CN206693494U - EPS prefabricated boards for building - Google Patents
EPS prefabricated boards for building Download PDFInfo
- Publication number
- CN206693494U CN206693494U CN201720361555.8U CN201720361555U CN206693494U CN 206693494 U CN206693494 U CN 206693494U CN 201720361555 U CN201720361555 U CN 201720361555U CN 206693494 U CN206693494 U CN 206693494U
- Authority
- CN
- China
- Prior art keywords
- eps
- stainless steel
- modules
- eps modules
- hole
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 239000010935 stainless steel Substances 0.000 claims abstract description 29
- 229910001220 stainless steel Inorganic materials 0.000 claims abstract description 29
- 230000002787 reinforcement Effects 0.000 claims abstract description 20
- 230000003014 reinforcing effect Effects 0.000 claims abstract description 9
- 238000007493 shaping process Methods 0.000 claims abstract description 3
- 229910000831 Steel Inorganic materials 0.000 claims description 8
- 239000010959 steel Substances 0.000 claims description 8
- RYGMFSIKBFXOCR-UHFFFAOYSA-N Copper Chemical compound [Cu] RYGMFSIKBFXOCR-UHFFFAOYSA-N 0.000 claims description 7
- 239000010949 copper Substances 0.000 claims description 7
- 229910052802 copper Inorganic materials 0.000 claims description 7
- 229910001297 Zn alloy Inorganic materials 0.000 claims description 4
- 241001124569 Lycaenidae Species 0.000 claims description 3
- 235000014987 copper Nutrition 0.000 claims description 3
- JEIPFZHSYJVQDO-UHFFFAOYSA-N iron(III) oxide Inorganic materials O=[Fe]O[Fe]=O JEIPFZHSYJVQDO-UHFFFAOYSA-N 0.000 claims 1
- 239000004566 building material Substances 0.000 abstract description 3
- 230000002093 peripheral effect Effects 0.000 abstract description 3
- 230000009286 beneficial effect Effects 0.000 abstract 1
- 241000719178 Carangoides ruber Species 0.000 description 3
- HXFVOUUOTHJFPX-UHFFFAOYSA-N alumane;zinc Chemical compound [AlH3].[Zn] HXFVOUUOTHJFPX-UHFFFAOYSA-N 0.000 description 2
- 235000008733 Citrus aurantifolia Nutrition 0.000 description 1
- 239000004793 Polystyrene Substances 0.000 description 1
- 235000011941 Tilia x europaea Nutrition 0.000 description 1
- FJMNNXLGOUYVHO-UHFFFAOYSA-N aluminum zinc Chemical compound [Al].[Zn] FJMNNXLGOUYVHO-UHFFFAOYSA-N 0.000 description 1
- 239000004035 construction material Substances 0.000 description 1
- 230000007812 deficiency Effects 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 239000006260 foam Substances 0.000 description 1
- 239000004571 lime Substances 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 239000004033 plastic Substances 0.000 description 1
- 229920003023 plastic Polymers 0.000 description 1
- 229920000642 polymer Polymers 0.000 description 1
- 229920002223 polystyrene Polymers 0.000 description 1
- 230000008092 positive effect Effects 0.000 description 1
- 239000007921 spray Substances 0.000 description 1
- 238000006467 substitution reaction Methods 0.000 description 1
Landscapes
- Laminated Bodies (AREA)
Abstract
The utility model provides EPS prefabricated boards for building, including EPS modules, stainless steel plate and stainless steel plug, two pieces of stainless steel plates are fixedly arranged on the EPS modules both sides, two pieces of stainless steel plugs are fixedly arranged on the EPS modules both ends, bar-mat reinforcement is provided with the EPS modules, the bar-mat reinforcement is integrally machined shaping with the EPS modules.The beneficial effects of the utility model are:Its EPS modular peripheral adds stainless steel reinforcing, and bar-mat reinforcement reinforcing is added inside it, and the weight capacity for the EPS prefabricated boards being consequently formed effectively improves, and is used available for building roof building materials.
Description
Technical field
Building structure field is the utility model is related to, EPS prefabricated boards specially for building.
Background technology
In the prior art, EPS modules are a kind of polystyrene polymeric polymer, foam of the finished product into rigid closed cell structure
Plastics, it is light durable, it is widely used in building field as a kind of preferably construction material, but existing use EPS module shapes
Though into prefabricated board weight it is light but weight capacity is poor, need to improve.
The content of the invention
The utility model is overcome the deficiencies in the prior art, there is provided a kind of EPS prefabricated boards for building, its EPS modular peripheral
Stainless steel reinforcing is added, bar-mat reinforcement reinforcing is added inside it, the weight capacity for the EPS prefabricated boards being consequently formed effectively is carried
Height, used available for building roof building materials.
In order to solve the above technical problems, the technical solution adopted in the utility model is:
EPS prefabricated boards for building, including EPS modules, stainless steel plate and stainless steel plug, two pieces of stainless steel plates are fixed
In the EPS modules both sides, two pieces of stainless steel plugs are fixedly arranged on the EPS modules both ends;
The EPS modules two sides are provided with some dovetail grooves laterally set, and the stainless steel plate medial surface is provided with some
The raised line coordinated with the dovetail groove, the raised line are plugged in the dovetail groove;
Some cross through hole are provided with the middle part of the EPS modules, some cross through hole are longitudinally in one line, described stainless
Steel plug includes vertical portion and the kink positioned at the vertical portion both sides, and some and dovetail is provided with the inside of the kink
The raised line that groove coordinates, the raised line are plugged in the dovetail groove, are provided with some plush coppers on the inside of the vertical portion, the plush copper is inserted
It is connected in the cross through hole.
Further, bar-mat reinforcement is provided with the EPS modules, the bar-mat reinforcement is integrally machined shaping, institute with the EPS modules
Stating bar-mat reinforcement includes some transverse steels and some longitudinal reinforcements.
Further, the both ends of some transverse steels are located in the corresponding cross through hole, its both ends and the horizontal stroke
To through hole flush with outer surface, reinforcing bar jack is provided with the middle part of the plush copper.
Further, the EPS modules outer surface is provided with plate golding aluminium zinc alloy layer, and its thickness is 0.6~1.2mm.
The utility model has the advantages and positive effects of:EPS modular peripherals add stainless steel reinforcing, add inside it
Bar-mat reinforcement is reinforced, and the weight capacity for the EPS prefabricated boards being consequently formed effectively improves, and its weight only accounts for conventional lime system
/ 3rd of prefabricated board, used available for building roof building materials.
Brief description of the drawings
Fig. 1, Fig. 2 are the structural representation that the assembling of EPS prefabricated boards is front and rear in embodiment;
Fig. 3 is the structural representation of EPS modules described in embodiment;
Fig. 4 is Fig. 3 cross-sectional view;
Fig. 5 is the structural representation of stainless steel plate described in embodiment;
Fig. 6 is the structural representation of stainless steel plug described in embodiment.
In figure:1st, EPS modules, 11, dovetail groove, 12, cross through hole, 2, stainless steel plate, 21, raised line, 3, stainless steel plug,
31st, vertical portion, 32, kink, 33, plush copper, 34, reinforcing bar jack, 4, bar-mat reinforcement, 41, transverse steel, 42, longitudinal reinforcement.
Embodiment
It should be noted that in the case where not conflicting, the feature in embodiment and embodiment in the utility model can
To be mutually combined.
In description of the present utility model, it is to be understood that term " " center ", " longitudinal direction ", " transverse direction ", " on ", " under ",
The orientation or position relationship of the instruction such as "front", "rear", "left", "right", " vertical ", " level ", " top ", " bottom ", " interior ", " outer " are
Based on orientation shown in the drawings or position relationship, it is for only for ease of description the utility model and simplifies description, rather than instruction
Or imply that signified device or element must have specific orientation, with specific azimuth configuration and operation, therefore be not understood that
For to limitation of the present utility model.In addition, term " first ", " second " etc. are only used for describing purpose, and it is not intended that instruction
Or imply relative importance or the implicit quantity for indicating indicated technical characteristic.Thus, " first ", " second " etc. are defined
Feature can express or implicitly include one or more this feature.In description of the present utility model, unless separately
It is described, " multiple " are meant that two or more.
Describe the utility model in detail below with reference to the accompanying drawings and in conjunction with the embodiments.
As shown in Fig. 1-6, EPS prefabricated boards for building, including EPS modules 1, stainless steel plate 2 and stainless steel plug 3, two pieces
The stainless steel plate 2 is fixedly arranged on the both sides of EPS modules 1, and two pieces of stainless steel plugs 3 are fixedly arranged on 1 liang of the EPS modules
End;
The two sides of EPS modules 1 are provided with some dovetail grooves 11 laterally set, and the medial surface of stainless steel plate 2 is provided with
Some raised lines 21 coordinated with the dovetail groove 11, the raised line 21 are plugged in the dovetail groove 11;
The middle part of EPS modules 1 is provided with some cross through hole 12, and some cross through hole are longitudinally in one line, described
Stainless steel plug 3 includes vertical portion 31 and the kink 32 positioned at the vertical portion both sides, if the inner side of the kink 32 is provided with
The dry raised line 21 coordinated with the dovetail groove 11, the raised line 21 are plugged in the dovetail groove 11, the inner side of vertical portion 31
Provided with some plush coppers 33, the plush copper 33 is plugged in the cross through hole 12.
I.e. the two sides of the EPS modules and two ends are reinforced with stainless steel, to increase its load-bearing.
It is below the improvement to the above-mentioned technical solutions of this embodiment.
Further, bar-mat reinforcement 4 is provided with the EPS modules 1, the bar-mat reinforcement 4 is integrally machined into the EPS modules 1
Type, the bar-mat reinforcement 4 include some transverse steels 41 and some longitudinal reinforcements 42.The setting of the bar-mat reinforcement can rise to EPS modules
To booster action.
Wherein, the both ends of some transverse steels 41 are located in the corresponding cross through hole 12, its both ends with it is described
The flush with outer surface of cross through hole 12, the middle part of plush copper 33 are provided with reinforcing bar jack 34.
Further, the outer surface of EPS modules 1 is provided with plate golding aluminium zinc alloy layer, and its thickness is 0.6~1.2mm, the aluminum-zinc alloy
Alloy-layer is spray mo(u)lding.
Preferred embodiment of the present utility model is the foregoing is only, it is all at this not to limit the utility model
Within the spirit and principle of utility model, any modification, equivalent substitution and improvements made etc., the utility model should be included in
Protection domain within.
Claims (4)
1. EPS prefabricated boards for building, it is characterised in that including EPS modules, stainless steel plate and stainless steel plug, described in two pieces not
Rust steel plate is fixedly arranged on the EPS modules both sides, and two pieces of stainless steel plugs are fixedly arranged on the EPS modules both ends;
The EPS modules two sides are provided with some dovetail grooves laterally set, and the stainless steel plate medial surface is provided with some and institute
The raised line of dovetail groove cooperation is stated, the raised line is plugged in the dovetail groove;
Some cross through hole are provided with the middle part of the EPS modules, some cross through hole are longitudinally in one line, and the stainless steel is inserted
Head includes vertical portion and the kink positioned at the vertical portion both sides, matches somebody with somebody on the inside of the kink provided with some with the dovetail groove
The raised line of conjunction, the raised line are plugged in the dovetail groove, are provided with some plush coppers on the inside of the vertical portion, the plush copper is plugged in
In the cross through hole.
2. EPS prefabricated boards for building according to claim 1, it is characterised in that bar-mat reinforcement is provided with the EPS modules,
The bar-mat reinforcement is integrally machined shaping with the EPS modules, and the bar-mat reinforcement includes some transverse steels and some longitudinal reinforcements.
3. EPS prefabricated boards for building according to claim 2, it is characterised in that the both ends position of some transverse steels
In in the corresponding cross through hole, its both ends and the cross through hole flush with outer surface, the plush copper middle part are inserted provided with reinforcing bar
Hole.
4. EPS prefabricated boards for building according to claim 1, it is characterised in that the EPS modules outer surface is provided with and aluminized
Zinc alloy layer, its thickness are 0.6~1.2mm.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201720361555.8U CN206693494U (en) | 2017-04-08 | 2017-04-08 | EPS prefabricated boards for building |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201720361555.8U CN206693494U (en) | 2017-04-08 | 2017-04-08 | EPS prefabricated boards for building |
Publications (1)
Publication Number | Publication Date |
---|---|
CN206693494U true CN206693494U (en) | 2017-12-01 |
Family
ID=60441720
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201720361555.8U Expired - Fee Related CN206693494U (en) | 2017-04-08 | 2017-04-08 | EPS prefabricated boards for building |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN206693494U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112177201A (en) * | 2020-10-14 | 2021-01-05 | 浙江普罗住工绿建科技股份有限公司 | Modular wall building system |
-
2017
- 2017-04-08 CN CN201720361555.8U patent/CN206693494U/en not_active Expired - Fee Related
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112177201A (en) * | 2020-10-14 | 2021-01-05 | 浙江普罗住工绿建科技股份有限公司 | Modular wall building system |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN206693494U (en) | EPS prefabricated boards for building | |
CN201574504U (en) | Paper mold armoured concrete wall | |
CN205976457U (en) | Aluminum alloy building formwork | |
CN209686854U (en) | A kind of glued board building template | |
CN215671008U (en) | Support with equipment building templates | |
CN214941589U (en) | Prefabricated assembled heat preservation energy-saving wall in technical field of constructional engineering | |
CN206218137U (en) | A kind of groove profile wall construction of ship oil tank | |
CN205131898U (en) | Pallet structure | |
CN206110648U (en) | A high accuracy environmental protection wood subassembly of moulding | |
CN205602478U (en) | Cornerite section bar | |
CN206693454U (en) | A kind of energy saving building integration EPS corner modules | |
CN208053441U (en) | A kind of crossbeam | |
CN207419867U (en) | Steel house panel splicing module | |
CN216239043U (en) | High strength EPS building module plate body connecting piece | |
CN219080966U (en) | Plastic formwork that holding power is strong | |
CN219340498U (en) | Corrosion-resistant strong compression-resistant stainless steel water tank | |
CN210439543U (en) | Four-cavity type masonry module | |
CN214525892U (en) | PET super corrosion resistant composite water tank | |
CN208815898U (en) | A kind of novel back cord external corner part | |
CN214609386U (en) | Assembled zinc-aluminum-magnesium PE composite water tank | |
CN210369536U (en) | Three-cavity masonry module | |
CN220607832U (en) | Goods shelf beam combining steel and high-strength grouting material | |
CN208310209U (en) | A kind of stair aluminum alloy mould plate convenient for construction | |
CN201309707Y (en) | Underframe structure of cargo container | |
CN214525893U (en) | PES (polyether sulfone) super-corrosion-resistant steel-plastic composite water tank |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20171201 |