CN206668953U - Forging tubular construction with needing bore hole after high pressure single case weld - Google Patents

Forging tubular construction with needing bore hole after high pressure single case weld Download PDF

Info

Publication number
CN206668953U
CN206668953U CN201720381665.0U CN201720381665U CN206668953U CN 206668953 U CN206668953 U CN 206668953U CN 201720381665 U CN201720381665 U CN 201720381665U CN 206668953 U CN206668953 U CN 206668953U
Authority
CN
China
Prior art keywords
forging
high pressure
bore hole
pressure single
welding
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201720381665.0U
Other languages
Chinese (zh)
Inventor
魏红利
柴建华
霍李龙
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanxi Yangmei Chemical Industry Machinery Group Co Ltd
Original Assignee
Shanxi Yangmei Chemical Industry Machinery Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanxi Yangmei Chemical Industry Machinery Group Co Ltd filed Critical Shanxi Yangmei Chemical Industry Machinery Group Co Ltd
Priority to CN201720381665.0U priority Critical patent/CN206668953U/en
Application granted granted Critical
Publication of CN206668953U publication Critical patent/CN206668953U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Pressure Welding/Diffusion-Bonding (AREA)

Abstract

The utility model discloses a kind of forging tubular construction with needing bore hole after high pressure single case weld, mainly it is made up of forging pipe, high pressure single housing, first formed by forging pipe with high pressure single case weld, after the completion of welding, only bottom bore hole need to be carried out in forging pipe, then Welded Joints carry out Non-Destructive Testing, and detection is qualified can to ensure welding point complete penetraction and fusion in welding, ensure welding quality.This novel forging tubular construction, have and save precious materials;Processing capacity is small, that is, reduces equipment manufacturing costs, in turn ensure that welding point complete penetraction and fusion in welding, ensure that welding quality, avoids triggering security incident.

Description

Forging tubular construction with needing bore hole after high pressure single case weld
Technical field
Individual layer high pressure vessel is the utility model is related to, after specially a kind of and individual layer high pressure vessel case weld The forging tubular construction of bore hole is needed, suitable for chemical industry high-pressure bottle.
Background technology:
Maximization and high parameter with pressure vessel, to ensure the security reliability of high-pressure bottle, managed frequently with forging With carrying out bore hole after high pressure single case weld, ensure welding point complete penetraction and fusion in welding, ensure welding quality, at present forging pipe and high pressure list The forging tubular construction of bore hole is needed after layer case weld, as shown in Fig. 2 having the following disadvantages:1st, it is consistent to forge bore, all bore holes Preceding size, especially forging pipe is precious metal, and substantial amounts of waste of material is caused after bore hole;2nd, forging pipe and high pressure single case weld Afterwards, whole bore holes need to be carried out by Fig. 1 forging bores, processing capacity is big, causes unnecessary manpower consumption and equipment loss, and increase is set Standby manufacturing cost.Therefore, it is necessary to a kind of forging tubular construction for reducing manpower and waste of material.
The content of the invention
The utility model is that tube material and manpower waste and processing capacity is big in order to solve the problems, such as to forge, there is provided Yi Zhongyu The small forging tubular construction of bore hole amount is needed after the welding of individual layer high pressure vessel.
The utility model adopts the following technical scheme that realization:
A kind of forging tubular construction with needing bore hole after high pressure single case weld, including forging tube body, the forging tube body lead to The flange for crossing its lower end is assemblied at the mouth of pipe of high pressure single housing and is welded to connect, and the forging tube body upper inner diameter is bore hole Size, lower inner diameter are size before bore hole afterwards, and the lower inner diameter of the forging tube body is less than the spout diameter of high pressure single housing.
Before welding job, by forging pipe according to pipe upper inner diameter is forged as size after bore hole, lower inner diameter is size before bore hole, The requirement that lower inner diameter is less than upper inner diameter is processed, and the purpose so forged is to after forging pipe is with case weld, forge Pipe top does not have to carry out Boring again, reduces labor content;Forging pipe bottom is welded with high pressure single housing afterwards Connection, because after bore hole, forging pipe bottom should be the same with the internal diameter size on top, so, it is necessary to be managed to forging after the completion of welding The opening part of bottom, weld part and housing carries out bore hole, and after bore hole terminates, Welded Joints carry out Non-Destructive Testing, and detection is closed Lattice can ensure welding point complete penetraction and fusion in welding, ensure welding quality.
The utility model reduces the workload of bore hole, reduces manpower consumption and equipment loss, reduces device fabrication Cost;Guarantee welding point complete penetraction and fusion in welding is reached again, ensure that the quality of welding, overcome the deficiencies in the prior art;When forging is managed For precious metal when, substantial amounts of waste of material will not be caused.
Brief description of the drawings
Fig. 1 is cross-sectional view of the present utility model.
Fig. 2 is the forging tubular construction schematic diagram before improving.
Fig. 3 is forging tubular construction schematic diagram of the present utility model.
In Fig. 1:1- forges tube body, 2- high pressure single housings, 3- weld parts, 11- flanges.
Embodiment
Specific embodiment of the utility model is illustrated below in conjunction with the accompanying drawings.
A kind of forging tubular construction with needing bore hole after high pressure single case weld, as shown in figure 1, forging tube body 1 is by under it The flange at end is assemblied at the mouth of pipe of high pressure single housing 2 and is welded to connect, and forging tube body 1 upper inner diameter is chi after bore hole Very little, lower inner diameter is size before bore hole, and the lower inner diameter of the forging tube body 1 is less than the spout diameter of high pressure single housing 2.
Forging pipe described in the utility model forges according to the structure shown in Fig. 3, will in order to reduce processing capacity and waste of material Forging pipe upper inner diameter is designed as size after bore hole, and the forging lower inner diameter of pipe 1 is designed as size before bore hole, forges the top and the bottom length ratio of pipe Example is 2:1~3:1.In the present embodiment, the two radius difference 8mm, i.e. bore hole thickness is 8mm;Welding when, will forging pipe lower end with High pressure single case weld, ensure welding quality;Then bore hole is carried out, only need to be by forging pipe bottom, unnecessary solder joint and housing Thickness machines away in bore hole, the housing spout diameter after processing and the internal diameter all same of forging pipe top and the bottom, saves processing capacity And manpower consumption.Last Welded Joints carry out Non-Destructive Testing, and detection is qualified can to ensure welding point complete penetraction and fusion in welding, ensure welding Quality, avoid triggering security incident.
Exemplary description is carried out to the utility model above in conjunction with accompanying drawing, it is clear that the utility model concrete implementation is not Limited by aforesaid way, if the various improvement that methodology and technical scheme of the present utility model are carried out are employed, or not Improved directly application and other occasions, in the scope of protection of the utility model.

Claims (3)

  1. A kind of 1. forging tubular construction with needing bore hole after high pressure single case weld, it is characterised in that:Including forging tube body(1), institute State forging tube body(1)Pass through the flange of its lower end(11)It is assemblied in high pressure single housing(2)The mouth of pipe at and be welded to connect, it is described Forge tube body(1)Upper inner diameter is size after bore hole, lower inner diameter is size before bore hole, the forging tube body(1)Bottom in Footpath is less than high pressure single housing(2)Spout diameter.
  2. 2. the forging tubular construction according to claim 1 with needing bore hole after high pressure single case weld, it is characterised in that:It is described Forge tube body(1)Upper inner diameter be more than its underpart internal diameter 16mm.
  3. 3. the forging tubular construction according to claim 1 or 2 with needing bore hole after high pressure single case weld, it is characterised in that: The forging tube body(1)Top and the bottom length ratio be 2:1~3:1.
CN201720381665.0U 2017-04-13 2017-04-13 Forging tubular construction with needing bore hole after high pressure single case weld Expired - Fee Related CN206668953U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720381665.0U CN206668953U (en) 2017-04-13 2017-04-13 Forging tubular construction with needing bore hole after high pressure single case weld

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720381665.0U CN206668953U (en) 2017-04-13 2017-04-13 Forging tubular construction with needing bore hole after high pressure single case weld

Publications (1)

Publication Number Publication Date
CN206668953U true CN206668953U (en) 2017-11-24

Family

ID=60381160

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720381665.0U Expired - Fee Related CN206668953U (en) 2017-04-13 2017-04-13 Forging tubular construction with needing bore hole after high pressure single case weld

Country Status (1)

Country Link
CN (1) CN206668953U (en)

Similar Documents

Publication Publication Date Title
CN201705226U (en) Integral type double-shoulder sulfur resistant drill rod
CN104652422B (en) For the device and method of pile foundation steel bar cage bar connecting
CN107524232A (en) A kind of integrated shaped steel and its live splicing construction
CN102155538A (en) Reusable welded hydraulic cover of boiler and pressure vessel and manufacturing method of reusable welded hydraulic cover
CN202516758U (en) Connecting device for ultrasonic amplitude transformer and toolhead
CN106312440A (en) Friction welding repair method for hollow steel drill rod
CN206668953U (en) Forging tubular construction with needing bore hole after high pressure single case weld
CN201269372Y (en) Soldering connection structure of aluminum and aluminum alloy pipe
CN203066882U (en) High-strength arc angle triquetrum drill rod
CN101694109B (en) Dropping semi-core-through joint of hollow laminated steel pipe concrete column and steel girder
CN212398558U (en) Friction welding end face structure of drill pipe body and drill pipe joint
CN205745755U (en) A kind of integration cast type flange
CN108036131A (en) A kind of attachment device and its application method for super-silent pipeline upside-down mounting
CN203175413U (en) Five-inch internal-external upset drill pipe
CN201525710U (en) Standard section joint of tower crane
CN203973073U (en) Mining hydraulic individual prop post friction welded joint alive structure
CN206207748U (en) The dome head of water storage tank or separator and pipe joint solid forging structure
CN109899018A (en) One kind is to reverse circulation washing device on oil well
CN103111769A (en) Novel process method for reducing welding deformation of oil inlet and outlet of hydraulic oil cylinder
CN204735806U (en) Middleware is connected to circumscribed copper iron
CN204321426U (en) A kind of pipeline soldering connecting structure
CN104439693A (en) Rotary forging connection process for homogeneous or heterogeneous metal tubes and bars
CN103104769A (en) Stainless steel anti-explosion flexible pipe free of welding
CN204785173U (en) Pipe flange is forged to little internal diameter
CN201653245U (en) Novel titanium steel double-pipe heat exchanger

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20171124

Termination date: 20190413

CF01 Termination of patent right due to non-payment of annual fee