CN206721805U - The interim transport harbour in river course - Google Patents
The interim transport harbour in river course Download PDFInfo
- Publication number
- CN206721805U CN206721805U CN201720227532.8U CN201720227532U CN206721805U CN 206721805 U CN206721805 U CN 206721805U CN 201720227532 U CN201720227532 U CN 201720227532U CN 206721805 U CN206721805 U CN 206721805U
- Authority
- CN
- China
- Prior art keywords
- supporting plate
- floating body
- inserted link
- river course
- hanging plate
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Revetment (AREA)
Abstract
The utility model discloses a kind of interim transport harbour in river course, including a supporting plate, one end of supporting plate is provided with a hanging plate, hanging plate is located at the upper surface of supporting plate, a step surface is formed between hanging plate and supporting plate, hanging plate is by being placed on river bank, the other end both sides of supporting plate respectively set an inserted link, inserted link is in same plane with supporting plate, an installation cavity is formed between inserted link and supporting plate, more than one floating body is set with inserted link, floating body is uniformly sleeved on inserted link, the outboard end of floating body is provided with a retaining mechanism, the openend of inserted link is inserted in the soil of river bank fixed.The utility model is simple in construction, is mainly used on river course building use temporarily, simple in construction, convenient disassembly, is not easy to rock after being completed, and overall structure is stable, saves financial cost, reusable.
Description
Technical field
The utility model is applied on river course, and in particular to a kind of interim transport harbour in river course.
Background technology
On river course, we can set many harbours, and these harbours are all permanently to build, and come as transport vessels
Past shipping platform.But due to the uncertainty of transport, cause sometimes to need to unload being less than port location, or
Goods loading is carried out in some position in river course, is a huge engineering so if building a permanent harbour, consumption
Take substantial amounts of manpower and materials using being once unnecessary, financial cost is higher.
The content of the invention
Technical problem to be solved in the utility model is to provide one kind and is mainly used on river course building use, structure temporarily
Simply, convenient disassembly, it is not easy to rock after being completed, overall structure is stable, uses the interim transport in more economical river course
Harbour.
The utility model is achieved through the following technical solutions:A kind of interim transport harbour in river course, including one
Supporting plate, one end of supporting plate are provided with a hanging plate, and hanging plate is located at the upper surface of supporting plate, one is formed between hanging plate and supporting plate
Individual step surface, hanging plate respectively set an inserted link by being placed on river bank, the other end both sides of supporting plate, and inserted link is in same with supporting plate
In one plane, an installation cavity is formed between inserted link and supporting plate, more than one floating body, the equal cloth set of floating body are set with inserted link
On inserted link, the outboard end of floating body is provided with a retaining mechanism, and the openend of inserted link is inserted in the soil of river bank
It is fixed.
Preferably, the floating body is more than one Plastic buoy, its cylindrical form, centre is provided with a confession and inserted
The jack that bar passes through, jack run through floating body, and floating body bottom contacts with the river in river course to be supported for buoyancy.
Preferably, the retaining mechanism includes the contiguous block for being arranged at each floating body outboard end, the centre of contiguous block is passed through
Wear and be equipped with a positioning hole, insertion sets a locating rod in each positioning hole, and locating rod is through positioning hole and is inserted in
Floating body is fixed on the water surface in riverbed, the upper surface of floating body is stretched out at the top of locating rod.
Preferably, the upper surface of the hanging plate has at least two spacing holes, a gag lever post is squeezed into through spacing hole,
Gag lever post is through spacing hole and squeezes into soil.
Preferably, the hanging plate and supporting plate, using having buoyant plank, inserted link uses metallic rod, its one end
It is fixedly connected by screw with supporting plate.
The beneficial effects of the utility model are:The utility model is simple in construction, is mainly used on river course building use temporarily,
It is simple in construction, convenient disassembly, it is not easy to rock after being completed, overall structure is stable, saves financial cost, reusable.
Brief description of the drawings
Fig. 1 is overall structure diagram of the present utility model;
Fig. 2 is the structural representation that hanging plate connects with supporting plate in the utility model.
Coding is respectively in figure:1 is hanging plate, and 2 be river bank, and 3 be inserted link, and 4 be positioning hole, and 5 be contiguous block, and 6 be floating body,
7 be supporting plate, and 8 be installation cavity, and 9 be spacing hole, and 10 be step surface.
Embodiment
As shown in figure 1, the interim transport harbour in this river course, including a supporting plate 7, one end of supporting plate 7 are provided with one
Hanging plate 1, hanging plate 1 are located at the upper surface of supporting plate 7, a step surface 10 are formed between hanging plate 1 and supporting plate 7, hanging plate 1 is by being placed on
River bank 2, the other end both sides of supporting plate 7 respectively set an inserted link 3, and inserted link 3 is in same plane with supporting plate 7, inserted link 3
An installation cavity 8 is formed between supporting plate 7, is set with more than one floating body 6 on inserted link 3, floating body 6 is uniformly sleeved on inserted link
On 3, the outboard end of floating body 6 is provided with a retaining mechanism, and the openend of inserted link 3, which is inserted in the soil of river bank 2, to be fixed.
In the present embodiment, floating body 6 is more than one Plastic buoy, and its cylindrical form, centre is provided with a confession and inserted
The jack that bar passes through, jack run through floating body 6, and floating body bottom contacts with the river in river course to be supported for buoyancy, each floating body set
It is inserted in after on inserted link, then by inserted link in the soil of river bank, realizes the position positioning of supporting plate and each floating body, ensure
Stability when in use.
In the present embodiment, retaining mechanism includes the contiguous block 5 for being arranged at each floating body outboard end, and the centre of contiguous block is run through
A positioning hole 4 is provided with, piece locating rod (not shown) of insertion setting, locating rod passes through positioning hole 4 in each positioning hole 4
And be inserted in riverbed and floating body is fixed on the water surface, the upper surface of floating body is stretched out at the top of locating rod, due on floating body
There is provided retaining mechanism, therefore it locating rod is inserted in positioning hole and is inserted in riverbed can effectively play secondary positioning
Effect, further fixed support plate and floating body are more stable during use.
In the present embodiment, the upper surface of hanging plate has at least two spacing holes 9, and a gag lever post is squeezed into through spacing hole 9
(not shown), gag lever post is through spacing hole 9 and squeezes into soil, and hanging plate is placed on river bank 2, is fixed by gag lever post
Afterwards, hanging plate can be effectively increased and the position on riverbank is fixed, further play stable effect.
Wherein, hanging plate 1 and supporting plate 7 are using having buoyant plank, and inserted link 3 uses metallic rod, and its one end passes through
Screw is fixedly connected with supporting plate, support of the supporting plate as whole harbour, for handling goods, it is therefore necessary to ensure supporting plate
And the stability of floating body, it is unlikely to wobble effects unloading when so unloading.
The beneficial effects of the utility model are:The utility model is simple in construction, is mainly used on river course building use temporarily,
It is simple in construction, convenient disassembly, it is not easy to rock after being completed, overall structure is stable, saves financial cost, reusable.
Claims (5)
- A kind of 1. interim transport harbour in river course, it is characterised in that:Including a supporting plate (7), one end of supporting plate (7) is set There is a hanging plate (1), hanging plate (1) is located at the upper surface of supporting plate (7), and a step surface is formed between hanging plate (1) and supporting plate (7) (10), hanging plate (1) is by being placed on river bank (2), and the other end both sides of supporting plate (7) respectively set an inserted link (3), inserted link (3) with Supporting plate (7) is in same plane, and an installation cavity (8) is formed between inserted link (3) and supporting plate (7), and inserted link is set with (3) There is more than one floating body (6), floating body (6) is uniformly sleeved on inserted link (3), and the outboard end of floating body (6) is provided with a lock Tight mechanism, the openend of inserted link (3), which is inserted in the soil of river bank (2), to be fixed.
- 2. the interim transport harbour in river course as claimed in claim 1, it is characterised in that:The floating body (6) is more than one Plastic buoy, its cylindrical form, centre be provided with one for inserted link (3) through jack, jack runs through floating body, floating body (6) bottom contacts with the river in river course supports for buoyancy.
- 3. the interim transport harbour in river course as claimed in claim 1, it is characterised in that:The retaining mechanism includes being arranged at The contiguous block of each floating body (6) outboard end, the centre of contiguous block are provided through a positioning hole (4), and each positioning hole (4) is interior Insertion sets a locating rod, and locating rod, which passes through positioning hole (4) and is inserted in riverbed, is fixed on floating body (6) on the water surface, The upper surface of floating body (6) is stretched out at the top of locating rod.
- 4. the interim transport harbour in river course as claimed in claim 1, it is characterised in that:The upper end mask of the hanging plate (1) There are at least two spacing holes (9), squeeze into a gag lever post through spacing hole (9), gag lever post is through spacing hole (9) and squeezes into mud In soil.
- 5. the interim transport harbour in river course as claimed in claim 1, it is characterised in that:The hanging plate (1) and supporting plate (7) using having buoyant plank, inserted link (3) uses metallic rod, and its one end is fixedly connected by screw with supporting plate (7).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201720227532.8U CN206721805U (en) | 2017-03-09 | 2017-03-09 | The interim transport harbour in river course |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201720227532.8U CN206721805U (en) | 2017-03-09 | 2017-03-09 | The interim transport harbour in river course |
Publications (1)
Publication Number | Publication Date |
---|---|
CN206721805U true CN206721805U (en) | 2017-12-08 |
Family
ID=60501512
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201720227532.8U Expired - Fee Related CN206721805U (en) | 2017-03-09 | 2017-03-09 | The interim transport harbour in river course |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN206721805U (en) |
-
2017
- 2017-03-09 CN CN201720227532.8U patent/CN206721805U/en not_active Expired - Fee Related
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN108755583A (en) | It is a kind of to be used to build dykes and dams or the three plug cage bodies blocked up of shutting off | |
GB1239967A (en) | Apparatus for offshore operations | |
CN105028270A (en) | Lift-type aquaculture net cage | |
CN206721805U (en) | The interim transport harbour in river course | |
CN204949101U (en) | Box with a net is bred to over -and -under type | |
CN203142990U (en) | Stabilizing mechanism for dredger | |
CN104649039A (en) | Concrete transfer device | |
CN205320920U (en) | Floating ball | |
CN205591204U (en) | Strengthen shaped steel sheet -pile structure | |
CN104310235B (en) | Maritime work accommodation platform complete superstructure lifting method | |
CN205855766U (en) | A kind of for sheet material shipment, the suspender of transfer | |
CN202925557U (en) | Steel cofferdam assembled floating platform | |
CN205131590U (en) | A only superficial device of double side wall formula for pitch ship | |
CN204940198U (en) | A kind of dock structure be applicable in ship mooring physical experiments | |
CN207589856U (en) | A kind of cultivation steck | |
CN208932341U (en) | A kind of trolley for the mobile fetal membrane of fabrication of reinforcing cage | |
CN206052825U (en) | A kind of measuring well dredger | |
CN207031084U (en) | It is a kind of can industrialized production it is surface cultivation plants floating bed | |
ATE526234T1 (en) | MULTIPLE FLOAT SHIP WITH MULTIPLE INFLATABLE ELEMENTS AND METHOD FOR USE THEREOF | |
CN103434947B (en) | offshore transfer gantry crane | |
CN206031713U (en) | Novel floater | |
CN206511077U (en) | A kind of equipment floating platform for hardground shoal | |
CN204854898U (en) | Floats | |
CN206394819U (en) | A kind of low temperature resistant prestressed steel bar anchoring assembly of high-strength and high ductility | |
CN108184739A (en) | A kind of cultivation steck |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20171208 Termination date: 20190309 |
|
CF01 | Termination of patent right due to non-payment of annual fee |