CN206941521U - A kind of more capsule gas shield dams - Google Patents

A kind of more capsule gas shield dams Download PDF

Info

Publication number
CN206941521U
CN206941521U CN201720893633.9U CN201720893633U CN206941521U CN 206941521 U CN206941521 U CN 206941521U CN 201720893633 U CN201720893633 U CN 201720893633U CN 206941521 U CN206941521 U CN 206941521U
Authority
CN
China
Prior art keywords
row
magnetic valve
branch pipe
filling
main pipeline
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201720893633.9U
Other languages
Chinese (zh)
Inventor
张洋
杨王生
王全虎
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
HENGSHUI HENGYANG ENGINEERING RUBBER Co Ltd
Original Assignee
HENGSHUI HENGYANG ENGINEERING RUBBER Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by HENGSHUI HENGYANG ENGINEERING RUBBER Co Ltd filed Critical HENGSHUI HENGYANG ENGINEERING RUBBER Co Ltd
Priority to CN201720893633.9U priority Critical patent/CN206941521U/en
Application granted granted Critical
Publication of CN206941521U publication Critical patent/CN206941521U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Barrages (AREA)

Abstract

The utility model belongs to rubber dam technical field, is concretely related to a kind of more capsule gas shield dams.Its main technical schemes:Mainly it is made up of shield dam body, some rubber pneumatic bags that branch pole dam body rises and falls and the arranging device that fills that is connected with the rubber pneumatic bag;There is rubber pneumatic bag respective independent filling to arrange branch pipe and branch's magnetic valve, fills row's branch pipe and is connected by sub-cylinder with filling row's main pipeline;Wherein, fill row branch pipe front end and set and standby fill discharge pipe and regulation and control magnetic valve, fill row's main pipeline and master control magnetic valve is set, it is described fill row branch pipe and sub-cylinder be respectively provided with pressure sensor, pressure sensor respectively sends pressure signal to PLC, PLC through pressure difference relatively after to regulation and control magnetic valve and master control magnetic valve send keying signal.More capsule gas shield dams, which have to automatically adjust, to be filled exhaust and realizes that shield dam rises and falls the characteristics of highly consistent.

Description

A kind of more capsule gas shield dams
Technical field
The utility model belongs to rubber dam technical field, is concretely related to a kind of more capsule gas shield dams.
Background technology
After air bag shield dam to rubber pneumatic bag inflation mainly by making up to certain pressure, steel shield plate is supported, it is real Existing dash water storage, steel shield plate water retaining height be by adjusting rubber pneumatic bag aeration quantity, realizing the height and angle of dash steel shield plate, Control the backwater area of upstream.
Existing rubber pneumatic bag, which fills exhaust mode, a two ways, and a kind of is by a master control valve while to be all Rubber pneumatic bag fills exhaust, and this control landing mode is simple in construction, it is ensured that gas shield dam it is safe for operation, but exist and rise a dam During close to height, dam crest is highly inconsistent, can not do secondary adjustment;Another way is respectively to rubber by multiple branching valves Glue air bag carries out filling exhaust, although it solves the problems, such as above-mentioned, potential safety hazard during dam body rises and falls be present, that is, drops If branching valve failure gas can not exclude during dam, and other branching valve normal exhausts, then the gas occurs The increase of the load of capsule drastically, once discovery processing is not in time, fault branch air bag has the risk of explosion.
Utility model content
The purpose of this utility model is just to provide one kind can be by detecting contrast gas shield dam bladder manifolds and filling supervisor row The pressure differential in road, automatically adjust and fill exhaust and realize that shield dam rises and falls highly consistent more capsule gas shield dams.
To achieve the above object, technical scheme is used by the utility model:
A kind of more capsule gas shield dams, some rubber pneumatic bags mainly to be risen and fallen by shield dam body, branch pole dam body and with the rubber Arranging device composition is filled in the connection of glue air bag;There is the rubber pneumatic bag respective independent filling to arrange branch pipe and branch's magnetic valve, described Row's branch pipe is filled to be connected with filling row's main pipeline by sub-cylinder;Wherein, it is described fill row branch pipe front end and set standby fill discharge pipe and tune Control magnetic valve, it is described fill row main pipeline set master control magnetic valve, it is described fill row branch pipe and sub-cylinder be respectively provided with pressure sensor, institute State pressure sensor respectively to send pressure signal to PLC, the PLC is through the relatively more backward regulation and control of pressure difference Magnetic valve and master control magnetic valve send keying signal.
Forming a kind of additional technical feature on above-mentioned more capsule gas shield dams also includes:
--- the air compressor machine and air pressure tank for filling arranging device and including being connected with filling row's main pipeline, the air compressor machine will compress Air is stored to the air pressure tank;Roots blower is connected by check valve with the end for filling row's main pipeline;
--- the row's main pipeline that fills sets cooling driers between the master control magnetic valve and air compressor machine, air pressure tank;
--- the standby discharge pipe that fills is included by the first magnetic valve with filling the gas ducting and lead to that row's main pipeline is connected Cross the drainage pipeline that second solenoid valve is connected with moisture separator, water ring vacuum pump, first, second magnetic valve respectively with institute State PLC connection.
A kind of more capsule gas shield dams provided by the utility model compared with prior art, have advantages below:First, due to There is the rubber pneumatic bag on the gas shield dam respective independent filling to arrange branch pipe and branch's magnetic valve, fills row's branch pipe by sub-cylinder and fills row Main pipeline connects, fill row branch pipe front end set it is standby fill discharge pipe and regulation and control magnetic valve, fill row's main pipeline and master control magnetic valve be set, Fill row's branch pipe and sub-cylinder is respectively provided with pressure sensor, pressure sensor respectively sends pressure signal to PLC, PLC Controller through pressure difference relatively after to regulation and control magnetic valve and master control magnetic valve send keying signal, that is, realize and risen and fallen process in dam body In, the lateral of PLC real-time reception air bag connection and the pressure signal of main pipeline, respective pressure difference is calculated, Contrasted through pressure difference and find the air bag pipeline for filling abnormal gas exhaust in time, started the regulation and control magnetic valve of abnormal air bag, fill comb through standby Continue to complete and fill exhaust work, ensure that air bag fills exhaust equilibrium, dam body adjustable height is consistent;Second, due to the gas shield dam Fill row's main pipeline and cooling driers, the upsurge compressed air that air compressor machine comes out are set between master control magnetic valve and air compressor machine, air pressure tank Dry, carry out heat exchange with refrigerant, the moisture being condensed out in compressed air, oil and impurity are separated and discharged outside main pipeline, Dry air output can effectively prevent pipeline dew condensation phenomenon;Third, because the standby discharge pipe that fills on the gas shield dam includes leading to The first magnetic valve is crossed with filling the gas ducting that is connected of row's main pipeline and by second solenoid valve and moisture separator, water ring vacuum pump The drainage pipeline of connection, first, second magnetic valve are connected with PLC respectively, you can with periodically automatically to remaining in air bag The condensed water for filling row's branch pipe is cleared up, and ensures that the rubber pneumatic bag on gas shield dam is safe for operation, water discharge method is convenient, reduces maintenance The labor intensity of personnel, has ensured personal safety.
Brief description of the drawings
Fig. 1 is the structural representation on the more capsule gas shield dams of the utility model;
Fig. 2 is the attachment structure schematic diagram of the PCL controllers on the poor more capsule gas shield dams of detection formula.
Embodiment
The structure and operation principle on a kind of more capsule gas shield dams provided by the utility model are made into one below in conjunction with the accompanying drawings The detailed description of step.
As shown in Figure 1, 2, it is a kind of structural representation on more capsule gas shield dams provided by the utility model.Form more capsules Some rubber pneumatic bags 2 that the structure on gas shield dam is mainly risen and fallen by shield dam body 1, branch pole dam body 1, are connected with rubber pneumatic bag 2 Fill arranging device composition, rubber pneumatic bag 2 have it is each independent fill row's branch pipe 31 and branch's magnetic valve 32, fill row's branch pipe 31 and pass through Sub-cylinder 4 is connected with filling row's main pipeline 5, fill row branch pipe 31 front end set it is standby fill discharge pipe 71 and regulation and control magnetic valve 72, fill row Main pipeline 5 sets master control magnetic valve 6, fills row's branch pipe 31 and sub-cylinder 4 is respectively provided with pressure sensor(30、40), both pressure Sensor(30、40)Pressure signal is sent to PLC respectively(Do not marked in figure), PLC through pressure difference relatively after Keying signal is sent to regulation and control magnetic valve 72 and master control magnetic valve 6.
Its operation principle is:When filling exhaust to rubber pneumatic bag 2, the pressure arranged on branch pipe 31 and sub-cylinder 4 is filled positioned at air bag Force snesor(30、40)Real-time pressure signal is transferred to PLC respectively air pressure difference is calculated, it is abnormal by contrast Difference can find failure fill row branch pipe 31 rubber pneumatic bag 2, now PLC to positioned at its fill row branch pipe 31 on regulation and control Magnetic valve 72, which is sent, opens order, start it is standby fills discharge pipe 71, that recovers that air bag fills row's branch pipe 31 fills capacity, make pressure with Other branch pipes keep suitable, have also reached the adjustable height of shield dam body 1 and have ensured consistent purpose.
In a kind of above-mentioned structure on more capsule gas shield dams is formed,
--- in order to improve charging efficiency, ensure inflatable safety, the above-mentioned arranging device that fills includes what is be connected with filling row's main pipeline 5 Air compressor machine 81 and air pressure tank 82, i.e. air compressor machine 81 are existing to be charged into compressed air in air pressure tank 82, then opens master control magnetic valve 6, Rubber pneumatic bag 2 is inflated;Roots blower 91 is connected by check valve 92 with filling the end of row's main pipeline 5, ensure that exhaust Air quantity is constant, operates steadily;
--- the above-mentioned row's main pipeline 5 that fills sets cooling driers 93 between master control magnetic valve 6 and air compressor machine 81, air pressure tank 82, Realize and cool drying is carried out to the air for filling row, effectively prevent pipeline dew condensation phenomenon, avoid remaining condensed water shadow in pipeline Ring equipment operation;
--- in order in time discharge the cool condensate that air bag is filled in row's branch pipe 31, the above-mentioned standby discharge pipe 71 that fills includes passing through First magnetic valve 10 with fill the gas ducting 101 that be connected of row's main pipeline 5 and by second solenoid valve 11 and moisture separator 111, The drainage pipeline 113 that water ring vacuum pump 112 connects, first, second magnetic valve(10、11)Connect respectively with the PLC Connect, PLC automatically controls draining and fills exhaust process, and equipment reliability of operation is more preferable, it is possible to achieve it is round-the-clock nobody It is on duty, while easily drainage pattern, efficiency is both improved, in turn ensures that the safety of attendant.

Claims (4)

1. a kind of more capsule gas shield dams, some rubber pneumatic bags mainly to be risen and fallen by shield dam body, branch pole dam body and with the rubber Arranging device composition is filled in air bag connection;It is characterized in that:There is the rubber pneumatic bag respective independent filling to arrange branch pipe and branch's electricity Magnet valve, the row's branch pipe that fills are connected by sub-cylinder with filling row's main pipeline;Wherein, it is described fill row branch pipe front end and set standby fill row Pipeline and regulation and control magnetic valve, it is described fill row main pipeline set master control magnetic valve, it is described fill row branch pipe and sub-cylinder be respectively provided with pressure Sensor, the pressure sensor respectively send pressure signal to PLC, the PLC through pressure difference relatively after Keying signal is sent to the regulation and control magnetic valve and master control magnetic valve.
A kind of 2. more capsule gas shield dams according to claim 1, it is characterised in that:The arranging device that fills is included with filling supervisor row The air compressor machine and air pressure tank of road connection, the air compressor machine is by compressed-air-storing to the air pressure tank;Roots blower passes through list It is connected to valve with the end for filling row's main pipeline.
A kind of 3. more capsule gas shield dams according to claim 2, it is characterised in that:The row's main pipeline that fills is in master control electricity Cooling driers are set between magnet valve and air compressor machine, air pressure tank.
A kind of 4. more capsule gas shield dams according to claim 1, it is characterised in that:The standby discharge pipe that fills is included by the One magnetic valve is with filling the gas ducting that is connected of row's main pipeline and being connected by second solenoid valve with moisture separator, water ring vacuum pump Drainage pipeline, first, second magnetic valve is connected with the PLC respectively.
CN201720893633.9U 2017-07-22 2017-07-22 A kind of more capsule gas shield dams Active CN206941521U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720893633.9U CN206941521U (en) 2017-07-22 2017-07-22 A kind of more capsule gas shield dams

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720893633.9U CN206941521U (en) 2017-07-22 2017-07-22 A kind of more capsule gas shield dams

Publications (1)

Publication Number Publication Date
CN206941521U true CN206941521U (en) 2018-01-30

Family

ID=61371050

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720893633.9U Active CN206941521U (en) 2017-07-22 2017-07-22 A kind of more capsule gas shield dams

Country Status (1)

Country Link
CN (1) CN206941521U (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108542730A (en) * 2018-03-26 2018-09-18 河北医科大学第三医院 A kind of extruding massage system for preventing venous thronbosis
CN109137837A (en) * 2018-08-16 2019-01-04 烟台桑尼橡胶有限公司 A kind of fast automatic fill-drain syctem in gas shield dam and its fill discharge method
CN110825021A (en) * 2019-11-21 2020-02-21 衢州市昊川水利设备有限公司 Intelligent control system and control method of ecological pneumatic dam
CN114606907A (en) * 2022-02-23 2022-06-10 陈曦 Bidirectional water retaining and water gas filling shield dam

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108542730A (en) * 2018-03-26 2018-09-18 河北医科大学第三医院 A kind of extruding massage system for preventing venous thronbosis
CN109137837A (en) * 2018-08-16 2019-01-04 烟台桑尼橡胶有限公司 A kind of fast automatic fill-drain syctem in gas shield dam and its fill discharge method
CN110825021A (en) * 2019-11-21 2020-02-21 衢州市昊川水利设备有限公司 Intelligent control system and control method of ecological pneumatic dam
CN114606907A (en) * 2022-02-23 2022-06-10 陈曦 Bidirectional water retaining and water gas filling shield dam
CN114606907B (en) * 2022-02-23 2024-05-31 铁岭尔凡橡塑研发有限公司 Bidirectional water retaining and filling air shield dam

Similar Documents

Publication Publication Date Title
CN206941521U (en) A kind of more capsule gas shield dams
CN107532510B (en) Compressed-air energy storage electricity-generating method and compressed-air energy storage power generator
CN103148031B (en) Hydraulic movable arm loop energy-saving control system
CN102619668B (en) Constant-pressure water-gas compatible cabin power energy storage system
CN108501926A (en) Pure electric coach braking energy storing device and its working method
CN107878223A (en) A kind of power battery cooling system for electronic vehicle and cooling means
CN106968262B (en) The channel steel cofferdam system quickly repaired for the slope lining cutting of water channel canal
CN105003437B (en) The pure electric coach control system and method for anti-inflating pump emulsification of lubricant
CN105757027B (en) A kind of plug-in system integration block of automatic start-stop formula hydraulic station
CN206973700U (en) The expansion moisturizing voltage-stabilizing system of cogeneration of heat and power central heating network
CN206829157U (en) The channel steel cofferdam system quickly repaired for the slope lining cutting of water channel canal
CN207033740U (en) Roots Vacuum Pump Units device
CN107130620B (en) Channel steel cofferdam method for arranging with the flow-compensated function of section
WO2015192710A1 (en) Evaporative cooling system of vertical-shaft motor
CN202153039U (en) Low-load high-efficiency energy-storage operation system of centralized air conditioner
CN202835963U (en) Air-conditioning refrigerant recycling and adding device
CN208849630U (en) A kind of Generator Stator Cooling water system run using high water tank
CN207331862U (en) A kind of combination compression system of water system
CN206160756U (en) Two backpressure condenser vacuum systems based on roots vacuum pump group
CN207776913U (en) A kind of constant pressure type air bag energy-storage system
CN207365738U (en) A kind of steam condenser of steam turbine set vacuum with high-low pressure condenser maintains equipment
CN108488106A (en) The open accumulator system of two-chamber driven by exhaust gas turbine compressor
CN207088715U (en) A kind of heat energy recycling device
CN206138887U (en) Power station high pressure compress air system
CN206771705U (en) A kind of condensate water circulatory utilizes equipment and central air conditioner system

Legal Events

Date Code Title Description
GR01 Patent grant