CN206712419U - Cable terminal structure - Google Patents

Cable terminal structure Download PDF

Info

Publication number
CN206712419U
CN206712419U CN201720523658.XU CN201720523658U CN206712419U CN 206712419 U CN206712419 U CN 206712419U CN 201720523658 U CN201720523658 U CN 201720523658U CN 206712419 U CN206712419 U CN 206712419U
Authority
CN
China
Prior art keywords
platform
tower
operation platform
terminal
terminals
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201720523658.XU
Other languages
Chinese (zh)
Inventor
顾恒
顾俊颉
唐天
唐天一
方浩
鲁斌
肖鑫鑫
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Electric Power Design Institute Co Ltd
Original Assignee
Shanghai Electric Power Design Institute Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Electric Power Design Institute Co Ltd filed Critical Shanghai Electric Power Design Institute Co Ltd
Priority to CN201720523658.XU priority Critical patent/CN206712419U/en
Application granted granted Critical
Publication of CN206712419U publication Critical patent/CN206712419U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Suspension Of Electric Lines Or Cables (AREA)

Abstract

The utility model discloses a kind of cable terminal structure, including at least terminal tower, operation platform, terminals base;The terminal tower uses narrow base steel pipe tower structure, and the terminal tower is fixed on ground with the operation platform using filling pile structure, and the terminals base is fixed on the inspection platform upper surface, and the operation platform and the terminal tower are separately positioned.The utility model uses narrow base terminal tower structure and bored concrete pile foundation, solves the uneven subsidence of terminal tower and operation platform, it is ensured that the safe operation of terminal tower.The utility model can effectively solve the problems, such as the excessive caused amount of deflection of platform.Because platform separates with tower body, terminal tower set in itself it is pre- partially, terminals base is not influenceed.Because operation platform uses higher height, it is ensured that terminal tower charging equipment and the electrical distance of surrounding environment, therefore, after the completion of to terminal tower and operation platform construction, without separately setting the safeguard procedures such as fence, its floor space is smaller.

Description

Cable terminal structure
Technical field
It the utility model is related to power Transmission equipment technical field, more particularly to a kind of cable termination tower.
Background technology
The continuous development of Chinese Urbanization construction, it is urban planning that electric power safety, which is transported in each user in city, With the important consideration of builder.High-tension bus-bar how is safely set up in city turns into a more and more important technology.
Aerial cable transition form mainly uses two kinds of structures in the prior art:Terminal station and terminal tower.Cable terminal station The characteristics of be that safe and reliable to operation, repair and maintenance is convenient.Cable termination tower can effectively reduce land area, relax due to political affairs Contradiction early stage caused by the reasons such as plan, planning, it is especially suitable for large size city or major metropolitan areas;Cable termination tower by terminals and Lightning protection is installed on terminal tower, makes full use of terminal tower tower body, and relevant device and existing terminal tower are designed and constructed simultaneously, It is the aerial cable conversion plan of current main flow.
But after use for many years, prior art constantly reflects some defects:
1st, in the prior art, the equipment such as arrester is arranged on terminal tower jointly, because platform size is larger, and steel construction The flexibility of itself is difficult to avoid that downward amount of deflection problem easily occurs for terminal platform, causes terminal head tilt.
If the 2, the backfill below the cable termination tower of prior art is not tamped, iron tower foundation and terminal support base can be caused The differential settlement of plinth, terminal platform type is caused to become.
3rd, in the prior art, cable termination need to such as be carried out thermometric and when detect to its running situation needs have a power failure into OK, increase scheduling burden, reduces circuit operational reliability.
Those skilled in the art are directed to solving above-mentioned technological deficiency.
Utility model content
In view of the drawbacks described above of prior art, a technical purpose of the present utility model is:It is whole to provide a kind of cable End structure, make it on the premise of Electrical Safety is ensured, mitigate the load on terminal tower, avoid caused degree of disturbing problem and ground Terminal platform type caused by the differential settlement of face becomes problem.
Another technical purpose of the present utility model is:Land used amount is reduced, reduces the influence to surrounding environment.
Another technical purpose of the present utility model is:During detection cable terminal operating situation, without power-off, carry Elevated track operational reliability, to ensure the normal electricity consumption of resident.
To realize above-mentioned technical purpose, the utility model provides a kind of cable terminal structure, including at least terminal tower, fortune Row platform, terminals base;The terminal tower uses narrow base steel pipe tower structure, and the terminal tower is with the operation platform using filling Note pilework is fixed on ground, and the terminals base is fixed on the operation platform upper surface, the operation platform with it is described Terminal tower is separately positioned.
Further, in addition to terminals, support insulator, the terminals are fixed on institute by the support insulator State on terminals base.
Further, in addition to fence, the fence are vertical and around the top surface edge for being arranged at the operation platform.
Further, in addition to arrester, arrester platform, the arrester platform are fixed on the terminal tower, institute State arrester to be fixed on the arrester platform by the support insulator, the arrester platform and the operation platform Positioned at the same side of the terminal tower.
Further, the terminals shift to install with the arrester platform, and the terminals are arranged at described keep away The outside of thunder device platform.
Further, in addition to cat ladder, the cat ladder are arranged at the vertical plane of the operation platform, the height of the cat ladder It is highly consistent with the operation platform.
Further, in addition to overground cable, aluminium alloy box culvert, the overground cable are arranged at the operation platform and institute The inside of terminals base is stated, the overground cable is protected by the aluminium alloy box culvert.
The beneficial effects of the utility model:
The utility model has the advantages that as a result of said structure design:
1st, narrow base terminal tower of the present utility model uses bored concrete pile foundation, and terminals base with dividing completely on terminal tower structure From solving the uneven subsidence of terminal tower and operation platform, it is ensured that the safe operation of terminal tower.
2nd, terminals base separates with the tower body of terminal tower, and terminals, arrester are separately provided platform, can effectively solve to put down Amount of deflection problem caused by platform is excessive.Because operation platform separates with the tower body of terminal tower, terminal tower set in itself it is pre- partially, to end Termination base does not influence.
3rd, because operation platform uses higher height, it is ensured that terminal tower charging equipment and surrounding environment it is electric away from From, therefore, after the completion of to terminal tower and operation platform construction, without separately setting the safeguard procedures such as fence, its floor space It is smaller, taken over the land for use without fence.
4th, operation platform is set higher, and attendant uses cat ladder upper mounting plate, and sets gate on cat ladder top, sets simultaneously Door lock is put, prevents inoperative attendant from climbing;Overground cable is protected using aluminium alloy box culvert.
5th, terminals and arrester platform shift to install in the horizontal plane, after the support insulator for removing top, you can right Terminals are lifted and changed.
6th, it is maintenance channels of the 1m around terminals base that operation platform, which provides width,.Terminals base and operation platform For vertical range with highly consistent in general transformer station, guarantee day-to-day operation safeguards safety.Climbing up this operation platform can be to terminal Head running situation is detected;And 360 ° of temperature and running situation detection can be carried out to cable termination without having a power failure, so as to not Influence resident's normal life.
Brief description of the drawings
Fig. 1 is the left view of one specific embodiment of the utility model.
Fig. 2 is the front view of one specific embodiment of the utility model.
Embodiment
Design, concrete structure and caused technique effect of the present utility model are made furtherly below with reference to accompanying drawing It is bright, to be fully understood from the purpose of this utility model, feature and effect.
Embodiment:
It is the sectional structure chart of a specific embodiment of the present utility model as shown in Figure 1, including terminal tower 1, operation are flat Platform 2, fence 3, terminals base 4, support insulator 5, terminals 6, arrester 7, arrester platform 8, cat ladder 9, aluminium alloy box Contain 10.
In the present embodiment, terminal tower 1 uses narrow base steel tube tower, and terminal tower 1 uses filling pile structure with operation platform 2, And operation platform 2 is fixed on the outside of terminal tower 1.Terminals base 4 is fixed on the upper surface of operation platform 2, on operation platform 2 The maintenance channel for the circular terminals base 4 that width is 1m is set.
Preferably, the height of operation platform 2 is arranged to 5.5m, and the height of terminals base 4 is 2.5m.
Support insulator 5 is fixed on the upper surface of terminals base 2, and terminals 6 are fixed on the upper end of support insulator 5 Portion.Fence 3 is vertical and surround the outward flange of the upper surface of operation platform 2.
In the present embodiment, arrester platform 8 is fixedly installed on terminal tower 1, and arrester platform 8 is set with terminals 6 In the same side of terminal tower 1 and shift to install, terminals 6 are arranged at the outside of arrester platform 8.Arrester 7 is exhausted by pillar Edge 5 is fixed on the upper surface of arrester platform 8.
Preferably, arrester platform 8 be located at terminal tower 1 at ground level 14.5m, operation platform 2 is located at terminal Tower 1 and compared to the outer lateral extent 14m of terminal tower 1.
The vertical plane of operation platform 2 is provided with cat ladder 9, and the height of cat ladder 9 and operation platform 2 is highly consistent.It is preferred that , the height of operation platform 2 is arranged to 5.5m.And gate and door lock are set on cat ladder top.
It is provided with overground cable in operation platform 2 to be connected with terminals 6, overground cable is protected by aluminium alloy box culvert 10.
In the present embodiment, because terminal tower 1 and operation platform 2 use filling pile structure, due to bored concrete pile substantially without Sedimentation, so terminal tower 1 and operation platform 2 are substantially without uneven subsidence.
The present embodiment is provided with 1m maintenance channel in the upper surface of operation platform 2, and convenient maintenance personal is climbing up operation Day-to-day operation maintenance is carried out to terminals 6 after platform 2, the running situation of terminals 6 examined on the premise of without power-off Survey, and the safety that fence 3 protects testing staff is vertically arranged in the outward flange of operation platform 2.
In the present embodiment, terminal tower 1 uses narrow base steel pipe tower structure, can effectively reduce floor space, while make terminal First 6 closer to terminal tower 1 tower body, reduce the influence to surrounding enviroment.Further, since using operation platform 2 and terminal tower 1 Separate, the structure of arrester platform 8, support insulator 5 and arrester 7 is only set on terminal tower 1, to 1 increased lotus of terminal tower Carry smaller, tower weight increases less compared with ordinary terminal tower, and weight is slightly light compared with prior art, alleviate due to load compared with Heavy and caused degree of disturbing problem.
In the present embodiment, the height of operation platform 2 is arranged to 5.5m, and sets gate and door lock on the top of cat ladder 9 It structure, can prevent inoperative attendant from climbing, and fence is set without the surrounding of terminal tower 1 again.
The structure that the present embodiment shifts to install as a result of terminals 6 and arrester platform 8, therefore above dismounting After support insulator 5, you can terminals 6 are lifted and changed.
The present embodiment separates as a result of operation platform 2 with terminal tower 1, and terminals 6, arrester 7 are separately provided platform Structure, can effectively solve the problem that platform it is excessive caused by degree of disturbing problem, and because operation platform 2 separates with the tower body of terminal tower 1, Terminal tower 1 itself is set pre- inclined, and terminals base 4 will not be had an impact.
Further, since overground cable is protected using aluminium alloy box culvert 10, it can be ensured that the safe handling of overground cable.
Preferred embodiment of the present utility model described in detail above.It should be appreciated that the ordinary skill people of this area Member makes many modifications and variations without creative work can according to design of the present utility model.Therefore, all this technology necks Technical staff passes through logic analysis, reasoning or limited reality on the basis of existing technology according to design of the present utility model in domain Available technical scheme is tested, all should be in the protection domain being defined in the patent claims.

Claims (7)

  1. A kind of 1. cable terminal structure, including at least terminal tower, operation platform, terminals base;It is characterized in that:The terminal Tower uses narrow base steel pipe tower structure, and the terminal tower is fixed on ground, the end with the operation platform using filling pile structure Termination base is fixed on the operation platform upper surface, and the operation platform and the terminal tower are separately positioned.
  2. 2. cable terminal structure according to claim 1, it is characterised in that:Also include terminals, support insulator, it is described Terminals are fixed on the terminals base by the support insulator.
  3. 3. cable terminal structure according to claim 2, it is characterised in that:Also include fence, the vertical simultaneously ring of the fence Around the top surface edge for being arranged at the operation platform.
  4. 4. cable terminal structure according to claim 2, it is characterised in that:Also include arrester, arrester platform, it is described Arrester platform is fixed on the terminal tower, and the arrester is fixed on the arrester platform by the support insulator On, the arrester platform is located at the same side of the terminal tower with the operation platform.
  5. 5. cable terminal structure according to claim 4, it is characterised in that:The terminals are wrong with the arrester platform Position is set, and the terminals are arranged at the outside of the arrester platform.
  6. 6. cable terminal structure according to claim 4, it is characterised in that:Also include overground cable, aluminium alloy box culvert, institute The inside that overground cable is arranged at the operation platform and the terminals base is stated, the overground cable is by the aluminium alloy box Contain protection.
  7. 7. cable terminal structure according to claim 1, it is characterised in that:Also include cat ladder, the cat ladder is arranged at institute The vertical plane of operation platform is stated, the height of the cat ladder is highly consistent with the operation platform.
CN201720523658.XU 2017-05-12 2017-05-12 Cable terminal structure Active CN206712419U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720523658.XU CN206712419U (en) 2017-05-12 2017-05-12 Cable terminal structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720523658.XU CN206712419U (en) 2017-05-12 2017-05-12 Cable terminal structure

Publications (1)

Publication Number Publication Date
CN206712419U true CN206712419U (en) 2017-12-05

Family

ID=60466211

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720523658.XU Active CN206712419U (en) 2017-05-12 2017-05-12 Cable terminal structure

Country Status (1)

Country Link
CN (1) CN206712419U (en)

Similar Documents

Publication Publication Date Title
CN206712419U (en) Cable terminal structure
CN205901071U (en) It can current -limiting type lightning rod to become
CN105507646B (en) Communication base station
CN107227858A (en) Overhead bridge pier safe construction safeguard structure under high-voltage line
CN206806841U (en) Hydroenergy storage station or the special inspection platform of equipment for hydroelectric station
CN205153620U (en) Oil -immersed transformer's box -type substation fire control oil storage facility
CN202384676U (en) Grounding net of urban indoor 220kV transformer substation
CN206135375U (en) Arrangement structure that passes by on one's way of GIL pipeline
CN103166141A (en) Grounding grid of urban full-indoor transformer substation of 220kV
CN209853591U (en) Insulating protective door type hoisting device used in case of insufficient safety clearance under high-voltage line
CN114541618A (en) Sound barrier system for reducing electric field distortion and sound environment improvement method
CN208220337U (en) A kind of shared high voltage iron tower job platform
CN201303211Y (en) Controllable discharge lightning rod
CN103594988B (en) 500kV transformer substation tubular busbar deflection correction method
CN209389663U (en) Anti-slip cable duct
CN112909751A (en) 500kV and 220kV indoor substation 500kV and 220kV same-side upper and lower double-layer overhead outgoing line structure
CN207027430U (en) A kind of repairing platform device for offshore boosting station accident oil tank
CN203521114U (en) Special isolation transformer box mounting structure for airport
US20240221712A1 (en) Sound barrier system for reducing electric field distortion
CN105370063A (en) Box-type substation fire control and oil storage facility for oil-immersed transformer
CN212875349U (en) Ground filling type cable trench
KR102309942B1 (en) Pull-out type buried underground switchboard installed in the electric power underground section
CN205543275U (en) Tower grounding device based on three -dimensional equalizer ring
CN217485941U (en) Lightning protection system for high-rise building construction
CN213741212U (en) Top beam plate system of seismic isolation floor of 500kV alternating-current power distribution device

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant