CN206774111U CN201720268700.8U CN201720268700U CN206774111U CN 206774111 U CN206774111 U CN 206774111U CN 201720268700 U CN201720268700 U CN 201720268700U CN 206774111 U CN206774111 U CN 206774111U
Authority
CN
China
Prior art keywords
track
progress
receiver
plate
construction management
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201720268700.8U
Other languages
Chinese (zh)
Inventor
邢振波
周兵
周兵一
武玉华
万东旭
赵明阳
于亿卓
李承霖
刘宝玉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Ronghua Construction Group Co Ltd
Original Assignee
Ronghua Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Ronghua Construction Group Co Ltd filed Critical Ronghua Construction Group Co Ltd
Priority to CN201720268700.8U priority Critical patent/CN206774111U/en
Application granted granted Critical
Publication of CN206774111U publication Critical patent/CN206774111U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model discloses a kind of construction management progress display plate, including plate body, track, swinging plate, regulating bolt and bearing, the surface inserting of the plate body has engineering famous brand, bumper is installed on the plate body, the track is connected with plate body, and track is installed below timetable, project board is fixed with the left of the track, progress bar is installed on the swinging plate, the right-hand member of the progress bar is fixed with receiver, it is fixed with and eats dishes without rice or wine on the left of the receiver, and progress bar passes through and eats dishes without rice or wine to be connected with rotating shaft, the bearing is connected with rotating shaft.The construction management progress display plate, provided with the writing whiteboard that repeated multiple times can be used, it is not in the situation of waste, progress bar provided with adjustable and retractable, progress regulation use is more convenient, provided with calendar, checks that Time of Day is more convenient, it is allowed to more easily to serve supervisor of construction and is managed operation, the convenient progress for clearly checking each project of engineering.

Description

A kind of construction management progress display plate
Technical field
Construction management equipment technical field is the utility model is related to, specially a kind of construction management progress Graphic Panel.
Background technology
The continuous development in epoch in recent years, economic structure have huge change, and the paces of Process of Urbanization Construction are progressively accelerated, It is on the increase therewith for the demand of construction construction, and then the demand of construction management equipment is also more and more, takes Construction management is mainly used in intuitively showing construction management progress, on the market progress display plate species with exemplified by progress display plate Pattern is different, but the progress display plate nowadays sold also influences people there is some more or less deficiencies and used.
For example the writing whiteboard that repeated multiple times can be used is not provided with, and can only be disposable, unnecessary waste is caused, Be not provided with the progress bar of adjustable and retractable, progress regulation in-convenience in use, be not provided with calendar, check Time of Day inconvenience Deng causing use demand not high, in order to solve the shortcomings that existing on the market and deficiency, be badly in need of improving construction management at present with entering The technology of Graphic Panel is spent, is allowed to more easily to serve supervisor of construction and is managed operation, it is convenient clearly to check engineering The progress of each project, improve the efficiency of engineering construction.
Utility model content
The purpose of this utility model is to provide a kind of construction management progress display plate, to solve above-mentioned background skill Itd is proposed in art can only the regulation of disposable, progress in-convenience in use the problems such as.
To achieve the above object, the utility model provides following technical scheme:A kind of construction management progress display Plate, including plate body, track, swinging plate, regulating bolt and bearing, the surface inserting of the plate body have engineering famous brand, the plate body On bumper is installed, when calendar groove and timetable are fixed with below the engineering famous brand, and being provided with the right side of calendar groove Between table, the track is connected with plate body, and track is provided with below timetable, and project is fixed with the left of the track Board, and project board is provided with below calendar groove, the swinging plate is connected by sliding block with track, is installed on the swinging plate There is progress bar, the right-hand member of the progress bar is fixed with receiver, and swinging plate is provided with receiver, and the regulating bolt is with turning Axle is connected, and the interior outside of receiver is separately installed with rotating shaft and regulating bolt, is fixed with and eats dishes without rice or wine on the left of the receiver, And progress bar, through eating dishes without rice or wine to be connected with rotating shaft, the bearing is connected with rotating shaft.
Preferably, the engineering famous brand and project board are erasable formula writing whiteboard.
Preferably, the length of the track and the equal length of timetable, and the height one of the width of track and project board Cause.
Preferably, the length of the progress bar is more than the length of timetable.
Preferably, the height sum of the height of the receiver and regulating bolt is less than the height of swinging plate.
Compared with prior art, the beneficial effects of the utility model are:The construction management progress display plate, is provided with The writing whiteboard that repeated multiple times can be used, can only be disposable the problem of is effectively avoided, is not in unnecessary waste Situation, the progress bar provided with adjustable and retractable, progress regulation use is more convenient, provided with calendar, checks that Time of Day is more square Just, it is allowed to more easily to serve supervisor of construction and is managed operation, it is convenient clearly to check entering for each project of engineering Degree, improve the efficiency of engineering construction.
Brief description of the drawings
Fig. 1 is the utility model positive structure diagram;
Fig. 2 is the utility model structure progress bar schematic diagram;
Fig. 3 is the utility model structure receiver schematic diagram.
In figure:1st, plate body, 2, engineering famous brand, 3, bumper, 4, calendar groove, 5, project board, 6, timetable, 7, track, 8, Swinging plate, 9, progress bar, 10, receiver, 11, sliding block, 12, regulating bolt, 13, eat dishes without rice or wine, 14, bearing, 15, rotating shaft.
Embodiment
Below in conjunction with the accompanying drawing in the utility model embodiment, the technical scheme in the embodiment of the utility model is carried out Clearly and completely describing, it is clear that described embodiment is only the utility model part of the embodiment, rather than whole Embodiment.Based on the embodiment in the utility model, those of ordinary skill in the art are not under the premise of creative work is made The every other embodiment obtained, belong to the scope of the utility model protection.
Fig. 1-3 are referred to, the utility model provides a kind of technical scheme:A kind of construction management progress display plate, Including plate body 1, engineering famous brand 2, bumper 3, calendar groove 4, project board 5, timetable 6, track 7, swinging plate 8, progress bar 9, receipts Case 10, sliding block 11, regulating bolt 12, eat dishes without rice or wine 13, bearing 14 and rotating shaft 15, the surface inserting of plate body 1 have engineering famous brand 2, plate Bumper 3 is installed, the lower section of engineering famous brand 2 is fixed with calendar groove 4 and timetable 6, and the right side of calendar groove 4 is set on body 1 Having time table 6, track 7 are connected with plate body 1, and the lower section of timetable 6 is provided with track 7, and the left side of track 7 is fixed with project Board 5, and the lower section of calendar groove 4 is provided with project board 5, engineering famous brand 2 and project board 5 are erasable formula writing whiteboard, can be weighed It is multiple repeatedly to be write, can only be disposable the problem of is effectively avoided, is not in the situation of unnecessary waste, swinging plate 8 are connected by sliding block 11 with track 7, the length of track 7 and the equal length of timetable 6, and the width of track 7 and project board 5 it is highly consistent, progress regulation can be carried out against each project on project board 5, progress bar 9 is installed on swinging plate 8, entered The length for spending bar 9 is more than the length of timetable 6, and the right-hand member of progress bar 9 is fixed with receiver 10, and is provided with and dials on receiver 10 Dynamic plate 8, regulating bolt 12 is connected with rotating shaft 15, and the interior outside of receiver 10 is separately installed with rotating shaft 15 and regulating bolt 12, the height of receiver 10 and the height sum of regulating bolt 12 facilitate rotating shaft 15 to progress bar 9 less than the height of swinging plate 8 Stored, using more convenient, the left side of receiver 10, which is fixed with, eats dishes without rice or wine 13 for progress regulation, and progress bar 9 is through eating dishes without rice or wine 13 It is connected with rotating shaft 15, bearing 14 is connected with rotating shaft 15, and rotational stability is stronger in receiver 10, is allowed to more easily take It is engaged in being managed operation, the convenient progress for clearly checking each project of engineering in supervisor of construction.
Operation principle:When using the construction management with progress display plate, construction is write in engineering famous brand 2 Title, then each project name is write on project board 5, calendar is put into calendar groove 4, can be observed by calendar specific Time of Day, when some project needs to carry out progress adjustment, by swinging plate by sliding block 11 slided on track 7 to it is corresponding when Between table 6 lower position, pin the swinging plate 8 in the left side of progress bar 9, then drag the swinging plate 8 on the right side of progress bar 9, progress bar 9 By the rotating shaft 15 in receiver 10 as bearing 14 rotates, and then progress bar 9 is deployed into suitable position, then enters to advance Degree displaying operation, can be by the rotating shaft 15 of regulating bolt 12 of the bottom of receiver 10, to progress bar when without using Graphic Panel 9 carry out winding operation, then wipe the word write on engineering famous brand 2, project board 5, can carry out repeatedly, circulation makes With practicality is higher, and here it is the whole process that construction management is worked with progress display plate.
While there has been shown and described that embodiment of the present utility model, for the ordinary skill in the art, It is appreciated that these embodiments can be carried out with a variety of changes in the case where not departing from principle of the present utility model and spirit, repaiied Change, replace and modification, the scope of the utility model are defined by the appended claims and the equivalents thereof.

Claims (5)

1. a kind of construction management progress display plate, including plate body (1), track (7), swinging plate (8), regulating bolt (12) With bearing (14), it is characterised in that:The surface inserting of the plate body (1) has engineering famous brand (2), is provided with the plate body (1) Bumper (3), calendar groove (4) and timetable (6) are fixed with below the engineering famous brand (2), and set on the right side of calendar groove (4) Timetable (6) is equipped with, the track (7) is connected with plate body (1), and track (7) is provided with below timetable (6), described Project board (5) is fixed with the left of track (7), and project board (5) is provided with below calendar groove (4), the swinging plate (8) is logical Cross sliding block (11) with track (7) to be connected, progress bar (9), the right-hand member of the progress bar (9) are installed on the swinging plate (8) Receiver (10) is fixed with, and swinging plate (8) is provided with receiver (10), the regulating bolt (12) is connected with rotating shaft (15) Connect, and the interior outside of receiver (10) is separately installed with rotating shaft (15) and regulating bolt (12), the left side of the receiver (10) Be fixed with eat dishes without rice or wine (13), and progress bar (9) through eat dishes without rice or wine (13) be connected with rotating shaft (15), the bearing (14) and rotating shaft (15) It is connected.
A kind of 2. construction management progress display plate according to claim 1, it is characterised in that:The engineering famous brand (2) and project board (5) is erasable formula writing whiteboard.
A kind of 3. construction management progress display plate according to claim 1, it is characterised in that:The track (7) Length and timetable (6) equal length, and the width of track (7) and project board (5) is highly consistent.
A kind of 4. construction management progress display plate according to claim 1, it is characterised in that:The progress bar (9) length is more than the length of timetable (6).
A kind of 5. construction management progress display plate according to claim 1, it is characterised in that:The receiver (10) height and the height sum of regulating bolt (12) is less than the height of swinging plate (8).
CN201720268700.8U 2017-03-20 2017-03-20 A kind of construction management progress display plate Expired - Fee Related CN206774111U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720268700.8U CN206774111U (en) 2017-03-20 2017-03-20 A kind of construction management progress display plate

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720268700.8U CN206774111U (en) 2017-03-20 2017-03-20 A kind of construction management progress display plate

Publications (1)

Publication Number Publication Date
CN206774111U true CN206774111U (en) 2017-12-19

Family

ID=60632734

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720268700.8U Expired - Fee Related CN206774111U (en) 2017-03-20 2017-03-20 A kind of construction management progress display plate

Country Status (1)

Country Link
CN (1) CN206774111U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108536217A (en) * 2018-05-04 2018-09-14 佛山科学技术学院 A kind of multiple-factor influence subject state comprehensive judgement auxiliary fish-bone target

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108536217A (en) * 2018-05-04 2018-09-14 佛山科学技术学院 A kind of multiple-factor influence subject state comprehensive judgement auxiliary fish-bone target

Similar Documents

Publication Publication Date Title
CN208737849U (en) A kind of portable project management progress chasing display board
CN206774111U (en) A kind of construction management progress display plate
CN209087168U (en) A kind of teaching multimedia teaching plate
CN210174469U (en) Information technology teaching tool
CN203314410U (en) Teaching frame with adjustment function
CN206194330U (en) Building engineering management bid device
CN210721891U (en) Novel marketing study case show board
CN206475263U (en) A kind of furniture pad pasting cutting edge locator
CN209300554U (en) A kind of pivoted board of education
CN206210132U (en) A kind of foreign language learning assistant teaching aid
CN103514528A (en) Warehouse item borrowing and returning registration system
CN211207525U (en) Financial data analysis presentation device
CN204726092U (en) Rainwater dustproof blackboard collected by a kind of convenient umbrella of hanging
CN207607275U (en) A kind of applied mathematics teaching auxiliary parsing panel
CN218594027U (en) Information statistics table for school canteen detection
CN211016091U (en) English teaching device
CN206363701U (en) A kind of novel and multifunctional advertising lamp box making apparatus
CN210970513U (en) Frame is accomodate to art supplies
CN206726573U (en) A kind of industrial and commercial administration teaching Graphic Panel
CN206505696U (en) A kind of real estate finance information management Graphic Panel
CN202816210U (en) Beer game simulation teaching sand table
CN211237361U (en) Large-scale think of political affairs education publicity column
CN204537113U (en) The energy-conservation general knowledge of one way of life shows wall
CN209971983U (en) Telescopic whiteboard for teaching
CN208664714U (en) A kind of Destination Management class blackboard for teaching

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20171219

Termination date: 20180320