CN206800202U - A kind of bridge construction cement grouting tube support arrangement - Google Patents
A kind of bridge construction cement grouting tube support arrangement Download PDFInfo
- Publication number
- CN206800202U CN206800202U CN201720452732.3U CN201720452732U CN206800202U CN 206800202 U CN206800202 U CN 206800202U CN 201720452732 U CN201720452732 U CN 201720452732U CN 206800202 U CN206800202 U CN 206800202U
- Authority
- CN
- China
- Prior art keywords
- cement
- counterweight
- adjustable plate
- cement grouting
- installed above
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)
Abstract
The utility model discloses a kind of bridge construction cement grouting tube support arrangement, including bottom support plate, bar shaped fixing bolt, top adjustable plate and cement recycling can, central tube is installed above the bottom support plate, bottom adjustable plate is installed above the central tube, counterweight is provided with above the bar shaped fixing bolt, balancing pole is installed above the counterweight, counterweight clamping valve is installed above the balancing pole, the top adjustable plate is connected with above the counterweight clamping valve, cement grouting pipe is installed below the top adjustable plate, intrusion pipe supporting table is installed below the cement grouting pipe, steel-wire screen is communicated with below the intrusion pipe supporting table, the cement recycling can is installed above the steel-wire screen, counterweight regulation hook is installed above the cement recycling can.Beneficial effect is:Cement grouting pipeline can be moved, while can prevent that cement drops during perfusion, not only increased perfusion operating efficiency while prevent the waste of cement.
Description
Technical field
Pipeline support equipment technical field is the utility model is related to, is managed more particularly to a kind of bridge construction cement grouting
Road support meanss.
Background technology
Cement:Powdery hydraulicity inorganic coagulation material.Add water stir after into slurry, can harden in atmosphere or in water
Preferably hardening, and can the materials such as sand, stone is cemented together securely.The words of cement mono- are developed by Latin caementum
, be rubble and slabstone the meaning.The mixture of early stage lime and volcanic ash and the lime pozzolanic cement in modern times are much like,
The concrete made of its cementing rubble, not only intensity is higher after hardening, and can also resist the erosion of fresh water or brackish water.It is long
Since phase, it is widely used in the engineerings such as civil construction, water conservancy, national defence as a kind of important binder materials.China exists at present
It can not be moved up and down after being supported when carrying out cement grouting to concrete duct, reduce the operating efficiency of perfusion.
Utility model content
The purpose of this utility model is that to solve the above problems and provides a kind of bridge construction cement grouting pipe
Road support meanss.
The utility model is achieved through the following technical solutions above-mentioned purpose:
A kind of bridge construction cement grouting tube support arrangement, including bottom support plate, bar shaped fixing bolt, top tune
Plate and cement recycling can are saved, central tube is installed above the bottom support plate, bottom regulation is installed above the central tube
Plate, the bottom adjustable plate top are provided with the bar shaped fixing bolt, are provided with counterweight above the bar shaped fixing bolt, institute
State and balancing pole is installed above counterweight, counterweight clamping valve is installed above the balancing pole, connected above the counterweight clamping valve
There is the top adjustable plate, cement grouting pipe is installed below the top adjustable plate, is provided with below the cement grouting pipe
Intrusion pipe supporting table, the intrusion pipe supporting table lower section are communicated with steel-wire screen, the water are provided with above the steel-wire screen
Mud recycling can, the cement recycling can top are provided with counterweight regulation hook.
Further, the bottom support plate is connected with the central tube, and the bottom adjustable plate is fixed with the bar shaped
Bolt connection.
Further, the counterweight is connected with the balancing pole, and the counterweight clamping valve is connected with the top adjustable plate.
Further, the cement grouting pipe is connected with the intrusion pipe supporting table, the steel-wire screen and the cement
Recycling can connects.
Further, the counterweight regulation hook is connected with the top adjustable plate, the counterweight and the intrusion pipe branch
Support platform connection.
The beneficial effects of the utility model are:Cement grouting pipeline can be moved, while can prevent from irrigating
When cement drop, not only increase perfusion operating efficiency while prevent the waste of cement.
Brief description of the drawings
Fig. 1 is a kind of front view of bridge construction cement grouting tube support arrangement described in the utility model;
Fig. 2 is a kind of left view of bridge construction cement grouting tube support arrangement described in the utility model.
Description of reference numerals is as follows:
1st, bottom support plate;2nd, central tube;3rd, bottom adjustable plate;4th, bar shaped fixing bolt;5th, counterweight;6th, balancing pole;7、
Counterweight clamping valve;8th, top adjustable plate;9th, cement grouting pipe;10th, intrusion pipe supporting table;11st, steel-wire screen;12nd, cement reclaims
Tank;13rd, counterweight regulation hook.
Embodiment
The utility model is described in further detail below in conjunction with the accompanying drawings:
As Figure 1-Figure 2, a kind of bridge construction cement grouting tube support arrangement, including bottom support plate 1, bar shaped
Fixing bolt 4, top adjustable plate 8 and cement recycling can 12, the top of bottom support plate 1 are provided with central tube 2, the top of central tube 2
Bottom adjustable plate 3 is installed, the top of bottom adjustable plate 3 is provided with bar shaped fixing bolt 4, and the top of bar shaped fixing bolt 4 is provided with
Counterweight 5, the top of counterweight 5 are provided with balancing pole 6, and the top of balancing pole 6 is provided with counterweight clamping valve 7, and the top of counterweight clamping valve 7 connects
There is top adjustable plate 8, the lower section of top adjustable plate 8 is provided with cement grouting pipe 9, and the lower section of cement grouting pipe 9 is provided with intrusion pipe branch
Platform 10 is supportted, the lower section of intrusion pipe supporting table 10 is communicated with steel-wire screen 11, and the top of steel-wire screen 11 is provided with cement recycling can 12, water
The top of mud recycling can 12 is provided with counterweight regulation hook 13.
Further, bottom support plate 1 is connected with central tube 2, and bottom adjustable plate 3 is connected with bar shaped fixing bolt 4, counterweight
5 are connected with balancing pole 6, and counterweight clamping valve 7 is connected with top adjustable plate 8, and cement grouting pipe 9 is connected with intrusion pipe supporting table 10,
Steel-wire screen 11 is connected with cement recycling can 12, and counterweight regulation hook 13 is connected with top adjustable plate 8, counterweight 5 and intrusion pipe branch
Support platform 10 connects.
General principle, principal character and advantage of the present utility model has been shown and described above.The technical staff of the industry
It should be appreciated that the utility model is not restricted to the described embodiments, the simply explanation described in above-described embodiment and specification is originally
The principle of utility model, on the premise of the spirit and scope of the utility model is not departed from, the utility model also has various change
And improvement, these changes and improvements are both fallen within claimed the scope of the utility model.The utility model requires protection scope
Defined by appended claims and its effect thing.
Claims (5)
- A kind of 1. bridge construction cement grouting tube support arrangement, it is characterised in that:Spiral shell is fixed including bottom support plate, bar shaped Bolt, top adjustable plate and cement recycling can, the bottom support plate top are provided with central tube, are provided with above the central tube Bottom adjustable plate, the bottom adjustable plate top are provided with the bar shaped fixing bolt, set above the bar shaped fixing bolt There is counterweight, balancing pole is installed above the counterweight, counterweight clamping valve, the counterweight clamping valve are installed above the balancing pole Top is connected with the top adjustable plate, is provided with cement grouting pipe below the top adjustable plate, under the cement grouting pipe Side is provided with intrusion pipe supporting table, and steel-wire screen is communicated with below the intrusion pipe supporting table, is installed above the steel-wire screen There is the cement recycling can, counterweight regulation hook is installed above the cement recycling can.
- A kind of 2. bridge construction cement grouting tube support arrangement according to claim 1, it is characterised in that:The bottom Portion's supporting plate is connected with the central tube, and the bottom adjustable plate is connected with the bar shaped fixing bolt.
- A kind of 3. bridge construction cement grouting tube support arrangement according to claim 1, it is characterised in that:It is described to match somebody with somebody Weight is connected with the balancing pole, and the counterweight clamping valve is connected with the top adjustable plate.
- A kind of 4. bridge construction cement grouting tube support arrangement according to claim 1, it is characterised in that:The water Mud intrusion pipe is connected with the intrusion pipe supporting table, and the steel-wire screen is connected with the cement recycling can.
- A kind of 5. bridge construction cement grouting tube support arrangement according to claim 1, it is characterised in that:It is described to match somebody with somebody Reset section hook to be connected with the top adjustable plate, the counterweight is connected with the intrusion pipe supporting table.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201720452732.3U CN206800202U (en) | 2017-04-27 | 2017-04-27 | A kind of bridge construction cement grouting tube support arrangement |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201720452732.3U CN206800202U (en) | 2017-04-27 | 2017-04-27 | A kind of bridge construction cement grouting tube support arrangement |
Publications (1)
Publication Number | Publication Date |
---|---|
CN206800202U true CN206800202U (en) | 2017-12-26 |
Family
ID=60738472
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201720452732.3U Expired - Fee Related CN206800202U (en) | 2017-04-27 | 2017-04-27 | A kind of bridge construction cement grouting tube support arrangement |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN206800202U (en) |
-
2017
- 2017-04-27 CN CN201720452732.3U patent/CN206800202U/en not_active Expired - Fee Related
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN105041336B (en) | A kind of very-high performance hybrid fiber concrete shield duct piece and preparation method thereof | |
CN204955109U (en) | Horizontal cement mixer | |
CN103936368B (en) | C40 level simple grain level regeneration self-compacting concrete and preparation method thereof | |
CN208857626U (en) | A kind of permeable and water storage pavement structure | |
CN207003174U (en) | Anti-block water permeable concrete road surface structure | |
CN106220078A (en) | A kind of mixed earth of lightweight self-compaction regeneration and preparation method thereof | |
CN112723906A (en) | Preparation and construction method of light filler based on building slurry | |
CN102674764A (en) | High water concrete for sidewalks and preparation method thereof | |
CN104529335A (en) | Waste sintered brick regenerative C35 steel fiber reinforced concrete and preparation method thereof | |
CN109824330A (en) | A kind of high-performance middle-and-low strength concrete | |
CN107382215A (en) | A kind of preparation method of high dense concrete road | |
CN107902997A (en) | A kind of pumpable weight concrete | |
CN109704674A (en) | A kind of whisker reinforcement dry slag pervious concrete | |
CN113293930A (en) | UHPC pipe restraint recycled concrete post externally pasted with FRP cloth | |
CN103193439B (en) | High integrity container sealing material and preparation method thereof and application | |
CN107216092B (en) | A kind of cement-based flexible water-permeable brick | |
CN206800202U (en) | A kind of bridge construction cement grouting tube support arrangement | |
CN109467370A (en) | A kind of high additive mixing ceramic tile aggregate C160UHPC and preparation method thereof | |
CN103922659A (en) | Underwater anti-dispersion mortar for large area cavity grouting, and preparation method thereof | |
CN105672203B (en) | A kind of plugging construction method of dykes and dams RCCP | |
CN205684470U (en) | A kind of cement recycle device for building | |
CN107140907A (en) | A kind of concrete of adulterate quartz artificial stone waste residue and flyash | |
CN206829632U (en) | Portable concrete pours device | |
CN107473673A (en) | A kind of double-decker iron tailings sand base water-permeable brick | |
CN207419806U (en) | A kind of girt strip lacing wire for built-in square plaster mould box cast-in-place concrete hollow floor slab |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20171226 Termination date: 20180427 |
|
CF01 | Termination of patent right due to non-payment of annual fee |