CN206942801U - Tunnel automatic ventilation control system - Google Patents

Tunnel automatic ventilation control system Download PDF

Info

Publication number
CN206942801U
CN206942801U CN201720602119.5U CN201720602119U CN206942801U CN 206942801 U CN206942801 U CN 206942801U CN 201720602119 U CN201720602119 U CN 201720602119U CN 206942801 U CN206942801 U CN 206942801U
Authority
CN
China
Prior art keywords
tunnel
unit
automatic
ventilation
blower fan
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201720602119.5U
Other languages
Chinese (zh)
Inventor
古尊勇
易图林
周晓松
张元海
邓禹
陈秀雯
赵晓飞
樊洪
刘本华
易星辰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway 15th Bureau Group Co Ltd
Third Engineering Co Ltd of China Railway 15th Bureau Group Co Ltd
Original Assignee
China Railway 15th Bureau Group Co Ltd
Third Engineering Co Ltd of China Railway 15th Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway 15th Bureau Group Co Ltd, Third Engineering Co Ltd of China Railway 15th Bureau Group Co Ltd filed Critical China Railway 15th Bureau Group Co Ltd
Priority to CN201720602119.5U priority Critical patent/CN206942801U/en
Application granted granted Critical
Publication of CN206942801U publication Critical patent/CN206942801U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Ventilation (AREA)

Abstract

The utility model discloses a kind of tunnel automatic ventilation control system, the system includes being used for the environmental monitoring unit for gathering the environmental data in tunnel, for the unit ventilators for automatic ventilation in tunnel, for the automatic aeration unit for automatic aeration in tunnel, and for according to the environmental data control unit ventilators and the automatic control unit of automatic aeration cell operation collected;The second ventilation unit that the unit ventilators includes the first ventilation unit for being arranged on the tunnel face in the tunnel and is arranged in the tunnel;The environmental monitoring unit includes the environment monitoring sensor being arranged in tunnel;The automatic control unit includes fuzzy controller, PLC, D/A converter and the blower fan distribution adjustment control device being sequentially connected, the fuzzy controller is connected by data transfer with converting unit with the environmental monitoring unit, and the blower fan distribution adjustment control device is connected with the unit ventilators and automatic aeration unit respectively.

Description

Tunnel automatic ventilation control system
Technical field
It the utility model is related to a kind of construction ventilation of tunnel control system, more particularly to a kind of tunnel automatic ventilation control system System.
Background technology
At present, with the fast development of communication, the construction of highway, railway and underwater major long tunnel over strait is increasingly It is more, and these engineerings are often the main projects of whole engineering, its main cause is long construction period, and construction environment is poor, Unidirectional digging footage time length in construction, and in addition to the pollutant near tunnel tunnel face is difficult to discharge, behind tunnel Construction area brings secondary pollution, has had a strong impact on the construction speed of Tunnel Engineering and the health of worker, especially highlands Also there is near face oxygen content deficiency, cause construction operation device efficiency decline, worker frequently change or carry compared with Weight oxygen supply equipment work, have a strong impact on the efficiency of constructing tunnel.
Traditional major long tunnel construction ventilation mode is applied mainly using modes such as parallel pilot tunnel, inclined shaft or vertical shafts The work cycle is grown, less efficient;Also, it is low using measuring method efficiency such as traditional pernicious gases and dust content in constructing, into This height is also not prompt enough;And use continuous draft type keep construction tunnel in environmental standard it is up to standard, although efficiency compared with Height, but it is high to the human users and equipment requirement at tunnel scene, and machine cost and cost of use are also high.
In addition, with the increase of tunnel piercing length, the discharge of poisonous waste and dilution in tunnel are difficult, auxiliary by increasing Ventilation time is helped, increase auxiliary construction vent passages or relies on manual control discharge and dilution evil material relatively difficult, using certainly Autocontrol system is present construction general orientation.
Utility model content
The purpose of this utility model is to provide a kind of tunnel automatic ventilation control system, is divulged information with solving existing major long tunnel The problem of automaticity is low, and drafting efficiency is low and cost is high.
In order to solve the above technical problems, the utility model provides a kind of tunnel automatic ventilation control system, including for adopting Collect the environmental monitoring unit of the environmental data in tunnel, for the unit ventilators for automatic ventilation in tunnel, for in tunnel The automatic aeration unit of automatic aeration, and for according to the environmental data control unit ventilators and automatic aeration unit collected The automatic control unit of work;Unit ventilators includes the first ventilation unit for being arranged on the tunnel face in tunnel and is arranged in tunnel Second ventilation unit;Automatic control unit includes fuzzy controller, PLC and the regulation control of blower fan distribution being sequentially connected Device processed, fuzzy controller are connected by data transfer with converting unit with environmental monitoring unit, blower fan distribution adjustment control device point It is not connected with unit ventilators and automatic aeration unit.
Further, the second ventilation unit is arranged on the side of lateral line vehicle passage in tunnel, and the second ventilation unit with The distance between lateral line vehicle passage is 40m-55m in tunnel.
Further, the second ventilation unit is arranged on the side by tunnel face of lateral line vehicle passage in tunnel.
Further, environmental monitoring unit includes dust sensor, carbon monoxide transducer, air velocity transducer, hydrogen sulfide The combination of one or both of sensor, nitric oxide sensor, oxygen sensor and methane transducer or whole.
Further, automatic aeration unit includes oxygenation instrument, and is connected with oxygenation instrument and blower fan distribution adjustment control device Oxygenation controller.
Further, D/A converting units are connected between PLC and blower fan distribution adjustment control device, D/A conversions are single Member includes the D/A converter being connected with the output end of control unit, is connected to output end and the regulation of blower fan distribution of D/A converter Signal amplifier between the input of controller, and it is connected to the output of the input and signal amplifier of D/A converter Overvoltage crowbar between end.
Further, the system also includes the centre being connected between D/A converting units and blower fan distribution adjustment control device Relay.
Further, the system also includes the central control equipment being connected with blower fan distribution adjustment control device.
The beneficial effects of the utility model are:The construction environment in major long tunnel is carried out by using environmental monitoring unit Monitoring obtains real time environmental data in real time, by control unit according to the real time environmental data automatic ventilation unit detected and certainly Dynamic oxygenation cell operation, to ensure that pernicious gas and dust, oxygen content in tunnel etc. are in rational scope, meet construction skill Art environmental requirement, while use and the run time of instrument and equipment have been saved, reduce bad construction environment in constructing tunnel and make Into accident and loss, ensured the personal safety of operating personnel.Also, the unit ventilators need not build secondary ventilation vertical shaft With inclined shaft etc., engineering construction time and expense have been saved, has reduced construction costs.In addition, the system using flexible is strong, play Automatic, intelligence, energy-saving and environmental protection, the effect of accelerating construction progress.
Brief description of the drawings
Accompanying drawing described herein is used for providing further understanding of the present application, the part of the application is formed, at this Same or analogous part, the schematic description and description of the application are represented using identical reference number in a little accompanying drawings For explaining the application, the improper restriction to the application is not formed.In the accompanying drawings:
Fig. 1 is the structured flowchart of the utility model one embodiment;
Fig. 2 is the wind turbine layout figure of the utility model one embodiment.
Wherein:1st, dust sensor;2nd, carbon monoxide transducer;3rd, air velocity transducer;4th, hydrogen sulfide sensor;5th, an oxygen Change nitrogen sensor;6th, oxygen sensor;7th, methane transducer;8th, PLC;9-15, fuzzy controller;16th, D/A conversions are single Member;17th, auxiliary reclay;18th, blower fan distribution adjustment control device;19th, automatic aeration unit;20th, central control equipment;21st, One ventilation unit;22nd, the second ventilation unit.
Embodiment
Tunnel automatic ventilation control system as shown in Figure 1, the system include environmental monitoring unit, unit ventilators, automatic Control unit and automatic aeration unit 19.Each part is described in detail separately below:
Environmental monitoring unit includes some environmental monitoring units being distributed in major long tunnel, and environmental monitoring unit includes powder Dust sensor 1, carbon monoxide transducer 2, air velocity transducer 3, hydrogen sulfide sensor 4, nitric oxide sensor 5, oxygen sensor Device 6 and methane transducer 7, and sensing element in integrated sensor apparatus and tool housing use special explosion-proof material, and can It is subjected to non-leakage under the effect of water pressure not less than 0.1mPa.In work progress, by using environmental monitoring unit to growing up Monitoring obtains real time environmental data in real time for the progress such as evil gas and dust, oxygen content in tunnel.
As shown in Fig. 2 unit ventilators includes the first ventilation unit 21 for being arranged on the tunnel face of major long tunnel and set The second ventilation unit 22 in major long tunnel.Wherein, the second ventilation unit 22 is arranged on one of lateral line vehicle passage in tunnel Side, and the distance between lateral line vehicle passage is 40m-55m in the second ventilation unit 22 and tunnel.
According to one embodiment of the application, what the second ventilation unit 22 was arranged on lateral line vehicle passage in tunnel leans on tunnel The side of mouth, and the distance between lateral line vehicle passage is 50mm in the second ventilation unit 22 and tunnel, and it is logical except laterally driving a vehicle Other transverse passage-ways in road should be closed using sealing curtain, avoid producing channelling, influence ventilation effect.
Automatic aeration unit 19 includes the oxygenation instrument being arranged in major long tunnel, and is adjusted with oxygenation instrument and blower fan distribution The oxygenation controller that controller 18 connects, in work progress, automatic control unit can be utilized according to the oxygen content in tunnel Oxygenation controller driving oxygenation instrument work is controlled, to carrying out oxygenation in tunnel.
Automatic control unit includes connecting one to one by data transfer and converting unit and some environmental monitoring units Some fuzzy controller 9-15 (the PLC Step7 chips of such as Siemens), connect with some fuzzy controller 9-15 output end The PLC 8 connect, the D/A converting units 16 being connected with the output end of PLC 8, the output with D/A converting units 16 End connection auxiliary reclay 17, and the blower fan distribution adjustment control device 18 being connected with the output end of auxiliary reclay 17.Wherein, First ventilation unit 21, second ventilation unit 22 and automatic aeration unit 19 are connected with blower fan distribution adjustment control device 18, are Signal transmission cable in system uses Shielded Twisted Pair cable, avoids mutual signal interference, influences using effect.Also, utilize PLC 8 produces automatic control signal according to the evil gas flow in the tunnel received and Dust Capacity, oxygen content, is ability The technological means that field technique people commonly uses, is not repeated herein.
D/A converting units 16 include the D/A converter being connected with the output end of automatic control unit, are connected to D/A conversions Signal amplifier between the output end of device and the input of blower fan distribution adjustment control device 18, and it is connected to D/A converter Input and signal amplifier output end between overvoltage crowbar.
In addition, the system also includes the central control equipment 20 and display unit being connected with blower fan distribution adjustment control device 18 (not shown).Central control equipment 20 can be formed with large conference room, field panel curtain or the Control Room individually established, right Automatic, manual and emergency stop button is set in indoor heating system, the automatic system in tunnel can be adjusted, prevents that resource is unrestrained Take.
The system carries out monitoring in real time to the construction environment in major long tunnel by using environmental monitoring unit and obtained in real time Environmental data, by automatic control unit according to the real time environmental data automatic ventilation unit and automatic aeration unit 19 detected Work, to ensure that pernicious gas and dust, oxygen content in tunnel etc. are in rational scope, meet that construction technology environment will Ask, while saved use and the run time of instrument and equipment, reduce accident caused by bad construction environment in constructing tunnel And loss, ensure the personal safety of operating personnel.Also, the unit ventilators need not build secondary ventilation vertical shaft and inclined shaft Deng having saved engineering construction time and expense, reduced construction costs.In addition, the system using flexible is strong, serve certainly Dynamic, intelligence, energy-saving and environmental protection, the effect of accelerating construction progress.
Finally illustrate, above example is only unrestricted to illustrate the technical solution of the utility model, although ginseng The utility model is described in detail according to preferred embodiment, it will be understood by those within the art that, can be to this The technical scheme of utility model is modified or equivalent substitution, without departing from the objective and model of technical solutions of the utility model Enclose, it all should cover among right of the present utility model.

Claims (7)

1. a kind of tunnel automatic ventilation control system, it is characterised in that including the environment for gathering the environmental data in tunnel Monitoring unit, for the unit ventilators for automatic ventilation in tunnel, for the automatic aeration unit for automatic aeration in tunnel, with And for according to the environmental data control unit ventilators and the automatic control unit of automatic aeration cell operation collected;It is described logical Wind unit includes the first ventilation unit for being arranged on the tunnel face in the tunnel and the second ventilation blower being arranged in the tunnel Group;The automatic control unit includes fuzzy controller, PLC and the blower fan distribution adjustment control device being sequentially connected, institute State fuzzy controller to be connected with converting unit with the environmental monitoring unit by data transfer, the blower fan distribution adjustment control Device is connected with the unit ventilators and automatic aeration unit respectively;
The environmental monitoring unit includes dust sensor, carbon monoxide transducer, air velocity transducer, hydrogen sulfide sensor, one The combination of one or both of nitrogen oxide sensor, oxygen sensor and methane transducer or whole.
2. tunnel automatic ventilation control system according to claim 1, it is characterised in that the second ventilation unit is set The side of lateral line vehicle passage in tunnel, and the distance between second ventilation unit and lateral line vehicle passage in the tunnel is 40m-55m。
3. tunnel automatic ventilation control system according to claim 1, it is characterised in that the second ventilation unit is set The side by tunnel face of lateral line vehicle passage in tunnel.
4. tunnel automatic ventilation control system according to claim 1, it is characterised in that the automatic aeration unit includes Oxygenation instrument, and the oxygenation controller being connected with the oxygenation instrument and blower fan distribution adjustment control device.
5. tunnel automatic ventilation control system according to claim 1, it is characterised in that the PLC and blower fan D/A converting units are connected between distribution adjustment control device, the D/A converting units include being connected with the output end of control unit D/A converter, the signal being connected between the output end of the D/A converter and the input of blower fan distribution adjustment control device Amplifier, and the overvoltage crowbar being connected between the input of D/A converter and the output end of signal amplifier.
6. tunnel automatic ventilation control system according to claim 5, it is characterised in that the system also includes being connected to institute State the auxiliary reclay between D/A converting units and blower fan distribution adjustment control device.
7. tunnel automatic ventilation control system according to claim 1, it is characterised in that the system also includes and the wind The central control equipment of machine distribution adjustment control device connection.
CN201720602119.5U 2017-05-26 2017-05-26 Tunnel automatic ventilation control system Active CN206942801U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720602119.5U CN206942801U (en) 2017-05-26 2017-05-26 Tunnel automatic ventilation control system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720602119.5U CN206942801U (en) 2017-05-26 2017-05-26 Tunnel automatic ventilation control system

Publications (1)

Publication Number Publication Date
CN206942801U true CN206942801U (en) 2018-01-30

Family

ID=61363358

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720602119.5U Active CN206942801U (en) 2017-05-26 2017-05-26 Tunnel automatic ventilation control system

Country Status (1)

Country Link
CN (1) CN206942801U (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108590765A (en) * 2018-03-26 2018-09-28 山东大学 Ventilation intelligent monitor system and method suitable for the tunneling and underground engineering construction time
CN108661687A (en) * 2018-05-17 2018-10-16 西安建筑科技大学 A kind of tunnel energy-saving ventilating air linkage complex control system and installation method
CN113309537A (en) * 2021-06-30 2021-08-27 济南市市政工程设计研究院(集团)有限责任公司 Integrated tunnel pilot tunnel and method for realizing forward slag-discharging, ventilating, escaping and exploring
CN113446044A (en) * 2021-07-06 2021-09-28 西南交通大学 Ventilation self-adsorption oxygen generation automatic inflation air bag supercharging cabin full-tunnel oxygen supply device

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108590765A (en) * 2018-03-26 2018-09-28 山东大学 Ventilation intelligent monitor system and method suitable for the tunneling and underground engineering construction time
CN108661687A (en) * 2018-05-17 2018-10-16 西安建筑科技大学 A kind of tunnel energy-saving ventilating air linkage complex control system and installation method
CN113309537A (en) * 2021-06-30 2021-08-27 济南市市政工程设计研究院(集团)有限责任公司 Integrated tunnel pilot tunnel and method for realizing forward slag-discharging, ventilating, escaping and exploring
CN113446044A (en) * 2021-07-06 2021-09-28 西南交通大学 Ventilation self-adsorption oxygen generation automatic inflation air bag supercharging cabin full-tunnel oxygen supply device
CN113446044B (en) * 2021-07-06 2022-05-10 西南交通大学 Ventilation self-adsorption oxygen generation automatic-inflation air bag supercharging bin full-tunnel oxygen supply device

Similar Documents

Publication Publication Date Title
CN206942801U (en) Tunnel automatic ventilation control system
CN107524467A (en) Highway tunnel construction laneway type exhaust system
CN209115139U (en) A kind of band erects the compensatory formula ventilating system of two-wire of inclined shaft
CN109958474A (en) Driving face in coal mine local ventilation intelligent control method and ventilated control system
CN107269307A (en) Tunnel ventilation system
CN111140269A (en) Multi-working-face single-head tunneling ventilation system for metal underground mine infrastructure period
CN206778058U (en) One kind can multistage absorption purification of chemical waste gas plumbing installation
CN107269306A (en) Double hole highway tunnel construction ventilating systems
CN102528339A (en) Ventilating system for adjusting welding station
CN101936301A (en) Automatic operation control device of tunnel ventilator
CN202823409U (en) Clean type weighing room
CN202991096U (en) Ventilation control system used for tunnel face
CN202991094U (en) Integrated monitoring system of tunnel ventilating device
CN108716420A (en) A kind of underground coal mine Intelligent ventilation control system
CN106968700A (en) A kind of mine ventilation system and its control method
CN204830356U (en) Indoor ring accuse system
CN206220988U (en) A kind of mine down-hole automatic ventilation control device
CN203274132U (en) Real-time monitoring device for evaporative cooling air conditioning unit
CN206131326U (en) Pathology air matter accuse system
CN210631916U (en) Sintering desulfurization system capable of avoiding equipment damage after positive pressure
CN206459507U (en) One kind sintering oxygen enrichment system
CN203081490U (en) Zero resistance rotary type ventilation air methane collecting device
CN103835744A (en) Integrated supervision and control system of tunnel ventilation equipment
CN207446926U (en) The anti-tampering air lock in dedusting air port
CN206075155U (en) A kind of self-loopa adjusting means for atmosphere pollution processing equipment

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant