CN206801066U - Formwork for placing temperature control system - Google Patents
Formwork for placing temperature control system Download PDFInfo
- Publication number
- CN206801066U CN206801066U CN201720626441.1U CN201720626441U CN206801066U CN 206801066 U CN206801066 U CN 206801066U CN 201720626441 U CN201720626441 U CN 201720626441U CN 206801066 U CN206801066 U CN 206801066U
- Authority
- CN
- China
- Prior art keywords
- heat
- water
- pipe
- formwork
- conducting
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)
Abstract
The utility model discloses a kind of formwork for placing temperature control system, heating and the water supply installation to form circulation waterway are connected including water-filled pipe and with water-filled pipe, water-filled pipe comprises at least the heat conducting pipe for being layed in and being set on formwork for placing, the heat-insulation layer that heat conducting pipe includes heat conduction tube body, the heat-conducting seat of corresponding heat conducting pipe body bottom portion fixed setting and outer cladding heat conducting pipe outer body are set;The utility model total system strong applicability, all templates are can apply to, be particularly suitable for use in steel form, is conducted heat by directly acting on template, heat loss can effectively ensure concrete temperature of the mould before form removal less, control concrete quality just, and total system cost is low, and the cost input of winter construction can be effectively controlled while controlling concrete quality, flexibility simultaneously is high, can be freely assembled according to location temperature, and template size and calligraphy or painting model shape.
Description
Technical field
Formwork for placing field is the utility model is related to, more particularly to a kind of formwork for placing temperature control system.
Background technology
Under the background of Large scale construction High-speed Railway Network and network of highways, the construction method of punching block auxiliary casting concrete should
With extensive, however, in north of China, engineering project generally faces such a problem:Because winter temperature is extremely low, concrete pours
When building construction, its temperature can not be efficiently controlled, causes many quality problems, delays the duration.Because traditional measure is typically adopted
With roof insulating is built, interior to be heated up with stove and iodine-tungsten lamp, temperature control effect is extremely bad, it is difficult to ensure that temperature when concrete enters mould
It is required that.Using covering cotton-wadded quilt after the completion of pouring, the traditional approach of additional coal stove heating, also easily cause the concrete temperature difference compared with
Big situation (often higher apart from the nearly temperature of stove, often relatively low apart from the remote temperature of stove), concrete is caused to occur seriously splitting
Line, influence concrete quality.Traditional approach not only puts into height, and operation is extremely inconvenient, and effect is also poor, and burn waste gas row not
Go out, serious body is caused to operating worker and technical staff, if temperature continues to reduce traditional measure with regard to lack scope for their abilities,
It can only stop work, it is particularly disadvantageous for duration tighter engineering project.Low temperature extreme temperature has very big shadow to construction quality
Ring, northern China most area often can all face this extreme temperature.Therefore, effectively control concrete placings temperature is applied to engineering
Work is particularly significant, wherein, effectively control the die plate temperature before mould to form removal mostly important.
Utility model content
In view of this, the utility model provides a kind of formwork for placing temperature control system, can be very good to control concrete
Enter mould to the temperature of form removal front template, and can effectively be reequiped according to any shape, the template of any size.
Formwork for placing temperature control system of the present utility model, including water-filled pipe and connect to form circulation with water-filled pipe
The heating in water route and water supply installation, water-filled pipe comprise at least the heat conducting pipe for being layed in and being set on formwork for placing, and heat conducting pipe includes
The insulation that heat conduction tube body, the heat-conducting seat of corresponding heat conducting pipe body bottom portion fixed setting and outer cladding heat conducting pipe outer body are set
Layer.
Further, heat conducting pipe is at least two be set up in parallel, and water-filled pipe also includes connecting adjacent heat conducting pipe and will led
The connecting pipe that heat pipe connects with heating and water supply installation.
Further, heating and water supply installation include heater and water pump, and control system also includes respectively in water-filled pipe
Water inlet end and water side respectively set one temperature sensor and be connected with temperature sensor and reception signal controller, control
Device processed electrically connects with water pump and heater.
Further, heat-conducting seat is the frustum shape become larger from up to down, and heat conduction bottom of the tube insertion heat-conducting seat is set.
Further, the heat-conducting plate contacted with heat conducting pipe is formed on the bottom of heat-conducting seat, and the heat-conducting plate bottom of each heat conducting pipe is set
It is equipped with the heat-conducting glue layer for being connected with formwork for placing.
Further, the lateral length of heat-conducting plate is more than the diameter of heat conducting pipe.
Further, heat-insulation layer is set around the upper outside of heat conduction tube body and radially opposite sides edge is extended in heat-conducting seat
Portion position.
The beneficial effects of the utility model:Formwork for placing temperature control system of the present utility model, heat conducting pipe, which is laid on, to be poured
On building mould, water is heated by heating and water supply installation and the water after heating is fed into heat conducting pipe, makes the heat-conducting seat of heat conducting pipe
Contacted with formwork for placing, so that the temperature of the water after heating is transmitted into formwork for placing, ensure that the temperature of formwork for placing reaches
Requirement;The utility model total system strong applicability, can apply to all templates, and be particularly suitable for use in steel form, passes through
Template heat transfer is directly acted on, heat loss can effectively ensure concrete temperature of the mould before form removal, control just less
Concrete quality, and total system cost is low, and the cost input of winter construction can be effectively controlled while controlling concrete quality,
Flexibility simultaneously is high, can be freely assembled according to location temperature, and template size and calligraphy or painting model shape.
Brief description of the drawings
The utility model is further described with reference to the accompanying drawings and examples.
Fig. 1 is the utility model total system frame diagram;
Fig. 2 is the heat conducting pipe structural representation in the utility model.
Embodiment
Fig. 1 is the utility model total system frame diagram, and Fig. 2 is the heat conducting pipe structural representation in the utility model, such as
Shown in figure:The formwork for placing temperature control system of the present embodiment, including water-filled pipe and connect to form recirculated water with water-filled pipe
The heating on road and water supply installation 1, water-filled pipe comprise at least the heat conducting pipe 2 for being layed in and being set on formwork for placing, and heat conducting pipe 2 includes
Outside the heat-conducting seat 2-2 and outer cladding heat conduction tube body 2-1 that heat conduction tube body 2-1, corresponding heat conduction tube body 2-1 bottoms are fixedly installed
The heat-insulation layer 2-3 that side is set.Heat conducting pipe 2 is at least two be set up in parallel, and water-filled pipe also includes connecting the adjacent He of heat conducting pipe 2
The connecting pipe 3 that heat conducting pipe 2 is connected with heating and water supply installation 1.Heating and water supply installation 1 include heater and water pump,
Control system also includes respectively setting the temperature sensor of one in the water inlet end of water-filled pipe and water side respectively and passed with temperature
Sensor connects and the controller of reception signal, controller electrically connect with water pump and heater;Wherein, heater is heating
Stove, heater can be integrated the monolithic construction of assembling, or individually independent structure, the water outlet of water-filled pipe with water pump
The water inlet end with heating and water supply installation 1 is held to connect, the water inlet end of the water side and water-filled pipe of heating and water supply installation 1 connects
Logical, temperature sensor sets two, and the water temperature of the water inlet end to water-filled pipe and water side detects respectively, and the temperature difference is at 5 DEG C
It is advisable, when template is excessive, water-filled pipe can be divided into two series loops, to ensure the temperature difference of water inlet end and water side, work as control
When the temperature difference that device processed receives temperature sensor exceedes setting, the water pump pumps speed control temperature difference is increased.
In the present embodiment, heat-conducting seat 2-2 is the frustum shape become larger from up to down, and the bottom of heat conducting pipe 2 is embedded in heat conduction
Seat 2-2 is set;Strengthen conduction heat transfer effect.
In the present embodiment, the heat-conducting plate 2-4 contacted with heat conducting pipe 2 is formed on heat-conducting seat 2-2 bottom, each heat conducting pipe 2
Heat-conducting plate 2-4 bottoms are provided with the heat-conducting glue layer for being connected with formwork for placing;Directly make heat conducting pipe 2 and mould by heat-conducting glue layer
Plate shape is convenient and swift into fixation.
In the present embodiment, heat-conducting plate 2-4 lateral length is more than the diameter of heat conducting pipe 2;Ensure the temperature that heat conducting pipe 2 is fixed
Property, and increase the heat transfer area with template.
In the present embodiment, heat-insulation layer 2-3 is set around heat conduction tube body 2-1 upper outside and radially opposite sides edge extends to
Heat-conducting seat 2-2 medium position;Ensure heat insulation effect.
Finally illustrate, above example is only unrestricted to illustrate the technical solution of the utility model, although ginseng
The utility model is described in detail according to preferred embodiment, it will be understood by those within the art that, can be to this
The technical scheme of utility model is modified or equivalent substitution, without departing from the objective and model of technical solutions of the utility model
Enclose, it all should cover among right of the present utility model.
Claims (7)
- A kind of 1. formwork for placing temperature control system, it is characterised in that:Including water-filled pipe and connect to be formed with water-filled pipe and follow The heating in ring water route and water supply installation, the water-filled pipe comprises at least the heat conducting pipe for being layed in and being set on formwork for placing, described Heat conducting pipe includes heat conduction tube body, the heat-conducting seat and outer cladding heat conducting pipe outer body of corresponding heat conducting pipe body bottom portion fixed setting The heat-insulation layer of setting.
- 2. formwork for placing temperature control system according to claim 1, it is characterised in that:The heat conducting pipe is to be set up in parallel At least two, the water-filled pipe also includes the company for connecting adjacent heat conducting pipe and connecting heat conducting pipe with heating and water supply installation Adapter road.
- 3. formwork for placing temperature control system according to claim 2, it is characterised in that:The heating and water supply installation bag Heater and water pump are included, the control system also includes respectively setting one in the water inlet end of water-filled pipe and water side respectively Temperature sensor and the controller that simultaneously reception signal is connected with temperature sensor, the controller and the water pump and the heating Device electrically connects.
- 4. formwork for placing temperature control system according to claim 3, it is characterised in that:The heat-conducting seat is from up to down The frustum shape become larger, the heat conduction bottom of the tube are embedded in the heat-conducting seat and set.
- 5. formwork for placing temperature control system according to claim 4, it is characterised in that:The bottom of heat-conducting seat is formed with leading The heat-conducting plate of heat pipe contact, the heat-conducting plate bottom of each heat conducting pipe are provided with the heat-conducting glue layer for being connected with formwork for placing.
- 6. formwork for placing temperature control system according to claim 5, it is characterised in that:The lateral length of the heat-conducting plate More than the diameter of the heat conducting pipe.
- 7. formwork for placing temperature control system according to claim 6, it is characterised in that:The heat-insulation layer is around heat conducting pipe sheet The upper outside setting of body and radially opposite sides edge extend to the medium position of heat-conducting seat.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201720626441.1U CN206801066U (en) | 2017-05-27 | 2017-05-27 | Formwork for placing temperature control system |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201720626441.1U CN206801066U (en) | 2017-05-27 | 2017-05-27 | Formwork for placing temperature control system |
Publications (1)
Publication Number | Publication Date |
---|---|
CN206801066U true CN206801066U (en) | 2017-12-26 |
Family
ID=60743618
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201720626441.1U Expired - Fee Related CN206801066U (en) | 2017-05-27 | 2017-05-27 | Formwork for placing temperature control system |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN206801066U (en) |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108843023A (en) * | 2018-07-21 | 2018-11-20 | 四川启创建设工程有限公司 | Extreme cold area in low temperature season concrete construction method |
CN109098459A (en) * | 2018-07-12 | 2018-12-28 | 天津市林海建设工程集团有限公司 | Hot environment concrete wood formwork plate water treatment building anticracking construction method |
CN109826098A (en) * | 2019-02-26 | 2019-05-31 | 东南大学 | A kind of attemperator for high-speed rail bridge winter construction |
CN110259110A (en) * | 2019-06-26 | 2019-09-20 | 中交第二航务工程局有限公司 | Composite shuttering structure and construction method suitable for mass concrete Winter protection |
CN111236668A (en) * | 2020-01-14 | 2020-06-05 | 中国建筑第五工程局有限公司 | Construction method for controlling temperature cracks of mass concrete |
DE202021104298U1 (en) | 2020-08-14 | 2021-09-30 | CHINA RAILWAY ERJU 2nd ENGINEERING CO.,LTD. | Heating and thermal insulation system for casting formwork during construction in winter |
-
2017
- 2017-05-27 CN CN201720626441.1U patent/CN206801066U/en not_active Expired - Fee Related
Cited By (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109098459A (en) * | 2018-07-12 | 2018-12-28 | 天津市林海建设工程集团有限公司 | Hot environment concrete wood formwork plate water treatment building anticracking construction method |
CN108843023A (en) * | 2018-07-21 | 2018-11-20 | 四川启创建设工程有限公司 | Extreme cold area in low temperature season concrete construction method |
CN108843023B (en) * | 2018-07-21 | 2020-08-14 | 四川启创建设工程有限公司 | Concrete construction method in cold region in low-temperature season |
CN109826098A (en) * | 2019-02-26 | 2019-05-31 | 东南大学 | A kind of attemperator for high-speed rail bridge winter construction |
CN110259110A (en) * | 2019-06-26 | 2019-09-20 | 中交第二航务工程局有限公司 | Composite shuttering structure and construction method suitable for mass concrete Winter protection |
CN111236668A (en) * | 2020-01-14 | 2020-06-05 | 中国建筑第五工程局有限公司 | Construction method for controlling temperature cracks of mass concrete |
DE202021104298U1 (en) | 2020-08-14 | 2021-09-30 | CHINA RAILWAY ERJU 2nd ENGINEERING CO.,LTD. | Heating and thermal insulation system for casting formwork during construction in winter |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN206801066U (en) | Formwork for placing temperature control system | |
CN106246209B (en) | A kind of tunnel inner lining concrete insulated curing constructing device and its construction method | |
CN103697595B (en) | The hot water apparatus of storage-type independence leveled heating | |
CN108858697A (en) | A kind of prefabricated simple supported box beam template of Winter protection heating | |
CN206875575U (en) | One kind can heat, zero cold water bathing set composite | |
CN107263690A (en) | Prefabricated components curing means | |
CN204535035U (en) | The electric heater of a kind of speed heat, constant temperature | |
CN205591382U (en) | Press from both sides core heat preservation externally -hanging wallboard | |
CN205636412U (en) | Summer road cooling protection and heat recovery system | |
CN202066208U (en) | Energy saving mechanism of gas water heater | |
CN204853921U (en) | Instant heating type dual -purpose electric water heater device of water storage | |
CN206737426U (en) | Hot environment lower concrete pouring building mould servicing unit | |
CN206982964U (en) | A kind of system of curing concrete prefabricated component | |
CN206859711U (en) | A kind of casting of concrete in mass anticracking heat-exchange system | |
CN106142315A (en) | Assembling die conduction oil maintenance technology | |
CN206488398U (en) | A kind of TABS radiation coolings device and its anti-condensation control system | |
CN206222690U (en) | A kind of drinking water heating furnace | |
CN212452319U (en) | Heating and heat-insulating system for winter construction pouring template | |
CN201443800U (en) | Gripped pipe type heating board | |
CN204448337U (en) | Instant heating type Water outlet spray head | |
CN201163105Y (en) | Constant-temperature fast water heater of external circulating water pump | |
CN209620644U (en) | A kind of cladding system of semi-automatic efficient concrete curing film | |
CN210035873U (en) | Intelligent controller of module pressure-bearing hot water system | |
CN209289503U (en) | A kind of prefabricated simple supported box beam template of Winter protection heating | |
CN206300360U (en) | A kind of domestic solar-energy water heater system |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20171226 Termination date: 20190527 |
|
CF01 | Termination of patent right due to non-payment of annual fee |