CN206693519U - The mounting structure of top rack sound absorption module - Google Patents
The mounting structure of top rack sound absorption module Download PDFInfo
- Publication number
- CN206693519U CN206693519U CN201720202424.5U CN201720202424U CN206693519U CN 206693519 U CN206693519 U CN 206693519U CN 201720202424 U CN201720202424 U CN 201720202424U CN 206693519 U CN206693519 U CN 206693519U
- Authority
- CN
- China
- Prior art keywords
- load
- sleeve pipe
- sleeve
- bearing frame
- pipe
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Buildings Adapted To Withstand Abnormal External Influences (AREA)
Abstract
It the utility model is related to a kind of mounting structure of top rack sound absorption module, including first sleeve, second sleeve pipe, load-bearing frame and noise elimination wedge mount pipe, load-bearing frame generally cuboid framework structure, load-bearing frame it is upper, the lower two layers longitude and latitude cross structure for up and down mutually corresponding to, the corner of load-bearing frame is fixedly connected with the second sleeve pipe respectively, the top of first sleeve is welded and fixed with genuine room roof, bottom and the top of the second sleeve pipe are set with and can carry out being set with length regulation, reinforced between second sleeve pipe and load-bearing frame by reinforcing joint, the bottom surface interval of load-bearing frame, some noise elimination wedges are abreast installed and mount pipe, it is opening down that noise elimination wedge, which mounts pipe, half C-shaped tubular construction of section.The utility model can realize the installation to noise elimination wedge on the basis of original factory building roof, rapidly and efficiently, reduce cost.
Description
Technical field
The utility model belongs to the technical field of anechoic room noise elimination wedge installation, more particularly to rack at the top of one kind inhale every
The mounting structure of sound module.
Background technology
Generally, the wedge at the top of anechoic room is arranged on top surface, and top surface is usually a plane, similar with side wall, in top surface
Transverse and longitudinal keel and support is added easily to mount wedge.But in some projects, the top that actual place leaves is not
One planar structure, this just needs other design and installation structure.
The content of the invention
Technical problem to be solved in the utility model is to provide a kind of mounting structure of top rack sound absorption module, energy
Enough Fast Installations realized on the basis of original factory building roof to noise elimination wedge.
Technical scheme is to provide rack sound absorption module at the top of one kind used by the utility model solves its technical problem
Mounting structure, including first sleeve, the second sleeve pipe, load-bearing frame and noise elimination wedge mount pipe, and the load-bearing frame is generally
Cuboid framework structure, the upper and lower two layers longitude and latitude cross structure for up and down mutually corresponding to of load-bearing frame, the load-bearing frame
Corner is fixedly connected with the second sleeve pipe respectively, and the top of the first sleeve is welded and fixed with genuine room roof, bottom and second
The top of sleeve pipe is set with and can carry out being set with length regulation, is added between second sleeve pipe and load-bearing frame by reinforcing joint
Gu the bottom surface interval of the load-bearing frame, being abreast provided with some noise elimination wedges and mounting pipe, the noise elimination wedge mounts pipe and is
Half tubular construction opening down, section is C-shaped.
As a kind of preferred embodiment of the utility model, it is right up and down to be fixed with the first sleeve and the second sleeve pipe
The adjustment sheet with holes answered, bolt is loaded in two adjustment sheets and is adjusted by tightening nut between first sleeve and the second sleeve pipe
It is set with length.
As the utility model another preferred embodiment, the first sleeve is inner sleeve, second sleeve pipe
For outer tube, the first sleeve bottom is inserted into the second inside pipe casing and is set with.
As the utility model another preferred embodiment, the bottom surface of the load-bearing frame and the bottom of the second sleeve pipe
Concordantly.
As the utility model another preferred embodiment, pass through diagonal brace between upper and lower two layers of the load-bearing frame
It is supported reinforcing.
Beneficial effect
In the utility model, tune that the horizontality of load-bearing frame passes through encapsulation length between first sleeve and the second sleeve pipe
Section carries out leveling, and noise elimination wedge mounts pipe by noise elimination wedge and can quickly be installed, therefore, the utility model by
Genuine room roof builds noise elimination wedge mounting bracket, so as to realize the installation to noise elimination wedge on the basis of original factory building roof,
Rapidly and efficiently, cost is reduced.
Brief description of the drawings
Fig. 1 is node detail view of the present utility model.
Fig. 2 is side block diagram of the present utility model.
Fig. 3 is overlooking structure figure of the present utility model.
Embodiment
With reference to specific embodiment, the utility model is expanded on further.It should be understood that these embodiments are merely to illustrate this
Utility model rather than limitation the scope of the utility model.In addition, it is to be understood that reading the content of the utility model instruction
Afterwards, those skilled in the art can make various changes or modifications to the utility model, and these equivalent form of values equally fall within this Shen
Please appended claims limited range.
A kind of mounting structure of top rack sound absorption module as Figure 1-3, including first sleeve 1, the second sleeve pipe
2nd, load-bearing frame 5 and noise elimination wedge mount pipe 7.
The generally cuboid framework structure of load-bearing frame 5, upper and lower two layers of load-bearing frame 5 pass through for up and down mutually corresponding to
Latitude cross structure, reinforcing is supported by diagonal brace 8 between upper and lower two layers of load-bearing frame 5.
The corner of load-bearing frame 5 is fixedly connected with the second sleeve pipe 2 respectively, the bottom surface of load-bearing frame 5 and the bottom of the second sleeve pipe 2
Hold level with both hands neat.The top of first sleeve 1 is welded and fixed with genuine room roof 9, and bottom and the top of the second sleeve pipe 2 are set with, first set
Pipe 1 is inner sleeve, and the second sleeve pipe 2 is outer tube, and the bottom of first sleeve 1 is inserted into inside the second sleeve pipe 2 and is set with.First set
Corresponding adjustment sheet with holes up and down is fixed with the sleeve pipe 2 of pipe 1 and second, loads bolt 3 and by tightening spiral shell in two adjustment sheets
Mother 4 adjusts the suit length between the sleeve pipe 2 of first sleeve 1 and second, so as to carry out leveling to load-bearing frame 5.Second sleeve pipe 2 with
Reinforced between load-bearing frame 5 by reinforcing joint 6.
The bottom surface interval of load-bearing frame 5, some noise elimination wedges are abreast installed mount pipe 7, noise elimination wedge mounts pipe 7 and is
Half tubular construction opening down, section is C-shaped, the hook structure of noise elimination wedge mounts pipe 7 by noise elimination wedge can be carried out soon
The cooperation installation of speed.
Claims (5)
1. a kind of mounting structure of top rack sound absorption module, including first sleeve (1), the second sleeve pipe (2), load-bearing frame
(5) and noise elimination wedge mounts pipe (7), it is characterised in that:The load-bearing frame (5) generally cuboid framework structure, load frame
The longitude and latitude cross structure for up and down mutually corresponding to of upper and lower two layers of frame (5), the corner of the load-bearing frame (5) is respectively with second
Sleeve pipe (2) is fixedly connected, and the top of the first sleeve (1) is welded and fixed with genuine room roof (9), bottom and the second sleeve pipe
(2) top is set with and can carry out being set with length regulation, passes through reinforcing between second sleeve pipe (2) and load-bearing frame (5)
Node (6) is reinforced, and the bottom surface interval of the load-bearing frame (5), is abreast provided with some noise elimination wedges and is mounted pipe (7), described
Noise elimination wedge mounts pipe (7) as half tubular construction opening down, section is C-shaped.
A kind of 2. mounting structure of top rack sound absorption module according to claim 1, it is characterised in that:Described first
Corresponding adjustment sheet with holes up and down is fixed with sleeve pipe (1) and the second sleeve pipe (2), loads bolt (3) in two adjustment sheets and leads to
Cross tighten nut (4) regulation first sleeve (1) and the second sleeve pipe (2) between suit length.
A kind of 3. mounting structure of top rack sound absorption module according to claim 1, it is characterised in that:Described first
Sleeve pipe (1) is inner sleeve, and second sleeve pipe (2) is outer tube, and first sleeve (1) bottom is inserted into the second sleeve pipe (2)
Inside is set with.
A kind of 4. mounting structure of top rack sound absorption module according to claim 1, it is characterised in that:The load
The bottom surface of framework (5) is concordant with the bottom of the second sleeve pipe (2).
A kind of 5. mounting structure of top rack sound absorption module according to claim 1, it is characterised in that:The load
Reinforcing is supported by diagonal brace (8) between upper and lower two layers of framework (5).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201720202424.5U CN206693519U (en) | 2017-03-03 | 2017-03-03 | The mounting structure of top rack sound absorption module |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201720202424.5U CN206693519U (en) | 2017-03-03 | 2017-03-03 | The mounting structure of top rack sound absorption module |
Publications (1)
Publication Number | Publication Date |
---|---|
CN206693519U true CN206693519U (en) | 2017-12-01 |
Family
ID=60442434
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201720202424.5U Active CN206693519U (en) | 2017-03-03 | 2017-03-03 | The mounting structure of top rack sound absorption module |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN206693519U (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106894581A (en) * | 2017-03-03 | 2017-06-27 | 上海声望声学科技股份有限公司 | The mounting structure of top rack sound absorption module |
CN113006287A (en) * | 2019-12-20 | 2021-06-22 | 陕西博睿信息科技有限公司 | A vertical connecting device in air for steel construction |
-
2017
- 2017-03-03 CN CN201720202424.5U patent/CN206693519U/en active Active
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106894581A (en) * | 2017-03-03 | 2017-06-27 | 上海声望声学科技股份有限公司 | The mounting structure of top rack sound absorption module |
CN113006287A (en) * | 2019-12-20 | 2021-06-22 | 陕西博睿信息科技有限公司 | A vertical connecting device in air for steel construction |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN206693519U (en) | The mounting structure of top rack sound absorption module | |
CN202048928U (en) | Novel shock-absorbing and supporting platform | |
CN207935554U (en) | One kind being used for subway transportation antidetonation suspension and support | |
CN203794508U (en) | Tower crane standard knot reinforced structure | |
CN211666180U (en) | Passive ultralow energy consumption window installation is with supplementary fixing device | |
MX2022006368A (en) | Self-supporting frame for photovoltaic panels. | |
CN106894581A (en) | The mounting structure of top rack sound absorption module | |
CN207700375U (en) | A kind of assembling type steel structure beam column node connection device | |
CN206903187U (en) | Sheet-type support | |
CN107631096B (en) | A kind of oil pipeline support | |
CN207191041U (en) | A kind of mounting structure of heavy truck gas receiver | |
CN206189636U (en) | Enlarge damping energy dissipation support system | |
CN207035355U (en) | A kind of idle call support frame | |
CN101710640B (en) | Power supply terminal antenna erection tower | |
CN213837958U (en) | Communication tower angle steel reinforcing apparatus | |
CN204646583U (en) | A kind of mounting bracket of air condition compressor | |
CN202867693U (en) | Installation under frame of multifunctional diesel generating set | |
CN207245856U (en) | One kind starts air conditioner adjustable mounting bracket | |
CN219240994U (en) | Intelligent structure curtain that facilitates connection | |
CN207348770U (en) | A kind of multi-functional band ladder aluminum wood pedal | |
CN205674857U (en) | A kind of integrated gear-box bracket assembly | |
CN207003971U (en) | A kind of assembling house builds carrying frame | |
CN213742361U (en) | Temperature control device for mass concrete transportation | |
CN107758557A (en) | A kind of mounting assist support of formula flat lamp easy to remove | |
CN204895611U (en) | Engine access hole frame construction |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |