CN206869110U - A kind of mobile fire-screen door device of ladle-pot hot-repair bottom blowing processing - Google Patents
A kind of mobile fire-screen door device of ladle-pot hot-repair bottom blowing processing Download PDFInfo
- Publication number
- CN206869110U CN206869110U CN201720508417.8U CN201720508417U CN206869110U CN 206869110 U CN206869110 U CN 206869110U CN 201720508417 U CN201720508417 U CN 201720508417U CN 206869110 U CN206869110 U CN 206869110U
- Authority
- CN
- China
- Prior art keywords
- ladle
- screen door
- fire
- moving cart
- bottom blowing
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 238000007664 blowing Methods 0.000 title claims abstract description 21
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 57
- 239000010959 steel Substances 0.000 claims abstract description 57
- 239000011449 brick Substances 0.000 claims abstract description 19
- 230000008439 repair process Effects 0.000 claims abstract description 9
- 239000000203 mixture Substances 0.000 claims 1
- 238000010276 construction Methods 0.000 abstract description 2
- 239000000428 dust Substances 0.000 abstract description 2
- 238000009434 installation Methods 0.000 abstract description 2
- 230000007774 longterm Effects 0.000 abstract description 2
- 238000006243 chemical reaction Methods 0.000 abstract 1
- QVGXLLKOCUKJST-UHFFFAOYSA-N atomic oxygen Chemical compound [O] QVGXLLKOCUKJST-UHFFFAOYSA-N 0.000 description 16
- 239000001301 oxygen Substances 0.000 description 16
- 229910052760 oxygen Inorganic materials 0.000 description 16
- 238000004519 manufacturing process Methods 0.000 description 3
- 238000009749 continuous casting Methods 0.000 description 2
- 238000010586 diagram Methods 0.000 description 2
- 238000000034 method Methods 0.000 description 2
- 229910000840 Capped steel Inorganic materials 0.000 description 1
- 238000003723 Smelting Methods 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 230000005540 biological transmission Effects 0.000 description 1
- 230000008859 change Effects 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 239000007789 gas Substances 0.000 description 1
- 239000003292 glue Substances 0.000 description 1
- 230000006872 improvement Effects 0.000 description 1
- 230000005055 memory storage Effects 0.000 description 1
- 230000008569 process Effects 0.000 description 1
- 238000007670 refining Methods 0.000 description 1
- 238000010079 rubber tapping Methods 0.000 description 1
- 239000004576 sand Substances 0.000 description 1
- 239000002893 slag Substances 0.000 description 1
- 230000009466 transformation Effects 0.000 description 1
- 230000007306 turnover Effects 0.000 description 1
- 238000003466 welding Methods 0.000 description 1
Landscapes
- Casting Support Devices, Ladles, And Melt Control Thereby (AREA)
Abstract
A kind of mobile fire-screen door device of ladle-pot hot-repair bottom blowing processing, belongs to ladle-pot hot-repair technical field of auxiliary equipment, for being capped ladle and not being capped ladle conversion ladle bottom blowing porous core steel bonding processing.Its technical scheme is:Fire-screen door is upright rectangle, fire-screen door top has rectangular fire-screen door to burn air brick steel bonding mouth, moving cart track laying was fallen in hot repair in front of steel ladle opening position, the length of moving cart track is more than twice of fire-screen door width, fire-screen door width matches with ladle mouth diameter, the lower end of fire-screen door is fixedly mounted in moving cart, and moving cart is placed on moving cart track.The utility model have simple in construction, reliable operation, simple installation, it is light and handy flexible the advantages of, capping ladle can be efficiently solved and be not capped the rapid translating of ladle bottom blowing porous core steel bonding processing, reliability can not be influenceed with long-term work in high temperature, high dust atmosphere.
Description
Technical field
The mobile fire-screen door device that air brick core steel bonding operation is burnt in a kind of ladle-pot hot-repair bottom blowing is the utility model is related to, belongs to steel
Bag hot repair technical field of auxiliary equipment.
Background technology
Molten steel tapped after Converter to continuous-casting steel pouring terminate during domestic demand to be placed in ladle, molten steel is warm during this period
Degree reduces, damaged portion heat.In order to reduce molten steel refining smelting procedure ton is reduced in intermediate link thermal loss, final realize
Steel electric quantity consumption purpose, steel mill generally using terminate from converter tapping to continuous-casting steel pouring link carry out ladle is capped,
Reducing temperature in the ladle memory storage molten steel unit interval reduces amplitude.
But in production period due to various odjective causes, it is difficult to realize and turnover ladle 100% is capped, be capped ladle
Ladle is not capped to be both needed to be had a swollen head bottom air brick core steel bonding, because bag mouth regional temperature is higher, capped steel with oxygen pipe in slide plate region
Bag slide plate work need to stand to be carried out grilling thoroughly gaseous core steel bonding operation on the ground beyond 2 meters of bag mouth, is not capped ladle and is difficult to stand
Carry out grilling thoroughly gaseous core steel bonding operation immediately ahead of bag mouth, and wrap Nei Wenduda 800~1000OC, it is internal discrete that oxygen lance stretches into bag
Quarter is red by burning, because the distance bag nearlyer spot temperature in bottom is higher, burns oxygen pipe and is burnt red be bent downwardly in the close bottom position leading portion that wraps
Deviate position immediately ahead of air brick core, influence slide plate work and burn air brick core steel bonding operation.Capping ladle burns oxygen pipe and rides over steel ladle cover
Drainage sand hole is added to carry out operation, if oxygen pipe leading portion, which is bent downwardly that the outer oxygen pipe of bag can be pushed, realizes that oxygen pipe leading portion and air brick core exist
Same level is completed to burn steel bonding operation.Uncovered ladle burning oxygen pipe can only ride over bag and wrapped along standing along the progress of the flank side surface of front two
Operation, if oxygen pipe leading portion is bent downwardly because bag is along from the ground compared with early work industry limited space, it is difficult to reached by will wrap outer oxygen pipe and push
To oxygen pipe leading portion and air brick core in same level situation, influence to burn air brick core steel bonding operation.If 2 meters immediately ahead of bag mouth
Block fireguard is put at place, can by burn oxygen pipe ride over fireguard grill thoroughly stomata main room stretch into bag in complete burn air brick core steel bonding operation,
But placing fixed fireguard influences to grill thoroughly gas brick core steel bonding operation to capping ladle, and placing or do not place fixed fireguard can not be same
When solve processing burn air brick core steel bonding shop problem, need further improvement badly.
Utility model content
Technical problem to be solved in the utility model is to provide a kind of mobile fire-screen door device of ladle-pot hot-repair bottom blowing processing,
The rapid translating of the ventilative steel bonding handling process of ladle-pot hot-repair can be realized to capping ladle and be not capped to this device, convenient, fast
Ladle bottom blowing porous core steel bonding processing is completed promptly.
Solve above-mentioned technical problem technical scheme be:
A kind of mobile fire-screen door device of ladle-pot hot-repair bottom blowing processing, it is by fire-screen door, moving cart, moving cart track groups
Into fire-screen door is upright rectangle, and fire-screen door top has rectangular fire-screen door to burn air brick steel bonding mouth, moving cart track
It is laid on hot repair to fall in front of steel ladle opening position, the length of moving cart track is more than twice of fire-screen door width, fire-screen door
Width matches with ladle mouth diameter, and the lower end of fire-screen door is fixedly mounted in moving cart, and it is small that moving cart is placed on movement
On track road.
The above-mentioned mobile fire-screen door device of ladle-pot hot-repair bottom blowing processing, the distance of the moving cart track and steel ladle opening are big
In 2 meters.
The beneficial effects of the utility model are:
The utility model can be placed on hot repair ladle and fall to hot repair platform, and capping ladle will move fire-screen door along rail
Road direction is pushed into place from position immediately ahead of ladle mouth, burns bottom blowing oxygen hose and through steel ladle cover grills thoroughly air-core hole and stretch into ladle and carries out
Gaseous core steel bonding is grilled thoroughly, ladle is not capped and mobile fire-screen door is pushed into position placement immediately ahead of ladle mouth along track, burn bottom blowing oxygen
Pipe stretches into ladle through the fire-screen door burning air brick steel bonding mouth in mobile fire-screen door and carries out grilling thoroughly gaseous core steel bonding, quickly and easily
Complete ladle bottom blowing porous core steel bonding processing.
The utility model have simple in construction, reliable operation, simple installation, it is light and handy flexible the advantages of, can effectively solve
Certainly it is capped ladle and is not capped the rapid translating of ladle bottom blowing porous core steel bonding processing.
Brief description of the drawings
Fig. 1 is the utility model and capping ladle ventilating processing schematic diagram;
Fig. 2 is Fig. 1 top view;
Fig. 3 is the utility model and is not capped ladle ventilating processing schematic diagram;
Fig. 4 is Fig. 3 top view.
Marked in figure as follows:Hot repair ladle 1, fire-screen door burn air brick steel bonding mouth 2, fire-screen door 3, moving cart track 4, shifting
Dynamic dolly 5, steel ladle cover grill thoroughly gaseous core mouth 6, channel-section steel 7.
Embodiment
The utility model is made up of hot repair ladle 1, fire-screen door 3, moving cart track 4, moving cart 5.
Shown in figure, fire-screen door 3 is upright rectangle, and the top of fire-screen door 3 has rectangular fire-screen door burning air brick to glue
Steel mouth 2, the width of fire-screen door 3 match with ladle mouth diameter, and the lower end of fire-screen door 3 is fixedly mounted in moving cart 5, and movement is small
Car 5 is placed on moving cart track 4.
Shown in figure, moving cart track 4 is laid on hot repair and fallen in front of steel ladle opening position, moving cart track 4
Length is more than twice of the width of fire-screen door 3, and the distance of moving cart track 4 and steel ladle opening is more than 2 meters.
Shown in figure, moving cart track 4 is that a steel plate of thickness 100 makes, and the transmission device of moving cart 5 is installed in small
4 89 × 980 belt rollers of car bottom, the steel plate of thickness 100 is as moving cart carrying roller moving track face, thick 100 steel plates two
The channel-section steel of side erecting and welding 200 serve moving cart 5 keep off it is inclined, moving cart 5 be located at the both sides of moving cart track 4 channel-section steel it
Between.
Fig. 1,2 displays, when being capped Ladle Treatment air brick core steel bonding, post work can be by moving cart 5 along moving cart rail
Road 4 pushes away the top of laying moving cart track 4 and leaves position immediately ahead of ladle mouth, and post work can will burn bottom blowing oxygen hose afterwards
Air-core hole 6 is grilled thoroughly through steel ladle cover stretch into ladle carry out grilling thoroughly gaseous core steel bonding.
Fig. 3,4 displays, when not being capped Ladle Treatment air brick core steel bonding, moving cart 5 can be pushed into laying by post work
Position immediately ahead of the top ladle mouth of moving cart track 4, post work can be by burning bottom blowing oxygen hose through fire-screen door burning air brick afterwards
Steel bonding mouth 2, which is stretched into ladle, to carry out grilling thoroughly gaseous core steel bonding.
The utility model can not influence reliability with long-term work in high temperature, high dust atmosphere.
After the completion of transformation, used by nearly half a year more, do not occurred to move fire-screen door and push away motionless influence ladle bottom blowing and breathe freely
Core slag processing production accident, mobile fire-screen door position and push away position operation side immediately ahead of ladle mouth immediately ahead of ladle mouth
Just, reliably, solve the operation for being capped ladle in production process and not being capped ladle bottom blowing porous core steel bonding processing to change, quickly
The problem of completing ladle bottom blowing porous core steel bonding processing.
Claims (2)
- A kind of 1. mobile fire-screen door device of ladle-pot hot-repair bottom blowing processing, it is characterised in that:It is by fire-screen door(3), moving cart (5), moving cart track(4)Composition, fire-screen door(3)For upright rectangle, fire-screen door(3)Rectangular fire-screen door is arranged at top Burn air brick steel bonding mouth(2), moving cart track(4)It is laid on hot repair to fall in front of steel ladle opening position, moving cart track (4)Length be more than fire-screen door(3)Twice of width, fire-screen door(3)Width matches with ladle mouth diameter, fire-screen door(3)'s Lower end is fixedly mounted on moving cart(5)On, moving cart(5)It is placed on moving cart track(4)On.
- 2. the mobile fire-screen door device of ladle-pot hot-repair bottom blowing processing according to claim 1, it is characterised in that:The movement is small Track road(4)It is more than 2 meters with the distance of steel ladle opening.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201720508417.8U CN206869110U (en) | 2017-05-09 | 2017-05-09 | A kind of mobile fire-screen door device of ladle-pot hot-repair bottom blowing processing |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201720508417.8U CN206869110U (en) | 2017-05-09 | 2017-05-09 | A kind of mobile fire-screen door device of ladle-pot hot-repair bottom blowing processing |
Publications (1)
Publication Number | Publication Date |
---|---|
CN206869110U true CN206869110U (en) | 2018-01-12 |
Family
ID=61339333
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201720508417.8U Expired - Fee Related CN206869110U (en) | 2017-05-09 | 2017-05-09 | A kind of mobile fire-screen door device of ladle-pot hot-repair bottom blowing processing |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN206869110U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111250689A (en) * | 2020-03-29 | 2020-06-09 | 无锡巨力重工股份有限公司 | Hot repair system for molten steel tank |
-
2017
- 2017-05-09 CN CN201720508417.8U patent/CN206869110U/en not_active Expired - Fee Related
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111250689A (en) * | 2020-03-29 | 2020-06-09 | 无锡巨力重工股份有限公司 | Hot repair system for molten steel tank |
CN111250689B (en) * | 2020-03-29 | 2024-04-12 | 无锡巨力重工股份有限公司 | Hot repair system for molten steel pot |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104858520B (en) | A kind of nitrogen protection continuous type soldering oven | |
CN107779543B (en) | Device for preheating scrap steel and alloy by using waste heat of converter steel slag and using method | |
CN206869110U (en) | A kind of mobile fire-screen door device of ladle-pot hot-repair bottom blowing processing | |
CN206289270U (en) | Converter secondary flue gas capturing device | |
CN204058551U (en) | The anti-dross device of a kind of band steel annealing furnace roller roll surface | |
CN202836226U (en) | Water-cooled submerged arc electric furnace burner burning-through device | |
CN105651070B (en) | Mobile molten iron rolls over tank smoke collecting cover | |
CN204188010U (en) | A kind of thick furnace dedusting is stretched airtight petticoat pipe | |
CN207779131U (en) | A kind of material leakage retracting device at flat burning formula sintering machine stirring | |
CN207231250U (en) | A kind of stove external heat reclaiming system of steel scrap | |
CN207608572U (en) | A kind of device for realizing molten iron alloying | |
CN202265585U (en) | Blast furnace iron tapping hole lifting sealing cover | |
CN206794744U (en) | A kind of baking and thermal insulation device of iron bag or ladle | |
CN208532683U (en) | A kind of coke guide being used in coke production | |
CN201735781U (en) | Ladle bottom baking combustion-supporting device | |
CN204396844U (en) | Vertical coal gas is baked packaging and is put | |
CN204730240U (en) | A kind of heat exchanger tube | |
CN104215082A (en) | Stretchable/retractable closed dust removal smoke hood for rough smelting furnace | |
CN204730233U (en) | A kind of heat-exchanger rig of heating furnace | |
CN201503208U (en) | Tee of support beam of walking beam reheating furnace | |
CN202671567U (en) | Smoke dust absorbing device for steel-making | |
CN108955243B (en) | Vehicle bottom type tunnel furnace heating system and heating process thereof | |
CN103100702A (en) | Hot metal ladle baking method | |
CN219484185U (en) | Device for preheating scrap steel in ladle by using oxygen burning gun | |
CN112094977B (en) | Process and system for efficient smelting of double-furnace electric-converter |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20180112 |