CN206774908U - A kind of novel transition cabinet for substation equipment maintenance and repair - Google Patents
A kind of novel transition cabinet for substation equipment maintenance and repair Download PDFInfo
- Publication number
- CN206774908U CN206774908U CN201720552956.1U CN201720552956U CN206774908U CN 206774908 U CN206774908 U CN 206774908U CN 201720552956 U CN201720552956 U CN 201720552956U CN 206774908 U CN206774908 U CN 206774908U
- Authority
- CN
- China
- Prior art keywords
- cabinet
- repair
- phase
- equipment maintenance
- substation equipment
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Abstract
The utility model discloses a kind of novel transition cabinet for substation equipment maintenance and repair, including first and second cabinet, linked together between first and second cabinet by two cable fast interfaces;The cabinet body both sides of first and second cabinet are respectively arranged with several auxiliary wheels, and the bottom of cabinet body is provided with universal wheel, and link cable fast interface is separately positioned on the top of first and second cabinet between cabinet.Split-type structural of the present utility model is easy to operating personnel to carry, enable operating personnel it is intuitive and reliable disconnect line, blind spot in cancel job human users, improve the security of operation, simplify and disconnect sequence of threads, shorten the time for disconnecting cable, it is ensured that recover power transmission within the work plan time, it is ensured that power grid operation.Mobile network's module is added simultaneously, realizes the service data of remote monitoring transition cabinet.
Description
Technical field
It the utility model is related to a kind of transition cabinet, more particularly to a kind of novel transition cabinet for substation equipment maintenance and repair.
Background technology
At present, the transition cabinet product of existing transformer station's ac and dc systemses operation is carried greatly constant, is easily collided with.And
The mode of connection of outgoing is a kind of guide tracked terminal block of common bar shaped, and every wiring is required for fastened by screw, fastening screw
Easily it is lost in operation in ordinary disconnect.Cable is disconnected from terminal block and is occupied and stops electric power feeding time as defined in most of operations, and
And each element laying is compact in transition cabinet, wiring mouth down is located at cabinet lower end, and operating personnel's sight, which is blocked, disconnects line pole
Its inconvenience.Terminal block and air switch are in cabinet, and former cable is accessed transition cabinet terminal in the external side of cabinet door by signal lamp every time
Row, close to need after air switch to shut cabinet door and check signal lamp situation or two people's above operating personnel's compounding practices, easily go out
Now link up bad or maloperation and accident occur.In actual job, every cable size has different situations, guide tracked terminal block
Socket is all unified size, there is the cable inserting situation that upper terminal is not arranged that diameter is excessive, and the interim emergent management that carries out simultaneously causes
Duration is delayed.Due to the limitation that transformer station's master control room equipment is put, transition cabinet and screen to be replaced are apart from cable that is long, pulling down
Length is too short can not to access transition cabinet terminal block, it is necessary to which operating personnel's manipulative compression joint jumper successively, causes to take time and effort
The situation of duration.Now most of is unattended operation transformer station, needs run within continuous several days according to work flow, night nobody
Make an inspection tour, running situation can not find to handle emergency situations in time.
The content of the invention
The purpose of this utility model is, there is provided a kind of novel transition cabinet for substation equipment maintenance and repair, transition cabinet design are closed
Reason, disconnects line and is more convenient, and security is more preferable, and operating efficiency is high.
To achieve the above object, the technical solution adopted in the utility model is, a kind of new mistake for substation equipment maintenance and repair
Cabinet, including the first cabinet and the second cabinet are crossed, is connected between first and second cabinet by link cable fast interface between two cabinets
It is connected together, the cabinet body both sides of first and second cabinet are respectively arranged with several auxiliary wheels, and the bottom of cabinet body is provided with universal
Take turns, link cable fast interface is separately positioned on the top of first and second cabinet between cabinet.
Preferably, instrument display, mobile network monitoring device, whole is disposed with first cabinet from top to bottom
Flow unit, insulated monitoring unit and battery control unit;
It has been arranged side by side that three-phase feeds out Wiring module and two-phase feeds out Wiring module in second cabinet.
The transition cabinet of this patent uses split-type structural, and specially placement is used in a cabinet and feeds out Wiring module, another
It is used to place some main electronic units in individual cabinet so that the distribution of transition cabinet is more reasonable, and maintenance is more convenient.
Preferably, positioned at the three-phase feed out Wiring module and two-phase feed out Wiring module between shared zero is installed
Phase and the fast connection interface of ground connection.
Preferably, the cabinet body both sides of first and second cabinet are respectively arranged with two auxiliary wheels, and two auxiliary wheels it
Between connected by bar, convenient lift fortune cabinet.
Preferably, the front and rear of second cabinet is both provided with cabinet door, and handle is installed in cabinet door, is easy to open cabinet
Door carries out checking maintenance.
Preferably, being provided with locking system on the universal wheel, the main effect of locking system is run in machine
When, play fixed effect.
Preferably, connected between two cabinets between link cable fast interface by one or more cable connections
Together, it is attached when facilitating two cabinets distant.
Preferably, the connection between every two cables is all linked together with the connected mode of pin and box sub, it is so electric
Cable, which links together, unique interface, prevents cable wrong plug head.
Preferably, the three-phase feeds out Wiring module by three-phase fast-wiring, air switch, signal lamp and display screen
Composition, three-phase fast-wiring mouth are vertically provided at the side of module, and it is fast that air switch, signal lamp and display screen are arranged on three-phase
The opposite side of fast connection jaws.Three-phase feeds out Wiring module and is provided with several, and it is fast by three-phase that each three-phase feeds out Wiring module
Quick access line, air switch, signal lamp and display screen composition, air switch are used for control circuit break-make, and signal lamp is used to show
The electriferous state of this circuit, display screen are used to show the information such as voltage, the electric current of this circuit.
The beneficial effects of the utility model:The operating process same plane of transition cabinet of the present utility model, improves behaviour
The efficiency of work, shortens power off time;Fast quick-recovery power transmission, reduces the loss of operation of power networks.Split of the present utility model
Formula structure is easy to operating personnel to carry, enable operating personnel it is intuitive and reliable disconnect line, the blind spot in cancel job human users,
The security of operation is improved, simplifies and disconnects sequence of threads, shortens the time for disconnecting cable, it is ensured that in the work plan time
Interior recovery power transmission, it is ensured that power grid operation.Mobile network's module is added simultaneously, realizes the operation of remote monitoring transition cabinet
Data.
Brief description of the drawings
, below will be to institute in embodiment or description of the prior art in order to illustrate more clearly of the technical solution of the utility model
The accompanying drawing needed to use is briefly described.
Fig. 1 is the structural representation of the cabinet of the utility model first;
Fig. 2 is Fig. 1 top view;
Fig. 3 is the structural representation of the cabinet of the utility model second;
Fig. 4 is Fig. 3 top view;
Fig. 5 is the structural representation that the utility model three-phase feeds out Wiring module;
In figure:1. the first cabinet, 2. second cabinets, link cable fast interface between 3. cabinets, 4. auxiliary wheels, 5. universal wheels,
6. instrument display, 7. mobile network monitoring devices, 8. rectification units, 9. three-phases feed out Wiring module, 10. two-phases feed out wiring mould
Block;11. fast connection interface, 12. bars, 13. handles, 14. three-phase fast-wiring mouths, 15. air switches, 16. signal lamps, 17.
Display screen, 18. insulated monitoring units, 19. battery control units.
Embodiment
In order that those skilled in the art more fully understand the technical scheme in the application, below in conjunction with embodiment pair
Technical scheme in the application is clearly and completely described.
As described in Fig. 1-Fig. 4, the utility model discloses a kind of novel transition cabinet for substation equipment maintenance and repair, including the first cabinet
The cabinet 2 of body 1 and second;Between first and second cabinet 1 and 2 one is connected to by link cable fast interface 3 between two cabinets
Rise, the first cabinet 1 inputs for exchange, and the second cabinet 2 is direct current output;The cabinet body both sides of first and second cabinet are set respectively
Have several auxiliary wheels 4, the bottom of cabinet body is provided with universal wheel 5, between cabinet link cable fast interface 3 be separately positioned on first,
The top of two cabinets.
Instrument display 6, mobile network monitoring device 7, rectification unit are disposed with first cabinet 1 from top to bottom
8th, insulated monitoring unit 18 and battery control unit 19;Three-phase has been arranged side by side on second cabinet 2 and has fed out wiring mould
Block 9 and two-phase feed out Wiring module 10.
The mobile network monitoring device 7 is used to monitor AC distribution, DC distribution, charging module, temporary accumulator cell group etc.
Specific running situation.The insulating monitoring unit 18 can monitor the insulation against ground situation of dc bus and each branch road on-line.
Wiring module 9 is fed out positioned at the three-phase and two-phase feeds out and is provided with zero shared phase between Wiring module 10 and connects
The fast connection interface 11 on ground, it is served only in the second cabinet 2 placing outgoing, facilitates maintenance and safeguard.
The cabinet body both sides of first and second cabinet are respectively arranged with two auxiliary wheels 4, and pass through between two auxiliary wheels 4
Bar 12 connects, convenient lift fortune cabinet.
The front and rear of second cabinet 2 is both provided with cabinet door, and handle 13 is provided with cabinet door, is easy to open cabinet door progress
Check maintenance;The front and rear of first cabinet 1 is also equipped with cabinet door.
Locking system is provided with the universal wheel 5, the main effect of locking system is, when machine is run, plays solid
Fixed effect.
Linked together between two cabinets between link cable fast interface 3 by one or more cable connections,
It is attached when facilitating two cabinets distant.
Connection between every two cables is all linked together with the connected mode of pin and box sub, and such cable connection is one
Rising has unique interface, prevents cable wrong plug head.
As shown in figure 5, the three-phase feed out Wiring module 9 by three-phase fast-wiring 14, air switch 15, signal lamp 16 with
And display screen 17 forms, three-phase fast-wiring mouth 14 is vertically provided at the side of module, air switch 15, signal lamp 16 and aobvious
Display screen 17 is arranged on the opposite side of three-phase fast-wiring mouth 14.Three-phase feeds out Wiring module 9 and is provided with several, each three-phase feedback
Go out Wiring module 9 to be all made up of three-phase fast-wiring 14, air switch 15, signal lamp 16 and display screen 17, air switch is used
In control circuit break-make, signal lamp is used for the electriferous state for showing this circuit, and display screen is used for voltage, the electric current for showing this circuit
Etc. information.
The transition cabinet of this patent uses split-type design, and the interior institute of a cabinet interim transition cable joint in need takes fast quick access
Head, outfit carry male and female snap joint, the standby assembling cable for having certain length, there is provided and lengthen former cable situation and use, root
According to concrete condition head and the tail connection increase length, to solve the too short situation that can not access transition cabinet of former cable length, by fast quick access
Joint terminal row, air switch and signal lamp are arranged on same cabinet face, are easy to operating personnel's verification, are checked operation, add 4G and move
Dynamic networkmonitor carrys out the real-time condition that exchange in remote monitoring transition cabinet inputted and fed out each circuit, grasps operation shape in time
Condition.
Its course of work is as follows:The access two-way exchange of first cabinet 1, through AC distribution selection, wherein exchange input carries all the way
Charging module is supplied, charging module exports stable direct current, and on the one hand battery boost charge and offer, which are closed a floodgate, exports, another
Aspect provides output control by pressure unit, and the load for the second cabinet 2 provides normal operating current;Insulating monitoring unit
18 can monitor the insulation against ground situation of dc bus and each branch road on-line;Mobile network monitoring device is used to monitoring AC distribution, straight
Flow collection, monitoring and the management of the operational factors such as distribution, charging module, temporary accumulator cell group.
Described embodiment is this patent part of the embodiment, rather than whole embodiments.Based in this patent
Embodiment, the every other embodiment that those of ordinary skill in the art are obtained under the premise of creative work is not made,
Belong to the scope of this patent protection.
Claims (9)
1. a kind of novel transition cabinet for substation equipment maintenance and repair, it is characterised in that including the first cabinet (1) and the second cabinet (2), institute
State and linked together by link cable fast interface (3) between two cabinets between first and second cabinet (1,2), first and second cabinet
The cabinet body both sides of body (1,2) are respectively arranged with several auxiliary wheels (4), and the bottom of cabinet body is provided with universal wheel (5), got in touch between cabinet
Cable fast interface (3) is separately positioned on the top of first and second cabinet (1,2).
2. the novel transition cabinet according to claim 1 for substation equipment maintenance and repair, it is characterised in that first cabinet (1)
Instrument display (6), mobile network monitoring device (7), rectification unit (8), insulated monitoring unit are inside disposed with from top to bottom
And battery control unit (19) (18);
It has been arranged side by side that three-phase feeds out Wiring module (9) and two-phase feeds out Wiring module (10) on second cabinet (2).
3. the novel transition cabinet according to claim 2 for substation equipment maintenance and repair, it is characterised in that fed out positioned at the three-phase
Wiring module (9) and two-phase are provided with zero shared phase and the fast connection interface (11) being grounded between feeding out Wiring module (10).
4. the novel transition cabinet according to claim 1 for substation equipment maintenance and repair, it is characterised in that first and second cabinet
The cabinet body both sides of (1,2) are respectively arranged with two auxiliary wheels (4), and are connected between two auxiliary wheels (4) by bar (12).
5. the novel transition cabinet according to claim 1 for substation equipment maintenance and repair, it is characterised in that second cabinet (2)
It is front and rear to be both provided with cabinet door, and handle (13) is installed in cabinet door.
6. the novel transition cabinet according to claim 1 for substation equipment maintenance and repair, it is characterised in that on the universal wheel (5)
It is provided with locking system.
7. the novel transition cabinet according to claim 3 for substation equipment maintenance and repair, it is characterised in that got in touch between two cabinets
Cable fast interface is linked together between (3) by one or more cable connections.
8. the novel transition cabinet according to claim 7 for substation equipment maintenance and repair, it is characterised in that between every two cables
Connection is all linked together with the connected mode of pin and box sub.
9. the novel transition cabinet according to claim 2 for substation equipment maintenance and repair, it is characterised in that the three-phase feeds out wiring
Module (9) is made up of three-phase fast-wiring mouth (14), air switch (15), signal lamp (16) and display screen (17), and three-phase is fast
Fast connection jaws (14) are vertically provided at the side of module, and air switch (15), signal lamp (16) and display screen (17) are arranged on
The opposite side of three-phase fast-wiring mouth (14).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201720552956.1U CN206774908U (en) | 2017-05-18 | 2017-05-18 | A kind of novel transition cabinet for substation equipment maintenance and repair |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201720552956.1U CN206774908U (en) | 2017-05-18 | 2017-05-18 | A kind of novel transition cabinet for substation equipment maintenance and repair |
Publications (1)
Publication Number | Publication Date |
---|---|
CN206774908U true CN206774908U (en) | 2017-12-19 |
Family
ID=60640489
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201720552956.1U Expired - Fee Related CN206774908U (en) | 2017-05-18 | 2017-05-18 | A kind of novel transition cabinet for substation equipment maintenance and repair |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN206774908U (en) |
-
2017
- 2017-05-18 CN CN201720552956.1U patent/CN206774908U/en not_active Expired - Fee Related
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN202602134U (en) | Portable DC system load transfer auxiliary tank | |
CN202495807U (en) | Remote centralized measurement and control system for power distribution network | |
CN206947797U (en) | A kind of Novel maintenance power box for power plant | |
CN110497817A (en) | A kind of integrated form is with filling integrated high power DC charging heap control method and system | |
CN103117595B (en) | Distributed direct current independent power supply system | |
CN201490760U (en) | Mobile DC power supply panel for transformer station | |
CN109786866A (en) | A kind of plug and play battery module and battery energy storage system | |
CN102646546A (en) | Intelligent self-energy-obtaining vacuum breaker | |
CN203312905U (en) | Portable mobile direct-current power cabinet | |
CN202695269U (en) | Intelligent self-energy-fetching vacuum circuit breaker | |
CN202978733U (en) | Power distribution network device | |
CN206774908U (en) | A kind of novel transition cabinet for substation equipment maintenance and repair | |
CN203481922U (en) | Distribution automation remote measuring and control device for distribution monitoring | |
CN206517122U (en) | Distributed AC power supply module for transformer station's prefabricated cabin | |
CN109861391A (en) | A kind of intelligent low-pressure comprehensive distribution box management system based on Internet of Things | |
CN205123368U (en) | Portable emergent direct current charging device | |
CN209389165U (en) | A kind of plug and play battery module and battery energy storage system | |
CN203119617U (en) | Distributed direct-current independent power supply system for transformer substation | |
CN208548711U (en) | Double local side direct-current remote feeding power systems with electromagnetism security protection comprehensive monitoring function | |
CN103117596B (en) | Distributed direct-current power supply system for substation | |
CN206451954U (en) | A kind of mobile DC power supply is transferred screen temporarily | |
CN205992695U (en) | A kind of integration console model cable distribution box | |
CN109245145A (en) | A kind of highway airfield equipment remote electric power system | |
CN206060356U (en) | A kind of two distant type monitoring switch controllers | |
CN218300682U (en) | Integrated mobile power transformation and distribution station |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20171219 Termination date: 20180518 |