CN206956530U CN201720911119.3U CN201720911119U CN206956530U CN 206956530 U CN206956530 U CN 206956530U CN 201720911119 U CN201720911119 U CN 201720911119U CN 206956530 U CN206956530 U CN 206956530U
Authority
CN
China
Prior art keywords
filled
concrete
web
steel pipe
steeltubewith
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201720911119.3U
Other languages
Chinese (zh)
Inventor
郑健
杨绿峰
凌忠
王建军
韩玉
李彩霞
冯春萌
王�锋
解威威
赵玉峰
唐颖贤
隗磊军
严胜杰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangxi Road and Bridge Engineering Group Co Ltd
Original Assignee
Guangxi Road and Bridge Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangxi Road and Bridge Engineering Group Co Ltd filed Critical Guangxi Road and Bridge Engineering Group Co Ltd
Priority to CN201720911119.3U priority Critical patent/CN206956530U/en
Application granted granted Critical
Publication of CN206956530U publication Critical patent/CN206956530U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The utility model discloses a kind of concrete-filled steeltubewith dumbbell sections arch rib, belong to CFST Arch Bridge technical field.Including the first body, the second body, web and concrete:First body section is in closed circular;Second body section is in closed circular, is placed in parallel with the first body, different from the first body section and/or wall thickness;Web quantity is two, and side by side parallel is placed, and web both sides connect the first outer surface of tube body and the second outer surface of tube body, the section constitution dumb-bell shape of the first body, the second body and web three respectively;Concrete:It is filled in the first body and the second body, and is filled in the closed channel that the first body, the second body and web three are formed respectively.Steel pipe equal thickness, the equal diameter because of concrete-filled steeltubewith dumbbell sections arch rib are avoided, and causes the waste of material and the irrational problem of stress.

Description

A kind of concrete-filled steeltubewith dumbbell sections arch rib
Technical field
CFST Arch Bridge technical field is the utility model is related to, particularly a kind of concrete-filled steeltubewith dumbbell sections arch Rib.
Background technology
CFST Arch Bridge has many advantages, such as compression strength is high, economical and beautiful, easy for construction, from nineteen ninety first Since seat Dumbbell-shaped CFST Arch Bridge-Sichuan Wangcang bridge is built up, the CFST Arch Bridge in China has obtained rapidly Development, according to《CFST Arch Bridge》Counted in the third edition, end in January, 2015, Dumbbell-shaped CFST Arch Bridge is existing More than 200 seats, account for the half of CFST Arch Bridge sum.Concrete-filled steel tube with dumbbell sections is by upper and lower concrete filled steel tube and company Connect the abdominal cavity composition of lower concrete filled steel tube.However, substantial amounts of engineering practice shows, in traditional concrete-filled steel tube with dumbbell sections Upper and lower concrete filled steel tube, the overwhelming majority is equal thickness, isodiametric concrete filled steel tube, due to concrete-filled steel tube with dumbbell sections In arch bridge, the stress of upper and lower concrete filled steel tube is typically different, using common load case-entirely across evenly load as Example, the stress of the second body is typically larger than the first body stress, and vault, using moment of flexure as important internal force, the first body cuts to be dangerous Face;And arch springing, then based on axle power, the second body is dangerouse cross-section.Thus, on the premise of ensureing that structure is safe and reliable, knot Structure is using equal thickness, isodiametric concrete filled steel tube by the waste for causing steel and the discontinuity of structure, unreasonable.Mesh Before, there has been no the research that related ends carried out correlation, it is therefore proposed that round steel pipe coagulation above and below a kind of concrete-filled steel tube with dumbbell sections The native not Novel dumbbell such as equal thickness, non-equal diameter shaped steel pipe concrete so that dumbbell shape rib structure is in loading process, up and down Two concrete filled steel tube uniform forces, so as to avoid the waste of material.
Utility model content
Goal of the invention of the present utility model is, in view of the above-mentioned problems, providing a kind of concrete-filled steeltubewith dumbbell sections arch Rib, avoid steel pipe equal thickness, equal diameter because of concrete-filled steeltubewith dumbbell sections arch rib, and cause material waste and stress not The problem of reasonable.
To reach above-mentioned purpose, technical scheme is used by the utility model:A kind of concrete-filled steeltubewith dumbbell sections Arch rib, it is characterised in that:Including the first body:Section is in closed circular;Second body:Section is in closed circular, with described One body is placed in parallel, different from the first body section and/or wall thickness;Web quantity is two, and side by side parallel is placed, web Both sides connect first outer surface of tube body and the second outer surface of tube body, first body, the second body and web three respectively The section constitution dumb-bell shape of person;Concrete:It is filled in respectively in first body and the second body, and is filled in described In the closed channel that one body, the second body and web three are formed.
First, the FEM model of concrete-filled steel tube with dumbbell sections structure is established by finite element software, then passes through difference Load case, the parameter comparison such as ratio of rise to span, determine shape, the wall thickness of the body of concrete-filled steel tube with dumbbell sections first and the second body And size, the first body and the second body are connected by web, and many places fill concrete reaches reasonable distribution stress problem, Avoid the effect of the waste of material.
Further, first body and the second body are cylinder, and the first body caliber is less than described the Two body calibers.
Further, first body and the second body are cylinder, and the first body pipe thickness is less than institute State the second body pipe thickness.
Further, first body and the second body are cylinder, and the first body caliber is less than described the Two body calibers, the first body pipe thickness are more than the second body pipe thickness.
Further, first body and the second body are elliptical cylinder-shape, and first body and the second body are short Footpath is identical, and the first body major diameter is less than the second body major diameter.
Further, first body and the second body are elliptical cylinder-shape, and the first body pipe thickness is less than The second body pipe thickness.
Further, first body and the second body are elliptical cylinder-shape, and the first body tube wall major diameter is less than The second body major diameter, but the first body pipe thickness is more than the second body pipe thickness.It is further square using above-mentioned six The beneficial effect of case is:The FEM model of concrete-filled steel tube with dumbbell sections structure is established by finite element software, is then passed through The parameter comparisons such as different load case, ratio of rise to span, determine the body of concrete-filled steel tube with dumbbell sections first and the second body wall thickness, Size and shape, reach optimization arch rib stress, save the effect of material.
Further, it is being provided with that some both ends are connected with two parallel webs medial surface center lines respectively between the web plus Strength plate, relatively described web medial surface is vertical respectively at the stiffener both ends, and the stiffener is parallel to each other and proper alignment.
Beneficial effect using above-mentioned further scheme is:Stiffener can not only reduce stress concentration and bring not Profit influences, and the generation of pipe explosion accident is reduced or avoided, while also can effectively prevent web from, because stress is excessive, causing Buckling of Web The problems such as generation.
Due to being had the advantages that using above-mentioned technical proposal, the utility model:
1. the utility model establishes the FEM model of concrete-filled steel tube with dumbbell sections structure, Ran Houtong by finite element software The parameter comparisons such as different load cases, ratio of rise to span are crossed, determine the shape of the body of concrete-filled steel tube with dumbbell sections first and the second body Shape, wall thickness and size, the first body and the second body are connected by web, and many places fill concrete reach reasonable distribution by Power problem, avoid the effect of the waste of material.
2. Buckling of Web can be both reduced or avoided by being provided with stiffener in the utility model, it can avoid or reduce again The generation of pipe explosion accident;
3. the utility model is simple in construction, operation degree-of-difficulty factor is very low, cost of labor bottom.
Brief description of the drawings
Fig. 1 is the cross-sectional view of the utility model embodiment 1.
Fig. 2 is the cross-sectional view of the utility model embodiment 2.
Fig. 3 is the cross-sectional view of the utility model embodiment 3.
Fig. 4 is the cross-sectional view of the utility model embodiment 4.
Fig. 5 is the cross-sectional view of the utility model embodiment 5.
Fig. 6 is the cross-sectional view of the utility model embodiment 6.
In accompanying drawing, the round steel pipes of 1- first, the round steel pipes of 2- second, 3- webs, 4- concrete, 5- stiffeners, 6- first are oval Steel pipe, the elliptic steel pipes of 7- second.
Embodiment
Embodiment 1
As shown in figure 1, concrete-filled steeltubewith dumbbell sections arch rib, including the first round steel pipe 1, the second round steel pipe 2, web 3 With concrete 4;The section of first round steel pipe 1 is in closed circular;The section of second round steel pipe 2 is in closed circular, flat with the first round steel pipe 1 Row is placed, different from the wall thickness of the first round steel pipe 1;The quantity of web 3 is two, and both sides respectively with the outer surface of the first round steel pipe 1 and the The outer surface of two round steel pipe 2 connects, the section constitution dumb-bell shape of the first round steel pipe 1, the second round steel pipe 2 and the three of web 3;Concrete 4:It is filled in respectively in the first round steel pipe 1 and the second round steel pipe 2, and is filled in the first round steel pipe 1, the second round steel pipe 2 and abdomen In the closed channel that the three of plate 3 is formed;Some both ends are provided between web 3 respectively with the medial surface center line of two parallel webs 3 to connect The stiffener 5 connect, the both ends of the stiffener 5 difference medial surface of opposite webs 3 is vertical, and stiffener 5 is parallel to each other and proper alignment.
Embodiment 2
As shown in Fig. 2 concrete-filled steeltubewith dumbbell sections arch rib, including the first round steel pipe 1, the second round steel pipe 2, web 3 With concrete 4;The section of first round steel pipe 1 is in closed circular;The section of second round steel pipe 2 is in closed circular, flat with the first round steel pipe 1 Row is placed, different from the diameter of the first round steel pipe 1;The quantity of web 3 be two, and both sides respectively with the outer surface of the first round steel pipe 1 Connected with the outer surface of the second round steel pipe 2, the section constitution dumb-bell shape of the first round steel pipe 1, the second round steel pipe 2 and the three of web 3;It is mixed Solidifying soil 4:It is filled in respectively in the first round steel pipe 1 and the second round steel pipe 2, and is filled in the first round steel pipe 1, the second round steel pipe 2 In the closed channel formed with the three of web 3;Be provided between web 3 some both ends respectively with the medial surface of two parallel webs 3 The stiffener 5 of line connection, the both ends of the stiffener 5 difference medial surface of opposite webs 3 is vertical, and stiffener 5 is parallel to each other and proper alignment.
Embodiment 3
As shown in figure 3, concrete-filled steeltubewith dumbbell sections arch rib, including the first round steel pipe 1, the second round steel pipe 2, web 3 With concrete 4;The section of first round steel pipe 1 is in closed circular;The section of second round steel pipe 2 is in closed circular, flat with the first round steel pipe 1 Row is placed, different from the diameter of the first round steel pipe 1 and wall thickness;The quantity of web 3 be two, and both sides respectively with the first round steel pipe 1 outer surface connects with the outer surface of the second round steel pipe 2, and the section constitution of the first round steel pipe 1, the second round steel pipe 2 and the three of web 3 is mute It is bell-shaped;Concrete 4:It is filled in respectively in the first round steel pipe 1 and the second round steel pipe 2, and is filled in the first round steel pipe 1, second In the closed channel that round steel pipe 2 and the three of web 3 are formed;Be provided between web 3 some both ends respectively with two parallel webs 3 The stiffener 5 of side center line connection, the both ends of the stiffener 5 difference medial surface of opposite webs 3 is vertical, and stiffener 5 is parallel to each other and whole Neat arrangement.
Embodiment 4
As shown in figure 4, concrete-filled steeltubewith dumbbell sections arch rib, including the first elliptic steel pipe 6, the second elliptic steel pipe 7, abdomen Plate 3 and concrete 4;The section of first elliptic steel pipe 6 is in closed circular;The section of second elliptic steel pipe 7 is in closed circular, ellipse with first Round steel pipe 6 is placed in parallel, different from the wall thickness of the first elliptic steel pipe 6;The quantity of web 3 be two, and both sides respectively with the first oval steel The outer surface of pipe 6 connects with the outer surface of the second elliptic steel pipe 7, the first elliptic steel pipe 6, the second elliptic steel pipe 7 and section of the three of web 3 Face forms dumb-bell shape;Concrete 4:It is filled in respectively in the first elliptic steel pipe 6 and the second elliptic steel pipe 7, and is filled in first In the closed channel that elliptic steel pipe 6, the second elliptic steel pipe 7 and the three of web 3 are formed;Some both ends point are provided between web 3 The stiffener 5 not being connected with the medial surface center line of two parallel webs 3, the both ends of the stiffener 5 difference medial surface of opposite webs 3 is vertical, adds Strength plate 5 is parallel to each other and proper alignment.
Embodiment 5
As shown in figure 5, concrete-filled steeltubewith dumbbell sections arch rib, including the first elliptic steel pipe 6, the second elliptic steel pipe 7, abdomen Plate 3 and concrete 4;The section of first elliptic steel pipe 6 is in closed circular;The section of second elliptic steel pipe 7 is in closed circular, ellipse with first Round steel pipe 6 is placed in parallel, different from the major diameter of the first elliptic steel pipe 6;The quantity of web 3 be two, and both sides respectively with the first oval steel The outer surface of pipe 6 connects with the outer surface of the second elliptic steel pipe 7, the first elliptic steel pipe 6, the second elliptic steel pipe 7 and section of the three of web 3 Face forms dumb-bell shape;Concrete 4:It is filled in respectively in the first elliptic steel pipe 6 and the second elliptic steel pipe 7, and is filled in first In the closed channel that elliptic steel pipe 6, the second elliptic steel pipe 7 and the three of web 3 are formed;Some both ends point are provided between web 3 The stiffener 5 not being connected with the medial surface center line of two parallel webs 3, the both ends of the stiffener 5 difference medial surface of opposite webs 3 is vertical, adds Strength plate 5 is parallel to each other and proper alignment.
Embodiment 6
As shown in fig. 6, concrete-filled steeltubewith dumbbell sections arch rib, including the first elliptic steel pipe 6, the second elliptic steel pipe 7, abdomen Plate 3 and concrete 4;The section of first elliptic steel pipe 6 is in closed circular;The section of second elliptic steel pipe 7 is in closed circular, ellipse with first Round steel pipe 6 is placed in parallel, different from the major diameter of the first elliptic steel pipe 6 and wall thickness;The quantity of web 3 is two, and both sides are respectively with the The outer surface of one elliptic steel pipe 6 connects with the outer surface of the second elliptic steel pipe 7, the first elliptic steel pipe 6, the second elliptic steel pipe 7 and web 3 The section constitution dumb-bell shape of three;Concrete 4:It is filled in the first elliptic steel pipe 6 and the second elliptic steel pipe 7, and fills out respectively Fill in the closed channel formed in the first elliptic steel pipe 6, the second elliptic steel pipe 7 and the three of web 3;If it is provided between web 3 The stiffener 5 that dry both ends are connected with the medial surface center line of two parallel webs 3 respectively, the both ends of the stiffener 5 difference medial surface of opposite webs 3 Vertically, stiffener 5 is parallel to each other and proper alignment.
Described above is the detailed description for the preferable possible embodiments of the utility model, but embodiment is not limited to Patent claim of the present utility model, the equal change or modification completed under the technical spirit suggested by all the utility model Change, all should belong to the utility model and cover the scope of the claims.

Claims (7)

  1. A kind of 1. concrete-filled steeltubewith dumbbell sections arch rib, it is characterised in that:Including
    First body:Section is in closed circular;
    Second body:Section is in closed circular, is placed in parallel with first body, with the first body section and/or wall It is thick different;
    Web:Quantity is two, and side by side parallel is placed, and web both sides connect outside first outer surface of tube body and the second body respectively Surface, first body, the second body and the section constitution dumb-bell shape of web three;
    Concrete:It is filled in respectively in first body and the second body, and is filled in first body, the second body In the closed channel formed with web three.
  2. A kind of 2. concrete-filled steeltubewith dumbbell sections arch rib according to claim 1, it is characterised in that:
    First body and the second body are cylinder, and the first body caliber is less than the second body caliber.
  3. A kind of 3. concrete-filled steeltubewith dumbbell sections arch rib according to claim 1, it is characterised in that:
    First body and the second body are cylinder, and the first body pipe thickness is less than the second body tube wall Thickness.
  4. A kind of 4. concrete-filled steeltubewith dumbbell sections arch rib according to claim 1, it is characterised in that:
    First body and the second body are cylinder, and the first body caliber is less than the second body caliber, institute State the first body pipe thickness and be more than the second body pipe thickness.
  5. A kind of 5. concrete-filled steeltubewith dumbbell sections arch rib according to claim 1, it is characterised in that:
    First body and the second body are elliptical cylinder-shape, and the first body pipe thickness is less than the second body pipe Wall thickness.
  6. A kind of 6. concrete-filled steeltubewith dumbbell sections arch rib according to claim 1, it is characterised in that:
    First body and the second body are elliptical cylinder-shape, and first body and the second body minor axis are identical, and described One body major diameter is less than the second body major diameter.
  7. 7. according to a kind of any described concrete-filled steeltubewith dumbbell sections arch ribs of claim 1-6, it is characterised in that:
    The stiffener that some both ends are connected with two parallel webs medial surface center lines respectively is provided between the web, it is described to put more energy into Relatively described web medial surface is vertical respectively at plate both ends, and the stiffener is parallel to each other and proper alignment.
CN201720911119.3U 2017-07-26 2017-07-26 A kind of concrete-filled steeltubewith dumbbell sections arch rib Expired - Fee Related CN206956530U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720911119.3U CN206956530U (en) 2017-07-26 2017-07-26 A kind of concrete-filled steeltubewith dumbbell sections arch rib

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720911119.3U CN206956530U (en) 2017-07-26 2017-07-26 A kind of concrete-filled steeltubewith dumbbell sections arch rib

Publications (1)

Publication Number Publication Date
CN206956530U true CN206956530U (en) 2018-02-02

Family

ID=61381550

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720911119.3U Expired - Fee Related CN206956530U (en) 2017-07-26 2017-07-26 A kind of concrete-filled steeltubewith dumbbell sections arch rib

Country Status (1)

Country Link
CN (1) CN206956530U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108677762A (en) * 2018-06-14 2018-10-19 无锡市航道工程有限公司 Concrete-filled steel tube tied arch arch springing crack comprehensive treatment structure

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108677762A (en) * 2018-06-14 2018-10-19 无锡市航道工程有限公司 Concrete-filled steel tube tied arch arch springing crack comprehensive treatment structure

Similar Documents

Publication Publication Date Title
CN202831402U (en) Concrete filled steel tubular column with inner-connected circular pipe and outer-sleeved concrete filled steel tube
CN103161154B (en) Distribution and application of pile foundation well squeezed bearing disk steel bars
CN201254768Y (en) Net bamboo reinforcement rammed earth wall
CN206956530U (en) A kind of concrete-filled steeltubewith dumbbell sections arch rib
CN207685692U (en) A kind of road and bridge crack ruggedized construction
CN106626032A (en) Integral type inner protrusion hollow uplift pile and preparation method thereof
CN202543966U (en) Pile-supported cantilever retaining wall
CN203247770U (en) Steel pipe barometric column
CN209642270U (en) A kind of novel power cable protection pipe
CN207079457U (en) CFST Arch Bridge and its arch rib
CN202882164U (en) Member for restraining grouting anchor connection by using two ends of reinforcing steel bar
CN209775994U (en) High strength sculpture structure
CN207934488U (en) A kind of Core Walls Structure bottom ruggedized construction
CN201835441U (en) Reinforcement cage framework structure for production of concrete pile
CN207259944U (en) CFST Arch Bridge arch springing fixed structure
CN209261310U (en) The concrete prefabricated assembly combined storehouse of Contiuum type
CN206784661U (en) The steel plate concrete combined shear wall of steel plate built in the middle part of the outsourcing of end
CN204959967U (en) Hoop reinforcing concrete filled steel tube
CN203878566U (en) Reinforced prefabricated concrete square pile
CN210031776U (en) Prefabricated RPC tubular pile structure of flute formula type
CN204225360U (en) A kind of prefabricated post and the syndeton with precast beam
CN103643695B (en) A kind of prefabricated fish belly type nested type wing plate basis
CN203361184U (en) Tower foundation form of overhead transmission line
CN202359550U (en) Anti-pulling cast-in-place pile
CN206216889U (en) A kind of hollow uplift pile of monoblock type internal projection

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CP02 Change in the address of a patent holder

Address after: 530200 No.21 Pingle Avenue, Liangqing District, Nanning City, Guangxi Zhuang Autonomous Region

Patentee after: GUANGXI ROAD AND BRIDGE ENGINEERING GROUP Co.,Ltd.

Address before: 530011 No. 17 Zhonghua Road, the Guangxi Zhuang Autonomous Region, Nanning

Patentee before: GUANGXI ROAD AND BRIDGE ENGINEERING GROUP Co.,Ltd.

CP02 Change in the address of a patent holder
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20180202

Termination date: 20210726

CF01 Termination of patent right due to non-payment of annual fee