CN206830195U - Construction section is coordinated by a kind of single-hole with four lanes tunnel branch for being applied to III grade of country rock - Google Patents

Construction section is coordinated by a kind of single-hole with four lanes tunnel branch for being applied to III grade of country rock Download PDF

Info

Publication number
CN206830195U
CN206830195U CN201720490494.5U CN201720490494U CN206830195U CN 206830195 U CN206830195 U CN 206830195U CN 201720490494 U CN201720490494 U CN 201720490494U CN 206830195 U CN206830195 U CN 206830195U
Authority
CN
China
Prior art keywords
pilot tunnel
tunnel
region
hole
dug
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201720490494.5U
Other languages
Chinese (zh)
Inventor
万利
张涛
张长安
吕新建
刘传利
张军伟
吴涛
王法军
胡瑶瑶
梁忠强
邵行
郝红升
迟作强
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shandong Luqiao Group Co Ltd
Shandong Provincial Communications Planning and Design Institute Group Co Ltd
Original Assignee
Shandong Provincial Communications Planning and Design Institute Co Ltd
Shandong Luqiao Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shandong Provincial Communications Planning and Design Institute Co Ltd, Shandong Luqiao Group Co Ltd filed Critical Shandong Provincial Communications Planning and Design Institute Co Ltd
Priority to CN201720490494.5U priority Critical patent/CN206830195U/en
Application granted granted Critical
Publication of CN206830195U publication Critical patent/CN206830195U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model discloses a kind of single-hole with four lanes tunnel branch for being applied to III grade of country rock to coordinate construction section, the region of inner side including the preliminary excavation hole body formed positioned at the pilot tunnel of upper left side first, the second pilot tunnel positioned at upper right side and the 3rd pilot tunnel positioned at lower right side, described the first pilot tunnel, the second pilot tunnel and the 3rd pilot tunnel is region to be dug.Temporary support is provided between described the first pilot tunnel and the second pilot tunnel, the upper end of the temporary support is fixedly connected with steel arch-shelf, and the lower end of the temporary support is inserted into region to be dug.It is the inclined-plane with certain slope α between the 3rd described pilot tunnel and region to be dug, and spray-up supporting is provided with described inclined-plane.The section piecemeal it is few, it is necessary to temporary support it is also few, not only increase the safety coefficient of construction, and shorten construction period.

Description

Construction section is coordinated by a kind of single-hole with four lanes tunnel branch for being applied to III grade of country rock
Technical field
A kind of tunnel excavation method is the utility model is related to, specifically a kind of car of single hole four for being applied to III grade of country rock Construction section is coordinated by tunnel branch in road.
Background technology
As the development of national economy and the input of national basis Facilities Construction increasingly increase, China's transport development scale Be in growing trend with speed, at the same time, tunnel due to ecological-environment differention it is smaller, build up after by mud-rock flow, cunning The Effect of Natural Disaster such as slope, earthquake are small, increasingly favored by transport development.
Due to the sharp increase of the magnitude of traffic flow, highway tunnel with four lanes is more and more in newly built tunnels and reorganization and expansion tunnel, Four-Lane Road Tunnel span is big, and for even up to 20m with upper span, therefore in III grade of country rock, wall rock condition is preferable, due to section span Greatly, be present greater risk in the conventional benching tunnelling method construction of III grade of country rock, reflected by multiple project Monitoring During The Access data, country rock Deform larger, the risk of fall be present.And the CD methods construction of use then speed of application be greatly reduced, be long in time limit, cost it is higher, It is primarily present following problem:(1) technique is cumbersome, and speed of application is slow, it is necessary to the repeatedly application and dismounting of temporary support;(2) Each several part construction influences each other restrictions, and each several part construction can not be coordinated to carry out, and top bar when constructing of getting out of a predicament or an embarrassing situation can not construct substantially, More drag slow construction speed;(3) construction cost is higher, including cost of labor and material cost, complex process, temporary support compared with More, duration increase both increases tunnel construction cost;(4) because the construction period is grown, traffic congestion caused by being closed a road to traffic around work area And built environment pollution problem increase.
According to engineering experience and statistics, between the 60m/ months~70m/ months, benching tunnelling method speed of application exists CD speed of applications Or so 100m/ months, although benching tunnelling method speed of application is significantly faster than that CD methods, working security is difficult to ensure that.
Utility model content
In view of the above-mentioned problems, the utility model provides a kind of association of single-hole with four lanes tunnel branch for being applied to III grade of country rock Adjust construction section, the section piecemeal it is few, it is necessary to temporary support it is also few, not only increase the safety coefficient of construction, and shorten Construction period.
The technical scheme in the invention for solving the technical problem is:
Construction section is coordinated by a kind of single-hole with four lanes tunnel branch for being applied to III grade of country rock, including positioned at upper left side first Pilot tunnel, the second pilot tunnel positioned at upper right side and the 3rd pilot tunnel positioned at lower right side, the first described pilot tunnel, the second pilot tunnel and the 3rd The region of the inner side for the preliminary excavation hole body that pilot tunnel is formed is region to be dug;
Temporary support, the upper end of the temporary support and steel arch-shelf are provided between described the first pilot tunnel and the second pilot tunnel It is fixedly connected, the lower end of the temporary support is inserted into region to be dug;
It is the inclined-plane with certain slope α between the 3rd described pilot tunnel and region to be dug, and is set on described inclined-plane There is spray-up supporting.
Further, the curved lateral wall of first pilot tunnel and the second pilot tunnel it is curved on be injected with concrete spray Layer, the inside of the lateral wall of first pilot tunnel and the second pilot tunnel is radial to have assigned some system anchor bolts, described Concrete spray coating, first pilot tunnel, the second pilot tunnel and the 3rd are injected with the lateral wall in perpendicular shape of 3rd pilot tunnel The first steel arch-shelf, the second steel arch-shelf and the 3rd linearly steel arch-shelf are fixedly installed in the concrete spray coating of pilot tunnel respectively, And described the first steel arch-shelf, the second steel arch-shelf and the 3rd steel arch-shelf joins end to end successively, described steel arch-shelf is formd;
Further, and the gradient α on inclined-plane is 1 on the right side of the region to be dug:0.2-1:0.75.
Further, distance M is less than or equal to 15m, second pilot tunnel and between first pilot tunnel and the second pilot tunnel The distance between three pilot tunnels N is less than or equal to 10m, and the distance between the 3rd pilot tunnel and region to be dug P are less than or equal to 10m.
Further, the width L of the 3rd pilot tunnel upper end is 5-7 rice, and the width Q of the upper end in the region to be dug is 12-14 rice.
Further, the height h of first pilot tunnel and the second pilot tunnel is the 1/3-2/3 of Tunnel overall height H.
Further, described temporary support inserts 0.1-0.3 rice in region to be dug.
Further, the temporary support is arcuate structure, and the radius R of circular arc corresponding to the temporary support is more than 8m。
The beneficial effects of the utility model are:
1st, by using the construction section, due to the excavation span of each section is reduced into half, therefore tunnel is improved The safety coefficient of construction.
2nd, by using the construction section, section piecemeal is few, and disturbance is small, and preliminary bracing and temporary support are few, saves material, The present invention only needs to perform a temporary support, and temporary support material is only the 1/2 of CD methods.
3rd, using section excavation tunnel of the present utility model, each several part, which excavates, to be coordinated in order, and construction influences each other Degree substantially reduces, i.e., section the latter half, which is excavated, does not influence top half construction, can effectively improve efficiency of construction, experience Card, using the speed of application of this method in the 90m/ months.
Brief description of the drawings
Fig. 1 is the front view that construction section is coordinated by a kind of single-hole with four lanes tunnel branch for being applied to III grade of country rock;
Fig. 2 is the stereochemical structure signal that construction section is coordinated by a kind of single-hole with four lanes tunnel branch for being applied to III grade of country rock Figure;
In figure:The pilot tunnels of 1- first, the steel arch-shelfs of 11- first, the pilot tunnels of 2- second, the steel arch-shelfs of 21- second, the pilot tunnels of 3- the 3rd, 31- 3rd steel arch-shelf, 4- regions to be dug, 5- system anchor bolts, 6- temporary supports.
Embodiment
As shown in figure 1, construction section is coordinated by a kind of single-hole with four lanes tunnel branch for being applied to III grade of country rock includes first Pilot tunnel 1, the second pilot tunnel 2 and the 3rd pilot tunnel 3.The first wherein described pilot tunnel 1 is located at upper left side, and the second described pilot tunnel 2 is located at Upper right side, the 3rd described pilot tunnel 3 are located at lower right side.The lower left side of Tunnel, i.e. the first described pilot tunnel 1, the and of the second pilot tunnel 2 The region of the inner side for the preliminary excavation hole body that 3rd pilot tunnel 3 is formed is region 4 to be dug.
As shown in Fig. 2 the leading flank (using the bearing of trend in tunnel before, similarly hereinafter) of first pilot tunnel 1 and the second pilot tunnel 2 Leading flank between distance M be less than or equal to 15m, between the leading flank of second pilot tunnel 2 and the leading flank of the 3rd pilot tunnel 3 Distance N be less than or equal to 10m, the distance between the leading flank of the 3rd pilot tunnel 3 and the leading flank in region 4 to be dug P are less than etc. In 10m.
As depicted in figs. 1 and 2, the lateral wall of the pilot tunnel 2 of the first pilot tunnel 1 and second is curved, and first pilot tunnel 1 With concrete spray coating, the inside of the lateral wall of the pilot tunnel 2 of the first pilot tunnel 1 and second are injected with the lateral wall of the second pilot tunnel 2 It is radial to have assigned some system anchor bolts 5, and some system anchor bolts 5 are evenly distributed in center line both sides each 60 ° In the range of.
The lateral wall of the 3rd described pilot tunnel 3 is perpendicular, and concrete is injected with the lateral wall of the 3rd pilot tunnel 3 Spray-up.
As shown in figure 1, fixation is set respectively in the concrete spray coating of first pilot tunnel 1, the second pilot tunnel 2 and the 3rd pilot tunnel 3 It is equipped with the first steel arch-shelf 11, the second steel arch-shelf 21 and the 3rd linearly steel arch-shelf 31, and the first described steel arch-shelf 11, the Two steel arch-shelfs 21 and the 3rd steel arch-shelf 31 join end to end successively, form steel arch-shelf.
Temporary support 6, the upper end of the temporary support 6 and institute are provided between described the first pilot tunnel 1 and the second pilot tunnel 2 The steel arch-shelf stated is fixedly connected, and the lower end of the temporary support 6 is inserted into region 4 to be dug.As a kind of embodiment, In the present embodiment, described temporary support 6 inserts 0.1-0.3 rice in region 4 to be dug.
Preferably, the temporary support 6 is arcuate structure, and the radius R of circular arc corresponding to the temporary support 6 is more than 8m。
Further, in order to ensure that the basis of temporary support 6 consolidates, it is between the 3rd described pilot tunnel 3 and region to be dug 4 Inclined-plane with certain slope α, it is preferred that be provided with spray-up branch on the inclined-plane between the 3rd pilot tunnel 3 and region to be dug 4 Shield, and the gradient α in the region to be dug 4 is 1:0.2-1:0.75.
Further, the width L of the upper end of the 3rd pilot tunnel 3 is 5-7 rice, and the width Q of the upper end of region 4 to be dug is 12-14 rice.So setting mainly has three purposes, and (1) ensures there is sufficient construction space, and branch at initial stage is performed to the 3rd pilot tunnel 3 Shield;(2) enough Core Soils of region to be dug 4 are reserved, ensure the firm of the basis of temporary support 6;(3) reserve that sufficient space is current to be applied Work machinery and personnel, such construction machinery and personnel's can are current on the upper side in region 4 to be dug, so as to ensure to the When three pilot tunnels 3 are excavated, the excavation construction of the first pilot tunnel 1 and the second pilot tunnel 2 is not influenceed, improves efficiency of construction, shortens construction Duration.
Further, in order to ensure the security of construction, first pilot tunnel 1 is identical with the height of the second pilot tunnel 2, is H, and the height h of the pilot tunnel 2 of first pilot tunnel 1 and second is the 1/3-2/3 of Tunnel overall height H.

Claims (8)

1. construction section is coordinated by a kind of single-hole with four lanes tunnel branch for being applied to III grade of country rock, it is characterised in that:Including positioned at The pilot tunnel of upper left side first, the second pilot tunnel positioned at upper right side and the 3rd pilot tunnel positioned at lower right side, the first described pilot tunnel, second The region of the inner side for the preliminary excavation hole body that pilot tunnel and the 3rd pilot tunnel are formed is region to be dug;
Temporary support is provided between described the first pilot tunnel and the second pilot tunnel, upper end and the steel arch-shelf of the temporary support are fixed Connection, the lower end of the temporary support is inserted into region to be dug;
It is the inclined-plane with certain slope α between the 3rd described pilot tunnel and region to be dug, and spray is provided with described inclined-plane Layer supporting.
2. construction section is coordinated by a kind of single-hole with four lanes tunnel branch for being applied to III grade of country rock according to claim 1, It is characterized in that:Concrete spray coating is injected with the curved lateral wall of first pilot tunnel and the second pilot tunnel is curved, institute State the lateral wall of the first pilot tunnel and the second pilot tunnel inside it is radial assigned some system anchor bolts, the described the 3rd leads It is injected with concrete spray coating on the lateral wall in perpendicular shape in hole, first pilot tunnel, the second pilot tunnel and the 3rd pilot tunnel The first steel arch-shelf, the second steel arch-shelf and the 3rd linearly steel arch-shelf are fixedly installed in concrete spray coating respectively, and it is described The first steel arch-shelf, the second steel arch-shelf and the 3rd steel arch-shelf join end to end successively, form described steel arch-shelf.
3. construction section is coordinated by a kind of single-hole with four lanes tunnel branch for being applied to III grade of country rock according to claim 1, It is characterized in that:And the gradient α on inclined-plane is 1 on the right side of the region to be dug:0.2-1:0.75.
4. construction section is coordinated by a kind of single-hole with four lanes tunnel branch for being applied to III grade of country rock according to claim 1, It is characterized in that:Distance M is less than or equal to 15m, second pilot tunnel and the 3rd pilot tunnel between first pilot tunnel and the second pilot tunnel The distance between N be less than or equal to 10m, the distance between the 3rd pilot tunnel and region to be dug P are less than or equal to 10m.
5. construction section is coordinated by a kind of single-hole with four lanes tunnel branch for being applied to III grade of country rock according to claim 1, It is characterized in that:The width L of the 3rd pilot tunnel upper end is 5-7 rice, and the width Q of the upper end in the region to be dug is 12-14 rice.
6. construction section is coordinated by a kind of single-hole with four lanes tunnel branch for being applied to III grade of country rock according to claim 1, It is characterized in that:The height h of first pilot tunnel and the second pilot tunnel is the 1/3-2/3 of Tunnel overall height H.
7. construction section is coordinated by a kind of single-hole with four lanes tunnel branch for being applied to III grade of country rock according to claim 1, It is characterized in that:Described temporary support inserts 0.1-0.3 rice in region to be dug.
8. construction section is coordinated by a kind of single-hole with four lanes tunnel branch for being applied to III grade of country rock according to claim 1, It is characterized in that:The temporary support is arcuate structure, and the radius R of circular arc corresponding to the temporary support is more than 8m.
CN201720490494.5U 2017-05-04 2017-05-04 Construction section is coordinated by a kind of single-hole with four lanes tunnel branch for being applied to III grade of country rock Active CN206830195U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720490494.5U CN206830195U (en) 2017-05-04 2017-05-04 Construction section is coordinated by a kind of single-hole with four lanes tunnel branch for being applied to III grade of country rock

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720490494.5U CN206830195U (en) 2017-05-04 2017-05-04 Construction section is coordinated by a kind of single-hole with four lanes tunnel branch for being applied to III grade of country rock

Publications (1)

Publication Number Publication Date
CN206830195U true CN206830195U (en) 2018-01-02

Family

ID=60769336

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720490494.5U Active CN206830195U (en) 2017-05-04 2017-05-04 Construction section is coordinated by a kind of single-hole with four lanes tunnel branch for being applied to III grade of country rock

Country Status (1)

Country Link
CN (1) CN206830195U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110847206A (en) * 2019-11-14 2020-02-28 中建八局轨道交通建设有限公司 Construction method for newly-built subway tunnel to penetrate existing bridge piles

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110847206A (en) * 2019-11-14 2020-02-28 中建八局轨道交通建设有限公司 Construction method for newly-built subway tunnel to penetrate existing bridge piles
CN110847206B (en) * 2019-11-14 2021-03-12 中建八局轨道交通建设有限公司 Construction method for newly-built subway tunnel to penetrate existing bridge piles

Similar Documents

Publication Publication Date Title
CN107060840B (en) A kind of construction method of large cross-section tunnel V grades of country rock excavation supportings
CN104533446B (en) Construction method and its structure that a kind of big cross section Support System in Soft Rock Tunnels bilayer pre- Geological disaster prevention of preliminary bracing occurs
CN103306680B (en) Existing single-track tunnel enlarging is the construction method of multiple track tunnel
CN108035733B (en) A kind of perpendicular support partial excavation method of rock matter large section tunnel steelframe dike combination
CN101858220A (en) Tunnel double upper sidewall heading construction method
CN103061771B (en) Second mining mine fully mechanized coal face cuts eye driving and supporting method thereof
CN102121385B (en) Tunnel excavation method for extending existing single-hole tunnel into double-arch tunnel
CN102312672A (en) Fast large-cross-section tunnel construction method adapting to complicated and variable geological conditions
CN103195432A (en) Weak surrounding rock, tunnel intersection and arc-shaped pilot tunnel construction method
CN103244130A (en) Quick excavation and expanding construction method of herringbone tunnel section
CN103485790A (en) Shallow tunneling method for pipe-proof-supporting structure combined system
CN106968691A (en) Improve CD method construction methods in a kind of extremely frigid zones silty clay tunnel
CN110439571A (en) Flat pilot tunnel leads to the adit construction method and transverse passage-way of main tunnel
CN108166979A (en) A kind of construction method of super-span tunnel top bar two side-wall pilot tunnel
CN107060825A (en) Construction method is coordinated by a kind of single-hole with four lanes tunnel branch for being applied to III grade of country rock
CN108222959B (en) Supporting structure for controlling tunnel primary supporting deformation based on monitoring measurement and construction method
CN108412502B (en) A kind of deep tunnel passes through upper-soft lower-hard ground construction method
CN107130968A (en) A kind of tunnel construction mid-board
CN106917628B (en) Small-clear-distance tunnel construction technique
CN110362932B (en) Shallow subsurface tunnel pipe curtain structure calculation model that buries under complicated environmental condition
CN102410031A (en) Underground space structure constructed by pile wall construction method
CN206830195U (en) Construction section is coordinated by a kind of single-hole with four lanes tunnel branch for being applied to III grade of country rock
CN109695457A (en) The enlarging large section tunnel in situ and step construction method of hard rock
CN205805546U (en) A kind of drift-sand stratum highway tunnel structure
CN110005440A (en) Double side wall pilot tunnel formula construction method under lateral pipe shed support

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CP01 Change in the name or title of a patent holder
CP01 Change in the name or title of a patent holder

Address after: 250031 Shandong Province Flyover District of Ji'nan city Shanxi Road No. 576.

Patentee after: Shandong transportation planning and Design Institute Co.,Ltd.

Patentee after: SHANDONG LUQIAO GROUP Co.,Ltd.

Address before: 250031 Shandong Province Flyover District of Ji'nan city Shanxi Road No. 576.

Patentee before: SHANDONG PROVINCIAL COMMUNICATIONS PLANNING AND DESIGN INSTITUTE

Patentee before: SHANDONG LUQIAO GROUP Co.,Ltd.

CP01 Change in the name or title of a patent holder
CP01 Change in the name or title of a patent holder

Address after: 250031 No. 576 Wushanxi Road, Tianqiao District, Jinan City, Shandong Province

Patentee after: Shandong transportation planning and Design Institute Group Co.,Ltd.

Patentee after: SHANDONG LUQIAO GROUP Co.,Ltd.

Address before: 250031 No. 576 Wushanxi Road, Tianqiao District, Jinan City, Shandong Province

Patentee before: Shandong transportation planning and Design Institute Co.,Ltd.

Patentee before: SHANDONG LUQIAO GROUP Co.,Ltd.