicating part
CN204127525U (en) A kind of pipe jointer
CN105546260A (en) Metal compensator for reinforced circulating fluid bed boiler
CN210219001U (en) Steel 90-degree r-shaped tee joint
CN210118565U (en) Flanged steel joint with inclined beam divergence
CN202597945U (en) Welding connection structure of corrugated pipe and joints
CN215763880U (en) Double-flange bent pipe convenient to butt joint dismouting
CN207777787U (en) A kind of recoverable compound pipeline complex pipeline
CN204986035U (en) Confession, fixed festival of return water be anchor block as an organic whole even
CN207945401U (en) The FlexbleJoint of end flanging positioning structure
CN205798062U (en) Nuclear boiler maintaining item bending tool
CN205781651U (en) Compound reparation pipeline compensator
CN205173838U (en) Pipeline under pressure straight line and little angle compensation of expansion and contraction device
CN219388992U (en) Ring clamp sealing type corrugated compensation connection metal pipe fitting
CN111075998A (en) Continuous fiber prepreg tape reinforced pipe end flanging piece and using method thereof
CN210739698U (en) Rectangular metal corrugated expansion joint
CN204852694U (en) Compound pipe is moulded to corrugated steel
CN109519636A (en) Electric heating melting compound pipeline complex pipeline compensator
CN210151923U (en) Four-support-position steel node with flange

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant