CN206707731U - A kind of underground grouting opening arrangement - Google Patents

A kind of underground grouting opening arrangement Download PDF

Info

Publication number
CN206707731U
CN206707731U CN201720506435.2U CN201720506435U CN206707731U CN 206707731 U CN206707731 U CN 206707731U CN 201720506435 U CN201720506435 U CN 201720506435U CN 206707731 U CN206707731 U CN 206707731U
Authority
CN
China
Prior art keywords
opening arrangement
pressure
pressure gauge
cover
grouting opening
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201720506435.2U
Other languages
Chinese (zh)
Inventor
田玮
张�杰
罗元斌
钟杰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shenzhen Zhongjin Lingnan Non-Ferrous Metal Co Ltd
Fankou Lead Zinc Mine of Shenzhen Zhongjin Lingnan Nonfemet Co Ltd
Original Assignee
Shenzhen Zhongjin Lingnan Non-Ferrous Metal Co Ltd
Fankou Lead Zinc Mine of Shenzhen Zhongjin Lingnan Nonfemet Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shenzhen Zhongjin Lingnan Non-Ferrous Metal Co Ltd, Fankou Lead Zinc Mine of Shenzhen Zhongjin Lingnan Nonfemet Co Ltd filed Critical Shenzhen Zhongjin Lingnan Non-Ferrous Metal Co Ltd
Priority to CN201720506435.2U priority Critical patent/CN206707731U/en
Application granted granted Critical
Publication of CN206707731U publication Critical patent/CN206707731U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)

Abstract

It the utility model is related to a kind of underground grouting opening arrangement, including a body, a diaphragm apparatus and a pressure gauge;Described body one end is connected by the diaphragm apparatus with the pressure gauge;The bottom of the pipe offers injection point and serum outlet, and the injection point is connected with grouting pipeline, and the serum outlet is with treating that inlet well connects;The diaphragm apparatus includes upper press cover, lower cover and barrier film, and the upper press cover and lower cover are funnel-form, and upper press cover and lower cover cover connection, enclose to form a cavity;The barrier film is located between the upper press cover and lower cover, and the cavity is divided into upper plenum and lower cavity;Saturation is filled with hydraulic oil in the upper plenum, and the lower cavity connects with the body.The underground grouting opening arrangement is reasonable in design, avoids the sensing plunger in pressure gauge gauge outfit from directly being contacted with slurries by way of medium isolation, so as to avoid the loss of pressure gauge, while improves the accuracy of pressure measxurement.

Description

A kind of underground grouting opening arrangement
Technical field
Mine Grouting engineering technical field is the utility model is related to, more particularly to a kind of underground grouting opening arrangement.
Background technology
All mouth Pb-Zn deposits lion ridge -320m mother-lodes 0# stopes two-sections are horizontal to -280m, and in July, 2010 is in ore removal process In there is side nation and collapse, share 25 stopes (containing foundation) is influenceed by area is caving, and causes about 150,000 tons of affected area, the region ore deposit Body is mainly high-grade compact massive Huang iron Pb- Zn orebody, and ore body, which emits backwardness, causes about 150,000 tons of ores for having formed mining conditions It can not exploit.For down-hole formation design feature and the particularity of stope construction is collapsed, by being reconnoitred in detail to stratum and slip casting Reinforce, it is ensured that the smooth exploitation of stope.
Underground ore body Collapsed zone detects Grouting engineering, is influenceed by Collapsed zone, geologic structure less stable, stope ore body It sink, roll, ore body and obturation cementing properties is poor, and frictional force weakens, and the potential safety hazard of stope construction is big.Detected in stope While with grouting and reinforcing, to the strict control grouting pressure of work progress, reduce pressure slurries as far as possible to Stope roof and highwall Disturbance, ensure job safety be very necessary.
Referring to Fig. 1, it is prior art underground grouting slurry pressure measuring principle schematic diagram.In the prior art, underground Slip casting needs to use opening arrangement that the slurries in high-voltage tube are transported in hole, needed in aperture install pressure gauge, with monitor into Hole slurry pressure, because the sensing plunger in slurries and pressure gauge gauge outfit occurs directly to contact, easily pressure gauge is caused to be scrapped.Adopt A pressure gauge can be averagely consumed with the direct pressure injection per tour of existing process, only N2-3# stopes slip casting uses 150, pressure gauge altogether, It is worth 80,000 yuan.Sense simultaneously after plunger blocks, pressure gauge no longer shows the pressure of pressure or display mistake, easily causes to note Slurry pressure is excessive, makes natively fragile stope pilaster damage, so as to induce the generation of security incident.
Utility model content
Based on this, the purpose of this utility model is overcome the deficiencies in the prior art, there is provided a kind of underground grouting aperture dress To put, its is reasonable in design, avoids the sensing plunger in pressure gauge gauge outfit from directly being contacted with slurries by way of medium isolation, So as to avoid the loss of pressure gauge, while improve the accuracy of pressure measxurement.
To achieve these goals, the technical solution adopted in the utility model is:
A kind of underground grouting opening arrangement, including a body, a diaphragm apparatus and a pressure gauge;Described body one end passes through The diaphragm apparatus is connected with the pressure gauge;The bottom of the pipe offers injection point and serum outlet, and the slurries enter Mouth is connected with grouting pipeline, and the serum outlet is with treating that inlet well connects;The diaphragm apparatus include upper press cover, lower cover and Barrier film, the upper press cover and lower cover are funnel-form, and upper press cover and lower cover cover connection, enclose to form a cavity;It is described Barrier film is located between the upper press cover and lower cover, and the cavity is divided into upper plenum and lower cavity;Satisfy in the upper plenum Connected with filled with hydraulic oil, the lower cavity with the body.
Compared to prior art, underground grouting opening arrangement described in the utility model, it is by setting diaphragm apparatus, profit The mode isolated with medium avoids the sensing plunger in pressure gauge gauge outfit and directly contacted with slurries, protect pressure gauge gauge outfit not by Slurries are cementing, greatly reduce the loss of pressure gauge, while the measurement precision of grouting pressure has been effectively ensured.
Further, the barrier film is the stainless steel thin rounded flakes of destressing.By set the stainless steel thin rounded flakes every Film, the diaphragm apparatus inner chamber of spindle-type α-Fe2O3 is divided into upper plenum and lower cavity, because upper plenum is closing, saturation filling There is the chamber of hydraulic oil, and lower cavity connects with body, that is, the medium descended in cavity is air;With the slurries liquid level in body Change, the air pressure in lower cavity and body top changes so that barrier film deforms, the hydraulic pressure in upper plenum The pressure conduction of oil is to pressure gauge so as to showing real-time pressure value.
Further, the diaphragm apparatus both ends are connected with the pressure gauge and body by connecting tube respectively.Pass through company The connection of adapter, the upper plenum of the diaphragm apparatus encloses to form closed space with the pressure gauge, and saturation is filled with liquid Force feed;The lower cavity of the diaphragm apparatus then connects with body top.Connecting tube is preferably adopted with diaphragm apparatus, pressure gauge and body With threaded connection.
Further, the injection point is connected by slip casting pipe joint with a Grouting Pipe.The Grouting Pipe, which is used to convey, starches Liquid.
Further, its bottom is installed on aperture by slip casting hole sleeve, and the body axis with it is vertical The angle of plane is less than or equal to 30 °.Preferably, the body is installed with horizontal plane.If because aperture condition limits nothing Method right angle setting, then the angle of the body axis and perpendicular be less than or equal to 30 °, with ensure in body slurries liquid level with Body top keeps enough distances.
Further, the underground grouting opening arrangement is additionally provided with a pressure security unloading valve, and it is located at and the slurries On the pipeline for exporting connection.The pressure security unloading valve is safety convenience instrument, and it completes off-load when slurry pressure is exceeded, from And ensure that the slurry pressure entered in drilling meets design requirement, avoid natively fragile stope pilaster damage and induce safety The generation of accident.
Further, the diaphragm diameter is 80mm, thick 0.2mm.The diaphragm diameter and the upper press cover and lower cover Hatch bore diameter it is identical, the thickness of barrier film can ensure that it can sensitively conduct hydraulic pressure of the air pressure to upper plenum of lower cavity Oil.
Further, the pressure gauge is shockproof pressure gage.
Further, the upper press cover of the diaphragm apparatus and lower cover are bolted, and are sealed by sealing ring.Should The sealing that can ensure that diaphragm apparatus is set.
Brief description of the drawings
Fig. 1 is prior art underground grouting slurry pressure measuring principle schematic diagram;
Fig. 2 is the measuring principle schematic diagram of underground grouting opening arrangement described in the utility model;
Fig. 3 is the structural representation of underground grouting opening arrangement described in the utility model.
Embodiment
To further illustrate each embodiment, the utility model is provided with accompanying drawing.These accompanying drawings are in the utility model discloses A part for appearance, it can coordinate the associated description of specification to explain the running of embodiment original mainly to illustrate embodiment Reason.Cooperation refers to these contents, and one of ordinary skill in the art will be understood that other may obtain embodiment and this practicality The advantages of new.
Please refer to Fig. 2 and Fig. 3, wherein Fig. 2 is that the measurement of underground grouting opening arrangement described in the utility model is former Manage schematic diagram;Fig. 3 is the structural representation of underground grouting opening arrangement described in the utility model.Underground note of the present utility model Starch opening arrangement, including a body 10, a diaphragm apparatus 20 and a pressure gauge 30;Described one end of body 10 is filled by the barrier film 20 are put to be connected with the pressure gauge 30;The lower end of body 10 offers injection point 12 and serum outlet 11, and the slurries enter Mouth 12 is connected with grouting pipeline, and the serum outlet 11 is with treating that inlet well connects.Slurries enter body 10 from injection point 11 Interior, pressure change is delivered to pressure gauge 30 and shows real-time pressure value by air 82 in slurries compression body 10, diaphragm apparatus 20.
Specifically, the diaphragm apparatus 20 is spindle-type α-Fe2O3, it includes upper press cover 21, lower cover 22 and barrier film 23, institute It is funnel-form to state upper press cover 21 and lower cover 22, and upper press cover 21 and lower cover 22 cover connection, enclose to form a cavity;It is described Barrier film 23 is located between the upper press cover 21 and lower cover 22, and the cavity is divided into upper plenum and lower cavity;The overhead Intracavitary saturation is filled with hydraulic oil, and the lower cavity connects with the body 10.
In the present embodiment, the barrier film 23 be destressing stainless steel thin rounded flakes, its a diameter of 80mm, thick 0.2mm.Should The inner space of diaphragm apparatus 20 is separated into upper plenum and lower cavity by barrier film 23, i.e., isolates hydraulic oil and air two media, And sensitively the pressure change of lower empty chamber air can be transmitted to the hydraulic oil in upper plenum, so that hydraulic oil passes pressure On the plunger for leading the gauge outfit of pressure gauge 30, pressure gauge 30 is set to sense in real time and show the pressure of slurries.
Further, the top of diaphragm apparatus 20 is connected with the pressure gauge 30 by connecting tube 41, bottom and body 10 are connected by connecting tube 42.The injection point 12 is connected by slip casting pipe joint 51 with a Grouting Pipe 50.In the present embodiment, Preferably, the length of connecting tube 41 and 42 is 30mm, is machined with M20mm internal threads.
Further, the bottom of body 10 is installed on aperture by slip casting hole sleeve 60, and the axis of the body 10 It is less than or equal to 30 ° with the angle of perpendicular.In the present embodiment, the body 10 preferably uses diameter 108mm geology set Pipe is process, and length is about 60cm, a diameter of 108mm, thickness of pipe wall 4.5mm, and top welding M20mm pipe joints, lower end is mark Quasi- geology pipe thread, from welding slip casting pipe joint 51 at the 15cm of bottom;After the completion of weld, packer permeability test reaches 3 times of design notes It is as qualified to starch pressure.Body 10 is used to store fraction slurries and air, and body installation is preferably installed with horizontal plane, if by Right angle setting can not be ensured by being limited to place, then the angle of the axis of body 10 and perpendicular should be less than or equal to 30 °, to protect Slurries liquid level and the top of body 10 distance are more than 30cm in card body 10.
In order to ensure that the pressure of slurries is up to standard, a pressure security unloading valve 70 is additionally provided with, it is located at and the serum outlet On the pipeline of 11 connections.The pressure security unloading valve 70 is the device that pressure unloading is adjusted by spring, more than setting pressure That is automatically unloading.
In the present embodiment, it is preferable that the upper press cover 21 and lower cover 22 of the diaphragm apparatus 20 are bolted, and are led to Cross the sealing of RUBBER O type sealing ring;The hydraulic oil uses 40# antiwear hydraulic oils;The pressure gauge is common anti-shock pressure meter.
Illustrate the operation principle of the underground grouting opening arrangement of the present embodiment below:
Slurries enter body 10 from Grouting Pipe 50, and are stored in body 10, the slurries compression upper end air 82 of body 10, pressure On barrier film 23, barrier film 23 deforms contracting air effect, makes the volume-diminished of diaphragm apparatus upper plenum, and hydraulic oil 81 is by pressure It is conducted to pressure gauge 30 and real-time display pressure.The lower end of body 10 sets pressure security unloading valve 70, even if the failure of pressure gauge 30 And causing pressure to be forbidden, safety unloading valve can also lay down pressure in time, be set so as to ensure that the slurry pressure entered in drilling meets Meter requires.
Compared to prior art, underground grouting opening arrangement described in the utility model, its by setting diaphragm apparatus 20, The mode isolated using medium is avoided the sensing plunger in the gauge outfit of pressure gauge 30 and directly contacted with slurries, protects the table of pressure gauge 30 Head is not cementing by slurries, greatly reduces the loss of pressure gauge, while the measurement precision of grouting pressure has been effectively ensured.
Embodiment described above only expresses several embodiments of the present utility model, and its description is more specific and detailed, But therefore it can not be interpreted as the limitation to utility model patent scope.It should be pointed out that the common skill for this area For art personnel, without departing from the concept of the premise utility, various modifications and improvements can be made, these are belonged to The scope of protection of the utility model.

Claims (9)

  1. A kind of 1. underground grouting opening arrangement, it is characterised in that:Including a body, a diaphragm apparatus and a pressure gauge;The pipe Body one end is connected by the diaphragm apparatus with the pressure gauge;The bottom of the pipe offers injection point and serum outlet, The injection point is connected with grouting pipeline, and the serum outlet is with treating that inlet well connects;The diaphragm apparatus includes upper pressure Lid, lower cover and barrier film, the upper press cover and lower cover are funnel-form, and upper press cover and lower cover cover connection, enclose to be formed One cavity;The barrier film is located between the upper press cover and lower cover, and the cavity is divided into upper plenum and lower cavity;It is described Saturation is filled with hydraulic oil in upper plenum, and the lower cavity connects with the body.
  2. 2. underground grouting opening arrangement according to claim 1, it is characterised in that:The barrier film is the stainless steel of destressing Thin rounded flakes.
  3. 3. underground grouting opening arrangement according to claim 1, it is characterised in that:The diaphragm apparatus both ends respectively with institute Pressure gauge is stated to connect by connecting tube with body.
  4. 4. underground grouting opening arrangement according to claim 1, it is characterised in that:The injection point is connect by Grouting Pipe Head is connected with a Grouting Pipe.
  5. 5. underground grouting opening arrangement according to claim 1, it is characterised in that:Its bottom passes through slip casting borehole jack Pipe is installed on aperture, and the angle of the body axis and perpendicular is less than or equal to 30 °.
  6. 6. underground grouting opening arrangement according to claim 1, it is characterised in that:A pressure security unloading valve is additionally provided with, It is located on the pipeline being connected with the serum outlet.
  7. 7. underground grouting opening arrangement according to claim 2, it is characterised in that:The diaphragm diameter is 80mm, thick 0.2mm。
  8. 8. underground grouting opening arrangement according to claim 1, it is characterised in that:The pressure gauge is shockproof pressure gage.
  9. 9. the underground grouting opening arrangement according to any one of claim 1~8, it is characterised in that:The diaphragm apparatus Upper press cover and lower cover are bolted, and are sealed by sealing ring.
CN201720506435.2U 2017-05-09 2017-05-09 A kind of underground grouting opening arrangement Active CN206707731U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720506435.2U CN206707731U (en) 2017-05-09 2017-05-09 A kind of underground grouting opening arrangement

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720506435.2U CN206707731U (en) 2017-05-09 2017-05-09 A kind of underground grouting opening arrangement

Publications (1)

Publication Number Publication Date
CN206707731U true CN206707731U (en) 2017-12-05

Family

ID=60466476

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720506435.2U Active CN206707731U (en) 2017-05-09 2017-05-09 A kind of underground grouting opening arrangement

Country Status (1)

Country Link
CN (1) CN206707731U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110985719A (en) * 2019-12-21 2020-04-10 江苏江林机械有限公司 Pressure control device for pneumatic grouting pump
CN112595469A (en) * 2020-12-09 2021-04-02 西安近代化学研究所 Circular weld sealing performance detection device of cylindrical shell

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110985719A (en) * 2019-12-21 2020-04-10 江苏江林机械有限公司 Pressure control device for pneumatic grouting pump
CN112595469A (en) * 2020-12-09 2021-04-02 西安近代化学研究所 Circular weld sealing performance detection device of cylindrical shell
CN112595469B (en) * 2020-12-09 2023-02-03 西安近代化学研究所 Circular weld sealing performance detection device of cylindrical shell

Similar Documents

Publication Publication Date Title
CN106018105A (en) Multifunctional physical simulation test system for coal engineering and coal model test method
CN104179491B (en) Underground rock cranny drilling supersonic sounding device and system
CN103510964B (en) A kind of method when using shield formula TBM to construct to beans gravel rockfill grouting
CN205000965U (en) Moisture drilling gas piezometry device
CN206573380U (en) Coal petrography triaxial creepage seepage tests system
CN203519230U (en) Coal-rock mass stress directional monitoring device
CN206707731U (en) A kind of underground grouting opening arrangement
CN107100612B (en) Method for investigating underground hydraulic fracturing influence area
CN110006760A (en) A kind of method that Accurate Determining deep hole water pressure blasting fracturing induces rupture reopening pressure
CN210269442U (en) Triaxial coal petrography multi-field multiphase coupling fracturing experimental apparatus
CN109973082A (en) The device and method for measuring multiple seam gas pressure simultaneously to layer-through drilling based on
CN106321001A (en) Drill hole anchoring structure for monitoring floor surrounding rock fractures and construction method thereof
CN106988738A (en) A kind of detection method of definitely stress distribution feature
CN205330609U (en) Novel hole sealing pressure measurement integration device
CN206038490U (en) Single power source binary channels country rock mining -induced fissure probe unit
CN103939075B (en) A kind of fracturing process improving coal mine gas drainage effect and device
CN203145925U (en) Device for quickly measuring coal seam gas pressure by upward remote drilling
CN205858326U (en) A kind of mine country rock gas pressure measurement drainage device
CN204571973U (en) Novel descending hole capsule-pressure mucus sealing of hole draining pressure tester
CN106323109A (en) Longhole pressure-bearing blasting method of hard coal rock
CN203702244U (en) Breaking roof caving area grouting filling system
CN203705269U (en) Coal mine old mined-out area caving zone fractured rock mass secondary deformation compression simulation experiment device
CN203241177U (en) Monitoring system of goaf rock coverage stability
CN202220566U (en) Wired communication screw
CN203499618U (en) Gas drive oil production annular test decentralized wellhead device

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CP02 Change in the address of a patent holder

Address after: Room 303C, tower 2, Shenye Jinyuan Building, No. 112, Qingshuihe 1st Road, Qingshuihe community, Luohu District, Shenzhen City, Guangdong Province

Patentee after: SHENZHEN ZHONGJIN LINGNAN NONFEMET Co.,Ltd.

Patentee after: FANKOU LEAD-ZINC MINE, SHENZHEN ZHONGJIN LINGNAN NONFEMET Co.,Ltd.

Address before: 24-26, building 6013, China Nonferrous building, No. 518040 Shennan Road, Futian District, Guangdong, Che Kung Temple, Shenzhen

Patentee before: SHENZHEN ZHONGJIN LINGNAN NONFEMET Co.,Ltd.

Patentee before: FANKOU LEAD-ZINC MINE, SHENZHEN ZHONGJIN LINGNAN NONFEMET Co.,Ltd.

CP02 Change in the address of a patent holder