CN206684248U - A kind of metallic oxide arrester electrification test experimental study system - Google Patents

A kind of metallic oxide arrester electrification test experimental study system Download PDF

Info

Publication number
CN206684248U
CN206684248U CN201720068678.2U CN201720068678U CN206684248U CN 206684248 U CN206684248 U CN 206684248U CN 201720068678 U CN201720068678 U CN 201720068678U CN 206684248 U CN206684248 U CN 206684248U
Authority
CN
China
Prior art keywords
arrester
moa
pillar
metal oxide
change
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn - After Issue
Application number
CN201720068678.2U
Other languages
Chinese (zh)
Inventor
郭磊
寇晓适
王伟
张科
董曼玲
丁国君
王天
赵磊
李予全
郑含博
邵颖彪
王栋
付海金
蒲兵舰
辛伟峰
王吉
王震宇
马德英
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
Electric Power Research Institute of State Grid Henan Electric Power Co Ltd
Original Assignee
State Grid Corp of China SGCC
Electric Power Research Institute of State Grid Henan Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, Electric Power Research Institute of State Grid Henan Electric Power Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN201720068678.2U priority Critical patent/CN206684248U/en
Application granted granted Critical
Publication of CN206684248U publication Critical patent/CN206684248U/en
Withdrawn - After Issue legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Testing Relating To Insulation (AREA)
  • Testing Electric Properties And Detecting Electric Faults (AREA)

Abstract

The utility model discloses a kind of metallic oxide arrester electrification test experimental study system, 110kV main transformer of transformer substation, bus, three-phase metal oxide arrester and pressure regulator including standard, also include leakage current of an arrester testing instrument for electrified, equivalent salt density solution spraying device and infrared thermography.The utility model is easy to existing corresponding relation between the rate of change of research equipment running temperature and the rate of change of MOA current in resistance property by setting regulator to change system operation voltage, equivalent salt density solution spraying device and thermal infrared imager monitoring device running temperature;Further by setting arrester pillar roller track, enough locus by changing MOA three-phases are enabled the system to be laid out, to simulate the change of MOA surrounding devices operating condition, it is practical for training and teaching or verification experimental verification etc., and can effectively examine the performance of different MOA leakage current live testing equipment good and bad.

Description

A kind of metallic oxide arrester electrification test experimental study system
Technical field
Power system be the utility model is related in fortune equipment live technical field of measurement and test, more particularly to a kind of metal oxide Lightning arrester live-line test experimental study system.
Background technology
At present, metal oxide arrester in transformer station(Hereinafter referred to as " MOA ")It is long-term to bear system operation phase voltage work With under the factors such as aging, humidity, filth and overvoltage valve block may being caused to gradually degrade, current in resistance property and active power Increase, finally cause insulation characterisitic to be destroyed, thus how by MOA charging test detect its performance quality with regard to ten Divide necessity.
MOA live testings are a kind of important detection methods:To the total current by valve block under MOA accidental conditions Measured with resistive component, and combine initial value difference to judge the deterioration condition of valve block.MOA live testings number in most cases Preferable according to uniformity, test data is to reflect the true characters of MOA reliablely, but indivedual such as extra-high voltage AC and DC power transformation Arrester in standing is sometimes due to by system operation voltage pulsation, insulator surface filth degree, MOA running temperatures(Ambient temperature and humidity Change), MOA surrounding devices operating conditions change(Geographical arrangement between MOA three-phases), nonstandard testing equipment or examination The influence of the various factors such as proved recipe method, cause MOA live testing data comparability bad, conclusion (of pressure testing) is relatively difficult to sentence sometimes It is disconnected, it is specific as follows shown;
System operation voltage has large effect to the point test of MOA bands, and actual measurement shows:Circuital size is transported with MOA There is certain relation in row phase voltage, MOA operations phase voltage is influential on total current and current in resistance property, as operation is mutually electric The increase of pressure, MOA total current can also increase with current in resistance property, and phase angle difference reduces, and vice versa.
Illustrated with the data instance in certain extra-high voltage #2M arresters in March, 2009 ~ January, should by tracing analysis contrast Group three-phase lightning protector operation phase voltage and circuital relation, it is found that circuital size and arrester operation phase voltage are most of When have certain relation, with arrester run phase voltage lifting, total current has also increased, and above analyzes resistive electricity Stream is consequently increased with circuital increase, and vice versa.This explanation MOA operation phase voltages are to have to total current and current in resistance property Influence, the variation tendency between three is basically identical.But the change for running phase voltage has on circuital change influence It is much irregular to follow, run and need between phase voltage rate of change and total current rate of change in the presence of what corresponding relation into one Step research.
The influence that surface filth has to MOA with point test.Outdoor MOA insulators are vulnerable to the filthy pollution of environment, in environment Insulator outer surface leakage current increases when relative humidity is larger, because the current in resistance property of MOA itself bodies is smaller, even if less Surface leakage will also result in certain measurement error, so that test data is bigger than normal, it is impossible to true reflection MOA situations.In addition, this A little surface filths equally influence the voltage's distribiuting of MOA valve block posts and make the increase of its internal leakage electric current.Therefore, the shadow of surface filth Sound causes the situation of MOA live testing bigger errors larger possibility to be present.But the degree and MOA live testing errors of surface filth What it need further to study in the presence of corresponding relation.
The influence that equipment running temperature has to MOA with point test.There are some researches show:ZnO valve plate has in small area analysis region There is negative temperature coefficient and MOA inner spaces are smaller, radiating condition is poor, heat caused by active loss can make the temperature of resistor disc Degree is higher than environment temperature, and current in resistance property increases with the rise of valve block temperature.But the rate of change of equipment running temperature and MOA are resistive What it need further to study in the presence of corresponding relation between the rate of change of electric current.
The influence that the change of MOA surrounding devices operating condition has to MOA with point test.There is actual measurement to show that some buses are taken shelter from the thunder Device can interfere during the equipment such as outlet switch, disconnecting link, CT, pillar to lightning arrester live-line test when close to outlet, cause B Phase current in resistance property is bigger than normal.After the switching state of outlet switch changes, lightning arrester live-line test data differences are larger.But MOA weeks Peripheral equipment operating condition changes between the test of MOA current in resistance property and need further to study in the presence of what corresponding relation.
In addition, nonstandard testing equipment or test method may also impact to MOA live testings, such as experiment is set Standby voltage signal wireless launcher electric power is insufficient, signal is interfered, testing equipment virtual earth, testing equipment measuring accuracy Requirement etc. is unsatisfactory for, may all cause the inaccuracy of MOA live testing data.
In summary, system operation voltage pulsation, insulator surface filth degree, MOA running temperatures, MOA surrounding devices fortune The influence of the various factors such as the changing of row operating mode, nonstandard testing equipment or test method is powered for arrester resistance current There is considerable influence in test, although many units found these phenomenons, mesh during MOA current in resistance property live testings The mechanism that the preceding country has carried out some correlative studys to above-mentioned three aspects is less, and research contents is not deep enough, it is impossible to shape Into more effective conclusion.Power system device is restricted by power supply reliability, can not at any time be had a power failure and be carried out the survey of correlation test Experiment card, it is impossible to which MOA these influence factors are in depth studied.
Utility model content
The purpose of this utility model is to provide a kind of metallic oxide arrester electrification test experimental study system, Neng Goutong Cross can easily and reliably realize under different influence factors to MOA leakage currents live testing carry out deeply effectively grind Study carefully, effectively examine the performance of different MOA leakage current live testing equipment good and bad.
The technical solution adopted in the utility model is:
A kind of metallic oxide arrester electrification test experimental study system, include the 110kV transforming plant main transformer pressures of standard Device, bus, three-phase metal oxide arrester and pressure regulator, main transformer are connected by pressure regulator with bus, bus connection gold Tool and three-phase metal oxide arrester, also include leakage current of an arrester testing instrument for electrified, equivalent salt density solution spraying dress Put and infrared thermography, described leakage current of an arrester testing instrument for electrified, equivalent salt density solution spraying device and infrared heat Imager is arranged at the side of three-phase metal oxide arrester;
Described metal oxide arrester has three-phase pillar, and the slip of each phase pillar lower section is provided with one and taken shelter from the thunder Device pillar roller track, the structures of three arrester pillar roller tracks, size are completely just as and three is arranged in parallel; Down conductor binding post is additionally provided near arrester pillar roller track, is grounded and connects for metal oxide arrester Connect;Every group of arrester posts bottom roller is all fixed by an arrester pillar roller track metal neck, prevents from keeping away The run-off the straight in moving process of thunder device.
There are two groups of arrester posts bottom rollers between described each pillar and arrester pillar roller track, for gold Category Oxide Arrester is rolled along arrester pillar roller track towards corresponding position.
The utility model changes system operation voltage by regulator first, is carried out under different system operation voltage The live testing of MOA leakage currents, it is existing right between research operation phase voltage rate of change and total current, current in resistance property rate of change It should be related to, find and refine VA characteristic curve of the MOA valve blocks in small area analysis region;Secondly by equivalent salt density solution spraying Device studies corresponding relation existing for the degree and MOA live testing errors of surface filth to MOA insulating coating surface sprayings; Finally different periods utilize thermal infrared imager monitoring device running temperature, the rate of change of research equipment running temperature among 1 year The existing corresponding relation between the rate of change of MOA current in resistance property;Further by setting arrester pillar roller track, make The system can be laid out by changing the locus of MOA three-phases, to simulate the change of MOA surrounding devices operating condition, Ke Yiyan Study carefully existing corresponding relation between the change of MOA surrounding devices operating condition and the test of MOA current in resistance property;The utility model can Check test equipment or test method performance it is good and bad, safe to use convenient, can easily and reliably realize in different influences MOA leakage currents live testing is carried out under factor deeply effectively to study, for practicalities such as training and teaching or verification experimental verifications Property it is strong, and can effectively examine the performance of different MOA leakage current live testing equipment good and bad.
Brief description of the drawings
Fig. 1 is overall structure figure of the present utility model;
Fig. 2 is the single MOA pillars roller track working state schematic representation of the utility model,
Fig. 3 is selection schematic diagram in MOA pillars roller track working condition position described in the utility model.
In figure:1st, bus connection gold utensil, 2, metal oxide arrester, 3, main transformer, 4, pressure regulator, 5, arrester branch Post roller track, 6, arrester posts bottom roller, 7, arrester pillar roller track metal neck, 8, down conductor wiring Terminal, 9, leakage current of an arrester testing instrument for electrified, 10, equivalent salt density solution spraying device, 11, infrared thermography.
Embodiment
The utility model can apply to the simulation training of metal oxide arrester MOA leakage current live testings, examination Test the related work such as research and the inspection of live testing equipment performance quality.
As shown in Fig. 1,2 and Fig. 3, the utility model includes a kind of metallic oxide arrester electrification test experimental study system System, including the 110kV main transformer of transformer substation 3 of standard, bus, three-phase metal oxide arrester 2 and pressure regulator, main transformer 3 are connected by pressure regulator 4 with bus, bus connection gold utensil 1 and three-phase metal oxide arrester 2, are also included arrester and are let out Leakage current testing instrument for electrified 9, equivalent salt density solution spraying device 10 and infrared thermography 11, described leakage current of an arrester Testing instrument for electrified 9, equivalent salt density solution spraying device 10 and infrared thermography 11 are arranged at three-phase metal oxide and taken shelter from the thunder The side of device 2;The described insulating coating surface of metal oxide arrester 2 can simulate different pollution levels:Pass through foundation The good equivalent salt density solution of filthy horizontal configured in advance, is kept away three-phase metal oxide using equivalent salt density solution spraying device 10 The insulating coating surface of thunder device 2 is uniformly sprayed, and after drying in extreme moistening, slight moistening or slightly, can use arrester Leakage current testing instrument for electrified 9 carries out the live detection of leakage current of an arrester, studies degree and the MOA band electrical measurements of surface filth Try corresponding relation existing for error.The influence that surface filth has to MOA with point test.
Outdoor MOA insulators are vulnerable to the filthy pollution of environment, the insulator outer surface leakage current when envionmental humidity is larger Increase, because the current in resistance property of MOA itself bodies is smaller, even if less surface leakage will also result in certain measurement error, So that test data is bigger than normal, it is impossible to true reflection MOA situations.In addition, these surface filths equally influence the electricity of MOA valve block posts Pressure is distributed and makes the increase of its internal leakage electric current.Therefore, the influence of surface filth causes the situation of MOA live testing bigger errors Larger possibility be present.So the utility model provides the degree of surface filth and what corresponding pass is MOA live testings error be present It is the experiment condition further studied.
The influence that equipment running temperature has to MOA with point test.ZnO valve plate has negative temperature system in small area analysis region Several and MOA inner spaces are smaller, radiating condition is poor, and heat caused by active loss can make the temperature of resistor disc be higher than environment temperature Degree, current in resistance property increase with the rise of valve block temperature.But the rate of change of the rate of change of equipment running temperature and MOA current in resistance property Between also treat further to study in the presence of what corresponding relation, based on this, the utility model also by set experiment condition, can The collection and accurately experiment of data are enough carried out by the utility model.
The influence that the change of MOA surrounding devices operating condition has to MOA with point test.There is actual measurement to show that some buses are taken shelter from the thunder Device can interfere during the equipment such as outlet switch, disconnecting link, CT, pillar to lightning arrester live-line test when close to outlet, cause B Phase current in resistance property is bigger than normal.After the switching state of outlet switch changes, lightning arrester live-line test data differences are larger.But MOA weeks Peripheral equipment operating condition changes between the test of MOA current in resistance property and need further to study in the presence of what corresponding relation.
In addition, nonstandard testing equipment or test method may also impact to MOA live testings, such as experiment is set Standby voltage signal wireless launcher electric power is insufficient, signal is interfered, testing equipment virtual earth, testing equipment measuring accuracy Requirement etc. is unsatisfactory for, may all cause the inaccuracy of MOA live testing data.The utility model is by setting experimental system, It can be tested and the collection of data.
Described metal oxide arrester 2 has three-phase pillar, and the slip of each phase pillar lower section is provided with one and kept away Thunder device pillar roller track 5, the structures of three arrester pillar roller tracks 5, size are completely just as and three is parallel to each other and set Put;Down conductor binding post 8 is additionally provided near arrester pillar roller track 5, for metal oxide arrester 2 Grounding connection;Every group of arrester posts bottom roller 6 is all consolidated by an arrester pillar roller track metal neck 7 It is fixed, prevent arrester run-off the straight in moving process.
Design and construction technique of the present utility model is according to 110kV main transformer of transformer substation 3, bus and the metal of standard Oxide Arrester is designed, and main transformer 3 carries out the regulation of system operation voltage by pressure regulator 4, in different systems Leakage current of an arrester testing instrument for electrified is used to the three-phase metal oxide arrester 2 in experimental study system under working voltage 9 carry out the live testing of leakage current, existing between research operation phase voltage rate of change and total current, current in resistance property rate of change Corresponding relation, find and refine VA characteristic curve of the MOA valve blocks in small area analysis region.
The each phase pillar of described three-phase metal oxide arrester 2 is respectively positioned on arrester pillar roller track 5, each There are two groups of arrester posts bottom rollers 6 between pillar and arrester pillar roller track 5, be connected removing arrester with bus After gold utensil 1, it is easy to three-phase metal oxide arrester 2 to be rolled along arrester pillar roller track 5 towards corresponding position, Every group of arrester posts bottom roller 6 is all fixed by an arrester pillar roller track metal neck 7, prevents from taking shelter from the thunder Device run-off the straight in moving process.There is down conductor binding post 8 near arrester pillar roller track 5, be easy to three Phase metal oxide arrester 2 reaches grounding connection during new position.In three-phase metal oxide arrester 2 along arrester pillar When roller track 5 is moved to relevant position, as shown in figure 3, three relative positions for passing through the first phase metal oxide arrester 2 Three relative positions B1, B2, B3 of A1, A2, A3 and the metal oxide arrester of the second phase 2 are oppositely arranged and third phase The relative position of three relative positions C1, C2, C3 of metal oxide arrester 2 three-phase metal oxide arrester 2 is not Can be with position relationship between three-phase lightning protector(Just " one " font, tiltedly " one " font, " product " font, " L " type or " V " type By between three-phase lightning protector position relationship change indirectly change arrester between each other and surrounding electromagnetic environment(Change Operating condition), it can now use leakage current of an arrester testing instrument for electrified 9 to carry out the live detection of leakage current of an arrester, Study existing corresponding relation between the change of MOA surrounding devices operating condition and the test of MOA current in resistance property.
Described three-phase metal oxide arrester 2 Various Seasonal among 1 year(Choose summer, winter extreme weather conditions Under), the equipment running temperature of three-phase metal oxide arrester 2 is observed and recorded using infrared thermography 11, while using lightning-arrest Device leakage current testing instrument for electrified 9 carry out leakage current of an arrester live detection, the rate of change of research equipment running temperature with Existing corresponding relation between the rate of change of MOA current in resistance property.
The system can verify that the quality of testing equipment or test method performance, such as the voltage signal of simulated test facility Wireless launcher electric power deficiency, signal is interfered, testing equipment virtual earth, testing equipment measuring accuracy are unsatisfactory for requiring Deng.
The system is safe to use convenient, can easily and reliably realize under different influence factors to MOA leakage currents Live testing deeply effectively study, practical for training and teaching or verification experimental verification etc., and can effectively examine It is good and bad to test the performance of different MOA leakage current live testing equipment, it is safe to use convenient, it is practical for training and teaching, With higher scientific research value.
The utility model can apply to metal oxide arrester(MOA)The simulation training of leakage current live testing, The related work such as experimental study and the inspection of live testing equipment performance quality, can realize following major function:First, it can lead to Cross regulator and change system operation voltage, the live testing of MOA leakage currents is carried out under different system operation voltage, is ground Study carefully existing corresponding relation between operation phase voltage rate of change and total current, current in resistance property rate of change, find and refine MOA valve blocks VA characteristic curve in small area analysis region;
Second, surface filth can be studied by equivalent salt density solution spraying device to MOA insulating coating surface sprayings Corresponding relation existing for degree and MOA live testing errors;
Third, different periods utilize thermal infrared imager monitoring device running temperature among 1 year, can be run with research equipment Existing corresponding relation between the rate of change of temperature and the rate of change of MOA current in resistance property;
Fourth, can be laid out by changing the locus of MOA three-phases, to simulate the change of MOA surrounding devices operating condition, Existing corresponding relation between the change of MOA surrounding devices operating condition and the test of MOA current in resistance property can be studied;Fifth, can be with The quality of check test equipment or test method performance, for example, simulated test facility voltage signal wireless launcher electric power not Foot, signal are interfered, testing equipment virtual earth, testing equipment measuring accuracy are unsatisfactory for requirement etc..The metal oxide is taken shelter from the thunder Device live testing experimental study system is safe to use convenient.
Therefore, the utility model can simulate the operating mode of a variety of MOA under true environment, including regulating system working voltage, Different insulator surface filth degree are set, the infrared operations of MOA are monitored using infrared thermography by the change of season extreme weather Temperature, change MOA surrounding devices operating conditions etc., it may be necessary to experimental test is carried out to MOA live testings testing equipment, with Detect MOA live testings test method and examine the performance of live testing equipment good and bad.
Above-mentioned embodiment is used for illustrating the utility model, rather than the utility model is limited, in this reality With any modifications and changes in new spirit and scope of the claims, made to the utility model, this is both fallen within The protection domain of utility model.

Claims (2)

  1. A kind of 1. metallic oxide arrester electrification test experimental study system, it is characterised in that:110kV power transformations including standard Station owner's transformer(3), bus, three-phase metal oxide arrester(2)And pressure regulator, main transformer(3)Pass through pressure regulator(4)With Bus connects, bus connection gold utensil and three-phase metal oxide arrester(2), also include leakage current of an arrester live testing Instrument(9), equivalent salt density solution spraying device(10)And infrared thermography(11), described leakage current of an arrester live testing Instrument(9), equivalent salt density solution spraying device(10)And infrared thermography(11)It is arranged at three-phase metal oxide arrester (2)Side;
    Described metal oxide arrester(2)With three-phase pillar, the slip of each phase pillar lower section is provided with one and taken shelter from the thunder Device pillar roller track(5), three arrester pillar roller tracks(5)Structure, size is completely just as and three is parallel to each other Set;In arrester pillar roller track(5)Nearby it is additionally provided with down conductor binding post(8), for metal oxide Arrester(2)Grounding connection;Every group of arrester posts bottom roller(6)All pass through an arrester pillar roller track metal card Groove(7)It is fixed, prevents arrester run-off the straight in moving process.
  2. 2. metallic oxide arrester electrification test experimental study system according to claim 1, it is characterised in that:It is described Each pillar and arrester pillar roller track(5)Between have two groups of arrester posts bottom rollers(6), aoxidized for metal Thing arrester(2)Along arrester pillar roller track(5)Rolled towards corresponding position.
CN201720068678.2U 2017-01-20 2017-01-20 A kind of metallic oxide arrester electrification test experimental study system Withdrawn - After Issue CN206684248U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720068678.2U CN206684248U (en) 2017-01-20 2017-01-20 A kind of metallic oxide arrester electrification test experimental study system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720068678.2U CN206684248U (en) 2017-01-20 2017-01-20 A kind of metallic oxide arrester electrification test experimental study system

Publications (1)

Publication Number Publication Date
CN206684248U true CN206684248U (en) 2017-11-28

Family

ID=60396270

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720068678.2U Withdrawn - After Issue CN206684248U (en) 2017-01-20 2017-01-20 A kind of metallic oxide arrester electrification test experimental study system

Country Status (1)

Country Link
CN (1) CN206684248U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111044830A (en) * 2019-12-31 2020-04-21 苏州华电电气股份有限公司 Zinc oxide arrester operating characteristic live monitoring device

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111044830A (en) * 2019-12-31 2020-04-21 苏州华电电气股份有限公司 Zinc oxide arrester operating characteristic live monitoring device

Similar Documents

Publication Publication Date Title
CN103257293B (en) A kind of power transmission line lightning shielding electro-magnetic transient moving die experiment system
CN202994931U (en) Lightning arrester state monitoring device based on wireless sensing technology
CN104360197B (en) Method for monitoring resistance of valve discs of arresters based on resistance-capacitance network
WO2014173314A1 (en) System for testing property of thunder and lightning traveling wave of power transmission line
Long et al. Online monitoring of substation grounding grid conditions using touch and step voltage sensors
CN106168640A (en) A kind of Zinc-Oxide Arrester state online test method
CN104833903A (en) Method for determining gap distance of surge arresters containing series gapped structures along with altitude change
CN104251956A (en) Lightning arrestor online monitoring device with shielding function
CN106646042A (en) Comprehensive evaluation method for aging performances of insulating separator plate of switch cabinet
CN106547953A (en) A kind of method of acquisition 800kV dc bus metal oxide arrester Potential distributions
CN104280637A (en) Lightning arrester online monitoring signal collection device with shielding function
CN204649859U (en) A kind of transmission line of electricity over-voltage measurement analogue test platform
CN206684248U (en) A kind of metallic oxide arrester electrification test experimental study system
CN106680652A (en) Metal oxide arrester electrification test experiment research system
CN203981826U (en) The detection platform of circuit phase ground and alternate gap discharge characteristic under simulation mountain fire condition
CN102542881B (en) Cable fault simulator and cable fault simulation system
CN205139349U (en) Arrester discharge counter and leakage current table check gauge
Volpov et al. Characterization of local environmental data and lightning-caused outages in the IECo transmission-line network
Maslowski et al. Experimental investigation and numerical modeling of surge currents in lightning protection system of a small residential structure
CN112395788A (en) Personal safety accurate evaluation method for distribution network neutral point grounding type reconstruction
CN205720494U (en) A kind of Zinc-Oxide Arrester state on-line detector
Mohajeryami et al. Including surge arresters in the lightning performance analysis of 132kV transmission line
Méndez et al. The 2018 revision of the standard IEC 61400-24: Lightning protection of wind turbines
CN203811519U (en) ADSS (All Dielectric Self Supporting) cable testing device
CN110046322A (en) A kind of long cable voltage test core voltage Analytic Calculation Method

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
AV01 Patent right actively abandoned
AV01 Patent right actively abandoned
AV01 Patent right actively abandoned

Granted publication date: 20171128

Effective date of abandoning: 20230407

AV01 Patent right actively abandoned

Granted publication date: 20171128

Effective date of abandoning: 20230407