CN206941600U - A kind of prestress anchorage cable stirring pile pit enclosure - Google Patents

A kind of prestress anchorage cable stirring pile pit enclosure Download PDF

Info

Publication number
CN206941600U
CN206941600U CN201720444651.9U CN201720444651U CN206941600U CN 206941600 U CN206941600 U CN 206941600U CN 201720444651 U CN201720444651 U CN 201720444651U CN 206941600 U CN206941600 U CN 206941600U
Authority
CN
China
Prior art keywords
mixing pile
pile
mixing
foundation ditch
anchor cable
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201720444651.9U
Other languages
Chinese (zh)
Inventor
林焕生
梁仕华
牛九格
曾伟华
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangdong University of Technology
Original Assignee
Guangdong University of Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangdong University of Technology filed Critical Guangdong University of Technology
Priority to CN201720444651.9U priority Critical patent/CN206941600U/en
Application granted granted Critical
Publication of CN206941600U publication Critical patent/CN206941600U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model discloses a kind of prestress anchorage cable stirring pile pit enclosure, including the first mixing pile, the second mixing pile, anchor cable, steel pipe and connector, the bottom of first mixing pile and the second mixing pile is inserted in foundation ditch, and be set up in parallel along the surrounding of foundation ditch, form multiple rows of stirring pilework;Wherein, the first mixing pile is in contact with foundation ditch surrounding soil, and the second mixing pile is less than distance of first mixing pile apart from foundation ditch apart from the distance of foundation ditch, and first mixing pile is fixedly attached together by connector and the second mixing pile;Inserted in first mixing pile and be fixed with the anchor cable, inserted in second mixing pile and be fixed with the steel pipe;Concrete has been poured in first mixing pile and the second mixing pile.The utility model has structure and construction is simple, convenient and efficiency high beneficial effect.

Description

A kind of prestress anchorage cable stirring pile pit enclosure
Technical field
The utility model belongs to technical field of buildings, is related to a kind of stirring pile pit enclosure, refers in particular to a kind of prestressing force Anchor cable stirring pile pit enclosure.
Background technology
In ground construction, foundation ditch is the soil excavated in basic engineering position by substrate absolute altitude and basic plane size Cheat, after the completion of excavation of foundation pit, pattern foundation pit supporting structure be set in surrounding and bottom, prevent that soil from dropping or foundation ditch collapses.Deep-cement Mixing pile is a kind of conventional structure of pattern foundation pit supporting structure.
Deep cement-mixed pile is by the use of materials such as cement as curing agent, by specific Mixing Machine, on the spot by ground Lower soil and cement mortar action of forced stirring, make soil scleroma into the cement stabilization with Zheng Ti ﹑ Shui Wen ﹑ sealings and some strength Body, so as to improve foundation soil strength and Wu reason Li Neng ﹑ increase deformation modulus.As shown in figure 1, existing mixing pile is represented in figure The general type gone along with sb. to guard him, it uses surrounding of the single mixing pile 1 along foundation ditch 2 to set, and mixing pile more than 1 is using double in Practical Project Or plurality of rows of form, by the way of being mutually twisted, to improve the bulk strength of mixing pile 1 and sealing performance.
In present Construction practices and patent, using in deep cement-mixed pile interpolation steel pipe combined prestressing force anchor pole Structure.In complete 12 hours of Deep Mixing Piles Construction, with engineering driller in mixing pile pore-forming, by anchor pole or anchor cable insertion anchoring Soil layer is held, carries out anchored end slip casting;Steel pipe socket is inserted deeply on anchor pole or anchor cable through mixing pile endoporus after grout cures Layer mixing pile bottom, pour concrete cover plate and solidify post-stretching anchor pole or anchor cable application prestressing force and locked with anchorage, then into steel pipe Cement injection or pea gravel concreten, micro pre-stressed steel pipe concrete stake is formed, improve the Kang Wan ﹑ shear-carrying capacities of pile body.This The structure and complicated construction technique of kind deep cement-mixed pile interpolation steel pipe combined prestressing force anchor pole, efficiency is low, construction period length, It greatly affected normally completing for engineering.
Utility model content
The purpose of this utility model is the knot for solving existing deep cement-mixed pile interpolation steel pipe combined prestressing force anchor pole Structure and complicated construction technique, efficiency is low, construction period length, greatly affected the problem of normally completing of engineering, there is provided a kind of Structure and construction is simple, convenient and efficiency high stirring pile pit enclosure.
The purpose of this utility model can be reached using following technical scheme:
A kind of prestress anchorage cable stirring pile pit enclosure, including the first mixing pile, the second mixing pile, anchor cable, steel pipe and company Junctor, the bottom of first mixing pile and the second mixing pile is inserted in foundation ditch, and is set up in parallel along the surrounding of foundation ditch, shape Into multiple rows of stirring pilework;Wherein, the first mixing pile is in contact with foundation ditch surrounding soil, distance of second mixing pile apart from foundation ditch Distance less than the first mixing pile apart from foundation ditch, first mixing pile are fixedly attached to one by connector and the second mixing pile Rise;Inserted in first mixing pile and be fixed with the anchor cable, inserted in second mixing pile and be fixed with the steel pipe; Concrete has been poured in first mixing pile and the second mixing pile.
As a kind of preferable scheme, the bottom of the anchor cable is provided with boss, and the floor space of the boss is more than anchor The cross-sectional area of rope.
As a kind of preferable scheme, the connector includes lattice body, reinforcing bar and concrete, the both ends difference of the lattice body It is fixedly connected with the first mixing pile and the second mixing pile, reinforcing bar is provided with the lattice body and has poured concrete and has been stirred first Stake and the second mixing pile are fixedly attached together.
As a kind of preferable scheme, the upper end of first mixing pile and the second mixing pile is provided with pressing plate, the anchor cable Upper end be fixedly connected with the pressing plate.
As a kind of preferable scheme, the upper end of the anchor cable is provided with external screw thread, accordingly, is provided with the pressing plate logical Hole, the upper end of the anchor cable are fixedly connected with the pressing plate through through hole and by nut.
Implement the utility model, have the advantages that:
1st, the utility model is in tension state due to the effect of foundation ditch surrounding soil pressure, the first mixing pile, by Anchor cable is set in the first mixing pile, prestressed pressure is generated to mixing pile, can make to be in contact with the cob wall of foundation ditch first stirs Stake has more preferable stretching resistance performance, reduces the first mixing pile in tension caused by stake side;And in the second mixing pile Insert into steel pipe, enhance the bending rigidity of the second mixing pile.The first mixing pile and the second mixing pile are fixed by connector Connect together, the ability of moment of flexure is drawn and cheated in the hole for being integrally improved mixing pile, had both been improved the intensity of mixing pile, and had been reduced again Deformation, crack is reduced, simple in construction, overall performance is good, and Stability Analysis of Structures is reliable.
2nd, the first mixing pile and the second mixing pile of the present utility model are affixed to together by lattice body, and by Reinforcing bar and casting concrete are set in lattice body and by the first mixing pile and the second mixing pile seamless connectivity to together so that first Mixing pile and the second mixing pile are tightly connected, and can preferably be prevented in extraneous infiltration to foundation ditch.
3rd, the first mixing pile and the second mixing pile are fixedly attached to one by construction method of the present utility model by connector Rise, and by constantly to being inserted respectively into anchor cable and steel pipe in the first mixing pile and the second mixing pile, improving the strong of mixing pile Degree, reduces the deformation of construction, reduces crack, improves the overall mechanical properties of mixing pile, and realizes the by connector The sealed connection of one mixing pile and the second mixing pile, preferably prevent external water from penetrating into foundation ditch, have construction technology relatively simple Singly, the characteristics of structural strength is high and reliable and stable.
Brief description of the drawings
, below will be to embodiment in order to illustrate more clearly of the utility model embodiment or technical scheme of the prior art Or the required accompanying drawing used is briefly described in description of the prior art, it should be apparent that, drawings in the following description are only It is some embodiments of the utility model, for those of ordinary skill in the art, is not paying the premise of creative work Under, other accompanying drawings can also be obtained according to these accompanying drawings.
Fig. 1 is the structural representation of existing mixing pile;
Fig. 2 is the structural representation of the utility model stirring pile pit enclosure;
Fig. 3 is sectional views of the Fig. 2 along A-A directions;
Fig. 4 is sectional views of the Fig. 2 along B-B directions;
Fig. 5 is the mounting structure schematic diagram of the utility model stirring pile pit enclosure.
Embodiment
Below in conjunction with the accompanying drawing in the utility model embodiment, the technical scheme in the embodiment of the utility model is carried out Clearly and completely describing, it is clear that described embodiment is only the utility model part of the embodiment, rather than whole Embodiment.Based on the embodiment in the utility model, those of ordinary skill in the art are not under the premise of creative work is made The every other embodiment obtained, belong to the scope of the utility model protection.
Embodiment
Reference picture 1 and Fig. 5, the present embodiment are related to stirring pile pit enclosure, including the first mixing pile 1, the second mixing pile 2, Anchor cable 3, steel pipe 4 and connector 5, the bottom of the mixing pile 2 of the first mixing pile 1 and second are inserted in foundation ditch, and along base The surrounding in hole is set up in parallel, and forms multiple rows of stirring pilework;Wherein, the first mixing pile 1 is in contact with foundation ditch surrounding soil 10, the Two mixing piles 2 are less than distance of first mixing pile 1 apart from foundation ditch apart from the distance of foundation ditch, and first mixing pile 1 passes through connection Body 5 is fixedly attached together with the second mixing pile 2;Inserting and the anchor cable 3 is fixed with first mixing pile 1, described the Inserted in two mixing piles 2 and be fixed with the steel pipe 4;Concrete has been poured in the mixing pile 2 of first mixing pile 1 and second.
Due to the effect of the pressure of foundation ditch surrounding soil 10, the first mixing pile 1 is in tension state, by the first mixing pile Anchor cable 3 is set in 1, prestressed pressure is generated to mixing pile, the first mixing pile 1 that can make to be in contact with the cob wall of foundation ditch 10 has More preferable stretching resistance performance, reduces the first mixing pile 1 in tension caused by stake side;And inserted in the second mixing pile 2 Enter steel pipe 4, enhance the bending rigidity of the second mixing pile 2, the second mixing pile 2 is as the cob wall wall around foundation ditch.Pass through connection First mixing pile 1 and the second mixing pile 2 are fixedly attached together by body 5, and moment of flexure is drawn and cheated in the hole for being integrally improved mixing pile Ability, had both improved the intensity of mixing pile, reduced deformation again, reduced crack, simple in construction, overall performance is good, Stability Analysis of Structures Reliably.
The bottom of the anchor cable 3 is provided with boss 31, and the floor space of the boss 31 is more than the cross section face of anchor cable 3 Product.Because the floor space of boss 31 is more than the cross-sectional area of anchor cable 3, increase the frictional force of the mixing pile 1 of anchor cable 3 and first, Allow to apply the first mixing pile 1 bigger prestressing force, ensure the steadiness of the first mixing pile 1.
As shown in Figures 2 to 4, the connector 5 includes lattice body 51, reinforcing bar and concrete 52, the both ends of the lattice body 51 Be fixedly connected respectively with the first mixing pile 1 and the second mixing pile 2, reinforcing bar is provided with the lattice body 51 and poured concrete 52 and First mixing pile 1 and the second mixing pile 2 are fixedly attached together.The first mixing pile 1 and the second mixing pile 2 of the structure pass through Lattice body 51 is affixed to together, and by setting reinforcing bar and casting concrete 52 in lattice body 51 by the first mixing pile 1 With the seamless connectivity of the second mixing pile 2 to together so that the first mixing pile 1 is tightly connected with the second mixing pile 2, can preferably be prevented Only in extraneous infiltration to foundation ditch.
The upper end of the mixing pile 2 of first mixing pile 1 and second is provided with pressing plate 6, upper end and the pressing plate of the anchor cable 3 6 are fixedly connected.Anchor cable 3 can improve the stretching resistance of the first mixing pile 1 in the presence of by pulling force and fixed on the first mixing pile 1 With the ability of moment of flexure.
The upper end of the anchor cable 3 is provided with external screw thread, accordingly, through hole, the upper end of the anchor cable 3 is provided with the pressing plate 6 It is fixedly connected through through hole and by nut 7 with pressing plate 6.Anchor cable 3 is fastened on pressing plate 6 by nut 7, anchor cable 3 by On pulling force effect, improve the ability of the stretching resistance of the first mixing pile 1 and moment of flexure.
The present embodiment also provides a kind of construction method of the stirring pile pit enclosure of prestress anchorage cable 3, as shown in Figures 1 to 5, Comprise the following steps:
1) the first mixing pile 1 and the second mixing pile 2 are set up in parallel in foundation ditch surrounding, form multiple rows of stirring pilework;
2) toward casting concrete 52 in the first mixing pile 1, before concrete 52 does not solidify, anchor cable 3 is inserted into first and stirred Mix in stake 1;And before mixing pile is not fully hardened, the upper end of anchor cable 3 through pressing plate 6 and is applied into pulling force, then will with nut Together with anchor cable 3 is tightened to pressing plate 6;
2) toward casting concrete 52 in the second mixing pile 2, before concrete 52 does not solidify, inserted in the second mixing pile 2 Steel pipe 4, the upper end of steel pipe 4 are not passed through pressing plate 6;
3) step 2) and 3) is repeated in, until will be all populated respectively in all mixing piles 2 of first mixing pile 1 and second Enter anchor cable 3 and steel pipe 4;
4) lattice body 51 is set, and inserted in lattice body 51 into reinforcing bar and casting concrete 52, by the first mixing pile 1 and second Mixing pile 2 is fixedly attached together.
Before construction, the anchor cable 3 and the quantity of steel pipe 4 that are needed according to the circumference calculating of foundation ditch.The construction method is by first The mixing pile 2 of mixing pile 1 and second is fixedly attached together by connector 5, and by constantly stirring the first mixing pile 1 and second The intensity for being inserted respectively in stake 2 and into anchor cable 3 and steel pipe 4, improving mixing pile is mixed, reduces the deformation of construction, crack is reduced, carries The high overall mechanical properties of mixing pile, and realize that the sealing of the first mixing pile 1 and the second mixing pile 2 connects by connector 5 Connect, preferably prevent external water from penetrating into foundation ditch, there is the spy that construction technology is relatively easy, structural strength is high and reliable and stable Point.
Above disclosed is only a kind of the utility model preferred embodiment, can not limit this practicality with this certainly New interest field, therefore the equivalent variations made according to the utility model claims, still belong to what the utility model was covered Scope.

Claims (5)

  1. A kind of 1. prestress anchorage cable stirring pile pit enclosure, it is characterised in that:Including the first mixing pile, the second mixing pile, anchor cable, Steel pipe and connector, the bottom of first mixing pile and the second mixing pile are inserted in foundation ditch, and along foundation ditch surrounding simultaneously Row are set, and form multiple rows of stirring pilework;Wherein, the first mixing pile is in contact with foundation ditch surrounding soil, the second mixing pile distance The distance of foundation ditch is less than distance of first mixing pile apart from foundation ditch, and first mixing pile is consolidated by connector and the second mixing pile Surely connect together;Inserted in first mixing pile and be fixed with the anchor cable, inserted in second mixing pile and fixed There is the steel pipe;Concrete has been poured in first mixing pile and the second mixing pile.
  2. A kind of 2. prestress anchorage cable stirring pile pit enclosure according to claim 1, it is characterised in that:The bottom of the anchor cable End is provided with boss, and the floor space of the boss is more than the cross-sectional area of anchor cable.
  3. A kind of 3. prestress anchorage cable stirring pile pit enclosure according to claim 1, it is characterised in that:The connector bag Lattice body, reinforcing bar and concrete are included, the both ends of the lattice body are fixedly connected with the first mixing pile and the second mixing pile respectively, the lattice Reinforcing bar is provided with vivo and has been poured concrete and has been fixedly attached together the first mixing pile and the second mixing pile.
  4. A kind of 4. prestress anchorage cable stirring pile pit enclosure according to claim 1 or 3, it is characterised in that:Described first The upper end of mixing pile and the second mixing pile is provided with pressing plate, and the upper end of the anchor cable is fixedly connected with the pressing plate.
  5. A kind of 5. prestress anchorage cable stirring pile pit enclosure according to claim 4, it is characterised in that:The anchor cable it is upper End is provided with external screw thread, accordingly, through hole is provided with the pressing plate, the upper end of the anchor cable through through hole and passes through nut and pressing plate It is fixedly connected.
CN201720444651.9U 2017-04-25 2017-04-25 A kind of prestress anchorage cable stirring pile pit enclosure Active CN206941600U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720444651.9U CN206941600U (en) 2017-04-25 2017-04-25 A kind of prestress anchorage cable stirring pile pit enclosure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720444651.9U CN206941600U (en) 2017-04-25 2017-04-25 A kind of prestress anchorage cable stirring pile pit enclosure

Publications (1)

Publication Number Publication Date
CN206941600U true CN206941600U (en) 2018-01-30

Family

ID=61359157

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720444651.9U Active CN206941600U (en) 2017-04-25 2017-04-25 A kind of prestress anchorage cable stirring pile pit enclosure

Country Status (1)

Country Link
CN (1) CN206941600U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107034895A (en) * 2017-04-25 2017-08-11 广东工业大学 A kind of prestress anchorage cable stirring pile pit enclosure and its construction method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107034895A (en) * 2017-04-25 2017-08-11 广东工业大学 A kind of prestress anchorage cable stirring pile pit enclosure and its construction method

Similar Documents

Publication Publication Date Title
CN201512810U (en) Retaining wall
CN112301887A (en) Suspension bridge main cable anchoring system under bedrock deep-buried condition and construction method
CN104863177A (en) Composite retaining wall structure and construction method thereof
CN101942830A (en) Combined concrete soil pile with core pile and construction method as well as construction device thereof
CN209011137U (en) A kind of prestressing force miniature steel pipe pile constructing structure
CN206941600U (en) A kind of prestress anchorage cable stirring pile pit enclosure
CN108130905A (en) Steel-pipe pile
CN207159983U (en) A kind of soft clay area building lot structure of cement mixing method combination Pulling-Resistant Anchor Rod
CN207891869U (en) Steel-pipe pile
CN112095586A (en) Prestressed post-inserted composite anchor cable uplift pile and preparation method thereof
KR102111153B1 (en) Retaining Wall Panel Structure using PC Strand
CN110206135A (en) A kind of stone masonry house foundation ruggedized construction and method
CN216041287U (en) Assembled spiral anchor foundation
CN107034895A (en) A kind of prestress anchorage cable stirring pile pit enclosure and its construction method
CN108005086A (en) A kind of high buttress counter pull type inclined support structure for pattern foundation pit supporting structure
CN110805060B (en) Base structure for stay wire of stay wire tower and stay wire fixing method
CN211395734U (en) Straight anchor and group anchor composite rock anchoring foundation for power transmission tower
KR102008413B1 (en) Construction method of buoyancy-resistant pile
CN208088311U (en) Back-pressure de-bowed type pile slab supporting structure after stake
CN218479196U (en) Rock-socketed consolidation structure of steel pipe inclined pile of ocean platform
CN220746899U (en) Stirring pile tension type prestress steel strand anti-floating anchor rod
CN220768043U (en) Stirring pile pressure type prestress steel strand anti-floating anchor rod
CN214530743U (en) Soft soil foundation goes up enclosure pile foundation
CN219315770U (en) Combined slide-resistant pile structure
CN108330986A (en) Back-pressure de-bowed type pile slab supporting structure and construction method after stake

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant