CN206935055U - Industrial waste gas processing system - Google Patents

Industrial waste gas processing system Download PDF

Info

Publication number
CN206935055U
CN206935055U CN201720760912.8U CN201720760912U CN206935055U CN 206935055 U CN206935055 U CN 206935055U CN 201720760912 U CN201720760912 U CN 201720760912U CN 206935055 U CN206935055 U CN 206935055U
Authority
CN
China
Prior art keywords
filter
balladeur train
waste gas
installing frame
processing system
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201720760912.8U
Other languages
Chinese (zh)
Inventor
徐杰
刘月平
阴立满
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Time Construction Group Ltd By Share Ltd
Original Assignee
Shanghai Yue Chun Construction And Installation Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Yue Chun Construction And Installation Engineering Co Ltd filed Critical Shanghai Yue Chun Construction And Installation Engineering Co Ltd
Priority to CN201720760912.8U priority Critical patent/CN206935055U/en
Application granted granted Critical
Publication of CN206935055U publication Critical patent/CN206935055U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model discloses a kind of industrial waste gas processing system, including blast pipe and absorption tower, the filter filtered for granule foreign in waste gas is provided with blast pipe, the spray thrower that pernicious gas absorbs in waste gas is provided in absorption tower, filter includes the installing frame being connected with blast pipe, the balladeur train slided in installing frame and the filter on balladeur train, two filter installation stations are provided with balladeur train, and balladeur train slides on installing frame and allows a wherein filter to be operated.The impurity of solid granular is removed by filter, absorption tower mainly absorbs to pernicious gas, form waste liquid, granule foreign will not be entered in absorption tower, the use of absorbing liquid can be reduced, filter carries out installation filter using the balladeur train of installation station in addition, and single filter can be allowed to be operated, and another filter carries out disassembling, assembling and replacing, so as to which filter need not be stopped during dismounting.

Description

Industrial waste gas processing system
Technical field
A kind of waste treatment system is the utility model is related to, more particularly to a kind of industrial waste gas processing system.
Background technology
In the industrial production, the production of many industries can all produce waste gas, and many waste gas are very big poison be present Property is, it is necessary to which carrying out strict processing can discharge.Notification number discloses one kind for CN205308122U Chinese patent and contains cyanogen The processing system of waste gas, scrubbing tower is introduced gases into by airduct, the waste gas in air is dissolved, form waste water, Agent-feeding treatment is carried out to waste water, reaches the purpose of processing HCN-containing gases.But this processing method is introducing gases into washing Before tower, all impurity can be all entered in waste water, so as to allow agent-feeding treatment part to cause the waste of medicine.
Utility model content
The purpose of this utility model is to provide a kind of industrial waste gas processing system, and this exhaust treatment system can be effective The impurity of solid granular and pernicious gas are separately filtered absorption of successively.
Above-mentioned technical purpose of the present utility model technical scheme is that:
A kind of industrial waste gas processing system, including blast pipe and absorption tower, it is provided with for waste gas on the blast pipe The filter of middle granule foreign filtering, the spray thrower that pernicious gas absorbs in waste gas is provided in the absorption tower, it is described Filter includes the installing frame being connected with blast pipe, the balladeur train slided in installing frame and the filtering on balladeur train Plate, is provided with two filters installation stations on the balladeur train, and the balladeur train slides on installing frame and allows a wherein filter It is operated.
By using above-mentioned technical proposal, the impurity of solid granular is removed by filter, and absorption tower is mainly right Pernicious gas is absorbed, and is formed waste liquid, is allowed granule foreign not enter in absorption tower in this process, so as to subtract The use of few absorbing liquid, in addition filter installation filter is carried out using the balladeur train of installation station, can allow single filter It is operated, and another filter carries out disassembling, assembling and replacing, so as to allow filter to stop work during dismounting Make.
The utility model is further arranged to:Chute is provided with the installing frame, the balladeur train is slided along slide Governor motion is provided between frame and installing frame.
By using above-mentioned technical proposal, chute can allow balladeur train to enter line slip, and governor motion can allow the position of balladeur train Putting to be adjusted, and then facilitates the dismounting of filter.
The utility model is further arranged to:The governor motion includes regulating block and is located on regulating block and regulation The adjusting screw rod of block threaded connection, regulating tank is offered on the chute, and the adjusting screw rod is arranged on installing frame and is placed in In regulating tank, the adjusting screw rod is rotatablely connected with installing frame, and the regulating block is wholely set with balladeur train and regulating block is placed in tune Groove interior edge regulating tank is saved to slide.
By using above-mentioned technical proposal, adjusting screw rod rotates, and allows regulating block to be slided up and down, and then allow balladeur train to carry out Slide up and down, allow the working condition of two filters to switch over, and then allow it to be convenient for changing.
The utility model is further arranged to:The adjusting screw rod extends installing frame setting.
By using above-mentioned technical proposal, adjusting screw rod extends installing frame, makes its rotation more convenient, can use work Has part regulation.
The utility model is further arranged to:Sliding groove is offered on the balladeur train, the filter slides along sliding groove.
By using above-mentioned technical proposal, the setting of sliding groove can allow filter easy installation and removal.
The utility model is further arranged to:Baffler is set to carry out two installation stations in sliding groove on the balladeur train Separate.
By using above-mentioned technical proposal, baffler can allow two filters to be mutually unaffected, and more Another filter to work will not be allowed to be affected when changing.
Brief description of the drawings
Fig. 1 is the structure chart of this exhaust-gas treatment;
Fig. 2 is the sectional view one of filter, to show the structure being connected with blast pipe;
Fig. 3 is the sectional view two of filter, to show the structure of governor motion;
Fig. 4 is processing structure figure of the waste gas absorption into wastewater fraction.
In figure:1st, absorption tower;11st, the first spray thrower;12nd, the second spray thrower;13rd, water pump;14th, demister;21st, air intake Pipe;22nd, escape pipe;3rd, filter;31st, installing frame;311st, ventilation orifice;312nd, chute;313rd, regulating tank;32nd, balladeur train; 321st, baffler;322nd, sliding groove;33rd, filter;34th, installing plate;4th, governor motion;41st, adjusting screw rod;42nd, regulating block;5、 Fluid infusion groove;61st, regulating reservoir;62nd, ozone generator;63rd, blender;71st, high-pressure pump;72nd, high-pressure water pipe;73rd, drencher; 74th, electron accelerator;75th, water curtain groove.
Embodiment
The utility model is described in further detail below in conjunction with accompanying drawing.
A kind of industrial waste gas processing system, as shown in figure 1, including blast pipe 21 and absorption tower 1, will by blast pipe 21 Industrial waste gas is imported, and absorbed by absorption tower 1, and many solid particulate matters be present in general waste gas, these Material can directly be collected processing, therefore, filter 3 can be set on blast pipe 21, will by filter 3 Fraction solids particle is filtered out.The bottom of absorption tower 1 is provided with absorbing liquid, spray thrower is set in absorption tower 1, passes through spray Leaching device is contacted by air with water, and then waste gas is absorbed, and water pump 13 is provided with absorption tower 1, is by water pump 13 Spray thrower carries out offer water, and water pump 13 connects with the bottom on absorption tower 1, and absorbing liquid is sent into spray thrower by water pump 13 enters Row spray-absorption.Absorption tower 1 is additionally provided with fluid infusion groove 5, and fluid infusion groove 5 is that absorption tower 1 supplements absorbing liquid, its be generally sodium hydroxide with And the liquid of sodium hypochlorite so that the pH value of absorbing liquid is all the time in alkalescence.
As shown in Figures 2 and 3, filter 3 includes installing frame 31, the balladeur train 32 being placed in installing frame 31 and is arranged on Filter 33 on balladeur train 32, installing frame 31 is arranged on blast pipe 21, is provided with installing frame 31 and the phase of blast pipe 21 Same ventilation orifice 311.Chute 312 is set on installing frame 31, allows balladeur train 32 to enter line slip along chute 312, and allows chute 312 Connected with ventilation orifice 311, so as to when allowing balladeur train 32 to be slided in chute 312 it be allowed to be carried out with ventilation orifice 311 Coordinate.Two installation stations are set on balladeur train 32, carry out that filter 33 is installed, by by the slip of balladeur train 32, allowing two installations Filter 33 on station carries out cooperation with ventilation orifice 311 successively and filtered.Barrier is provided between two installation stations Plate 321, two stations are allowed to be separated from each other by baffler 321, it is then more convenient in the handoff procedure of filter 33.In order to Facilitate the installation of filter 33 to change, sliding groove 322 is provided with balladeur train 32, allow filter 33 to be carried out in sliding groove 322 Slide, so as to easy disassembly.
As shown in Figures 2 and 3, governor motion 4 is provided between balladeur train 32 and installing frame 31 to be used to adjust balladeur train 32 Position.Governor motion 4 is adjusted using screw-nut structure, and it includes adjusting screw rod 41 and in regulating block 42, regulating block 42 are directly fixed with balladeur train 32, and extend regulating tank 313 in chute 312, and regulating block 42 is placed in into regulating tank 313 It is interior, allow adjusting rod to be located in regulating tank 313 and be rotatablely connected with installing frame 31, adjust for convenience, allow it to extend peace Frame up 31.Installing plate 34 is respectively arranged with the both ends of installing frame 31, and opening is set at the both ends of installing frame 31, by installing plate 34 are covered in opening closes to installing frame 31.
As shown in figure 1, spray thrower includes the first spray thrower 11 and the second spray thrower 12, wherein, the first spray thrower 11 is set Into screw spraying head, spray area is bigger, and the second spray thrower 12 is arranged to fog-spray nozzle, can spray water smoke.By the second spray Device 12 is disposed adjacent to the bottom position of absorption tower 1, and the first spray thrower 11 is disposed adjacent to the tip position of absorption tower 1, at the top of absorption tower 1 Escape pipe 22 is set, the waste gas after processing is carried out by detection discharge by escape pipe 22, because fog-spray nozzle produces a large amount of water smokes, because This, sets demister 14 in the position of escape pipe 22, water smoke is removed, prevents it from being flowed out with air-flow.
As shown in Figure 1 and Figure 4, the absorbing liquid after waste gas absorption is turned into waste water, contains other more dirts in waste water, because This needs is further processed, and absorbing liquid is imported into regulating reservoir 61, while sets ozone generator 62, by regulating reservoir 61 Waste liquid and ozone generator 62 caused by Ozone Water be sent to blender 63(Typically select static mixer)In mixed. After being mixed with Ozone Water, but ozone does not carry out complete oxidation degraded to liquid, therefore, is passing through blender 63 After mixing, it is sent to irradiation devices position and is handled, irradiation devices includes water curtain generation mechanism and water curtain is entered The electron accelerator 74 of row irradiation.Water curtain generation mechanism includes high-pressure pump 71, high-pressure water pipe 72 and drencher 73, high-pressure pump Mixed liquid is carried out pressurized treatments by 71, is sent to drencher 73 by high-pressure water pipe 72, is formed water curtain.Water curtain is sprayed Penetrate in water curtain groove 75, while the electron accelerator 74 is set above water curtain groove 75, radiation treatment is carried out to water curtain, finally Complete the processing of waste gas.
This specific embodiment is only that it is not to limitation of the present utility model, ability to explanation of the present utility model Field technique personnel can make the modification of no creative contribution to the present embodiment as needed after this specification is read, but As long as all protected in right of the present utility model by Patent Law.

Claims (6)

1. a kind of industrial waste gas processing system, including blast pipe(21)And absorption tower(1), it is characterized in that:The blast pipe (21)On be provided with waste gas granule foreign filter filter(3), the absorption tower(1)Inside it is provided in waste gas The spray thrower that pernicious gas absorbs, the filter(3)Including with blast pipe(21)The installing frame of connection(31), in installing frame (31)The balladeur train of interior slip(32)And installed in balladeur train(32)On filter(33), the balladeur train(32)On be provided with two Filter(33)Station, and the balladeur train are installed(32)In installing frame(31)Upper slip allows a wherein filter(33)Carry out work Make.
2. industrial waste gas processing system according to claim 1, it is characterized in that:The installing frame(31)On be provided with chute (312), the balladeur train(32)Along chute(312)Slide, and balladeur train(32)With installing frame(31)Between be provided with governor motion (4).
3. industrial waste gas processing system according to claim 2, it is characterized in that:The governor motion(4)Including regulating block (42)And it is located in regulating block(42)Upper and regulating block(42)The adjusting screw rod of threaded connection(41), the chute(312)On Offer regulating tank(313), the adjusting screw rod(41)Installed in installing frame(31)Go up and be placed in regulating tank(313)It is interior, it is described Adjusting screw rod(41)With installing frame(31)Rotation connection, the regulating block(42)With balladeur train(32)It is wholely set and regulating block(42) It is placed in regulating tank(313)Interior edge regulating tank(313)Slide.
4. industrial waste gas processing system according to claim 3, it is characterized in that:The adjusting screw rod(41)Extend installation Frame(31)Set.
5. industrial waste gas processing system according to claim 1, it is characterized in that:The balladeur train(32)On offer sliding groove (322), the filter(33)Along sliding groove(322)Slide.
6. industrial waste gas processing system according to claim 5, it is characterized in that:The balladeur train(32)On sliding groove (322)Interior setting baffler(321)Two installation stations are separated.
CN201720760912.8U 2017-06-28 2017-06-28 Industrial waste gas processing system Expired - Fee Related CN206935055U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720760912.8U CN206935055U (en) 2017-06-28 2017-06-28 Industrial waste gas processing system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720760912.8U CN206935055U (en) 2017-06-28 2017-06-28 Industrial waste gas processing system

Publications (1)

Publication Number Publication Date
CN206935055U true CN206935055U (en) 2018-01-30

Family

ID=61367382

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720760912.8U Expired - Fee Related CN206935055U (en) 2017-06-28 2017-06-28 Industrial waste gas processing system

Country Status (1)

Country Link
CN (1) CN206935055U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111035960A (en) * 2019-12-31 2020-04-21 昆明弘承商贸有限公司 Slurry extraction equipment with pre-filtering function and use method thereof
CN114432827A (en) * 2022-03-07 2022-05-06 中国船舶重工集团公司第七一九研究所 Guiding device for steam separation

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111035960A (en) * 2019-12-31 2020-04-21 昆明弘承商贸有限公司 Slurry extraction equipment with pre-filtering function and use method thereof
CN111035960B (en) * 2019-12-31 2023-06-13 昆明弘承食品科技有限公司 Extraction equipment with prefilter function for slurry and application method of extraction equipment
CN114432827A (en) * 2022-03-07 2022-05-06 中国船舶重工集团公司第七一九研究所 Guiding device for steam separation
CN114432827B (en) * 2022-03-07 2024-02-02 中国船舶重工集团公司第七一九研究所 Guiding device for steam separation

Similar Documents

Publication Publication Date Title
CN103585868B (en) The flue gas processing device of the de-mercury dedusting of a kind of synchronized desulfuring and denitrifying and method
CN203556243U (en) Industrial organic waste gas processing device
CN105318734A (en) Device and method for applying and purifying waste heat of low-temperature waste gas of large sintering flue
CN206935055U (en) Industrial waste gas processing system
CN203196519U (en) Gas purifying device of baking finish house
CN204806906U (en) Big flue low temperature waste gas waste heat recovery of sintering and purifier
CN105318444B (en) A kind of air purifier
CN104801165A (en) Three-stage dust removal and desulphurization device
CN208032292U (en) Pollutant denitrating system smoke eliminator
CN110559834A (en) ascending pipe type gas lifting cap for removing fine particles in sintering flue gas tower
CN105536534A (en) Flue-gas desulfurization-and-denitration dust-deeply-collecting system
CN207694579U (en) A kind of emission-control equipment
CN207342419U (en) Smoke eliminator and purifying column
CN215233108U (en) Smoke outlet spraying dust-settling device for desulfurization and denitrification
CN108926975A (en) A kind of microwave plasma exhaust gas purifying method
CN106823640A (en) A kind of simple efficiency of waste gas purifying processing device
CN205730888U (en) Two-track movable bed activated carbon denitrification apparatus in parallel
CN205340583U (en) Flue gas desulfurization denitration degree of depth dust pelletizing system
CN205340539U (en) High -efficient low -cost flue gas desulfurization denitration degree of depth dust pelletizing system
CN211098370U (en) Novel spray desulfurizing tower
CN203694885U (en) Industrial waste gas eliminating equipment
CN107335290A (en) A kind of gas-liquid separation device of wind-cowl
CN209464754U (en) A kind of exhaust processor
CN206950814U (en) A kind of wind-cowl gas-liquid separation device
CN207525091U (en) Wet desulphurization waste water zero discharge device

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CP03 Change of name, title or address
CP03 Change of name, title or address

Address after: 201914 A1-57 room 58, Fumin Road, Chongming District, Shanghai.

Patentee after: China time construction group Limited by Share Ltd.

Address before: 201914 Hengtai Economic Development Zone, Chongming County, Shanghai, A1-57 (room 58, Fumin Road, Chongming)

Patentee before: Shanghai Yue Chun construction and Installation Engineering Co., Ltd.

CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20180130

Termination date: 20210628