Prior art keywords
pipeline
elbow
flange
conduit assembly
face
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201720912331.1U
Other languages
Chinese (zh)
Inventor
张福义
郝培波
张恺
崔世华
杨洋洋
张森田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China National Offshore Oil Corp CNOOC
CNOOC Petrochemical Engineering Co Ltd
COOEC Enpal Engineering Co Ltd
CNOOC Oil and Petrochemicals Co Ltd
Original Assignee
China National Offshore Oil Corp CNOOC
COOEC Enpal Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China National Offshore Oil Corp CNOOC, COOEC Enpal Engineering Co Ltd filed Critical China National Offshore Oil Corp CNOOC
Priority to CN201720912331.1U priority Critical patent/CN206958455U/en
Application granted granted Critical
Publication of CN206958455U publication Critical patent/CN206958455U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model discloses a kind of chemical plant installations and its conduit assembly and elbow, conduit assembly to include:First and second pipelines;First and second flanges, first flange are connected with the first end of the first pipeline, and second flange is connected with the first end of second pipe;Two the first elbows, the first end face of each first elbow are configured to flange face, and each first elbow has runner, and the first end face of first elbow is connected with first flange, and the first end face of another the first elbow is connected with second flange;Third and fourth pipeline, the first end of the 3rd pipeline are connected with the second opening of first elbow, and the first end of the 4th pipeline is open with the second of another the first elbow to be connected, and at least one in the third and fourth pipeline is provided with medicament inlet;And valve, the inlet and outlet of valve are connected with the second end of the third and fourth pipeline respectively.According to the conduit assembly of the utility model embodiment has the advantages that to be easy to transformation, improvement cost is low, downtime is short.

Description

Conduit assembly and its elbow and the chemical plant installations with the conduit assembly
Technical field
Chemical machinery field is the utility model is related to, in particular it relates to which conduit assembly, further relates to the curved of the conduit assembly Head, and the chemical plant installations with the conduit assembly.
Background technology
In the chemical plant installations run (such as petrochemical plant), because transformation process requirement is, it is necessary in work Increase medicament inlet on skill pipeline.Because the medium of process pipe conveying is inflammable and explosive oil gas, therefore increase medicament note The program of entrance is typically:Device is first stopped work, and then thoroughly purges the combustible medium in clean process pipe, then process pipe Perforate welding medicament inlet is carried out, last process pipeline carries out Welding Testing and pressure test.
But this method has the disadvantage that:Process pipe purging expends time and manpower, increases disposal of pollutants, and construction is completed After to test and test at the scene, waste time and energy, increase device downtime.
Another solution is that the valve on process pipe is dismantled, and on both sides, flange sets up companion flange and elbow (i.e. former flange-newly-increased companion flange-elbow-introduction pipe-former valve-introduction pipe-elbow-newly-increased companion flange-former method It is blue), then valve is installed on the pipeline of extraction again.But this scheme has the defects of installation length is inadequate, i.e., one Two flanges and elbow are not enough installed in the length of individual valve.
Utility model content
Present invention design and invention difficult point simultaneously do not lie in the brand-new conduit assembly with medicament inlet of setting. Present invention is conceived and invention difficult point is:Less transformation is carried out to existing conduit assembly, i.e., by existing pipe The limitation of the structure of road component, it becomes possible in the increase setting medicament inlet on existing conduit assembly.
The problem of the purpose of this utility model is to overcome prior art to exist, there is provided conduit assembly and its elbow and Chemical plant installations with the conduit assembly, the conduit assembly have the advantages of being easy to low transformation, improvement cost, downtime.
To achieve these goals, the utility model first aspect provides a kind of conduit assembly, and the conduit assembly includes: First pipeline and second pipe;First flange and second flange, the first flange are connected with the first end of first pipeline, The second flange is connected with the first end of the second pipe;Two the first elbows, the first end of each first elbow Surface construction is flange face, and each first elbow has runner, and the first of the runner is opened in the first end face On, the second of the runner is opened on the side face of first elbow, the first end face of first elbow with The first flange is connected, and the first end face of another first elbow is connected with the second flange;3rd pipeline and Four pipelines, the first end of the 3rd pipeline are connected with the second opening of first elbow, and the of the 4th pipeline One end is connected with the second opening of the first elbow another described, wherein in the 3rd pipeline and the 4th pipeline at least One is provided with medicament inlet;And valve, the import of the valve and one in the 3rd pipeline and the 4th pipeline The second individual end is connected, outlet and another the second end phase in the 3rd pipeline and the 4th pipeline of the valve Even.
According to the conduit assembly of the utility model embodiment by setting two be connected with first flange and second flange First elbow, i.e., two the first elbows are set in former valvular opening position, so as to set the 3rd pipeline of extraction and the Four pipelines, medicament inlet is set to install on valve and at least one in the 3rd pipeline and the 4th pipeline.
Thus during increase sets medicament inlet, not only without in original pipeline (the first pipeline and second Pipeline) on be open and welded operation, and without be purged to original pipeline and replacement operator.In addition, medicament is noted Manufacture, inspection, the experiment of entrance can be carried out in job shop, so as to reduce the time of device shut-down, to save into Originally, increase economic benefit.
Therefore, according to the conduit assembly of the utility model embodiment have be easy to transformation, improvement cost is low, downtime is short The advantages of, without being open and being welded operation on original pipeline, without original pipeline being purged and being replaced behaviour Make.
Preferably, the runner of each first elbow is L-shaped.
Preferably, the first end face of first elbow is connected by multiple studding bolts with the first flange, The first end face of another first elbow is connected by multiple studding bolts with the second flange.
Preferably, the first end of the 3rd pipeline is welded on the side face of first elbow, the 4th pipe The first end in road is welded on the side face of another first elbow.
Preferably, each in the 3rd pipeline and the 4th pipeline includes lower horizontal segment, vertical section and upper water Flat section, the second opening of the first end of the lower horizontal segment and first elbow are connected, the lower end of the vertical section with it is described Second end of lower horizontal segment is connected, and the upper end of the vertical section is connected with the first end of the upper horizontal segment, wherein the valve Import be connected with second end of one in the upper horizontal segment of the 3rd pipeline and the upper horizontal segment of the 4th pipeline, institute State the outlet of valve and another second in the upper horizontal segment of the 3rd pipeline and the upper horizontal segment of the 4th pipeline End is connected.
Preferably, the conduit assembly further comprises:Medicament ascending pipe;Threeway, the first end of the threeway with it is described The upper end of the vertical section of 3rd pipeline is connected, the second end of the threeway and the first end phase of the upper horizontal segment of the 3rd pipeline Even, the 3rd end of the threeway is connected with the lower end of the medicament ascending pipe;With the second elbow, the first end of second elbow It is connected with the upper end of the vertical section of the 4th pipeline, the second end of second elbow and the upper horizontal segment of the 4th pipeline First end be connected.
Preferably, the lower horizontal segment and the upper horizontal segment are into predetermined angular.
Preferably, the predetermined angular be more than or equal to 15 degree and be less than etc. 30 degree.
The utility model second aspect provides elbow, and the first end face of the elbow is configured to flange face, the elbow tool Have runner, the first of the runner is opened in the first end face, the second of the runner be opened in it is described curved On the side face of head.
The function of elbow and flange is integrated with according to elbow of the present utility model.
The utility model third aspect provides chemical plant installations, and the chemical plant installations is included according to the utility model first aspect Described conduit assembly.
Brief description of the drawings
Fig. 1 is the structural representation according to the conduit assembly of the utility model embodiment;
Fig. 2 is Fig. 1 sectional view along A-A directions;
Fig. 3 is Fig. 1 view along B-B directions;
Fig. 4 is the partial structural diagram according to the conduit assembly of the utility model embodiment;
Fig. 5 is the structural representation according to the first elbow of the conduit assembly of the utility model embodiment.
Embodiment
Embodiment of the present utility model is described below in detail, the example of the embodiment is shown in the drawings.Below by The embodiment being described with reference to the drawings is exemplary, it is intended to for explaining the utility model, and it is not intended that new to this practicality The limitation of type.
Present invention design and invention difficult point simultaneously do not lie in the brand-new conduit assembly with medicament inlet of setting. Present invention is conceived and invention difficult point is:Less transformation is carried out to existing conduit assembly, i.e., by existing pipe The limitation of the structure of road component, it becomes possible in the increase setting medicament inlet on existing conduit assembly.
Below with reference to the accompanying drawings conduit assembly 10 according to the utility model embodiment is described.As Figure 1-Figure 5, according to this The conduit assembly 10 of utility model embodiment includes the first pipeline 111, second pipe 112, first flange 121, second flange 122nd, two the first elbows 130, the 3rd pipeline 140a, the 4th pipeline 140b and valve 150.
First flange 121 is connected with the first end of the first pipeline 111, second flange 122 and the first end of second pipe 112 It is connected.The first end face 131 of each first elbow 130 is configured to flange face, and each first elbow 130 has runner 132, runner 132 the first opening 1321 is opened in the first end face 131 of the first elbow 130, and the second opening 1322 of runner 132 is opened in On the side face 133 of first elbow 130.The first end face 131 of one the first elbow 130 is connected with first flange 121, and another The first end face 131 of one elbow 130 is connected with second flange 122.In other words, first elbow 130 and the phase of first flange 121 Even, another first elbow 130 is connected with second flange 122.
3rd pipeline 140a first end is connected with the second opening 1322 of first elbow 130, the 4th pipeline 140b The second opening 1322 of first end and another the first elbow 130 be connected.Wherein, the 3rd pipeline 140a and the 4th pipeline 140b In at least one be provided with medicament inlet.The import of valve 150 and one in the 3rd pipeline 140a and the 4th pipeline 140b The second individual end is connected, outlet and another the second end phase in the 3rd pipeline 140a and the 4th pipeline 140b of valve 150 Even.
Existing conduit assembly includes the first pipeline 111, second pipe 112, first flange 121, second flange 122 and valve Door 150, the both ends of valve 150 are provided with flange, two flanges of valve 150 respectively with first flange 121 and the phase of second flange 122 Even.
When in increase setting medicament inlet on existing conduit assembly, existing conduit assembly can be changed Make, to obtain the conduit assembly 10 according to the utility model embodiment.Specifically, can be by valve 150 from first flange 121 and second flange 122 on disassemble, then make the first end face 131 (flange face) of first elbow 130 and the first method Orchid 121 is connected and the first end face 131 (flange face) of another the first elbow 130 is connected with second flange 122.Then, will 3rd pipeline 140a be connected on the side face 133 of first elbow 130 and by the 4th pipeline 140b be connected to another first On the side face 133 of elbow 130, to make the 3rd pipeline 140a be connected with the runner 132 of first elbow 130 and to make the 4th Pipeline 140b connects with the runner 132 of another the first elbow 130.Finally, manage the pipeline 140a of valve 150 and the 3rd and the 4th Road 140b is connected.
Thus, material can flow successively through the first pipeline 111, first flange 121, the first elbows 130, the 3rd pipelines 140a, valve 150, the 4th pipeline 140b, another first elbow 130, second flange 122 and second pipe 112.In addition, thing The flow direction of material can also be opposite with above-mentioned flow direction.
Existing elbow is totally different from according to the first elbow 130 of the conduit assembly 10 of the utility model embodiment.Tool For body, the first elbow 130 has flange face, i.e., the first end face 131 of the first elbow 130 is flange face, and existing elbow All do not have flange face.Therefore, the first elbow 130 can also be considered as the flange with nonlinear runner.Existing method Blue runner is all linear, i.e., the runner of existing flange is all axially extending along its.That is, the first elbow 130 collects Into the function of elbow and flange.Thus two the first elbows 130 are equivalent to existing two elbows and two valves, and two Total installation length of first elbow 130 is less than the length of the valve of identical nominal diameter, so as in the length of a valve Two the first elbows 130 of interior installation.
According to the conduit assembly 10 of the utility model embodiment by setting and first flange 121 and the phase of second flange 122 Two the first elbows 130 even, i.e., two the first elbows 130 are set in former valvular opening position, drawn so as to set The 3rd pipeline 140a and the 4th pipeline 140b, to install valve 150 and in the 3rd pipeline 140a and the 4th pipeline 140b It is at least one it is upper setting medicament inlet.
Thus during increase sets medicament inlet, not only without in original pipeline (the first pipeline 111 and the Two pipelines 112) on be open and welded operation, and without be purged to original pipeline and replacement operator.In addition, medicine Manufacture, inspection, the experiment of agent inlet can be carried out in job shop, so as to reduce the time of device shut-down, to save About cost, increase economic benefit.
Therefore, had according to the conduit assembly 10 of the utility model embodiment be easy to transformation, improvement cost is low, downtime The advantages that short, without being open and being welded operation on original pipeline, without original pipeline is purged and replaced Operation.
As Figure 1-Figure 5, in some embodiments of the utility model, conduit assembly 10 can include the first pipeline 111st, second pipe 112, first flange 121, second flange 122, two the first elbows 130, the 3rd pipeline 140a, the 4th pipelines 140b and valve 150.
First flange 121 can be by known methods with the first pipeline 111 first end be connected, second flange 122 First end that can be by known methods with second pipe 112 is connected.
As shown in figure 4, the first end face 131 of first elbow 130 can pass through multiple methods of studding bolt 170 and first Orchid 121 is connected, and the first end face 131 of another the first elbow 130 can pass through multiple studding bolts 170 and second flange 122 It is connected.In other words, first elbow 130 can be connected by multiple studding bolts 170 with first flange 121, and another One elbow 130 can be connected by multiple studding bolts 170 with second flange 122.
Preferably, multiple studding bolts 170 can be along the circumference of first elbow 130 and the circumference of first flange 121 Equally spacedly set.It is possible thereby to first elbow 130 and first flange 121 are installed together more securely.It is multiple Studding bolt 170 can equally spacedly be set along the circumference of another the first elbow 130 and the circumference of second flange 122.Thus Another first elbow 130 and second flange 122 can be installed together more securely.
First opening 1321 of runner 132 is opened in the first end face 131 of the first elbow 130.One the first elbow 130 The first opening of runner 132 1321 can be connected by first flange 121 with the first pipeline 111, another first elbow 130 The first opening of runner 132 1321 can be connected by second flange 122 with second pipe 112.
As shown in Figure 4 and Figure 5, the runner 132 of each first elbow 130 can be L-shaped.That is, each first is curved First 130 runner 132 can include the axially extending axial direction part along the first elbow 130 and the radial direction along the first elbow 130 Radially extending section, the axial direction part is connected with the radial section.It is possible thereby to make the structure of the first elbow 130 more reasonable.
Second opening 1322 of runner 132 is opened on the side face 133 of the first elbow 130.At one of the present utility model In embodiment, the 3rd pipeline 140a first end can be welded on the side face 133 (periphery wall) of first elbow 130, the Four pipeline 140b first end can be welded on the side face 133 (periphery wall) of another the first elbow 130.Wherein, one Second opening 1322 of one elbow 130 can be positioned at the of the inner side of the 3rd pipeline 140a first ends or the 3rd pipeline 140a One end can be connected with the edge of the second opening 1322 of first elbow 130, the second opening of another the first elbow 130 1322 can positioned at the inner side of the 4th pipeline 140b first end or the 4th pipeline 140b first end can with another the The edge of second opening 1322 of one elbow 130 is connected.
As shown in Figure 1-Figure 3, in some examples of the present utility model, the 3rd pipeline 140a can include lower horizontal segment 141a, vertical section 142a and upper horizontal segment 143a.Lower horizontal segment 141a first end can be with the second of first elbow 130 Opening 1322 is connected, and vertical section 142a lower end can be connected with lower horizontal segment 141a the second end, vertical section 142a upper end It can be connected with upper horizontal segment 143a first end.
4th pipeline 140b can include lower horizontal segment 141b, vertical section 142b and upper horizontal segment 143b.Lower horizontal segment 141b first end can be connected with the second of another the first elbow 130 the opening 1322, and vertical section 142b lower end can be with Lower horizontal segment 141b the second end is connected, and vertical section 142b upper end can be connected with upper horizontal segment 143b first end.
Wherein, the import of valve 150 and the 3rd pipeline 140a upper horizontal segment 143a and the 4th pipeline 140b upper level Second end of one in section 143b is connected, outlet and the pipes of the 3rd pipeline 140a upper horizontal segment 143a and the 4th of valve 150 Another the second end in road 140b upper horizontal segment 143b is connected.It is possible thereby to make the structure more adduction of conduit assembly 10 Reason.
3rd pipeline 140a lower horizontal segment 141a, vertical section 142a and upper horizontal segment 143a's and the 4th pipeline 140b Medicament inlet can be provided with least one in lower horizontal segment 141b, vertical section 142b and upper horizontal segment 143b.
As shown in figure 1, in an example of the present utility model, conduit assembly 10 may further include medicament ascending pipe 161st, the elbow 163 of threeway 162 and second.The first end of threeway 162 can be with the 3rd pipeline 140a vertical section 142a upper end It is connected, the second end of threeway 162 can be connected with the 3rd pipeline 140a upper horizontal segment 143a first end, and the of threeway 162 Three ends can be connected with the lower end of medicament ascending pipe 161.The first end of second elbow 163 can be vertical with the 4th pipeline 140b Section 142b upper end is connected, and the second end of the second elbow 163 can be with the 4th pipeline 140b upper horizontal segment 143b first end It is connected.It is possible thereby to make the structure of conduit assembly 10 more reasonable.
Preferably, switch valve can be provided with medicament ascending pipe 161.
In a specific example of the present utility model, the 3rd pipeline 140a lower horizontal segment 141a and the 3rd pipeline 140a Upper horizontal segment 143a can be into predetermined angular, the 4th pipeline 140b lower horizontal segment 141b and the 4th pipeline 140b upper level Section 143b can also be into the predetermined angular.It is possible thereby to make the structure of conduit assembly 10 more reasonable.
That is, the 3rd pipeline 140a lower horizontal segment 141a and the 4th pipeline 140b lower horizontal segment 141b can position In on same straight line, the 3rd pipeline 140a upper horizontal segment 143a and the 4th pipeline 140b upper horizontal segment 143b can also be located at On same straight line.Wherein, the 3rd pipeline 140a lower horizontal segment 141a can be not parallel to the 3rd pipeline 140a upper horizontal segment 143a, the 4th pipeline 140b lower horizontal segment 141b can also be not parallel to the 4th pipeline 140b upper horizontal segment 143b.
Preferably, the predetermined angular can be more than or equal to 15 degree and be less than etc. 30 degree.It is possible thereby to make conduit assembly 10 Structure is more reasonable.
The utility model additionally provides chemical plant installations.Included according to the chemical plant installations of the utility model embodiment according to this reality With the conduit assembly 10 of new above-described embodiment.
Had according to the chemical plant installations of the utility model embodiment be easy to transformation, that improvement cost is low, downtime is short etc. is excellent Point, without being open and being welded operation on original pipeline, without being purged to original pipeline and replacement operator.
In description of the present utility model, it is to be understood that term " " center ", " longitudinal direction ", " transverse direction ", " length ", " width Degree ", " thickness ", " on ", " under ", "front", "rear", "left", "right", " vertical ", " level ", " top ", " bottom " " interior ", " outer ", " suitable The orientation or position relationship of the instruction such as hour hands ", " counterclockwise ", " axial direction ", " radial direction ", " circumference " are based on orientation shown in the drawings Or position relationship, be for only for ease of description the utility model and simplify and describe, rather than instruction or imply signified device or Element must have specific orientation, with specific azimuth configuration and operation, therefore it is not intended that to limit of the present utility model System.
In addition, term " first ", " second " are only used for describing purpose, and it is not intended that instruction or hint relative importance Or the implicit quantity for indicating indicated technical characteristic.Thus, define " first ", the feature of " second " can be expressed or Implicitly include at least one this feature.In description of the present utility model, " multiple " are meant that at least two, such as two It is individual, three etc., unless otherwise specifically defined.
In the utility model, unless otherwise clearly defined and limited, term " installation ", " connected ", " connection ", " Gu It is fixed " etc. term should be interpreted broadly, for example, it may be fixedly connected or be detachably connected, or integrally;Can be Mechanically connect or electrically connect or can communicate each other;Can be joined directly together, the indirect phase of intermediary can also be passed through Even, can be two element internals connection or two elements interaction relationship, limited unless otherwise clear and definite.For this For the those of ordinary skill in field, concrete meaning of the above-mentioned term in the utility model can be understood as the case may be.
In the utility model, unless otherwise clearly defined and limited, fisrt feature is "above" or "below" second feature Can be that the first and second features directly contact, or the first and second features pass through intermediary mediate contact.Moreover, first is special Sign second feature " on ", " top " and " above " can be fisrt feature directly over second feature or oblique upper, or only Represent that fisrt feature level height is higher than second feature.Fisrt feature second feature " under ", " lower section " and " below " can be with Be fisrt feature immediately below second feature or obliquely downward, or be merely representative of fisrt feature level height and be less than second feature.
In the description of this specification, reference term " one embodiment ", " some embodiments ", " example ", " specifically show The description of example " or " some examples " etc. means specific features, structure, material or the spy for combining the embodiment or example description Point is contained at least one embodiment or example of the present utility model.In this manual, to the schematic table of above-mentioned term State and be necessarily directed to identical embodiment or example.Moreover, specific features, structure, material or the feature of description can be with Combined in an appropriate manner in any one or more embodiments or example.In addition, in the case of not conflicting, this area Technical staff the different embodiments or example and the feature of different embodiments or example described in this specification can be entered Row combines and combination.
Although embodiment of the present utility model has been shown and described above, it is to be understood that above-described embodiment is Exemplary, it is impossible to it is interpreted as to limitation of the present utility model, one of ordinary skill in the art is in the scope of the utility model It is interior above-described embodiment to be changed, changed, replaced and modification.

Claims (10)

  1. A kind of 1. conduit assembly, it is characterised in that including:
    First pipeline and second pipe;
    First flange and second flange, the first flange are connected with the first end of first pipeline, the second flange with The first end of the second pipe is connected;
    Two the first elbows, the first end face of each first elbow are configured to flange face, and each first elbow has Runner, the first of the runner is opened in the first end face, and the second of the runner is opened in described first On the side face of elbow, the first end face of first elbow is connected with the first flange, another described first elbow First end face be connected with the second flange;
    3rd pipeline and the 4th pipeline, the first end of the 3rd pipeline are connected with the second opening of first elbow, The first end of 4th pipeline is connected with the second opening of the first elbow another described, wherein the 3rd pipeline and described At least one in 4th pipeline is provided with medicament inlet;With
    Valve, the import of the valve is connected with second end of one in the 3rd pipeline and the 4th pipeline, described The outlet of valve is connected with another the second end in the 3rd pipeline and the 4th pipeline.
  2. 2. conduit assembly according to claim 1, it is characterised in that the runner of each first elbow is L-shaped.
  3. 3. conduit assembly according to claim 1, it is characterised in that the first end face of first elbow passes through more Individual studding bolt is connected with the first flange, and the first end face of another first elbow passes through multiple studding bolts and institute Second flange is stated to be connected.
  4. 4. conduit assembly according to claim 1, it is characterised in that the first end of the 3rd pipeline is welded on an institute On the side face for stating the first elbow, the first end of the 4th pipeline is welded on the side face of another first elbow.
  5. 5. conduit assembly according to claim 1, it is characterised in that every in the 3rd pipeline and the 4th pipeline One includes lower horizontal segment, vertical section and upper horizontal segment, and the first end of the lower horizontal segment is opened with the second of first elbow Mouth is connected, and the lower end of the vertical section is connected with the second end of the lower horizontal segment, the upper end of the vertical section and the upper water The first end of flat section is connected, wherein the upper horizontal segment of the import of the valve and the 3rd pipeline and the 4th pipeline is upper Second end of one in horizontal segment is connected, the outlet of the valve and the upper horizontal segment of the 3rd pipeline and the 4th pipe Another the second end in the upper horizontal segment in road is connected.
  6. 6. conduit assembly according to claim 5, it is characterised in that further comprise:
    Medicament ascending pipe;
    Threeway, the first end of the threeway are connected with the upper end of the vertical section of the 3rd pipeline, the second end of the threeway with The first end of the upper horizontal segment of 3rd pipeline is connected, the 3rd end of the threeway and the lower end phase of the medicament ascending pipe Even;With
    Second elbow, the first end of second elbow are connected with the upper end of the vertical section of the 4th pipeline, and described second is curved Second end of head is connected with the first end of the upper horizontal segment of the 4th pipeline.
  7. 7. conduit assembly according to claim 5, it is characterised in that the lower horizontal segment and the upper horizontal segment are into predetermined Angle.
  8. 8. conduit assembly according to claim 7, it is characterised in that the predetermined angular be more than or equal to 15 degree and be less than etc. 30 degree.
  9. 9. a kind of elbow, it is characterised in that the first end face of the elbow is configured to flange face, and the elbow has runner, institute State runner first is opened in the first end face, and the second of the runner is opened in the side face of the elbow On.
  10. 10. a kind of chemical plant installations, it is characterised in that including the conduit assembly according to any one of claim 1-8.
CN201720912331.1U 2017-07-25 2017-07-25 Conduit assembly and its elbow and the chemical plant installations with the conduit assembly Active CN206958455U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720912331.1U CN206958455U (en) 2017-07-25 2017-07-25 Conduit assembly and its elbow and the chemical plant installations with the conduit assembly

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720912331.1U CN206958455U (en) 2017-07-25 2017-07-25 Conduit assembly and its elbow and the chemical plant installations with the conduit assembly

Publications (1)

Publication Number Publication Date
CN206958455U true CN206958455U (en) 2018-02-02

Family

ID=61381343

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720912331.1U Active CN206958455U (en) 2017-07-25 2017-07-25 Conduit assembly and its elbow and the chemical plant installations with the conduit assembly

Country Status (1)

Country Link
CN (1) CN206958455U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110759431A (en) * 2019-11-08 2020-02-07 润电能源科学技术有限公司 Positive tower of fine treatment regeneration system and transformation method thereof

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110759431A (en) * 2019-11-08 2020-02-07 润电能源科学技术有限公司 Positive tower of fine treatment regeneration system and transformation method thereof

Similar Documents

Publication Publication Date Title
CN201658921U (en) Gas cleaning and filtering device
US9518735B2 (en) Nozzle assembly
CN206958455U (en) Conduit assembly and its elbow and the chemical plant installations with the conduit assembly
CN205938242U (en) Double -wall pipe inner tube is to removable outer tube of interface welding seam department
CN103245222B (en) Pipeline configuration structure of triple-inlet air cooler system for hydrogenation reaction effluents
CN204329686U (en) Be convenient to the spiral heat exchanger cleaned
EP2131088A2 (en) Draing or venting device for a compensator
CN207814744U (en) A kind of thin oil fuel tank pipe leakage Quick repairing device
CN203803195U (en) Vertical filter convenient to assemble and disassemble
CN103638738B (en) A kind of through type exempts from disassembly, cleaning type filter
CN209917426U (en) Temporary filter for pipeline
CN206072625U (en) Elbow and double-tube heat exchanger
CN205424248U (en) Removable bellows safety cover
US20110289751A1 (en) Field Erectable Abatement System Methods
CN203750277U (en) Thickening agent discharging filter
CN204827387U (en) Recovery unit of associated gas
CN218178623U (en) Injection facility for 90-degree turning pipeline
CN210739648U (en) Natural gas line convenient to concatenation
CN220169186U (en) Liquid draining device
CN104344073A (en) Chemical pipe installation method
RU41357U1 (en) DEVICE FOR DIRECTING FLOW IN A GAS PIPELINE
CN212003119U (en) Novel oil production metering module type valve group
CN209130382U (en) A kind of liquid-injection equipment that can be dismounted under stream state
CN208074594U (en) A kind of blowdown collection conveying device
CN207445956U (en) A kind for the treatment of tail gas environmental protection equipment

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CP03 Change of name, title or address
CP03 Change of name, title or address

Address after: 100010 Chaoyangmen North Street, Dongcheng District, Dongcheng District, Beijing

Co-patentee after: CNOOC OIL & PETROCHEMICALS Co.,Ltd.

Patentee after: CHINA NATIONAL OFFSHORE OIL Corp.

Co-patentee after: COOEC-ENPAL ENGINEERING Co.,Ltd.

Address before: 100010 Hai Yuan building, 25 Chaoyangmen North Street, Dongcheng District, Beijing.

Co-patentee before: CNOOC OIL & PETROCHEMICALS Co.,Ltd.

Patentee before: CHINA NATIONAL OFFSHORE OIL Corp.

Co-patentee before: COOEC-ENPAL ENGINEERING Co.,Ltd.

TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20180515

Address after: 100010 Chaoyangmen North Street, Dongcheng District, Dongcheng District, Beijing

Co-patentee after: CNOOC OIL & PETROCHEMICALS Co.,Ltd.

Patentee after: CHINA NATIONAL OFFSHORE OIL Corp.

Co-patentee after: CNOOC PETROCHEMICAL ENGINEERING Co.,Ltd.

Address before: 100010 Chaoyangmen North Street, Dongcheng District, Dongcheng District, Beijing