CN206793445U - New two-component gum production equipment - Google Patents

New two-component gum production equipment Download PDF

Info

Publication number
CN206793445U
CN206793445U CN201720187023.7U CN201720187023U CN206793445U CN 206793445 U CN206793445 U CN 206793445U CN 201720187023 U CN201720187023 U CN 201720187023U CN 206793445 U CN206793445 U CN 206793445U
Authority
CN
China
Prior art keywords
screw rod
component
rod conveyor
finished product
batch mixing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201720187023.7U
Other languages
Chinese (zh)
Inventor
吴葵清
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Yunfu Ze New Material Science And Technology Development Co Ltd
Original Assignee
Yunfu Ze New Material Science And Technology Development Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Yunfu Ze New Material Science And Technology Development Co Ltd filed Critical Yunfu Ze New Material Science And Technology Development Co Ltd
Priority to CN201720187023.7U priority Critical patent/CN206793445U/en
Application granted granted Critical
Publication of CN206793445U publication Critical patent/CN206793445U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Basic Packing Technique (AREA)

Abstract

A kind of new two-component gum production equipment, including:Raw material puts in storage component, its first screw rod conveyor for including hopper and being connected with hopper;Gauge assembly, it includes measuring chute, and measuring chute is arranged on below the first screw rod conveyor;Second screw rod conveyor, the second screw rod conveyor are connected with measuring chute;Batch mixing component, batch mixing component are arranged on below the second screw rod conveyor;3rd screw rod conveyor, the 3rd screw rod conveyor are connected with batch mixing component;Package component, package component are connected with the 3rd screw rod conveyor.Realize that the mechanization of granular material conveys using screw rod conveyor in the utility model, gauge assembly, batch mixing component and package component, material can be measured, mixed and be packed, for traditional manual work, not only operating efficiency is improved for it, also, is completed in material conveying process by plant equipment, it need not manually participate in, which solve the problem of airborne dust impacts for staff's health.

Description

New two-component gum production equipment
Technical field
Waterproof gum production equipment technology is the utility model is related to, it is more specifically, more particularly to a kind of new double Component gum production equipment.
Background technology
In the prior art, it is essentially all that ground is pasted using cement slurry to the ceramic tile either stone material such as marble Or on metope, although the stone material such as ceramic tile or marble has excellent water resistance, easily occur in its stitching portion Seepage problem, also, the cement slurry for pasting can not be filled up completely between ceramic tile or marble and cement base aspect Gap, once there is seepage problem, the water body of infiltration is filled in gap for a long time, can gradually permeate ceramic tile or marble, So that ceramic tile or marble surface discoloration, influence its aesthetic property.In addition, the water body of infiltration can also reduce ceramic tile or marble Service life, if in high residential building, infiltration can also cause lower floor's leak, influence to live.
, typically all can be in cement basic layer in order to solve above-mentioned seepage problem to improve ceramic tile or marmorean water resistance Water-proofing treatment is done in face, although can so solve the problems, such as infiltration downwards in skyscraper, exist in ceramic tile or Dali Stone can aggravate to ceramic tile or marmorean erosion with the water body in cement base aspect.
In order to solve infiltration to ceramic tile or marmorean influence, one can be typically brushed in ceramic tile or the marmorean back side Layer waterproof gum, waterproof gum is usually to be made of unsaturated-resin powder, all by people in waterproof gum production process Work realizes transhipment of the raw material between each production equipment, and so there are the following problems for meeting:1st, production efficiency is relatively low, productive labor Intensity is larger;2nd, easily there is airborne dust in unsaturated-resin powder, influences the health of staff.
Utility model content
(1) technical problem
In summary, a kind of waterproof gum production system how is provided, for the mechanization production of waterproof gum, so as to carry High efficiency, become those skilled in the art's urgent problem to be solved.
(2) technical scheme
The utility model provides a kind of new two-component gum production equipment, and the production equipment specifically includes:
Raw material puts in storage component, and the raw material component that puts in storage includes for the hopper of loaded material and for conveying material The first screw rod conveyor, first screw rod conveyor is obliquely installed, and first screw rod conveyor includes first entrance End and first exit end, on vertical direction, the first exit end be higher than the first entrance end, first screw rod is defeated Machine is sent to be connected by the first entrance end with the hopper;
For the gauge assembly measured to material, the gauge assembly includes measuring chute, and the measuring chute is bucket Shape structure, the measuring chute is vertically arranged, its upper end is heavy caliber entrance, its lower end is small-bore outlet, the measuring chute Heavy caliber entrance is oppositely arranged with the first exit end in the vertical direction;
For the second screw rod conveyor conveyed to material, second screw rod conveyor is obliquely installed, and described Two screw rod conveyors include second entrance end and second outlet end, on vertical direction, the second outlet end be higher than institute State second entrance end, the small-bore outlet pair that second screw rod conveyor passes through the second entrance end and the measuring chute Connect;
For the batch mixing component mixed to material, the batch mixing component includes crust of the device, described device shell With mixing chamber, in being provided with agitating device in the mixing chamber, batch mixing entrance is offered in the top of described device shell, in The side wall of described device shell simultaneously offers batch mixing outlet close to the position of its bottom, and the batch mixing entrance goes out with described second Mouth end in the vertical direction is oppositely arranged;
For the 3rd screw rod conveyor conveyed to material, the 3rd screw rod conveyor is obliquely installed, and described Three screw rod conveyors include the 3rd arrival end and the 3rd port of export, on vertical direction, the 3rd port of export be higher than institute The 3rd arrival end is stated, the 3rd screw rod conveyor is docked by the 3rd arrival end with batch mixing outlet;
Package component, the package component include finished product bin, be provided with the downside of the finished product bin for pair The packing machine that granular material is packed, finished product charging aperture, the bottom of the finished product bin are offered at the top of the finished product bin Portion offers finished product discharging opening, and the packing machine is installed on the finished product discharging opening, the finished product charging aperture and the described 3rd Port of export in the vertical direction is oppositely arranged.
Preferably, the utility model also includes dedusting component;The dedusting component includes exhaust column, dust removing funnel, wind Machine and aggregate bin, the dust removing funnel are vertically arranged, and the dust removing funnel has dirt pocket, in being provided with dedusting in the dirt pocket Filter screen, positioned at the upside of the dedusting filter screen, suction opeing is offered at the top of the dust removing funnel, the blower fan is arranged at described On suction opeing, air intake vent is offered positioned at the downside of the dedusting filter screen, in the side wall of the dust removing funnel, the one of the exhaust column End docked with the air intake vent, the other end of the exhaust column is arranged in packing machine, positioned at the downside of the dedusting filter screen, in The bottom of the dust removing funnel offers dust-exhausting port, and the aggregate bin is arranged on the dust-exhausting port.
Preferably, the finished product bin is funnel-shaped structure.
Preferably, the hopper is stainless steel hopper, and the finished product bin is stainless steel finished product bin, and the aggregate bin is Stainless steel aggregate bin, the dust removing funnel are stainless steel dedusting bucket.
Preferably, the raw material component that puts in storage is provided with least two, and whole raw materials component that puts in storage is set up in parallel.
(3) beneficial effect
Pass through said structure design, in new two-component gum production equipment provided by the utility model, the first screw rod Conveyer, the second screw rod conveyor and the 3rd screw rod conveyor can realize the mechanization of granular material between the individual devices Conveying, also, the utility model additionally provides gauge assembly, batch mixing component and package component, and material can be measured, Mixing and packaging.The utility model produce waterproof gum, its conveying for material, metering, mixing and packaging all by Plant equipment is completed, and for traditional manual work, not only operating efficiency is improved for it, also, defeated in material Send in link and completed by plant equipment, it is not necessary to it is artificial to participate in, which solve what airborne dust impacted for staff's health Problem.
Brief description of the drawings
Fig. 1 is the structural representation of new two-component gum production equipment in the utility model embodiment;
Fig. 2 is the side structure schematic diagram of new two-component gum production equipment in the utility model embodiment;
In fig. 1 and 2, the corresponding relation of component names and accompanying drawing number is:
Hopper 1, the first screw rod conveyor 2, measuring chute 3, it is small-bore outlet 4,
Second screw rod conveyor 5, crust of the device 6, mixing chamber 7, the 3rd screw rod conveyor 8,
Finished product bin 9, packing machine 10, exhaust column 11, dust removing funnel 12, blower fan 13,
Aggregate bin 14.
Embodiment
Embodiment of the present utility model is described in further detail with reference to the accompanying drawings and examples.Following examples For illustrating the utility model, but can not be used for limiting the scope of the utility model.
In description of the present utility model, unless otherwise indicated, " multiple " are meant that two or more;Term The orientation or position of the instruction such as " on ", " under ", "left", "right", " interior ", " outer ", " front end ", " rear end ", " head ", " afterbody " are closed It is to be described based on orientation shown in the drawings or position relationship, to be for only for ease of description the utility model and simplifying, rather than Indicate or imply that signified device or element there must be specific orientation, with specific azimuth configuration and operation, therefore can not It is interpreted as to limitation of the present utility model.In addition, term " first ", " second ", " the 3rd " etc. are only used for describing purpose, and can not It is interpreted as indicating or implying relative importance.
, it is necessary to illustrate in description of the present utility model, unless otherwise clearly defined and limited, term " phase Even ", " connection " should be interpreted broadly, for example, it may be being fixedly connected or being detachably connected, or be integrally connected;Can To be mechanical connection or electrical connection;Can be joined directly together, can also be indirectly connected by intermediary.For this For the those of ordinary skill in field, concrete meaning of the above-mentioned term in the utility model can be understood with concrete condition.
Fig. 1 and Fig. 2 are refer to, wherein, Fig. 1 is the knot of new two-component gum production equipment in the utility model embodiment Structure schematic diagram;Fig. 2 is the side structure schematic diagram of new two-component gum production equipment in the utility model embodiment.
The utility model provides a kind of new two-component gum production equipment, and the gum production equipment is used to realize waterproof The mechanization production operation of gum.
In an embodiment of the present utility model, the two-component gum production equipment has specifically included following equipment:
1st, raw material puts in storage component, and the raw material component that puts in storage includes for the hopper 1 of loaded material and for conveying material The first screw rod conveyor 2.Hopper 1 uses bucket-shaped structure design, and in the utility model, hopper 1 is used to load raw material, hopper 1 is made of metal material, and it is preferably made of stainless-steel sheet welding, and certainly, hopper 1 can also use aluminium sheet.
First screw rod conveyor 2 is obliquely installed, and the first screw rod conveyor 2 includes feed pipe, rotatable in feed pipe Ground is provided with power transmission shaft, in being provided with spiral wing plate on power transmission shaft, sets a motor on the top of feed pipe, utilizes drive Dynamic motor driven drive axis, the spiral wing plate being arranged on power transmission shaft rotate, it becomes possible to realize the conveying of granular material.
First screw rod conveyor 2 includes first entrance end and first exit end, specifically, first entrance end and One port of export is opened in the both ends of feed pipe respectively, on vertical direction, first exit end be higher than first entrance end, the first screw rod Conveyer 2 is connected by first entrance end with hopper 1.The bottom of hopper 1 offers an opening, first entrance end and the opening Dock, the granular material inside hopper 1 can enter in the first screw rod conveyor 2 from first entrance end under gravity, so The conveying of material between devices is realized in the presence of the first screw rod conveyor 2 afterwards.
2nd, gauge assembly, gauge assembly are used to measure material, and gauge assembly includes measuring chute 3, and measuring chute 3 is Bucket-shaped structure, measuring chute 3 is vertically arranged, its upper end is heavy caliber entrance, its lower end be it is small-bore outlet 4, the big mouth of measuring chute 3 Footpath entrance is oppositely arranged with first exit end in the vertical direction.
The volume measurement scale for being identified to its volume is provided with measuring chute 3.Due in the utility model Using granular material, the density of material is held essentially constant, and this makes it possible to entered volume of material and weight of material by calculating Row conversion, the volume by determining material can just obtain the weight of material.The volume measurement scale set inside measuring chute 3 For being measured to volume of material, thus can is measured to weight of material.
3rd, it is obliquely installed for the second screw rod conveyor 5 conveyed to material, the second screw rod conveyor 5, the second spiral shell Bar conveyer 5 includes second entrance end and second outlet end, on vertical direction, second outlet end be higher than second entrance End, the second screw rod conveyor 5 are docked by second entrance end with the small-bore outlet 4 of measuring chute 3.
In the utility model, the second screw rod conveyor 5 is similar to the structure of the first screw rod conveyor 2, refer to above-mentioned first The structure of screw rod conveyor 2, no longer the structure of the second screw rod conveyor 5 is repeated herein.
4th, for the batch mixing component mixed to material, due to raw material used in the utility model include it is a variety of, Therefore, the utility model provides batch mixing component and the raw material of whole can be mixed.
Batch mixing component includes crust of the device 6, and crust of the device 6 has mixing chamber 7, is filled in being provided with stirring in mixing chamber 7 Put, batch mixing entrance is offered in the top of crust of the device 6, offered in the side wall of crust of the device 6 and the position of its close bottom Batch mixing is exported, and batch mixing entrance is oppositely arranged with second outlet end in the vertical direction.
The upper end of mixing chamber 7 is provided with batch mixing entrance, and plurality of raw materials can be entered in mixing chamber 7 by batch mixing entrance. Blade stirrer device is provided with mixing chamber 7, after being mounted with material in mixing chamber 7, starts agitating device and is slowly stirred. Batch mixing outlet is offered in the side wall of mixing chamber 7, batch mixing is provided with valve in outlet, when needing that mixing is stirred to material When, valve is closed, when material stirring finishes, opening valve is exported mixed material.
5th, it is obliquely installed for the 3rd screw rod conveyor 8 conveyed to material, the 3rd screw rod conveyor 8, the 3rd spiral shell Bar conveyer 8 includes the 3rd arrival end and the 3rd port of export, on vertical direction, the 3rd port of export be higher than the 3rd entrance End, the 3rd screw rod conveyor 8 are docked by the 3rd arrival end with batch mixing outlet.
In the utility model, the 3rd screw rod conveyor 8 is similar to the structure of the first screw rod conveyor 2, refer to above-mentioned first The structure of screw rod conveyor 2, no longer the structure of the 3rd screw rod conveyor 8 is repeated herein.
6th, package component, package component are used to pack mixed finished product material.Package component includes finished product material Storehouse 9, finished product bin 9 are used to load finished product powder, are provided with the downside of finished product bin 9 for being packed to granular material Packing machine 10, the top of finished product bin 9 offer finished product charging aperture, and the bottom of finished product bin 9 offers finished product discharging opening, packaging Machine 10 is installed on finished product discharging opening, and finished product charging aperture is oppositely arranged with the 3rd port of export in the vertical direction.
Packing machine 10 used in the utility model uses the packing machine that can be packed in the prior art to granular material, Because the utility model is not improved to the structure of packing machine 10, therefore, the concrete structure of packing machine 10 is not repeated.
Pass through said structure design, in new two-component gum production equipment provided by the utility model, the first screw rod Conveyer 2, the second screw rod conveyor 5 and the 3rd screw rod conveyor 8 can realize the machine of granular material between the individual devices Toolization conveys, also, the utility model additionally provides gauge assembly, batch mixing component and package component, and material can be carried out Metering, mixing and packaging.The utility model produces waterproof gum, and its conveying for material, metering, mixing and packaging are complete Portion is completed by plant equipment, and for traditional manual work, not only operating efficiency is improved for it, also, in thing Completed in material conveying process by plant equipment, it is not necessary to it is artificial to participate in, which solve airborne dust and cause shadow for staff's health The problem of ringing.
Specifically, the utility model also includes dedusting component, and dedusting component is used to carry out dedusting operation to packing machine 10.
In the utility model, dedusting component includes exhaust column 11, dust removing funnel 12, blower fan 13 and aggregate bin 14, removes Dirt bucket 12 is vertically arranged, and dust removing funnel 12 has dirt pocket, in being provided with dedusting filter screen in dirt pocket, positioned at the upper of dedusting filter screen Side, in the top of dust removing funnel 12 offer suction opeing, blower fan 13 is arranged on suction opeing, positioned at the downside of dedusting filter screen, in except The side wall of dirt bucket 12 offers air intake vent, and one end of exhaust column 11 is docked with air intake vent, and the other end of exhaust column 11 is arranged at bag In installation 10, dust-exhausting port is offered positioned at the downside of dedusting filter screen, in the bottom of dust removing funnel 12, aggregate bin 14 is arranged at dust-exhausting port On.
Packing machine 10 includes discharging gate, material inevitably airborne dust after discharging gate output, in discharging gate Top one dust excluding hood is set, the end of exhaust column 11 is set onto dust excluding hood, the startup optimization of blower fan 13 enables to remove Dirt room forms negative pressure, and dirt pocket is by exhaust column 11 to carrying out air-breathing around discharging gate, this makes it possible to by around discharging gate Airborne dust siphons away.Airborne dust enters in dirt pocket and is filtered, reclaimed in the presence of dedusting filter screen.
Specifically, finished product bin 9 is funnel-shaped structure.
Specifically, hopper 1 is stainless steel hopper, and finished product bin 9 is stainless steel finished product bin, and aggregate bin 14 is stainless steel collection Hopper, dust removing funnel 12 are stainless steel dedusting bucket.
In order to accelerate feeding efficiency and realize the feeding operation of multi-component masses, the utility model puts in storage raw material component It is provided with least two, whole raw materials component that puts in storage is set up in parallel.
Embodiment of the present utility model in order to example and description for the sake of and provide, and be not exhaustively or will The utility model is limited to disclosed form.Many modifications and variations are aobvious and easy for the ordinary skill in the art See.Selection and description embodiment are to more preferably illustrate principle and practical application of the present utility model, and make this area Those of ordinary skill it will be appreciated that the utility model so as to designing the various embodiments with various modifications suitable for special-purpose.

Claims (5)

  1. A kind of 1. new two-component gum production equipment, it is characterised in that including:
    Raw material puts in storage component, and the raw material component that puts in storage includes for the hopper (1) of loaded material and for conveying material The first screw rod conveyor (2), first screw rod conveyor is obliquely installed, and first screw rod conveyor includes first and entered Mouthful end and first exit end, on vertical direction, the first exit end be higher than the first entrance end, first screw rod Conveyer is connected by the first entrance end with the hopper;
    For the gauge assembly measured to material, the gauge assembly includes measuring chute (3), and the measuring chute is bucket-shaped Structure, the measuring chute is vertically arranged, its upper end is heavy caliber entrance, its lower end is small-bore outlet (4), the measuring chute Heavy caliber entrance is oppositely arranged with the first exit end in the vertical direction;
    For the second screw rod conveyor (5) conveyed to material, second screw rod conveyor is obliquely installed, and described second Screw rod conveyor includes second entrance end and second outlet end, on vertical direction, the second outlet end is higher than described Second entrance end, second screw rod conveyor are docked by the second entrance end with the small-bore outlet of the measuring chute;
    For the batch mixing component mixed to material, the batch mixing component includes crust of the device (6), described device shell tool There is mixing chamber (7), in being provided with agitating device in the mixing chamber, batch mixing entrance offered in the top of described device shell, Side wall in described device shell and the position close to its bottom offer batch mixing outlet, the batch mixing entrance and described second Port of export in the vertical direction is oppositely arranged;
    For the 3rd screw rod conveyor (8) conveyed to material, the 3rd screw rod conveyor is obliquely installed, and the described 3rd Screw rod conveyor includes the 3rd arrival end and the 3rd port of export, on vertical direction, the 3rd port of export is higher than described 3rd arrival end, the 3rd screw rod conveyor are docked by the 3rd arrival end with batch mixing outlet;
    Package component, the package component include finished product bin (9), are provided with the downside of the finished product bin for powder The packing machine (10) that shape material is packed, finished product charging aperture is offered at the top of the finished product bin, the finished product bin Bottom offers finished product discharging opening, and the packing machine is installed on the finished product discharging opening, the finished product charging aperture and described the Three port of export in the vertical directions are oppositely arranged.
  2. 2. new two-component gum production equipment according to claim 1, it is characterised in that
    Also include dedusting component;
    The dedusting component includes exhaust column (11), dust removing funnel (12), blower fan (13) and aggregate bin (14), the dust removing funnel It is vertically arranged, the dust removing funnel has dirt pocket, in being provided with dedusting filter screen in the dirt pocket, positioned at the dedusting filter screen Upside, suction opeing is offered at the top of the dust removing funnel, the blower fan is arranged on the suction opeing, is filtered positioned at the dedusting The downside of net, in the side wall of the dust removing funnel air intake vent is offered, one end of the exhaust column is docked with the air intake vent, described The other end of exhaust column is arranged in the packing machine, is opened positioned at the downside of the dedusting filter screen, in the bottom of the dust removing funnel Provided with dust-exhausting port, the aggregate bin is arranged on the dust-exhausting port.
  3. 3. new two-component gum production equipment according to claim 1, it is characterised in that
    The finished product bin is funnel-shaped structure.
  4. 4. new two-component gum production equipment according to claim 2, it is characterised in that
    The hopper is stainless steel hopper, and the finished product bin is stainless steel finished product bin, and the aggregate bin gathers materials for stainless steel Bucket, the dust removing funnel is stainless steel dedusting bucket.
  5. 5. the new two-component gum production equipment according to any one of Claims 1-4, it is characterised in that
    The raw material component that puts in storage is provided with least two, and whole raw materials component that puts in storage is set up in parallel.
CN201720187023.7U 2017-02-28 2017-02-28 New two-component gum production equipment Expired - Fee Related CN206793445U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720187023.7U CN206793445U (en) 2017-02-28 2017-02-28 New two-component gum production equipment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720187023.7U CN206793445U (en) 2017-02-28 2017-02-28 New two-component gum production equipment

Publications (1)

Publication Number Publication Date
CN206793445U true CN206793445U (en) 2017-12-26

Family

ID=60728365

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720187023.7U Expired - Fee Related CN206793445U (en) 2017-02-28 2017-02-28 New two-component gum production equipment

Country Status (1)

Country Link
CN (1) CN206793445U (en)

Similar Documents

Publication Publication Date Title
CN204823321U (en) Material delivery system
CN207808071U (en) A kind of concrete batching and mixing tower
CN203821209U (en) Multifunctional continuous asphalt concrete mixing station and multifunctional continuous cement stabilized soil mixing station
CN205735543U (en) Automatic blending stirring bipyramid mortar jar
CN207256547U (en) A kind of batching plant of automatic blanking
CN207535080U (en) A kind of dry powder and mortar mixing plant
CN109506749A (en) Strontium ferrite powder weighs feed proportioning system
CN109676785A (en) A kind of dry powder and mortar mixing arrangement convenient for quantitative discharging
CN206793445U (en) New two-component gum production equipment
CN206339287U (en) A kind of dry powder and mortar metering device
CN205651515U (en) Dry powder mortar agitating mixing apparatus
CN104191522B (en) Concrete raw material container and concrete raw material storage mixing output all-in-one
CN209254615U (en) A kind of construction material dosing conveying mixing device
CN207656961U (en) Powder weighing device and the mixing plant for using the powder weighing device
CN202053375U (en) Device for continuously producing stucco gypsum
CN205704666U (en) A kind of concrete integrated production system
CN203391118U (en) Floor standing type dry-mixed mortar mixing plant
CN211310171U (en) Efficient, environment-friendly and energy-saving dry powder mortar production line
CN211310188U (en) Rock wool batching fill
CN210616915U (en) A pnematic mixing arrangement of concrete preparation for little engineering
CN211893716U (en) Powder packagine machine and powder stirring equipment for packing
CN210556973U (en) Dry-mixed mortar batching and discharging device
CN209903597U (en) Gypsum-based dry powder mortar production equipment
CN102975291A (en) Thermal-insulating mortar proportioning and stirring equipment
CN207310264U (en) Environmentally friendly mortar integration production case

Legal Events

Date Code Title Description
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20171226