CN206885987U - Can vertical-lift belt of belt conveyor - Google Patents
Can vertical-lift belt of belt conveyor Download PDFInfo
- Publication number
- CN206885987U CN206885987U CN201720684962.2U CN201720684962U CN206885987U CN 206885987 U CN206885987 U CN 206885987U CN 201720684962 U CN201720684962 U CN 201720684962U CN 206885987 U CN206885987 U CN 206885987U
- Authority
- CN
- China
- Prior art keywords
- belt
- strut rail
- endothelium
- vertical
- crust
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 210000003038 endothelium Anatomy 0.000 claims abstract description 18
- 230000002687 intercalation Effects 0.000 claims abstract description 11
- 238000009830 intercalation Methods 0.000 claims abstract description 11
- 238000002788 crimping Methods 0.000 claims abstract 3
- 230000002787 reinforcement Effects 0.000 claims description 4
- 239000000463 material Substances 0.000 abstract description 8
- 238000004519 manufacturing process Methods 0.000 abstract description 3
- 238000007789 sealing Methods 0.000 abstract description 2
- 238000010586 diagram Methods 0.000 description 2
- 229910000831 Steel Inorganic materials 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 238000000926 separation method Methods 0.000 description 1
- 239000010959 steel Substances 0.000 description 1
Landscapes
- Structure Of Belt Conveyors (AREA)
Abstract
The utility model is related to belt feeder equipment technical field, more particularly to can vertical-lift belt of belt conveyor, including:Crust belt, endothelium belt and strut rail;Wherein, crust belt is pipe belt, endothelium belt is spliced to form by a plurality of arrowband, it is attached on the inside of crust belt, strut rail is triangle, every arrowband of endothelium belt is mounted on a strut rail perpendicular to Belt Conveying direction, and strut rail root width is not more than twice of narrowband width, and root interlocks intercalation between strut rail;The utility model passes through the endothelium belt and strut rail structure for the mutual intercalation of pipe crimping type belt of belt conveyor increase, the vertical transport material ability of pipe crimping type belt conveyor is realized while keeping and sealing, relevant device space-consuming can be effectively reduced, reduces associated production facility cost.
Description
Technical field:
The utility model is related to belt feeder equipment technical field, it is more particularly to a kind of can be with the circular pipe type of vertical-lift material
Belt.
Background technology:
In industrial processes, the improving material that hoists is generally required, is fed when such as making steel to self-baking electrode feed end,
The work is carried out using pipe belt conveyor more.
Existing pipe belt conveyor has larger limitation to lifting angle, and material can be along Belt Conveying side when angle is excessive
Slid to reverse, cause transfer efficiency to reduce, material lifting channel blockage is caused when serious, it is therefore desirable to design less lifting
Angle, accordingly, belt conveyor space-consuming when hoisting depth is larger are very big, are unfavorable for plant area's arrangement and cost is high.
The content of the invention:
A kind of it can be solved the above problems in consideration of it, being necessary to design with the belt of belt conveyor of vertical-lift material.
Can vertical-lift belt of belt conveyor, including:Crust belt, endothelium belt and strut rail;Wherein, crust belt
For pipe belt, endothelium belt is spliced to form by a plurality of arrowband, is attached on the inside of crust belt, and strut rail is triangle, endothelium belt
Every arrowband is mounted on a strut rail perpendicular to Belt Conveying direction, and strut rail root width is not more than the two of narrowband width
Times, root interlocks intercalation between strut rail.
During work, belt in open and flat region feeding, after pipe intervolved into by conventional pipe belt roller mechanism, its internal strut rail phase
Mutual intercalation is spliced to form circular division surface, realizes the separation that area is accommodated to being intervolved before and after strut rail, and then is turned to vertically by conveyer,
Material is lifted by strut rail and realizes vertical transport.
Preferably, interlaced intercalation between each arrowband in endothelium belt, is carried during belt intervolves by the intercalation structure
For main deformation, to avoid strut rail in internal belt layer from causing curling effect.
Preferably, fillet is provided with the top of strut rail, after intervolving, each fillet overlapping prevents from setting to improve strut rail load intensity
Standby failure.
Preferably, strut rail root is provided with the reinforcement in the same direction with Belt Conveying direction, and it is strong further to improve strut rail load
Degree.
The utility model by increasing the endothelium belt and strut rail structure of mutual intercalation for circular pipe type belt of belt conveyor,
The vertical transport material ability of circular pipe type belt conveyor is realized while keeping and sealing, relevant device can be effectively reduced and account for
With space, associated production facility cost is reduced.
Brief description of the drawings:
Accompanying drawing 1 be can vertical-lift belt of belt conveyor specific embodiment structural representation;
Accompanying drawing 2 be can the specific embodiment of belt of belt conveyor of vertical-lift intervolve status architecture schematic diagram;
Accompanying drawing 3 be can vertical-lift belt of belt conveyor specific embodiment overlooking the structure diagram.
In figure:Crust belt 1, endothelium belt 2, socket 201, strut rail 3, fillet 301, reinforcement 302.
Embodiment:
Can vertical-lift belt of belt conveyor, including:Crust belt 1, endothelium belt 2 and strut rail 3;Wherein, crust
Belt 1 is pipe belt, and endothelium belt 2 is spliced to form by a plurality of arrowband, is attached on the inside of crust belt 1, each narrow in endothelium belt 2
Interband sets socket 201 and interlaced intercalation;Strut rail 3 is the triangle that top is fillet 301, the every arrowband of endothelium belt 2
It is mounted on a strut rail 3 perpendicular to Belt Conveying direction, strut rail root width is 1.5 times of narrowband width, between strut rail 3
Root interlocks intercalation, and the root of strut rail 3 is provided with the reinforcement 302 in the same direction with Belt Conveying direction.
Claims (4)
1. can vertical-lift belt of belt conveyor, it is characterised in that including:Crust belt, endothelium belt and strut rail;
Wherein, crust belt is pipe crimping belt, and endothelium belt is spliced to form by a plurality of arrowband, is attached on the inside of crust belt, strut rail
For triangle, every arrowband of endothelium belt is mounted on a strut rail perpendicular to Belt Conveying direction, and strut rail root width is not
More than twice of narrowband width, root interlocks intercalation between strut rail.
2. as claimed in claim 1 can vertical-lift belt of belt conveyor, it is characterised in that it is each in the endothelium belt
Interlaced intercalation between arrowband.
3. as claimed in claim 2 can vertical-lift belt of belt conveyor, it is characterised in that set at the top of the strut rail
There is fillet.
4. as claimed in claim 1 can vertical-lift belt of belt conveyor, it is characterised in that the strut rail root is set
There is the reinforcement in the same direction with Belt Conveying direction.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201720684962.2U CN206885987U (en) | 2017-06-14 | 2017-06-14 | Can vertical-lift belt of belt conveyor |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201720684962.2U CN206885987U (en) | 2017-06-14 | 2017-06-14 | Can vertical-lift belt of belt conveyor |
Publications (1)
Publication Number | Publication Date |
---|---|
CN206885987U true CN206885987U (en) | 2018-01-16 |
Family
ID=61319066
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201720684962.2U Expired - Fee Related CN206885987U (en) | 2017-06-14 | 2017-06-14 | Can vertical-lift belt of belt conveyor |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN206885987U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111559615A (en) * | 2020-05-19 | 2020-08-21 | 焦作大学 | Vertical elevator is carried with dregs to urban tunnel excavation |
-
2017
- 2017-06-14 CN CN201720684962.2U patent/CN206885987U/en not_active Expired - Fee Related
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111559615A (en) * | 2020-05-19 | 2020-08-21 | 焦作大学 | Vertical elevator is carried with dregs to urban tunnel excavation |
CN111559615B (en) * | 2020-05-19 | 2021-06-25 | 焦作大学 | Vertical elevator is carried with dregs to urban tunnel excavation |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104925497B (en) | A kind of C-type steel induction system clamping-type upending device | |
CN202478983U (en) | Roller bundling press | |
CN104909148A (en) | C-shaped steel overlapping and buckling conveying system | |
CN203946679U (en) | Prestressed spiral rib steel wire production pay-off | |
CN206885987U (en) | Can vertical-lift belt of belt conveyor | |
CN206066621U (en) | A kind of computer panel saw and double surfacer milling machine automatic loading/unloading connection system | |
CN204727211U (en) | A kind of C-type steel delivery system upset blanking device | |
CN201942254U (en) | Environmental protection type wrapped hoist | |
CN204621416U (en) | T-steel automatic turning system | |
CN201834537U (en) | Spacer device for ordered conveying of production line | |
CN204714026U (en) | Bagged product is conveyer along separate routes | |
CN205328439U (en) | Hanger | |
CN102390678A (en) | Jacking and conveying machine | |
CN203382171U (en) | Wear-resisting discharge hopper of conveyor | |
CN206494539U (en) | A kind of continuous feeding device of not building bridge of fruit shell carbon production line | |
CN207671180U (en) | A kind of product loading and unloading equipment | |
CN205367165U (en) | Transfer chain suitable for grit is transported and is stacked | |
CN205114397U (en) | Two storehouses formula feed lifting machine is with preventing making garrulous device | |
CN206013819U (en) | A kind of conveyer device of paper tube fine cut shaping linkage conveying | |
CN206502427U (en) | Material paves conveying arrangement | |
CN205465425U (en) | An axle type part does not have humanization processingequipment | |
CN202245216U (en) | Device for removing ores accumulating at lower part of plate type feeding machine | |
CN202897369U (en) | Multi-angle elevating conveyor | |
CN206842417U (en) | A kind of leaking material of belt conveyor device | |
CN206901282U (en) | A kind of beverage can fast lifting pusher |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CP01 | Change in the name or title of a patent holder |
Address after: 753204 Hongguozi Lanshan Industrial Park, Huinong District, Shizuishan City, Ningxia Hui Autonomous Region Patentee after: NINGXIA RONGHUAYUAN SPECIAL NEW MATERIAL Co.,Ltd. Address before: 753204 Hongguozi Lanshan Industrial Park, Huinong District, Shizuishan City, Ningxia Hui Autonomous Region Patentee before: SHIZUISHAN CITY RONGHUA MARGIN METALLURGICAL CO.,LTD. |
|
CP01 | Change in the name or title of a patent holder | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20180116 |