CN206768755U CN201720631580.3U CN201720631580U CN206768755U CN 206768755 U CN206768755 U CN 206768755U CN 201720631580 U CN201720631580 U CN 201720631580U CN 206768755 U CN206768755 U CN 206768755U
Authority
CN
China
Prior art keywords
dam
water intaking
branch pipe
pipe
pipe laying
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn - After Issue
Application number
CN201720631580.3U
Other languages
Chinese (zh)
Inventor
秦卫星
胡惠仁
邓思佳
杨涛
陈宏�
余韬
李蕾
吴依婷
晏巍
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Changsha University of Science and Technology
Original Assignee
Changsha University of Science and Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Changsha University of Science and Technology filed Critical Changsha University of Science and Technology
Priority to CN201720631580.3U priority Critical patent/CN206768755U/en
Application granted granted Critical
Publication of CN206768755U publication Critical patent/CN206768755U/en
Withdrawn - After Issue legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Revetment (AREA)

Abstract

The utility model discloses a kind of overflow dam of pipe laying water intaking.The overflow dam, including dam body, Ren Hangdun, pipe laying system;The dam body is reinforced concrete structure;People's row pier is located at dam crest;The pipe laying system includes dam crest water inlet, dam facing water intaking valve, control valve, two level branch pipe, branch pipe, house steward;The dam crest water inlet is located between people's row pier;The dam facing water intaking valve is located at dam body upstream face;The control valve is located at dam body side;The two level branch pipe connection dam facing water intaking valve and branch pipe;The branch pipe connection dam crest water inlet and house steward;House steward's tail end sets control valve.The overflow dam that the utility model is related to, the water intaking of built-in pipe laying, there is flexible water-supply method, quick construction, traffic convenience and elegant in appearance.

Description

A kind of overflow dam of pipe laying water intaking
Technical field
Hydraulic engineering overflow dam field is the utility model is related to, more particularly to a kind of overflow dam of pipe laying water intaking.
Background technology
Because of the features such as gradient of river bed is big, current are anxious, flood fluctuation is fast, usually there is riverbank damaged or destroyed by flood in mountain channel, river course breaks The problems such as stream, have a strong impact on river channel ecology with water, littoral resident living water and crops water.Overflow dam is as a kind of Have the low water head hydraulic structure of the function such as " lift water ", " water storage ", " sluicing " concurrently, be that mountain channel improves the important of water intaking condition Building.At present, in order to reach water intaking purpose, generally require separately to build intake structure, typically using bank intake gate and manually Two kinds of structural shapes of bend.The another mode for building intake structure, often has that quantities is big, construction cost is high, overall aesthetics The drawbacks such as difference.
Utility model content
In view of the above-mentioned problems, the utility model utilizes the theory of pipe laying water intaking, there is provided a kind of rolling for possessing water intaking function Dam, inside configuration pipe laying system make it possess water intaking function, and water-supply method flexibly, quick construction, traffic convenience and U.S. See generous.
To achieve the above object, technical scheme is as follows used by the utility model.
A kind of overflow dam of pipe laying water intaking, it is characterised in that including dam body, Ren Hangdun, pipe laying system;The dam body is steel Muscle concrete structure;People's row pier is located at dam crest;The pipe laying system includes dam crest water inlet, dam facing water intaking valve, control valve, two level Branch pipe, branch pipe, house steward;The dam crest water inlet is located between people's row pier;The dam facing water intaking valve is located at dam body upstream face;It is described Control valve is located at dam body side;The two level branch pipe connection dam facing water intaking valve and branch pipe;Branch pipe connection dam crest water inlet with House steward;House steward's tail end sets control valve.
Further, the dam body is reinforced concrete structure, and concrete strength is C20 ~ C30.
Further, people's row pier uses prefabricated reinforced concrete cuboid block, and a length of 400mm ~ 800mm, a width of 300mm ~ 500mm, a height of 300mm ~ 1000mm, laying spacing are 400mm ~ 600mm.
Further, the dam crest water inlet uses round steel pipe, and bore is 100mm ~ 200mm, centre point and the dam The distance of body upstream face is the half of people's row pier width, and mouth face sets steel wire.
Further, the dam facing water intaking valve bore is consistent with dam crest water inlet.
Further, the control valve bore is 200mm ~ 600mm, and bore is more than single dam crest water inlet.
Further, the two level branch pipe uses round steel pipe, and bore is consistent with dam facing water intaking valve, and the gradient is:0°~30°.
Further, the branch pipe uses round steel pipe, and bore is consistent with two level branch pipe.
Further, the house steward uses round steel pipe, and bore is consistent with control valve, and the gradient is:0°~30°.
Compared with the prior art, the beneficial effects of the utility model are embodied in:
1st, overflow dam has water intaking function;
2nd, the design of multiple dam crest water inlets, different elevation water intaking valves, allows water intaking to become more flexible;
3rd, by the way of prefabrication fetches water pipe laying and humanoid pier, site operation is greatly facilitated;
4th, the setting of people's row pier meets the footpound force traffic requirement of two sides;
5th, built-in type diversion system meets the overall aesthetics of dam structure in dam.
Brief description of the drawings
Fig. 1 is structure overall schematic of the present utility model.
Fig. 2 is the utility model manifold configuration partial schematic diagram.
In figure:1-dam body;2-Ren Hangdun;3-dam crest water inlet;4-dam facing water intaking valve;5-control valve;6-two Level branch pipe;7-branch pipe;8-house steward.
Embodiment
The technical solution of the utility model is described in further detail below in conjunction with the accompanying drawings.
Embodiment 1.
The utility model provides a kind of overflow dam of pipe laying water intaking, including dam body 1, people's row pier 2, pipe laying system;It is described Dam body 1 is reinforced concrete structure;People's row pier 2 is located at dam crest;The pipe laying system includes dam crest water inlet 3, dam facing water intaking valve 4th, control valve 5, two level branch pipe 6, branch pipe 7, house steward 8;The dam crest water inlet 3 is located between people's row pier 2;The dam facing water intaking valve 4 are located at the upstream face of dam body 1;The control valve 5 is located at the side of dam body 1;The two level branch pipe 6 connects dam facing water intaking valve 4 and branch pipe 7;The branch pipe 7 connects dam crest water inlet 3 and house steward 8;The tail end of house steward 8 sets control valve 5.
Further, the dam body 1 is reinforced concrete structure, concrete strength C25, reinforcing bar model HRB400E.
Further, people's row pier 2 uses prefabricated reinforced concrete cuboid block, and size is:500mm×400mm×300mm (Length × width × height), laying spacing is 500mm.Meet the basic traffic requirement of river course two sides people.
Further, the dam crest water inlet 3 uses round steel pipe, bore 150mm, centre point and the upstream face of dam body 1 Distance is 250mm.On the one hand, water inlet is arranged on dam crest, is advantageous to fetch water when overflow occurs for dam facing;On the other hand, pipe laying The security that certain spacing can ensure dam structure be present with the upstream face of dam body 1.
Further, the bore of dam facing water intaking valve 4 and dam crest water inlet 3 are unanimously 150mm.On the one hand, bore is consistent The quality of connection of the two can be ensured;On the other hand, water intaking valve, which is arranged on the upstream face of dam body 1, can ensure overflow dam upper pond level Water intaking during decline.
Further, the bore of control valve 5 is 400mm.It is easy to need aqueous condition to control flow according to downstream irrigated area.
Further, the two level branch pipe 6 uses round steel pipe, and bore and dam facing water intaking valve 4 are unanimously 150mm, the gradient For 15 °.On the one hand, bore can unanimously ensure the quality of connection of the two;On the other hand, the setting of the gradient can improve current bar Part.
Further, the branch pipe 7 uses round steel pipe, and bore is unanimously with top surface water intaking valve 3 and dam facing water intaking valve 4 150mm.This can ensure the quality of connection between three.
Further, the house steward 8 uses round steel pipe, and bore is unanimously 400mm with control valve 5, and the gradient is 15 °.One Aspect.It can guarantee that quality of connection between the two;On the other hand, the setting of the gradient can improve flow condition.
Finally it should be noted that:Above example is only illustrating the technical solution of the utility model rather than it is limited System;Although the utility model is described in detail with reference to preferred embodiment, those of ordinary skill in the art should Understand:Specific embodiment of the present utility model can still be modified or some technical characteristics are equally replaced Change;Without departing from the spirit of technical solutions of the utility model, it all should cover in the claimed technical scheme of the utility model.

Claims (5)

1. a kind of overflow dam of pipe laying water intaking, it is characterised in that including dam body(1), Ren Hangdun(2), pipe laying system;The dam body (1)For reinforced concrete structure;People's row pier(2)Located at dam crest;The pipe laying system includes dam crest water inlet(3), dam facing water inlet Valve(4), control valve(5), two level branch pipe(6), branch pipe(7), house steward(8);The dam crest water inlet(3)Located at people's row pier(2)It Between;The dam facing water intaking valve(4)Located at dam body(1)Upstream face;The control valve(5)Located at dam body(1)Side;The two level branch Pipe(6)Connect dam facing water intaking valve(4)With branch pipe(7);The branch pipe(7)Connect dam crest water inlet(3)With house steward(8);It is described total Pipe(8)Tail end sets control valve(5).
A kind of 2. overflow dam of pipe laying water intaking according to claim 1, it is characterised in that people's row pier(2)A length of 400mm ~ 800mm, a width of 300mm ~ 500mm, a height of 300mm ~ 1000mm.
A kind of 3. overflow dam of pipe laying water intaking according to claim 1, it is characterised in that the dam crest water inlet(3)Use Round steel pipe, centre point and dam body(1)The distance of upstream face is people's row pier(2)The half of width.
A kind of 4. overflow dam of pipe laying water intaking according to claim 1, it is characterised in that the two level branch pipe(6)The gradient is: 0°~30°。
A kind of 5. overflow dam of pipe laying water intaking according to claim 1, it is characterised in that the house steward(8)The gradient is:0°~ 30°。
CN201720631580.3U 2017-06-02 2017-06-02 A kind of overflow dam of pipe laying water intaking Withdrawn - After Issue CN206768755U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720631580.3U CN206768755U (en) 2017-06-02 2017-06-02 A kind of overflow dam of pipe laying water intaking

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720631580.3U CN206768755U (en) 2017-06-02 2017-06-02 A kind of overflow dam of pipe laying water intaking

Publications (1)

Publication Number Publication Date
CN206768755U true CN206768755U (en) 2017-12-19

Family

ID=60635976

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720631580.3U Withdrawn - After Issue CN206768755U (en) 2017-06-02 2017-06-02 A kind of overflow dam of pipe laying water intaking

Country Status (1)

Country Link
CN (1) CN206768755U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107012835A (en) * 2017-06-02 2017-08-04 长沙理工大学 The overflow dam and construction method of a kind of pipe laying water intaking

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107012835A (en) * 2017-06-02 2017-08-04 长沙理工大学 The overflow dam and construction method of a kind of pipe laying water intaking

Similar Documents

Publication Publication Date Title
CN101660305A (en) Field drainage control system
CN104963322A (en) Hydraulic junction facility
CN208501642U (en) A kind of water conservancy irrigation water channel with dredging function
CN204590069U (en) A kind of retaining wall for hydraulic engineering
CN206768755U (en) A kind of overflow dam of pipe laying water intaking
CN205296100U (en) Husky equipment is arranged in reservoir segmentation
CN104452682A (en) Automatic control type steel faceplate dam
CN201165661Y (en) Anti-drawing high pressure rotary spray pile
CN107288104A (en) A kind of cradle-type checkdam structure
CN109853491A (en) Gate valve duct type fish pass structure
CN107012835A (en) The overflow dam and construction method of a kind of pipe laying water intaking
CN205242369U (en) Special high pressure gate fills water surge suppressor
CN202440787U (en) Riverway diversion device
CN209011260U (en) A kind of sinking garden rain sewerage system with underground garage
CN104074174A (en) Method for relieving low-temperature water environment influence of reservoir project and dam structure
CN204252393U (en) Corrugated steel web-compound section, concrete filled steel tube edge of a wing cross section column
CN205399343U (en) Reinforcement type waterproof and anti -seepage bank protection
CN207469194U (en) Lift adjustment dropping equipment
CN206173891U (en) River protection is with ecological protection slope
CN103614986A (en) Free surface flow water inflow method suitable for draining off floodwaters of tailing pond
CN210905095U (en) Composite sand basin for severe cold area
CN203729376U (en) Water intake well pipe structure used for hydraulic and hydropower engineering
CN209053074U (en) The surface grouting structure of diversion outlet closuring concrete
CN209194509U (en) A kind of steel sheet pile lock steel composite structure
CN207405584U (en) A kind of checkdam for hydraulic and hydroelectric engineering

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
AV01 Patent right actively abandoned
AV01 Patent right actively abandoned
AV01 Patent right actively abandoned

Granted publication date: 20171219

Effective date of abandoning: 20220527

AV01 Patent right actively abandoned

Granted publication date: 20171219

Effective date of abandoning: 20220527