CN206722201U CN201720351590.1U CN201720351590U CN206722201U CN 206722201 U CN206722201 U CN 206722201U CN 201720351590 U CN201720351590 U CN 201720351590U CN 206722201 U CN206722201 U CN 206722201U
Authority
CN
China
Prior art keywords
floor
frp
backing plate
battenboards
plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201720351590.1U
Other languages
Chinese (zh)
Inventor
冯鹏
郑毅
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tsinghua University
Original Assignee
Tsinghua University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tsinghua University filed Critical Tsinghua University
Priority to CN201720351590.1U priority Critical patent/CN206722201U/en
Application granted granted Critical
Publication of CN206722201U publication Critical patent/CN206722201U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The pre-buried system and its application process of FRP battenboards, it is made up of backing plate, the floor of some interconnections and connecting plate, the floor of interconnection be connected on backing plate and at the top of the backing plate on form rectangle installing space, floor both ends set dovetail groove respectively, and connecting plate is arranged in rectangle installing space.The utility model provides a kind of pre-buried system of FRP battenboards, the installation strength of pre-buried system can be improved using steel backing plate, it is connected using the floor of interconnection with thirty, and dovetail groove is set at floor both ends, the stress concentration of pre-buried system can be eliminated significantly, realized the assembled installation of pre-buried system, shortened the set-up time, operational risk is reduced, there is the advantages of reasonable in design, installation facility and Stability Analysis of Structures.

Description

The pre-buried system of FRP battenboards
Technical field
It the utility model is related to technical field of buildings, and in particular to a kind of pre-buried system of FRP battenboards.
Background technology
FRP, fibre-reinforced plastics, FRP composites are mixed according to a certain percentage with matrix material by fibrous material The high-performance section bar material formed after conjunction.With the progress of social science and technology, the development of civil engineering structure subject, very big Have benefited from the new material of excellent, the application of new technology and development in degree, and FRP with its excellent mechanical property and is fitted Modern project structure is answered to across the demand of, towering, heavily loaded, lightweight development, being just applied to bridge work more and more widely greatly In journey, all kinds of civil buildings, ocean engineering, underground engineering, by Structural Engineering circle extensive concern.
The domestic development of correlative study work of the design and embedding method of FRP battenboard application built-in fittings is less.Form folder Characteristic difference is larger between each component material and built-in fitting material of Rotating fields, and the discontinuity of this characteristic certainly will be caused pre- Occurs more serious stress concentration phenomenon on interface between embedded part and covering, core.Under fatigue load effect, stress collection The middle intensity that can greatly reduce sandwich, decline the service life of product.Metal embedded part is with reinforcing material in addition By resin bonding, the intensity at this depends primarily on matrix material performance, and this will further limit the carrying of embedded part structure Ability.Embedded body owner will include buried metal built-in fitting in covering and be bonded in skin-surface pre-buried in FRP battenboards at present Part.The former is that this will lead, it is necessary to be cut before laying to prepreg or fiber cloth before metalwork is embedded into laminate The reinforcing fiber in structure is caused inborn discontinuous feature to be present, if fiber cross-sectional bad, Yi Jie Nian Jie with metal embedded part Lamination is produced on face.
Utility model content
The utility model is in view of the deficienciess of the prior art, provide a kind of pre-buried system of FRP battenboards.
Technical scheme is used by the utility model solves its technical problem:
A kind of pre-buried system of FRP battenboards, is made up of backing plate, the floor of some interconnections and connecting plate, intersects and connects The floor connect be connected on backing plate and at the top of the backing plate on form rectangle installing space, floor both ends set dovetail groove respectively, even Fishplate bar is arranged in rectangle installing space.
Above-mentioned connecting plate front and rear sides conveniently set dowel, and connecting plate is otic placode or end plate, and otic placode is bolted On backing plate, end plate is welded on backing plate.
Above-mentioned floor is FRP plate material, and backing plate is steel plate.
The application process of the pre-buried system of above-mentioned FRP battenboards, comprises the following steps:
(1) backing plate is cut into square, backing plate is cleared up;
(2) FRP plate both ends are cut out into dovetail groove respectively, and neck is cut out in FRP battenboards bottom, so as to obtain rib Plate;
(3) by floor it is intersected with each other be connected on backing plate and at the top of the backing plate on form rectangle installing space;
(4) connecting plate is fixed in the middle part of rectangle installing space, and dowel is conveniently set in connecting plate front and rear sides;
(5) the rectangle installing space near connecting plate is filled;
(6) long and wide and floor length and wide identical filling groove are cut out on FRP battenboards, clogs depth of groove More than floor thickness, then the floor of pre-buried system is connected in the filling groove on FRP battenboards, and outside filling groove Part be fixed, finally by connecting plate with building suspension be connected.
The utility model provides a kind of pre-buried system of FRP battenboards, and pre-buried system can be improved using steel backing plate Installation strength, it is connected using the floor of interconnection with thirty, and dovetail groove is set at floor both ends, embedded body can be eliminated significantly The stress concentration of system, the assembled installation of pre-buried system is realized, the set-up time is shortened, reduces operational risk, have and set Meter is reasonable, installs the advantages of convenient and Stability Analysis of Structures.
Brief description of the drawings
The utility model is further illustrated with reference to the accompanying drawings and examples.
Fig. 1 is the structural representation of the pre-buried system of the utility model;
Fig. 2 is the schematic top plan view of the pre-buried system of the utility model;
Fig. 3 is the schematic cross-sectional view of the pre-buried system of the utility model.
1 backing plate, 2 floors, 3 rectangle installing spaces, 4 connecting plates, 5 dovetail grooves, 6 reinforcements in figure.
Embodiment
As shown in Figure 1, Figure 2 and Figure 3, a kind of pre-buried system of FRP battenboards, by backing plate 1, the floor of some interconnections 2 and connecting plate 4 form, the floor 2 of interconnection is connected on backing plate 1 and forms rectangle installing space 3 on the top of backing plate 1, The both ends of floor 2 set dovetail groove 5 respectively, and connecting plate 4 is arranged in rectangle installing space 3.The front and rear sides of connecting plate 4 are convenient to be set Dowel 6, connecting plate 4 are otic placode or end plate, and otic placode is bolted on backing plate, and end plate is welded on backing plate, and floor is FRP plate material, backing plate are steel plate.
The application process of the pre-buried system of above-mentioned FRP battenboards, comprises the following steps:
(1) backing plate is cut into square, backing plate is cleared up;
(2) FRP plate both ends are cut out into dovetail groove respectively, and neck is cut out in FRP battenboards bottom, so as to obtain rib Plate;
(3) by floor it is intersected with each other be connected on backing plate and at the top of the backing plate on form rectangle installing space;
(4) connecting plate is fixed in the middle part of rectangle installing space, and dowel is conveniently set in connecting plate front and rear sides;
(5) the rectangle installing space near connecting plate is filled;
(6) long and wide and floor length and wide identical filling groove are cut out on FRP battenboards, clogs depth of groove More than floor thickness, then the floor of pre-buried system is connected in the filling groove on FRP battenboards, and outside filling groove Part be fixed, finally by connecting plate with building suspension be connected.
The utility model provides a kind of pre-buried system of FRP battenboards, and pre-buried system can be improved using steel backing plate Installation strength, it is connected using the floor of interconnection with thirty, and dovetail groove is set at floor both ends, embedded body can be eliminated significantly The stress concentration of system, the assembled installation of pre-buried system is realized, the set-up time is shortened, reduces operational risk, have and set Meter is reasonable, installs the advantages of convenient and Stability Analysis of Structures.
Preferred embodiment of the present utility model is the foregoing is only, it is all in this practicality not to limit the utility model Within new spirit and principle, any modification, equivalent substitution and improvements made etc., guarantor of the present utility model should be included in Within the scope of shield.

Claims (3)

1. a kind of pre-buried system of FRP battenboards, it is characterized in that be made up of backing plate, the floor of some interconnections and connecting plate, The floor of interconnection be connected on backing plate and at the top of the backing plate on form rectangle installing space, floor both ends set dovetail respectively Groove, connecting plate are arranged in rectangle installing space.
2. the pre-buried system of FRP battenboards according to claim 1, it is characterized in that the convenient company of setting in connecting plate front and rear sides Muscle is connect, connecting plate is otic placode or end plate, and otic placode is bolted on backing plate, and end plate is welded on backing plate.
3. the pre-buried system of FRP battenboards according to claim 1, it is characterized in that floor is FRP plate material, backing plate is steel Plate.
CN201720351590.1U 2017-04-06 2017-04-06 The pre-buried system of FRP battenboards Expired - Fee Related CN206722201U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720351590.1U CN206722201U (en) 2017-04-06 2017-04-06 The pre-buried system of FRP battenboards

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720351590.1U CN206722201U (en) 2017-04-06 2017-04-06 The pre-buried system of FRP battenboards

Publications (1)

Publication Number Publication Date
CN206722201U true CN206722201U (en) 2017-12-08

Family

ID=60503375

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720351590.1U Expired - Fee Related CN206722201U (en) 2017-04-06 2017-04-06 The pre-buried system of FRP battenboards

Country Status (1)

Country Link
CN (1) CN206722201U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106988479A (en) * 2017-04-06 2017-07-28 清华大学 The pre-buried system and its application process of FRP battenboards

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106988479A (en) * 2017-04-06 2017-07-28 清华大学 The pre-buried system and its application process of FRP battenboards

Similar Documents

Publication Publication Date Title
CN103477069B (en) For keeping the module of at least one lining
CN103061415B (en) Gluing composite connection joint and gluing composite connection method for FRP (fiber reinforced polymer) section and barbed plates
CN103123041B (en) Composite material stiffened plate with connecting joints and composite material stiffened plate connecting structure
CN103448338B (en) Metal plate/fiber mixed reinforced type sandwich plate
CN206722201U (en) The pre-buried system of FRP battenboards
Zhang et al. Effect of groove spacing on bond strength of near-surface mounted (NSM) bonded joints with multiple FRP strips
US8567146B2 (en) Method and apparatus for repairing concrete
CN105172317A (en) Solidified composite and enhancing method of repairing structure and connecting structure of solidified composite
CN103104067B (en) FRP (Fiber Reinforce Plastic) profile connecting node and method
CN106988479A (en) The pre-buried system and its application process of FRP battenboards
Zhang et al. Bending and shear performance of a cross-laminated composite consisting of flattened bamboo board and Chinese fir lumber
CN104032861B (en) Mixing coupled wall steel column and non-energy dissipating beam connecting node structure and construction method thereof
CN211114233U (en) Vertical connection structure of assembled shear force wall
CN110284725B (en) Reinforced concrete frame node beam hogging moment assembly steel structure and reinforcing method thereof
CN105952182B (en) A kind of method of composite consolidation wooden frame
CN105484355A (en) Connection system of wood-concrete composite structure
CN203567307U (en) Hybrid enhanced sandwich plate
CN203487427U (en) Composite material base plate
CN207504539U (en) A kind of cable trough with cable protection external member
CN203307725U (en) Composite material orthogonal cell structure sandwich bridge deck slab with reinforcing member
CN105544857B (en) Close rib composite plate structure system
CN210049428U (en) Sandwich heat-insulating steel concrete composite pipe structure
CN104563354B (en) Combined long-span ribbed slab structure
CN208267090U (en) A kind of light cement prefab conducive to installation and transportation
CN203066245U (en) Stab plate type glued composite connector used for FRP (fiber reinforced plastic) section

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20171208

Termination date: 20190406

CF01 Termination of patent right due to non-payment of annual fee