CN206656063U - A kind of powder material is blown transmission pipeline component - Google Patents
A kind of powder material is blown transmission pipeline component Download PDFInfo
- Publication number
- CN206656063U CN206656063U CN201720366991.4U CN201720366991U CN206656063U CN 206656063 U CN206656063 U CN 206656063U CN 201720366991 U CN201720366991 U CN 201720366991U CN 206656063 U CN206656063 U CN 206656063U
- Authority
- CN
- China
- Prior art keywords
- inner tube
- way
- assembly
- powder material
- blown
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Rigid Pipes And Flexible Pipes (AREA)
- Thermal Insulation (AREA)
Abstract
The utility model belongs to powder material transportation art, and a kind of powder material is blown transmission pipeline component, including pipeline assembly, compensator assembly and four-way assembly, and flange connection is passed sequentially through between pipeline assembly, compensator assembly and four-way assembly;Pipeline assembly includes the first inner tube and the first outer tube being set in outside first inner tube, and compensator assembly includes the second inner tube and the second outer tube being set in outside second inner tube;The both ends of first outer tube and the second outer tube wall are provided with some supporting plates, and adjusting sleeve is provided between some supporting plates, and the adjusting sleeve is set in outside the first inner tube and the second inner tube, and some regulating bolts are provided with the adjusting sleeve;Four-way assembly includes four-way shell and four the 3rd inner tubes being separately positioned in four through holes of the four-way shell;Between first inner tube and the first outer tube, between the second inner tube and the second outer tube and between the four-way shell and the 3rd inner tube filled with insulation filler.
Description
Technical field
The utility model belongs to powder material transportation art, more particularly to a kind of powder material injection transmission pipeline component.
Background technology
Melting reduction steel-making project is the forward position advanced technology in domestic steel-making industry, belongs to the production mould of environment-friendly high-efficiency
Formula, for more than 800 DEG C of hot miberal powder of conveying, it is blown transmission pipeline and to be incubated, be high temperature resistant, wear-resistant, and guarantee again is born
Certain fatigue strength.It is not easy to change or need integral replacing after existing injection abrasion of conveying pipes, cost is higher.
Utility model content
The defects of to need integral replacing after abrasion of conveying pipes existing for solution prior art, the utility model provides one
Kind powder material injection transmission pipeline component.
In order to solve the above technical problems, technical scheme is used by the utility model:A kind of powder material injection transmission
Conduit assembly, including pipeline assembly, compensator assembly and four-way assembly, described pipeline assembly, compensator assembly and four-way are total
Flange connection is passed sequentially through between;Described pipeline assembly includes the first inner tube and be set in outside first inner tube the
One outer tube, described compensator assembly include the second inner tube and the second outer tube being set in outside second inner tube;Described
The both ends of first outer tube and the second outer tube wall are provided with some supporting plates, and adjustment is provided between some supporting plates
Set, the adjusting sleeve are set in outside the first inner tube and the second inner tube, and some regulating bolts are provided with the adjusting sleeve;It is described
Four-way assembly include four-way shell and four the 3rd inner tubes being separately positioned in four through holes of the four-way shell;It is described
The first inner tube and the first outer tube between, between the second inner tube and the second outer tube and between the four-way shell and the 3rd inner tube
Filled with insulation filler.
Preferably, the second described outer tube includes being set in the upper casing on the second inner tube top and is set in described the
The lower casing of two inner tube bottoms, one end of the lower casing are set in outside one end of the upper casing, and described compensator assembly also wraps
Telescoping connection is included, the telescoping connection both ends are separately fixed on the upper casing and lower casing.Can be effectively according to production using telescoping connection
Need the length of the second inner tube of matching.
Preferably, it is described it is flexible be connected in 65 manganese steel telescopics, the 65 manganese steel telescopic is in corrugated tube shape.65 manganese steel
Telescopic has good intensity and elastic performance.
Further, the position that the upper casing is located in the lower casing is provided with annular mounting groove, is set in the mounting groove
It is equipped with sealing ring.The setting of sealing structure can ensure to ensure sealing between the two while upper casing and lower casing are socketed.
Further, the end of described upper casing and lower casing is provided with flange, and adjustment knot is provided with described flange
Structure, the adjustment structure include the first connecting plate and second being fixedly connected respectively with the flange on the flange and lower casing on upper casing
Connecting plate, strip hole being provided with first connecting plate, through hole being provided with second connecting plate, bolt passes through described logical
Hole and strip hole fix first connecting plate and the second connecting plate.It can further strengthen stretching structure using structure is adjusted
Stability and intensity.
Preferably, described sealing ring is asbestos cord.
Further, described four-way assembly also includes covering in four-way, the 3rd inner pipe end difference grafting described in four
In four through holes covered in the four-way and connect to forming internal layer four-way pipeline, the Heavenly Stems and Earthly Branches are also equipped with if being put in the four-way
Fagging, the supporting plate one end put in the four-way are fixedly connected with the four-way shell.Using in four-way set can effectively by
The positioning of 3rd inner tube is fixed.
Preferably, be fixedly installed some fastening seats in the 3rd each described inner tube, relative two described the
Connected between the corresponding and corresponding fastening seat of fastening seat in three inner tubes by pull bar.Can will be corresponding using pull bar
Two the 3rd inner tubes tense, and prevent from loosening, while be also convenient for dismounting and change.
Preferably, the first described inner tube, the second inner tube and the 3rd inner tube are bimetallic tubing.Composite bimetal pipe
Material have stamping resistance, low thermal expansion, pressure-resistant, high temperature resistant, it is wear-resisting the advantages of
Beneficial effect:More than 800 DEG C of hot miberal powder leads to the application conduit assembly from the endoporus of each assembly at work
Cross, after the abrasion of long-term use of inner tube, individually inner tube can be changed, it is not necessary to integral replacing, cost is greatlyd save,
And the concentricity between inner tube and outer tube can be adjusted using adjusting sleeve and regulating bolt, and it is same between inner tube and inner tube
Axle, concentricity, ensure that material transferring is smooth and the stability of structure.
Brief description of the drawings
Fig. 1 is the utility model conduit assembly structural representation;
Fig. 2 is the utility model conduit assembly sectional view;
Fig. 3 is partial structurtes enlarged drawing in Fig. 2;
Fig. 4 is inner tube mounting structure schematic diagram;
1. pipeline assembly in figure, 11. first inner tubes, 12. first outer tubes, 2. compensator assemblies, 21. second inner tubes, on 22.
Shell, 23. lower casings, 24. sealing rings, 25. telescoping connections, 26. first connecting plates, 27. second connecting plates, 28. strip holes, 3. four-ways are total
Into, 31. four-way shells, 32. the 3rd inner tubes, cover in 33. four-ways, 34. fastening seats, 35. pull bars, 4. flanges, 5. adjustment structures, 6.
Supporting plate, 7. insulation fillers, 8. adjusting sleeves, 81. regulating bolts, 9. pads.
Embodiment
Embodiment
As illustrated in fig. 1 and 2, a kind of powder material injection transmission pipeline component, including pipeline assembly 1, the and of compensator assembly 2
Four-way assembly 3, pass sequentially through flange 4 between described pipeline assembly 1, compensator assembly 2 and four-way assembly 3 and connect, be connected
Two flanges 4 between be provided with pad 9;Described pipeline assembly 1 includes the first inner tube 11 and is set in first inner tube
The first outer tube 12 outside 11, described compensator assembly 2 include the second inner tube 21 and are set in outside second inner tube 21
The second outer tube, the second described outer tube include be respectively sleeved at second inner tube 21 upper and lower part upper casing 22 and under
Shell 23, telescoping connection 25 and adjustment structure 5, one end of the lower casing 23 is set in outside one end of the upper casing 22, such as Fig. 2 and 3
Shown, the position that the upper casing 22 is located in the lower casing 23 is provided with annular mounting groove, and sealing is provided with the mounting groove
Circle 24, in the present embodiment so that described sealing ring 24 is asbestos cord as an example, described compensator assembly 2 also includes telescoping connection 25,
The both ends of telescoping connection 25 are separately fixed on the upper casing 22 and lower casing 23, and described telescoping connection 25 is 65 manganese steel telescopics,
The 65 manganese steel telescopic is in corrugated tube shape;Described upper casing 22 and the end of lower casing 23 are provided with flange 4, described flange
Be provided with 4 it is described adjustment structure 5, it is described adjustment structure 5 include respectively with the flange on the flange 4 and lower casing 23 on upper casing 22
4 the first connecting plates 26 and the second connecting plate 27 being fixedly connected, are provided with strip hole 28 on first connecting plate 26, and described
Through hole is provided with two connecting plates 27, bolt is connected first connecting plate 26 and second by the through hole and strip hole 28
Plate 27 is fixed.
The first described outer tube 12 and the both ends of the second outer tube wall are provided with some supporting plates 6, some supports
Adjusting sleeve 8 is provided between plate 6, the adjusting sleeve 8 is set in outside the first inner tube 11 and the second inner tube 21, the adjusting sleeve 8
On be provided with some regulating bolts 81;
The four-way assembly 3 as described in shown in Fig. 1,2 and 4 includes four-way shell 31 and four-way shell 31 as described in being separately positioned on
Four through holes in four the 3rd inner tubes 32;Specifically, described four-way assembly 3 also includes covering 33 in four-way, the four-way
Some supporting plates 6 are also equipped with middle set 33, the one end of supporting plate 6 covered in the four-way on 33 is fixed with the four-way shell 31
Connection, in the end of the 3rd inner tube 32 described in four is plugged in the four-way in four through holes of set 33 and connects and to be formed respectively
Layer four-way pipeline, is fixedly installed some fastening seats 34 in the 3rd each described inner tube 32, relative two the described 3rd
Connected between the corresponding and corresponding fastening seat 34 of fastening seat 34 in inner tube 32 by pull bar 35.
Between the first described inner tube 11 and the first outer tube 12, between the second inner tube 21 and the second outer tube and the four-way
Filled with insulation filler 7 between the inner tube 32 of shell 31 and the 3rd.Described the first inner tube 11, the second inner tube 21 and the 3rd inner tube
32 be bimetallic tubing.
During installation, the inner tube of each assembly is arranged in outer tube by adjusting sleeve 8, and by regulating bolt 81 to inner tube
Positioned, be fixed, ensureing inner tube and the concentricity of outer tube, the 3rd inner tube 32 being set in four-way in set 33, and pass through drawing
Bar 35 tenses two relative the 3rd inner tubes 32, to be fixedly assembled, after each assembly inner and outer pipes assemble, and practical rock wool
Synthesized with waterglass lightweight thermal insulation layer cavity is filled up it is substantial, and by each assembly with flange 4 connection form transmission pipeline component,
Shell tool 9 is to ensure sealing between two flanges 4 being connected.Wherein compensator assembly 2 can be according to needs of production
The length of the second different inner tubes 21 is selected, while passes through telescoping connection 25 between upper casing 22 and lower casing 23 and adjustment structure 5, adjustment
The length of length compensator assembly 2, and fix.In work more than 800 DEG C of hot miberal powder from the inner tube of each assembly by,
After being worn by long-term use of inner tube, individually inner tube can be changed, it is not necessary to integral replacing.
Claims (9)
1. a kind of powder material is blown transmission pipeline component, it is characterised in that:Including pipeline assembly (1), compensator assembly (2) and
Four-way assembly (3), flange (4) is passed sequentially through between described pipeline assembly (1), compensator assembly (2) and four-way assembly (3) even
Connect;Described pipeline assembly (1) includes the first inner tube (11) and is set in the first outside outer tube of first inner tube (11)
(12), described compensator assembly (2) includes the second inner tube (21) and is set in outside the second of the second inner tube (21) outside
Pipe;Described the first outer tube (12) and the both ends of the second outer tube wall are provided with some supporting plates (6), some supporting plates
(6) adjusting sleeve (8) is provided between, the adjusting sleeve (8) is set in the first inner tube (11) and the second inner tube (21) is outside, described
Some regulating bolts (81) are provided with adjusting sleeve (8);Described four-way assembly (3) includes four-way shell (31) and set respectively
Four the 3rd inner tubes (32) in four through holes of the four-way shell (31);Described the first inner tube (11) and the first outer tube
(12) filled out between, between the second inner tube (21) and the second outer tube and between the four-way shell (31) and the 3rd inner tube (32)
Filled with insulation filler (7).
2. powder material according to claim 1 is blown transmission pipeline component, it is characterised in that:The second described outer tube bag
Include the upper casing (22) for being set in the second inner tube (21) top and be set in the lower casing (23) of the second inner tube (21) bottom,
One end of the lower casing (23) is set in outside one end of the upper casing (22), and described compensator assembly (2) also includes flexible
Connect (25), telescoping connection (25) both ends are separately fixed on the upper casing (22) and lower casing (23).
3. powder material according to claim 2 is blown transmission pipeline component, it is characterised in that:Described telescoping connection (25)
For 65 manganese steel telescopics, the 65 manganese steel telescopic is in corrugated tube shape.
4. powder material according to claim 2 is blown transmission pipeline component, it is characterised in that:The upper casing (22) is located at
Position in the lower casing (23) is provided with annular mounting groove, and sealing ring (24) is provided with the mounting groove.
5. the powder material injection transmission pipeline component according to claim 2 or 4, it is characterised in that:Described upper casing
(22) and the end of lower casing (23) is provided with flange (4), and adjustment structure (5), the adjustment are provided with described flange (4)
Structure (5) includes the first connecting plate being fixedly connected respectively with the flange (4) on the flange (4) and lower casing (23) on upper casing (22)
(26) strip hole (28), second connecting plate (27) and the second connecting plate (27), are provided with first connecting plate (26)
On be provided with through hole, bolt is by the through hole and strip hole (28) by first connecting plate (26) and the second connecting plate (27)
It is fixed.
6. powder material according to claim 4 is blown transmission pipeline component, it is characterised in that:Described sealing ring (24)
For asbestos cord.
7. powder material according to claim 1 is blown transmission pipeline component, it is characterised in that:Described four-way assembly
(3) also include covering (33) in four-way, the 3rd inner tube (32) end described in four is plugged in the four-way respectively covers (33)
In four through holes and connect to forming internal layer four-way pipeline, covered in the four-way and be also equipped with some supporting plates (6) on (33), it is described
Supporting plate (6) one end covered in four-way on (33) is fixedly connected with the four-way shell (31).
8. powder material according to claim 7 is blown transmission pipeline component, it is characterised in that:In each described the 3rd
Manage and some fastening seats (34) are fixedly installed on (32), fastening seat (34) phase on relative two the 3rd inner tubes (32)
It is corresponding, and connected between corresponding fastening seat (34) by pull bar (35).
9. powder material according to claim 1 is blown transmission pipeline component, it is characterised in that:The first described inner tube
(11), the second inner tube (21) and the 3rd inner tube (32) are bimetallic tubing.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201720366991.4U CN206656063U (en) | 2017-04-07 | 2017-04-07 | A kind of powder material is blown transmission pipeline component |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201720366991.4U CN206656063U (en) | 2017-04-07 | 2017-04-07 | A kind of powder material is blown transmission pipeline component |
Publications (1)
Publication Number | Publication Date |
---|---|
CN206656063U true CN206656063U (en) | 2017-11-21 |
Family
ID=60318645
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201720366991.4U Active CN206656063U (en) | 2017-04-07 | 2017-04-07 | A kind of powder material is blown transmission pipeline component |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN206656063U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110778841A (en) * | 2019-10-30 | 2020-02-11 | 铜陵新创流体科技有限公司 | Double-ripple metal expansion piece |
-
2017
- 2017-04-07 CN CN201720366991.4U patent/CN206656063U/en active Active
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110778841A (en) * | 2019-10-30 | 2020-02-11 | 铜陵新创流体科技有限公司 | Double-ripple metal expansion piece |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN100453881C (en) | Heat proof vacuum tube | |
CN205938206U (en) | A sealing device for quick -witted casket pipeline | |
CN206656063U (en) | A kind of powder material is blown transmission pipeline component | |
CN104075074B (en) | Detachable heat-insulation shell | |
CN209991018U (en) | Direct-buried steam heat-insulation pipe | |
CN208268564U (en) | A kind of petroleum transportation pipeline | |
CN102927378A (en) | Vacuum vertical burying heating pipe | |
CN208649360U (en) | Air-supply apparatus of blast furnace expansion joint | |
CN201014129Y (en) | Labyrinth packing flow guiding cover expansion node | |
CN2766134Y (en) | Rotary buried compensation assembly | |
CN108220627A (en) | A kind of distilling apparatus produced during titanium sponge | |
CN203880325U (en) | Detachable insulating tube shell | |
CN104848003B (en) | Vacuum tube structure and low temperature pipeline adopting same | |
CN209725576U (en) | A kind of straight pipe pressure-equalizing corrugated pipe compensator | |
CN210164435U (en) | Heat-point-free heat-insulation tubing coupling heat-insulation structure | |
CN218154264U (en) | High-temperature-resistant pipeline balancer | |
CN204083515U (en) | A kind of high/low temperature pipeline extension bearing | |
CN208967306U (en) | The structure of the import or export of vertical water cold methanol synthetic tower cooling tube | |
CN212338539U (en) | Thermal insulation corrugated expansion joint | |
CN105864548A (en) | Pipeline compensator | |
CN205956633U (en) | High temperature resistant rectangle expansion joint | |
CN205298833U (en) | High temperature pipeline fixed bolster | |
CN209399021U (en) | A kind of sleeve expansion joint | |
CN114263802A (en) | Full-fixed bidirectional outer pipe metal corrugated compensator | |
CN206973139U (en) | Remote heat supply pipeline flexible expandable non-metal compensator |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |