CN206801599U - Digging tunnel face guard - Google Patents
Digging tunnel face guard Download PDFInfo
- Publication number
- CN206801599U CN206801599U CN201720412717.6U CN201720412717U CN206801599U CN 206801599 U CN206801599 U CN 206801599U CN 201720412717 U CN201720412717 U CN 201720412717U CN 206801599 U CN206801599 U CN 206801599U
- Authority
- CN
- China
- Prior art keywords
- face
- guard
- face guard
- supporting
- tunnel
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Refuge Islands, Traffic Blockers, Or Guard Fence (AREA)
Abstract
The utility model discloses digging tunnel face guard, belong to digging supporting field, including supporting guard beam, supporting guard beam forms colliery tunnel support, in addition to face guard, and one end of face guard is " u "-shaped crotch, the crotch of face guard one end is hooked on supporting guard beam, the other end of face guard is stretched out outside roadway support, and face guard is provided with multiple, and multiple face guards simultaneously form a face baffle plate together.Tunnel face guard of the present utility model can be with roadway support, in one protection face of upper formation of roadway support, the protection face can move extension with the extension of roadway support, and the staff or equipment for making working face are under the protection of protection face all the time, are advantageous to Safety of Coal Mine Production.
Description
Technical field
Digging supporting field is the utility model is related to, specifically, the utility model is related to a kind of digging tunnel face guard.
Background technology
Supporting is the stabilization and construction safety after underground passage excavates, and the structure for support, reinforcement or the coated country rock taken
The general name of part or other measures.During using traditional mining method construction, Support types with a hook at the end ore pillar, erection bracket, reinforce rock
Three kinds.
Coal mining tunnel is mostly coal road, is constructed using fully-mechanized digging machine.It is comprehensive excavated goods after, meet head on regular to use defense-help network
Sealed a mountain pass temporarily to meeting face, but two help can not advance support, side portion's wall caving falls cash accident and happens occasionally.For this this project team of phenomenon
The mode that the continuous shift-forward type of forestope uses is imitated, in advance with face guard, improves safety in production coefficient.
The content of the invention
Technical problem to be solved in the utility model is to provide a kind of coal mine roadway face guard, and the face guard can be with lane
Road construction speed shifts to an earlier date supporting, improves safety in production coefficient.
In order to solve the above-mentioned technical problem, technical scheme is used by the utility model:Digging tunnel face guard, including
Supporting guard beam, the supporting guard beam form colliery tunnel support, in addition to face guard, and one end of the face guard is curved for " u "-shaped
Hook, the crotch of face guard one end are hooked on supporting guard beam, and the other end of face guard is stretched out outside roadway support, and the face guard is provided with
Multiple, multiple face guards simultaneously form a face baffle plate together.
Preferably, the face guard is provided with clamp with supporting guard beam contact position, face guard is contacted more with supporting guard beam
Step up close.
Using the technical solution of the utility model, following beneficial effect can be obtained:
Tunnel face guard of the present utility model can be protected with roadway support in the upper formation one of roadway support
Face, the protection face can move extension with the extension of roadway support, make working face staff or equipment be in all the time it is anti-
Under the protection of mask, be advantageous to Safety of Coal Mine Production.
Brief description of the drawings
Brief description is made to the content expressed by each accompanying drawing of this specification and the mark in figure below:
Fig. 1 is structural representation of the present utility model;
Fig. 2 is the structural representation of face guard in Fig. 1;
Mark in above-mentioned figure is:1st, supporting guard beam;2nd, face guard;3rd, clamp;4th, crotch.
Embodiment
Below against accompanying drawing, by the description to embodiment, to specific embodiment of the present utility model as involved
Mutual alignment and annexation, the effect of each several part and operation principle between the shape of each component, construction, each several part etc. make into
The detailed description of one step.
As shown in figure 1, this digging tunnel face guard includes supporting guard beam 1, supporting guard beam 1 forms colliery tunnel support, also
Including face guard 2, as shown in figure 1, one end of face guard 2 is " u "-shaped crotch 4, the crotch 4 of the one end of face guard 2 is hooked in supporting shield
On beam 1, the other end of face guard 2 is stretched out outside roadway support, and face guard 2 is provided with multiple, and multiple face guards simultaneously form one together
Face baffle plate, face guard 2 are provided with clamp 3 with the contact position of supporting guard beam 1, face guard 2 is contacted with supporting guard beam 1 even closer.
Tunnel face guard 2 can be with roadway support during use, and in one protection face of upper formation of roadway support, this is anti-
Mask can move extension with the extension of roadway support, the staff of working face or equipment is in the anti-of protection face all the time
Under shield, be advantageous to Safety of Coal Mine Production.
The utility model is exemplarily described above in conjunction with accompanying drawing, it is clear that the utility model specific implementation not by
The limitation of aforesaid way, as long as employing changing for the various unsubstantialities that methodology and technical scheme of the present utility model are carried out
Enter, or it is not improved by it is of the present utility model design and technical scheme directly apply to other occasions, in the utility model
Protection domain within.
Claims (2)
1. digging tunnel face guard, including supporting guard beam, the supporting guard beam forms colliery tunnel support, it is characterised in that:Also
Including face guard, one end of the face guard is " u "-shaped crotch, and the crotch of face guard one end is hooked on supporting guard beam, face guard
The other end stretch out roadway support outside, the face guard be provided with it is multiple, multiple face guards simultaneously form a face baffle plate together.
2. digging tunnel according to claim 1 face guard, it is characterised in that:The face guard and supporting guard beam contact position
Provided with clamp, face guard is set to be contacted with supporting guard beam even closer.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201720412717.6U CN206801599U (en) | 2017-04-19 | 2017-04-19 | Digging tunnel face guard |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201720412717.6U CN206801599U (en) | 2017-04-19 | 2017-04-19 | Digging tunnel face guard |
Publications (1)
Publication Number | Publication Date |
---|---|
CN206801599U true CN206801599U (en) | 2017-12-26 |
Family
ID=60733348
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201720412717.6U Active CN206801599U (en) | 2017-04-19 | 2017-04-19 | Digging tunnel face guard |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN206801599U (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108915732A (en) * | 2018-07-14 | 2018-11-30 | 高峥嵘 | A kind of novel digging tunnel face guard |
CN110130928A (en) * | 2019-06-28 | 2019-08-16 | 淮北矿业(集团)有限责任公司 | Integrated mole and technique under fully mechanized coal face coal top |
-
2017
- 2017-04-19 CN CN201720412717.6U patent/CN206801599U/en active Active
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108915732A (en) * | 2018-07-14 | 2018-11-30 | 高峥嵘 | A kind of novel digging tunnel face guard |
CN110130928A (en) * | 2019-06-28 | 2019-08-16 | 淮北矿业(集团)有限责任公司 | Integrated mole and technique under fully mechanized coal face coal top |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US11008860B2 (en) | Equipment system for no-roadway no-coal-pillar retained roadway mining method | |
CN205422813U (en) | Detachable filling and retaining wall | |
CN103615250B (en) | The full Open stope mining afterwards filling of itemize studding works in coordination with mining codes | |
CN105443143B (en) | A kind of coal mine gob roadway support device and its construction method | |
CN104653187B (en) | Water-rich sand layer geology large cross-section tunnel excavation method | |
CN205977229U (en) | Arcading tunnel non - flushes entrance to a cave structure suitable for bias voltage condition | |
CN103628911A (en) | Fully-mechanized coal mining/ caving working face sectional type gob-side entry retaining method | |
WO2016206617A1 (en) | Anti-collapse structure beside roadway based on 110 construction method for breaking roof | |
CN107882566A (en) | A kind of gob-side entry retaining method for not influenceing coal mining process | |
CN107956509A (en) | One kind cuts top gob side entry retaining Anti-air-leakage method stage by stage | |
CN107091091A (en) | A kind of steeply-inclined seam mining gob-side entry retaining method of prefabricated arc support | |
CN206801599U (en) | Digging tunnel face guard | |
CN105003288A (en) | Medium-thickness coal seam gob-side entry retaining method and support system | |
CN205277446U (en) | Colliery collecting space area roadway support device | |
CN102966359A (en) | Working face ventilation oxidization zone roof control method | |
CN109915197A (en) | A kind of method that rock gangway km directional long borehole substitution middle part bottom pumping rock gangway is taken out at bottom | |
CN105863639A (en) | Coal-mining method of loose coal seam | |
CN104863588A (en) | Advanced pier column pre-arranging gob-side entry retaining method | |
CN107165641B (en) | High inclination-angle ladder way opposite direction excavating construction method in thin layer breaking up hard rock stratum | |
CN105240012A (en) | F-type section coal-mining method allowing commingled mining of coal pillars | |
CN107503790B (en) | Fast extraction fully mechanized coal face comprehensive gas drainage arranges administering method | |
CN102425431B (en) | Ultra-close coal layer mining roadway distributing method | |
CN204984458U (en) | Medium -thickness seam gob entry's support system | |
CN104179511A (en) | Novel hole arrangement grouting method for enabling ground pre-grouting reinforcing roadway to penetrate through surrounding rocks at fault fracture zone | |
CN107956481A (en) | A kind of suspension device for superelevation tunnel gob side entry retaining |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant |